Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Drilling operations need to be carried out in a safe, efficient, and environmental friendly manner for
successfully completing the well to meet the desired geological objectives. By following recommended
practices, a well can be drilled in shortest possible time and with minimum of complications.
This chapter includes the following topics on drilling operations:
a) Preparation for spudding the well
b) Common drilling practices for all phases
c) Drilling 12 ¼” hole section
d) Drilling 8 ½" hole section
e) Drilling 6” hole section
f) Recommended practices for tripping out
g) Recommended practices for tripping in
h) Recommended practices for reaming
i) Recommended practices for back-reaming
j) Recommended practices for pack-off
k) Recommended practices for wiper trip in deviated hole
a) Preparation for spudding the well:
1. Ensure rig mast centering is carried out before spudding.
2. Check and test all surface equipment viz engines, mud pumps, draw works, compressors, mud handling
equipment, mud tanks etc prior to spudding the well.
3. Pressure test surface high pressure lines and system to its rated pressure.
4. Pressure test high pressure mud lines, mud pump safety valve, rotary hose and standpipe to rated pressure of
pump liner.As Give below.
Rated Horsepower: 1,600 HP
Performance
Liner Size, inches 7 6-3/4 6-1/2 6 5-1/2 5
5. In normal area, false conductor may be grouted 3 m below cellar pit bottom.
6. In surface seepage prone area, false conductor may be pre-installed to a depth of approximately 15-20 ft below
bottom of cellar pit along with concrete grouting with minimum 1 meter concrete layer at surface.
7. Ensure that all equipment for this hole and casing section (surface casing and casing handling) equipment are
on location.
8. Inspect drill string components as necessary.
9. Ensure availability of GTO at appropriate places on the rig.
10. Ensure that minimum 5-7% pre hydrated bentonite suspension is available for spudding. LCM material must
be available at site for contingency of seepage loss.
11. Hold Pre Spud meeting to short out any discrepancies.
12. Follow the pre-spud Checklist.
13. Any issues prior to spudding must be mitigated to Higher authority.
Preparation:
1. Record clear distance from Rotary Table to bottom of Cellar Pit.
2. Confirm arrangement for cellar pit cleaning is installed and tested.
3. Confirm 9-5/8” Casing and casing handling equipment are on location.
4. Ensure proper diameter of return flow line from conductor to shale shaker is installed.
SN Items No required
1 12 ¼” Bit (TCR/ PDC) As planned
2 12 ¼” Bit Breaker (TCR / PDC) 01 each
3 Circlip nose pliers for nozzles 01
4 Nozzle gauge 01
5 5” Drill Pipe Elevator (250/350 t) 02
6 6 ½”Drill Collar Elevator (150 t) 02
7 8” Drill Collar Elevator(150 t) 02
8 5” Drill Pipe Slip 02
9 6 ½” Drill Collar Slip 02
10 8” Drill Collar Slip 02
11 Bit sub (6 ⅝” RBox X 6 ⅝” RBox) 02
12 X-over (4 ½”IFBox X 6 ⅝” RPin) 02
13 X-over (4” IFBox X 6 ⅝” RPin) 02
14 X-over (4 ½” IFBox X 4” IFPin) 02
15 Kelly saver sub (4½” IFBox X IFPin) 02
16 Drill pipe/ Drill collar dope 02 Buckets
17 12¼” String Stabilizer 03
18 12¼” Near Bit Stabilizer 01
19 Steel Measuring tape 02
20 Core bit 01
21 Core barrel with handling tools 02
22 Safety clamp 01
23 Drill pipe wiper 02
Sequence of Operations:
1. Make up 12-1/4” bit and BHA for spudding. After drilling two singles make up string stabilizer at 18m (60 ft).
2. Install float valve with baffle plate.
3. RIH with the 12-1/4” BHA inside the 20” Conductor.
4. Use a lower flow rate(54-55 spm with liner size 170 mm,stroke length 12 inch.) when drilling around 20” shoe
to avoid wash out of the shoe. In case of severe seepage, discharge is recommended to maintain at lowest.
5. While drilling first 50 m below false conductor, conduct controlled drilling with only one pump or at 50 - 60%
of recommended flow rate to avoid seepage.
6. In the next 30m, flow rate should be increased to recommended flow rate to drill and maintained.
7. Drill ahead to phase target depth with controlled drilling to avoid annulus loading.
8. Viscous sweeps of sufficient volume should be frequently used for drilling this section and monitor the volume
of cuttings coming out to confirm proper hole cleaning.
9. After reaching phase TD, sweep hole with 10 m3 Hi-Vis pill of 120-150 sec viscosity and circulate to clean the
hole.
SOP DRILLING OPERATION
10. Ream if necessary. Check for fill and circulate for hole clean.
11. Wash down last single to avoid plugging of nozzle.
12. Sweep hole with 10m3 Hi-Vis pill of 120-150 sec and circulate until hole is cleaned with recommended flow
rate.
13. Circulate and condition mud. As a general practice place fresh mud of 0.05 SG higher density in well before
pulling out for casing.
16. POOH to run 9-5/8” casing.
Preparation:
1. Ensure all required tools and material are available on the rig.
Preparation:
1. Lay down the previous BHA & 5” DP.
2. Change liners of mud pump, as per requirement.
3. Keep compatible well head test plug ready and Check test plug seals.
4. Keep drilling jar ready, if planned.
5. Keep FOSV and IBOP with required X/O ready in open position on rig floor.
6. Schematic diagram of choke and kill manifold, MGS and positions of choke and manual valves should be
displayed
List of Handling Tools:
SN Items Nos.
1. 6’’ Bit (TCR & PDC) As planned
2. 6’’ Bit Breaker (TCR & PDC) 01each
3. Circlip nose pliers for nozzles 01
4. Nozzle and Bit gauge 01 each
5. 3 ½”Drill Pipe Elevator 02
6. 3½”or 4 ¾”Drill Collar Elevator 02
7. 5” Drill Pipe Elevator 02
8. 3 ½”Drill Pipe Slip 02
9. 5” Drill Pipe Slip 02
10. 4 ¾”Drill Collar Elevator 02
11. Bit sub (3½”IFBox X 3½”RBox) 02
12. Cross-over (4 ½” IFBox X 3½”IFPin) 02
13. Kelly saver sub (4½” IFBox X 4½” IFPin) 02
14. Drill pipe/ Drill collar dope 02
15. Steel Measuring tape 02
16. 3 ½” Drill pipe wiper 02
17. 5” Drill pipe wiper 02
18. Safety clamp 01
SOP DRILLING OPERATION
Sequence of Drilling Operations:
2. Wash down last 3-4 singles where Kelly is used to avoid hole pack-off.
3. Circulate at casing shoe for 1.5 cycles in wiper trips to remove all cuttings from the annulus if pumping out
due to tight pull is a frequent observation.
4. Pump-out in tight portions if required back reaming may be done. Tandem pill sweep to be given
intermittently.
k) Recommended practices to clear pack-off:
To avoid possible pack-off:
1. To prevent annulus loading and consequent packing-off by ensuring that recently drilled cuttings are well
above the BHA length by circulation especially when the ROP is more than 25-30 meters per hour.
2. In case of pack off, stop pump. Continuous pumping will lead to formation break down and stop all chances
of establishing circulation.
3. Come up with running in hole and establish circulation and try to go down while pulling out of hole.
4. Try to reciprocate the string, hydraulic hammering i.e., bleed the trapped pressure and again pressurize 200-
500psi to physically dislodge the packed cuttings. Intermittently try establishing circulation.
SOP DRILLING OPERATION