Sei sulla pagina 1di 5

DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME

Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
783 30-Dec-19 29-Dec-22
DC04 DMRC_DC04- Construction Schedule
DC04.1 Contract Award 0 30-Dec-19 30-Dec-19 30-Dec-19, DC04.1 ContractAward

NTP Notice to proceed 0 30-Dec-19 30-Dec-19 Notice to proceed

DC04.KD Key Dates ( Milestones) 1067 27-Jan-20 29-Dec-22

DC04.KD.1 Key Dates For Complete Viaduct including Viaduct in Station portion as per Appendix-2B 1067 27-Jan-20 29-Dec-22
V-KD-8 (i) (i) Partial Access of the Viaduct including in stations area 0 14-Dec-20
V-KD-8 (ii) (ii) Partial Access of the Viaduct including in stations area for next 2.0 Km (min.) 0 31-May-21
V-KD-8 (iii) (iii) Full Access of the Viaduct including in stations area to Track contractor for laying track. 0 29-Nov-21
V-KD-2 Commissioning of 1st Batching Plant (production of 1st batch of concrete) 0 10-Feb-20 Commissioning of 1st Batching Plant (production of 1st batch of concrete),
V-KD-5 Commissioning of 2nd Batching Plant 0 23-Mar-20 Commissioning of 2nd Batching Plant,
V-KD-6 Completion of 1st working pile 0 13-Apr-20
V-KD-4 Completion of 1st Formwork for precast U – girder element of production line for Engineer’s approval 0 23-Mar-20 Completion of 1st Formwork for precast U – girder element of production line for Engineer’s approval,
V-KD-910 Completion of entire works as per the Contract 0 29-Dec-22
V-KD-7 Erection of 1st U-Girder 0 13-Jul-20
V-KD-9 Full Access to system contractors including G.I Hangers for laying of ables 0 18-Apr-22
V-KD-1 Submission of construction programme 0 27-Jan-20 Submission of construction programme,
V-KD-3 Submission of Definitive Design 0 09-Mar-20 Submission of Definitive Design,
DC04.KD.2 Key Dates For Stations as per Appendix-2B-1 1053 10-Feb-20 29-Dec-22
S-KD-4.1 Access to lift shaft & Escalator pits For first Twostation 0 22-Feb-21
S-KD-4.2 Access to lift shaft & Escalator pits For next Two stations 0 29-Nov-21
S-KD-6.1 Access to PEB contractor for erection of roof structure For first station 0 22-Mar-21
S-KD-7 Access to PEB contractor for erection of roof structure For last station 0 29-Dec-22
S-KD-6.2 Access to PEB contractor for erection of roof structure For next Two stations 0 18-Oct-21
S-KD-2 Completion of 1st Formwork for precast elements i.e. Cross arm, π Girder, Cross beam for Engineer’s approval 0 23-Mar-20 Completion of 1st Formwork for precast elements i.e. Cross arm, π Girder, Cross beam for Engineer’s approval,
S-KD-5.1 Completion of structure works of one Entry/Exit For first Two station 0 07-Jun-21
S-KD-5.2 Completion of structure works of one Entry/Exit For nextTwo stations 0 20-Sep-21
S-KD-3.1 Partial access to finishing contractor in operational rooms For first station 0 20-Sep-21
S-KD-3.3 Partial access to finishing contractor in operational rooms For last station 0 18-Apr-22
S-KD-3.2 Partial access to finishing contractor in operational rooms For next Two stations 0 07-Feb-22
S-KD-1 Submission of Definitive Design 0 10-Feb-20 Submission of Definitive Design,
DC04.KD.3 Key Dates For Integrated Elevated Viaduct and Underpass: as per Appendix-2B-1 1053 10-Feb-20 29-Dec-22
IEV-KD-8 (i) (i) Completion of structural work of the flyover (minimum 1.0 Km in one stretch) 0 10-Aug-20
IEV-KD-8 (ii) (ii) Completion of structural work of the flyover (minimum 2.0 Km in one stretch) 0 12-Jul-21
IEV-KD-8 (iii) (iii) Full completion of structural work of the flyover including approaches 0 29-Nov-21
IEV-KD-9 Complete work of Flyover including Bituminous Carpeting/wearing coat 0 27-Jun-22
IEV-KD-910 Completion of entire works as per the Contract. 0 29-Dec-22
IEV-KD-4 Completion of 1st Formwork for precast I – girder element of production line for Engineer’s approval 0 20-Apr-20
IEV-KD-5 Erection of 1st I-Girder 0 10-Aug-20
IEV-KD-1 Submission of construction programme 0 10-Feb-20 Submission of construction programme,
IEV-KD-3 Submission of Definitive Design 0 23-Mar-20 Submission of Definitive Design,
IEV-KD-2 Submission of preliminary Design 0 24-Feb-20 Submission of preliminary Design,

DC04.EMP Employer Obligation 41 30-Dec-19 09-Feb-20 09-Feb-20, DC04.EMP Employer Obligation

DC04.EMP.LHO Employer's Obligation- Land Handing Over 7 30-Dec-19 06-Jan-20 06-Jan-20, DC04.EMP.LHO Employer's Obligation- Land Handing Over
A1070 Land Handing over for Integrated Flyover Viauduct 7 30-Dec-19 06-Jan-20 Land Handing over for Integrated Flyover Viauduct
A1060 Land Handing over for Stations 7 30-Dec-19 06-Jan-20 Land Handing over for Stations
A1050 Land Handing over for Viaduct 7 30-Dec-19 06-Jan-20 Land Handing over for Viaduct
DC04.EMP.DRW Employer's Obligation- Issuing of Super Structure Drawing for Viaduct 10 30-Dec-19 09-Jan-20 09-Jan-20, DC04.EMP.DRW Employer's Obligation- Issuing of Super Structure Drawing for Viaduct
EMP.DRW.4 Issuing GFC drawing of Bearing GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of Bearing GA & Reinfocement
EMP.DRW.3 Issuing GFC drawing of Crash barrier GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of Crash barrier GA & Reinfocement
EMP.DRW.1 Issuing GFC drawing of Pier Cap GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of Pier Cap GA & Reinfocement
EMP.DRW.2 Issuing GFC drawing of U Girder GA & Reinfocement 10 30-Dec-19 09-Jan-20 Issuing GFC drawing of U Girder GA & Reinfocement
DC04.EMP.UTI Employer's Obligation-Permission for diversion of utilities 15 01-Jan-20 16-Jan-20 16-Jan-20, DC04.EMP.UTI Employer's Obligation-Permission for diversion of utilities
UTI10 Permission for diversion of Civil utilties 15 01-Jan-20 16-Jan-20 Permission for diversion of Civil utilties
UTI Permission for diversion of Electric utilties 15 01-Jan-20 16-Jan-20 Permission for diversion of Electric utilties
UTI20 Permission for diversion of Uncharted utilties 15 01-Jan-20 16-Jan-20 Permission for diversion of Uncharted utilties
DC04.EMP.DIV Employer's Obligation- Diversion of Utlities 30 10-Jan-20 09-Feb-20 09-Feb-20, DC04.EMP.DIV Employer's Obligation- Diversion of Utliti es
A1010 Diversion of Other uncharted Utilities 30 10-Jan-20 09-Feb-20 Diversion of Other uncharted Utilities
A1000 Diversion of Overhead HT Line 30 10-Jan-20 09-Feb-20 Diversion of Overhead HT Line
DC04.EMP.TC Employer's Obligation- Permission for Tree cutting 10 01-Jan-20 11-Jan-20 11-Jan-20, DC04.EMP.TC Employer's Obligation- Permission for Tree cutting
A1040 Permission for tree cutting in Integrated Flyover Viaduct 10 01-Jan-20 11-Jan-20 Permission for tree cutting in Integrated Flyover Viaduct
A1030 Permission for tree cutting in Station 10 01-Jan-20 11-Jan-20 Permission for tree cutting in Station
A1020 Permission for tree cutting in Viaduct including th tation viduct 10 01-Jan-20 11-Jan-20 Permission for tree cutting in Viaduct including th tation viduct

DC04.PL Preliminaries work 115 30-Dec-19 08-Jun-20

DC04.PL.SUB Contractual Submission 12 30-Dec-19 11-Jan-20 11-Jan-20, DC04.PL.SUB Contractual Submission


CONT-40 Submission of BOCW registration 1 30-Dec-19 31-Dec-19 Submission of BOCW registration
CONT-30 Submission of CAR Policy 1 30-Dec-19 31-Dec-19 Submission of CAR Policy
CONT-20 Submission of Insurances 1 10-Jan-20 11-Jan-20 Submission of Insurances
CONT-50 Submission of Labour Registration 1 30-Dec-19 31-Dec-19 Submission of Labour Registration
CONT-10 Submission of Performance Security 1 10-Jan-20 11-Jan-20 Submission of Performance Security
CONT-60 Submission of PII 1 30-Dec-19 31-Dec-19 Submission of PII
DC04.PL.GEN General Item Submission 33 27-Jan-20 29-Feb-20 29-Feb-20, DC04.PL.GEN General Item Submission
GEN-30 Poject Environment Management Plan 1 28-Feb-20 29-Feb-20 Poject Environment Management Plan
GEN-20 Poject Quality Plan 1 28-Feb-20 29-Feb-20 Poject Quality Plan
GEN-10 Project SHE Plan 1 28-Feb-20 29-Feb-20 Project SHE Plan
GEN-40 Submission of Construction Program 0 27-Jan-20 27-Jan-20 Submission of Construction Program
GEN-50 Submission of Traffic Management Plan 1 29-Jan-20 30-Jan-20 Submission of Traffic Management Plan
DC04.PL.VP Submission of Vendor Profile 146 14-Jan-20 08-Jun-20
VP-10 Submission of Vendor Profile for DDC 10 29-Jan-20 08-Feb-20 Submission of Vendor Profile for DDC
VP-60 Submission of Vendor Profile for Diversion of utilities 1 07-Jun-20 08-Jun-20
VP-70 Submission of Vendor Profile for DIversion of utilities 1 07-Jun-20 08-Jun-20
VP-20 Submission of Vendor Profile for Geotech Investigation agency 1 14-Jan-20 15-Jan-20 Submission of Vendor Profile for Geotech Investigation agency
VP-50 Submission of Vendor Profile for PileAgency 1 03-Feb-20 04-Feb-20 Submission of Vendor Profile for PileAgency
VP-30 Submission of Vendor Profile for Survey agency 1 14-Jan-20 15-Jan-20 Submission of Vendor Profile for Survey agency
VP-40 Submission of Vendor Profile for Temporary structure Designer 1 14-Jan-20 15-Jan-20 Submission of Vendor Profile for Temporary structure Designer
DC04.PL.FORM Submission of Shop Drawing for formwork 45 26-Jan-20 11-Mar-20 11-Mar-20, DC04.PL.FORM Submission of Shop Drawing for formwork
DC04.PL.1 Mobilization, General Activities & Site Installations 106 06-Jan-20 02-Jun-20
DC04.PL.1.1 Mobilization 66 06-Jan-20 07-Apr-20
DC04.PL.1.1.1.1. Survey Work 53 14-Jan-20 07-Mar-20 07-Mar-20, DC04.PL.1.1.1.1. Survey Work
SURVEY-20 Checking of Control Points 30 14-Jan-20 13-Feb-20 Checking of Control Points
SURVEY-30 Construction of Control Point Pillars 30 14-Jan-20 13-Feb-20 Construction of Control Point Pillars
SURVEY-10 Control Points from DMRC 5 14-Jan-20 19-Jan-20 Control Points from DMRC
SURVEY-50 Submission of Survey report 7 29-Feb-20 07-Mar-20 Submission of Survey report
SURVEY-40 Topographical Survey 45 14-Jan-20 28-Feb-20 Topographical Survey
DC04.PL.1.1.2 Geotech Investigation 79 15-Jan-20 03-Apr-20 03-Apr-20, DC04.PL.1.1.2 Geotech Investigation
GI-30 Lab test and inetrpretation 60 24-Jan-20 24-Mar-20 Lab test and inetrpretation
GI-10 Mobilisation of Soil Investigation Setup 7 15-Jan-20 22-Jan-20 Mobilisation of Soil Investigation Setup
GI-40 Result and report analysis 60 27-Jan-20 27-Mar-20 Result and report analysis
GI-20 Soil Investigation work at each bore hole location 60 17-Jan-20 17-Mar-20 Soil Investigation work at each bore hole location
GI-50 Subission of Geotech Investigation report ( Ful ) 7 27-Mar-20 03-Apr-20 Subission of Geotech Investigation report ( Ful )
DC04.PL.1.1.3 Installation 66 06-Jan-20 07-Apr-20
INST-80 Batching plant No.1 Calibration and Lab trial Mix 1 09-Feb-20 10-Feb-20 Batching plant No.1 Calibration and Lab trial Mix
INST-91 Batching plant No.2 calibration and Lab trial mix 2 20-Mar-20 22-Mar-20 Batching plant No.2 calibration and Lab trial mix
INST-96 COnstrcution of Internal Road at casting yard 65 02-Feb-20 07-Apr-20
INST-60 Construction of Cement Godown 34 06-Jan-20 09-Feb-20 Construction of Cement Godown
INST-30 Construction of Engineers Office 60 13-Jan-20 13-Mar-20 Construction of Engineers Office
INST-50 Construction of Lab with Equipment (As per Appendix-11) 60 14-Jan-20 14-Mar-20 Construction of Lab with Equipment (As per Appendix-11)
INST-20 Construction of Site Office 60 13-Jan-20 13-Mar-20 Construction of Site Office
INST-40 Construction of Site Store 60 20-Jan-20 20-Mar-20 Construction of Site Store
INST-11 Fencing Work at casting Yard 30 20-Jan-20 02-Mar-20 Fencing Work at casting Yard
INST-70 Installation of 1st Batching Plant 34 06-Jan-20 09-Feb-20 Installation of 1st Batching Plant
INST-90 Installation of 2nd Batching Plant 30 19-Feb-20 20-Mar-20 Installation of 2nd Batching Plant
INST-92 Installation of Chiller water Plant 30 19-Feb-20 20-Mar-20 Installation of Chiller water Plant
INST-95 Installation of Fabrication Yard 60 28-Jan-20 28-Mar-20 Installation of Fabrication Yard
INST-10 Installation of Initial Site Establishment 7 06-Jan-20 13-Jan-20 Installation of Initial Site Establishment
INST-93 Installation of RO Plant 12 28-Jan-20 09-Feb-20 Installation of RO Plant

Actual Level of Effort Remaining Work Milestone Page 1 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
INST-94 Installation of STeel Yard 60 28-Jan-20 28-Mar-20 Installation of STeel Yard
DC04.PL.1.4 CastingYard Setup 89 20-Jan-20 18-Apr-20
DC04.PL.1.4.1 Bay 1 73 20-Jan-20 02-Apr-20 02-Apr-20, DC04.PL.1.4.1 Bay 1
B1-05 Area Marking for Bay 12 1 20-Jan-20 21-Jan-20 Area Marking for Bay 12
B1-50 Concreting Work for Gantry foundation 55 02-Feb-20 28-Mar-20 Concreting Work for Gantry foundation
B1-70 EOT Gantry Installation 10 19-Feb-20 29-Feb-20 EOT Gantr y Installation
B1-10 Excavation for Gantry foundation 10 23-Jan-20 02-Feb-20 Excavation for Gantry foundation
B1-40 Formwork for Gantry foundation 55 31-Jan-20 26-Mar-20 Formwork for Gantry foundation
B1-80 Laying GSB at casting Bed 35 09-Feb-20 15-Mar-20 Laying GSB at casting Bed
B1-90 Laying RMC at Casting Bed 35 11-Feb-20 17-Mar-20 Laying RMC at Casting Bed
B1-20 PCC for Gantry foundation 15 25-Jan-20 09-Feb-20 PCC for Gantry foundation
B1-60 Rail FIxing Work for Gantry foundation 50 12-Feb-20 02-Apr-20 Rail FIxing Work for Gantry foundation
B1-30 Reinforcement work for Gantry foundation 55 27-Jan-20 22-Mar-20 Reinforcement work for Gantry foundation
DC04.PL.1.4.2 Bay -2 73 20-Jan-20 02-Apr-20 02-Apr-20, DC04.PL.1.4.2 Bay -2
B2-100 Area Marking for Bay 12 1 20-Jan-20 21-Jan-20 Area Marking for Bay 12
B2-150 Concreting Work for Gantry foundation 55 02-Feb-20 28-Mar-20 Concreting Work for Gantry foundation
B2-170 EOT Gantry Installation 10 19-Feb-20 29-Feb-20 EOT Gantr y Installation
B2-110 Excavation for Gantry foundation 10 23-Jan-20 02-Feb-20 Excavation for Gantry foundation
B2-140 Formwork for Gantry foundation 55 31-Jan-20 26-Mar-20 Formwork for Gantry foundation
B2-180 Laying GSB at casting Bed 35 09-Feb-20 15-Mar-20 Laying GSB at casting Bed
B2-190 Laying RMC at Casting Bed 35 11-Feb-20 17-Mar-20 Laying RMC at Casting Bed
B2-120 PCC for Gantry foundation 15 25-Jan-20 09-Feb-20 PCC for Gantry foundation
B2-160 Rail FIxing Work for Gantry foundation 50 12-Feb-20 02-Apr-20 Rail FIxing Work for Gantry foundation
B2-130 Reinforcement work for Gantry foundation 55 27-Jan-20 22-Mar-20 Reinforcement work for Gantry foundation

DC04.PL.1.4.3 Bay -3 73 05-Feb-20 18-Apr-20


B3-200 Area Marking for Bay 12 1 05-Feb-20 06-Feb-20 Area Marking for Bay 12
B3-250 Concreting Work for Gantry foundation 55 18-Feb-20 13-Apr-20
B3-270 EOT Gantry Installation 10 06-Mar-20 16-Mar-20 EOT Gantr y Installation
B3-210 Excavation for Gantry foundation 10 08-Feb-20 18-Feb-20 Excavation for Gantry foundation
B3-240 Formwork for Gantry foundation 55 16-Feb-20 11-Apr-20
B3-280 Laying GSB at casting Bed 35 25-Feb-20 31-Mar-20 Laying GSB at casting Bed
B3-290 Laying RMC at Casting Bed 35 27-Feb-20 02-Apr-20 Laying RMC at Casting Bed
B3-220 PCC for Gantry foundation 15 10-Feb-20 25-Feb-20 PCC for Gantry foundation
B3-260 Rail FIxing Work for Gantry foundation 50 28-Feb-20 18-Apr-20
B3-230 Reinforcement work for Gantry foundation 55 12-Feb-20 07-Apr-20
DC04.PL.1.5 Supply & Installation of Production Bed 95 21-Jan-20 02-Jun-20
DC04.PL.1.5.9 Design & Drawing of Fabricaion for U Girder 45 21-Jan-20 06-Mar-20 06-Mar-20, DC04.PL.1.5.9 Design & Drawing of Fabricaion for U Girder
FAB-41 Submision fo design and Formwork Drawing for Cross Arm & Beam 7 28-Feb-20 06-Mar-20 Submision fo design and Formwork Drawing for Cross Arm & Beam
FAB-21 Submision fo design and Formwork Drawing for Flyover Box Girder 7 25-Feb-20 03-Mar-20 Submision fo design and Formwork Drawing for Flyover Box Girder
FAB-11 Submision fo design and Formwork Drawing for Pier Cap 7 04-Feb-20 11-Feb-20 Submision fo design and Formwork Drawing for Pier Cap
FAB-31 Submision fo design and Formwork Drawing for TT Girder 7 11-Feb-20 18-Feb-20 Submision fo design and Formwork Drawing for TT Girder
FAB-1 Submision for design and Formwork Drawing for U Girder 7 21-Jan-20 28-Jan-20 Submision for design and Formwork Drawing for U Girder
DC04.PL.1.5.1 Mould Bed - 1 for U Girder 40 28-Jan-20 23-Mar-20 23-Mar-20, DC04.PL.1.5.1 Mould Bed - 1 for U Girder
DC04.PL.1.5.1.1 Fabrication of Mould Bed-1 41 31-Jan-20 12-Mar-20 12-Mar-20, DC04.PL.1.5.1.1 Fabrication of Mould Bed-1
NB-1 Bottom Frame 6 31-Jan-20 06-Feb-20 Bottom Frame
NB-41 Frame/Trolly for Inner Shutter 5 26-Feb-20 02-Mar-20 Frame/Trolly for Inner Shutter
NB-31 Inner Side Shutter 5 21-Feb-20 26-Feb-20 Inner Side Shutter
NB-61 Lifter Beam for Reinforcement 5 07-Mar-20 12-Mar-20 Lifter Beam for Reinforcement
NB-21 Outer side shutter 5 16-Feb-20 21-Feb-20 Outer side shutter
NB-11 Soffit 10 06-Feb-20 16-Feb-20 Soffit
NB-51 Zig Fabrication 5 02-Mar-20 07-Mar-20 Zig Fabrication
DC04.PL.1.5.1.2 Installation of Mould. Bed-1 40 28-Jan-20 23-Mar-20 23-Mar-20, DC04.PL.1.5.1.2 Installation of Mould. Bed-1
IM-41 Beam Casting 23 28-Feb-20 22-Mar-20 Beam Casting
IM-51 Erection & assembly of fabricated Moulds 23 29-Feb-20 23-Mar-20 Erection & assembly of fabricated Moulds
IM-11 Excavation 2 11-Feb-20 13-Feb-20 Excavation
IM-21 PCC 2 14-Feb-20 16-Feb-20 PCC
IM-32 Pile Cap 12 24-Feb-20 10-Mar-20 Pile Cap
IM-31 Pile Chipping 4 16-Feb-20 20-Feb-20 Pile Chipping
IM-1 Piling Work 10 28-Jan-20 07-Feb-20 Piling Work
DC04.PL.1.5.2 Mould Bed - 2 for U Girder 40 09-Feb-20 05-Apr-20
DC04.PL.1.5.2.1 Fabrication of Mould Bed-2 41 10-Feb-20 22-Mar-20 22-Mar-20, DC04.PL.1.5.2.1 Fabrication of Mould Bed-2
NB-211 Bottom Frame 6 10-Feb-20 16-Feb-20 Bottom Frame
NB-251 Frame/Trolly for Inner Shutter 5 07-Mar-20 12-Mar-20 Frame/Trolly for In ner Shutter
NB-241 Inner Side Shutter 5 02-Mar-20 07-Mar-20 Inner Side Shutter
NB-271 Lifter Beam for Reinforcement 5 17-Mar-20 22-Mar-20 Lifter Beam for Reinforcement
NB-231 Outer side shutter 5 26-Feb-20 02-Mar-20 Outer side shutter
NB-221 Soffit 10 16-Feb-20 26-Feb-20 Soffit
NB-261 Zig Fabrication 5 12-Mar-20 17-Mar-20 Zig Fabrication
DC04.PL.1.5.2.2 Installation of Mould Bed-2 40 09-Feb-20 05-Apr-20
IM-9111 Beam Casting 23 12-Mar-20 04-Apr-20 Beam Casting
IM-9121 Erection & assembly of fabricated Moulds 23 13-Mar-20 05-Apr-20
IM-71 Excavation 2 23-Feb-20 25-Feb-20 Excavation
IM-81 PCC 2 26-Feb-20 28-Feb-20 PCC
IM-9101 Pile Cap 12 05-Mar-20 23-Mar-20 Pile Cap
IM-91 Pile Chipping 4 28-Feb-20 03-Mar-20 Pile Chipping
IM-61 Piling Work 10 09-Feb-20 19-Feb-20 Piling Work
DC04.PL.1.5.3 Mould Bed - 1 for Box Girder 40 24-Feb-20 20-Apr-20
DC04.PL.1.5.3.1 Fabrication of Mould Bed-1 41 26-Feb-20 07-Apr-20
NB-281 Bottom Frame 6 26-Feb-20 03-Mar-20 Bottom Frame
NB-321 Frame/Trolly for Inner Shutter 5 23-Mar-20 28-Mar-20 Frame/Trolly for In ner Shutter
NB-311 Inner Side Shutter 5 18-Mar-20 23-Mar-20 Inner Side Shutter
NB-341 Lifter Beam for Reinforcement 5 02-Apr-20 07-Apr-20
NB-301 Outer side shutter 5 13-Mar-20 18-Mar-20 Outer side shutter
NB-291 Soffit 10 03-Mar-20 13-Mar-20 Soffit
NB-331 Zig Fabrication 5 28-Mar-20 02-Apr-20 Zig Fabrication
DC04.PL.1.5.3.2 Installation of Mould. Bed-1 40 24-Feb-20 20-Apr-20
IM-9181 Beam Casting 23 27-Mar-20 19-Apr-20
IM-9191 Erection & assembly of fabricated Moulds 23 28-Mar-20 20-Apr-20
IM-9141 Excavation 2 09-Mar-20 11-Mar-20 Excavation
IM-9151 PCC 2 12-Mar-20 14-Mar-20 PCC
IM-9171 Pile Cap 12 20-Mar-20 07-Apr-20
IM-9161 Pile Chipping 4 14-Mar-20 18-Mar-20 Pile Chipping
IM-9131 Piling Work 10 24-Feb-20 05-Mar-20 Piling Work
DC04.PL.1.5.4 Mould Bed - 2 for Box Girder 47 03-Mar-20 07-May-20
DC04.PL.1.5.4.1 Fabrication of Mould Bed-2 41 03-Mar-20 13-Apr-20
NB-351 Bottom Frame 6 03-Mar-20 09-Mar-20 Bottom Frame
NB-391 Frame/Trolly for Inner Shutter 5 29-Mar-20 03-Apr-20 Frame/Trolly for Inner Shutter
NB-381 Inner Side Shutter 5 24-Mar-20 29-Mar-20 Inner Side Shutter
NB-411 Lifter Beam for Reinforcement 5 08-Apr-20 13-Apr-20
NB-371 Outer side shutter 5 19-Mar-20 24-Mar-20 Outer side shutter
NB-361 Soffit 10 09-Mar-20 19-Mar-20 Soffit
NB-401 Zig Fabrication 5 03-Apr-20 08-Apr-20
DC04.PL.1.5.4.2 Installation of Mould Bed-2 40 12-Mar-20 07-May-20
IM-9251 Beam Casting 23 13-Apr-20 06-May-20
IM-9261 Erection & assembly of fabricated Moulds 23 14-Apr-20 07-May-20
IM-9211 Excavation 2 26-Mar-20 28-Mar-20 Excavation
IM-9221 PCC 2 29-Mar-20 31-Mar-20 PCC
IM-9241 Pile Cap 12 06-Apr-20 22-Apr-20
IM-9231 Pile Chipping 4 31-Mar-20 04-Apr-20 Pile Chipping
IM-9201 Piling Work 10 12-Mar-20 22-Mar-20 Piling Work
DC04.PL.1.5.5 Mould Bed for Precast Pier cap 52 11-Feb-20 03-Apr-20 03-Apr-20, DC04.PL.1.5.5 Mould Bed for Precast Pier cap
A1090 Casting of Bed 30 11-Feb-20 12-Mar-20 Casting of Bed
A1080 Fabrication of Shutter 45 11-Feb-20 27-Mar-20 Fabrication of Shutter
A1100 Installation of Bed 7 27-Mar-20 03-Apr-20 Installation of Bed
DC04.PL.1.5.6 Mould Bed for Precast Π Girder 105 18-Feb-20 02-Jun-20
A1120 Casting of Bed 45 18-Feb-20 03-Apr-20 Casting of Bed
A1110 Fabrication of Shutter 90 18-Feb-20 18-May-20

Actual Level of Effort Remaining Work Milestone Page 2 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
A1130 Installation of Bed 90 04-Mar-20 02-Jun-20
DC04.PL.1.5.7 Mould Bed for Precast Cross Arm and Beam 52 06-Mar-20 27-Apr-20
A1180 Casting of Bed 30 06-Mar-20 05-Apr-20
A1170 Fabrication of Shutter 45 06-Mar-20 20-Apr-20
A1190 Installation of Bed 7 20-Apr-20 27-Apr-20
DC04.PL.1.5.8 Mould Bed for Precast Flyover Pier cap 45 06-Mar-20 20-Apr-20
A1150 Casting of Bed 30 06-Mar-20 05-Apr-20
A1140 Fabrication of Shutter 45 06-Mar-20 20-Apr-20
A1160 Installation of Bed 7 05-Apr-20 12-Apr-20
DC04.5 Submission of Method Statement 5 30-Dec-19 06-Jan-20 06-Jan-20, DC04.5 Submission of Method Statement

DC04.5.1 Submission of Method Statement 5 30-Dec-19 06-Jan-20 06-Jan-20, DC04.5.1 Submission of Method Statement
A1220 Submission of MS for Flyover 5 30-Dec-19 06-Jan-20 Submission of MS for Flyover
A1210 Submission of MS for Station 5 30-Dec-19 06-Jan-20 Submission of MS for Station
A1200 Submission of MS for Viaduct 5 30-Dec-19 06-Jan-20 Submission of MS for Viaduct
DC04.5.2 Approval of Method Statement 5 30-Dec-19 06-Jan-20 06-Jan-20, DC04.5.2 Approval of Method Statement
A1240 Approval of MS for Station 5 30-Dec-19 06-Jan-20 Approval of MS for Station
A1250 Approval of MS for Flyover 5 30-Dec-19 06-Jan-20 Approval of MS for Flyover
A1230 Approval of MS for Viaduct 5 30-Dec-19 06-Jan-20 Approval of MS for Viaduct

DC04.6 Initial Pile Load test 194 27-Jan-20 08-Aug-20

DC04.6.1 Initial Pile Load test for Viaduct 57 13-Apr-20 09-Jun-20


A1270 Load Test-01 2 23-Apr-20 25-Apr-20
A1290 Load Test-02 2 07-Jun-20 09-Jun-20
A1260 Test Pile 01 0 13-Apr-20 13-Apr-20
A1280 Test Pile 02 0 28-May-20 28-May-20
DC04.6.3 Initial Pile Load test for Stations 172 18-Feb-20 08-Aug-20
A1350 Load Test-01- Sangam Vihar 2 28-Feb-20 01-Mar-20 Load Test-01- Sangam Vihar
A1370 Load Test-02 - Abedkar Nagar 2 07-Jun-20 09-Jun-20
A1390 Load Test-03 - -Khanpur 2 07-Jul-20 09-Jul-20
A1410 Load Test-04- Saket G 2 06-Aug-20 08-Aug-20
A1340 Test Pile 01 - Sangam Vihar 0 18-Feb-20 18-Feb-20 Test Pile 01 - Sangam Vihar
A1360 Test Pile 02 -Abedkar Nagar 0 28-May-20 28-May-20
A1380 Test Pile 03 -Khanpur 0 27-Jun-20 27-Jun-20
A1400 Test Pile 03- Saket G 0 27-Jul-20 27-Jul-20
DC04.6.2 Initial Pile Load test for Integrated Flyover with Viaduct 104 27-Jan-20 10-May-20
A1310 Load Test-01 2 06-Feb-20 08-Feb-20 Load Test-01
A1330 Load Test-02 2 08-May-20 10-May-20
A1300 Test Pile 01 0 27-Jan-20 27-Jan-20 Test Pile 01
A1320 Test Pile 02 0 28-Apr-20 28-Apr-20
DC04.9 Design and Drawing 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9 Design and Drawing

DC04.9.10 Design Submission 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.10 Design Submission


DC04.9.10.Design Submission of design and drawing for For Complete Viaduct including Viaduct in Station portion: 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.10.Design Submission of design and drawing for For Complete Viaduct including Viaduct in Station portion:
A1620 Eleavted ramp -01 2 30-Dec-19 31-Dec-19 Eleavted ramp -01
A1690 Eleavted ramp -02 2 30-Dec-19 31-Dec-19 Eleavted ramp -02
A1610 Other Misc work 2 30-Dec-19 31-Dec-19 Other Misc work
A1580 Pier 2 30-Dec-19 31-Dec-19 Pier
A1560 Pile 2 30-Dec-19 31-Dec-19 Pile
A1570 Pile Cap 2 30-Dec-19 31-Dec-19 Pile Cap
A1590 Porta Beam 2 30-Dec-19 31-Dec-19 Porta Beam
A1600 Steel Span 2 30-Dec-19 31-Dec-19 Steel Span
DC04.9.10.2 Submission of design and drawing for Stations 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.10.2 Submission of design and drawing for Stations
DC04.9.10.1 Submission of design and drawing for Integrated Elevated Viaduct andUnderpass: 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.10.1 Submission of design and drawing for Integrated Elevated Viaductand Underpass:
DC04.9.2 Design Approval 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.2 Design Approval
DC04.9.2.Design Approval of design and drawingfor For Complete Viaduct including Viaduct in Station portion: 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.2.Design Approval of design and drawing for For Complete Viaduct including Viaduct in Station portion:
DC04.9.2.2 Approval of design and draw ing for Stations 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.2.2 Approval of design and drawing for Stations
DC04.9.2.1 Approval of design and draw ing for Integrated Elevated Viaduct and Underpass: 2 30-Dec-19 31-Dec-19 31-Dec-19, DC04.9.2.1 Approval of design and drawing for Integrated Elevated Viaduct and Underpass:
DC04.7 Construction Work 0

DC04.7.1 Precast Work 0


DC04.7.1.1 Precasting work for U-Girder for viaduct and Stations 0
DC04.7.1.3 Precasting work for Pier Cap 0
DC04.7.1.2 Precasting work for Cross-arms for PWD flyover 0
DC04.7.1.5 Precasting work for I Girder for Viaduct Non Standard Span 0
DC04.7.1.4 Precasting work for Post stress Girder for PWD Flyover 0
DC04.7.1.7 Precasting work for Cross arm for station 0
DC04.7.1.6 Precasting work for Π girder for station 0
DC04.7.8 Construction Work 0
DC04.7.8.2 CONSTRUCTION WORK FOR VIADUCT, EMERGENCY SIDING LINE, ELEVATED RAMP & SPECIALSPANS 0
DC04.7.8.2.2 Viaduct 0
DC04.7.8.2.2.Sec. 1 Viaduct Section 1 0
DC04.7.8.2.2.Sec. 1.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.2.2.Sec. 1.6 Barricading Work 0
DC04.7.8.2.2.Sec. 1.2 Utilities Identification Work 0
DC04.7.8.2.2.Sec. 1.3 Utility Diversion Work if any byYFC 0
DC04.7.8.2.2.Sec. 1.7 Utility Diversion Work if any byDMRC 0
DC04.7.8.2.2.Sec. 1.4 Dismantling Work i.e. Light Poles, Road Median, Railing etc. 0
DC04.7.8.2.2.Sec. 1.5 Clearing and Grabbing work 0
DC04.7.8.2.2.Sec. 1.8 Installation of working piles 0
DC04.7.8.2.2.Sec. 1.9 Construction of Pile Caps 0
DC04.7.8.2.2.Sec. 1.10 Construction of Pier 0
DC04.7.8.2.2.Sec. 1.21 Construction of Pier - 1st lift in Station and Flyover Portion 0
DC04.7.8.2.2.Sec. 1.23 Construction of Cast in Situ Pier Cap 0
DC04.7.8.2.2.Sec. 1.22 Construction of Pier 2 nd Lift at Station and FLyover Portion 0
DC04.7.8.2.2.Sec. 1.11 Production of Precast Pier Cap 0
DC04.7.8.2.2.Sec. 1.12 Erection of Precast Pier Cap 0
DC04.7.8.2.2.Sec. 1.13 Bearing fixing work 0
DC04.7.8.2.2.Sec. 1.14 Production of U Girder (Precast U Girder) 0
DC04.7.8.2.2.Sec. 1.15 Erection U Girder (Precast U Girder) 0
DC04.7.8.2.2.Sec. 1.16 Cable tray & OHE Insert 0
DC04.7.8.2.2.Sec. 1.17 Expansion Joint 0
DC04.7.8.2.2.Sec. 1.18 Restoration of Median 0
DC04.7.8.2.2.Sec. 1.19 Rain Water Harvesting Work 0
DC04.7.8.2.2.Sec. 1.20 Anti Carbonation paint 0
DC04.7.8.2.2.Sec 2 Viaduct Section 2 0
DC04.7.8.2.2.Sec 2.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.2.2.Sec 2.6 Barricading Work 0
DC04.7.8.2.2.Sec 2.2 Utilities Identification Work 0
DC04.7.8.2.2.Sec 2.3 Utility Diversion Work if any byYFC 0
DC04.7.8.2.2.Sec 2.7 Utility Diversion Work if any by DMRC 0
DC04.7.8.2.2.Sec 2.4 Dismantling Work i.e. Light Poles, RoadMedian, Railing etc. 0
DC04.7.8.2.2.Sec 2.5 Clearing and Grabbing work 0
DC04.7.8.2.2.Sec 2.8 Installation of working piles 0
DC04.7.8.2.2.Sec 2.9 Construction of Pile Caps 0
DC04.7.8.2.2.Sec 2.10 Construction of Pier 0
DC04.7.8.2.2.Sec 2.25 Construction of Pier 2 nd Lift at Station and FLyover Portion 0
DC04.7.8.2.2.Sec 2.24 Construction of Cast in Situ Pier Cap 0
DC04.7.8.2.2.Sec 2.23 Construction of Pier - 1st lift in Station and Flyover Portion 0
DC04.7.8.2.2.Sec 2.11 Production of Precast Pier Cap 0
DC04.7.8.2.2.Sec 2.12 Erection of Precast Pier Cap 0
DC04.7.8.2.2.Sec 2.13 Bearing fixing work 0
DC04.7.8.2.2.Sec 2.14 Production of U Girder (Precast U Girder) 0
DC04.7.8.2.2.Sec 2.15 Erection U Girder (Precast U Girder) 0
DC04.7.8.2.2.Sec 2.16 Cable tray & OHE Insert 0
DC04.7.8.2.2.Sec 2.17 Expansion Joint 0
DC04.7.8.2.2.Sec 2.18 Restoration of Median 0
DC04.7.8.2.2.Sec 2.19 Rain Water Harvesting Work 0
DC04.7.8.2.2.Sec 2.20 Anti Carbonation paint 0
DC04.7.8.2.2.3 Viaduct Section 3 - 0
DC04.7.8.2.2.3.1 Hindrance free Area handing over byDMRC 0
DC04.7.8.2.2.3.6 Barricading Work 0
DC04.7.8.2.2.3.2 Utilities Identification Work 0
DC04.7.8.2.2.3.3 Utility Diversion Work if any by YFC 0
DC04.7.8.2.2.3.7 Utility Diversion Work if any by DMRC 0
DC04.7.8.2.2.3.4 Dismantling Work i.e. Light Poles, Road Median, Railing etc. 0

Actual Level of Effort Remaining Work Milestone Page 3 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
DC04.7.8.2.2.3.5 Clearing and Grabbing work 0
DC04.7.8.2.2.3.8 Installation of working piles 0
DC04.7.8.2.2.3.9 Construction of Pile Caps 0
DC04.7.8.2.2.3.22 Construction of Pier 0
DC04.7.8.2.2.3.23 Construction of Pier - 1st lift in Station and Flyover Portion 0
DC04.7.8.2.2.3.24 Construction of Cast in Situ Pier Cap 0
DC04.7.8.2.2.3.25 Construction of Pier 2 nd Lift at Station and FLyover Portion 0
DC04.7.8.2.2.3.11 Production of Precast Pier Cap 0
DC04.7.8.2.2.3.12 Erection of Precast Pier Cap 0
DC04.7.8.2.2.3.13 Bearing fixing work 0
DC04.7.8.2.2.3.14 Production of U Girder (Precast U Girder) 0
DC04.7.8.2.2.3.15 Erection U Girder (Precast U Girder) 0
DC04.7.8.2.2.3.16 Cable tray & OHE Insert 0
DC04.7.8.2.2.3.17 Expansion Joint 0
DC04.7.8.2.2.3.18 Restoration of Median 0
DC04.7.8.2.2.3.19 Rain Water Harvesting Work 0
DC04.7.8.2.2.3.20 Anti Carbonation paint 0
DC04.7.8.2.3 Emergency Sliding Line 0
DC04.7.8.2.3.2 Stabling Line 0
DC04.7.8.2.3.3 Sick Line 0
DC04.7.8.2.1 Elevated Ramp 0
DC04.7.8.2.1.2 Elevated Ramp - 1 0
DC04.7.8.2.1.2.6 Shoring Work 0
DC04.7.8.2.1.2.1 Excavation 0
DC04.7.8.2.1.2.2 PCC Work 0
DC04.7.8.2.1.2.7 Footing Work 0
DC04.7.8.2.1.2.3 Base Slab 0
DC04.7.8.2.1.2.4 Wallup to Track SLab 0
DC04.7.8.2.1.2.8 Backfilling 0
DC04.7.8.2.1.2.5 Track Slab 0
DC04.7.8.2.1.2.9 Parapet Wall 0
DC04.7.8.2.1.2.10 Railing & Fencing Work 0
DC04.7.8.2.1.5 Elevated Ramp - 2 0
DC04.7.8.2.1.5.6 Shoring Work 0
DC04.7.8.2.1.5.1 Excavation 0
DC04.7.8.2.1.5.2 PCC Work 0
DC04.7.8.2.1.5.7 Footing Work 0
DC04.7.8.2.1.5.3 Base Slab 0
DC04.7.8.2.1.5.4 Wallup to Track SLab 0
DC04.7.8.2.1.5.8 Backfilling 0
DC04.7.8.2.1.5.5 Track Slab 0
DC04.7.8.2.1.5.9 Parapet Wall 0
DC04.7.8.2.1.5.10 Railing & Fencing Work 0
DC04.7.8.2.4 Special Spans ( Steel Structure) 0
DC04.7.8.2.4.1 Special Span Near PP 12 Location 0
DC04.7.8.2.4.1.1 Fabrication Work 0
DC04.7.8.2.4.1.2 Assembly WORK 0
DC04.7.8.2.4.1.3 Erection Work 0
DC04.7.8.2.4.1.4 Paint Work 0
DC04.7.8.2.4.1.5 Railing Work 0
DC04.7.8.2.4.1.6 Cable Tray,OHE Mast 0
DC04.7.8.2.4.2 Special Span Near P64 Location 0
DC04.7.8.2.4.2.1 Fabrication Work 0
DC04.7.8.2.4.2.2 Assembly WORK 0
DC04.7.8.2.4.2.3 Erection Work 0
DC04.7.8.2.4.2.4 Paint Work 0
DC04.7.8.2.4.2.5 Railing Work 0
DC04.7.8.2.4.2.6 Cable Tray,OHE Mast 0
DC04.7.8.1 CONSTRUCTION WORK FOR INTEGRATED ELEVATED VIADUCTAND UNDERPASS 0
DC04.7.8.1.1 Section 1 0
DC04.7.8.1.2 Section 2 0
DC04.7.8.3 CONSTRUCTION WORK FOR STATIONS 0
DC04.7.8.3.1 Station Sangam Vihar 0
DC04.7.8.3.1.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.1.6 Barricading Work 0
DC04.7.8.3.1.2 Utilities Identification Work 0
DC04.7.8.3.1.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.1.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.1.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.1.5 Clearing and Grabbing work 0
DC04.7.8.3.1.8 Installation of working piles 0
DC04.7.8.3.1.9 Construction of Pile Caps 0
DC04.7.8.3.1.22 Construction of Pier 0
DC04.7.8.3.1.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.1.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.1.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.1.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.1.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.1.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.1.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.1.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.1.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.1.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.1.18 Misc cast in situ concrete work 0
DC04.7.8.3.1.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.1.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.1.14 Entry Structure 1 0
DC04.7.8.3.1.15 Entry Structure 2 0
DC04.7.8.3.1.16 Cable tray & OHE Insert 0
DC04.7.8.3.1.17 Expansion Joint 0
DC04.7.8.3.1.20 Anti Carbonation paint 0
DC04.7.8.3.1.19 Misc & Other Work 0
DC04.7.8.3.3 Station Khanpur 0
DC04.7.8.3.3.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.3.6 Barricading Work 0
DC04.7.8.3.3.2 Utilities Identification Work 0
DC04.7.8.3.3.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.3.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.3.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.3.5 Clearing and Grabbing work 0
DC04.7.8.3.3.8 Installation of working piles 0
DC04.7.8.3.3.9 Construction of Pile Caps 0
DC04.7.8.3.3.22 Construction of Pier 0
DC04.7.8.3.3.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.3.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.3.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.3.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.3.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.3.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.3.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.3.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.3.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.3.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.3.18 Misc cast in situ concrete work 0
DC04.7.8.3.3.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.3.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.3.14 Entry Structure 1 0
DC04.7.8.3.3.15 Entry Structure 2 0
DC04.7.8.3.3.16 Cable tray & OHE Insert 0
DC04.7.8.3.3.17 Expansion Joint 0
DC04.7.8.3.3.20 Anti Carbonation paint 0
DC04.7.8.3.3.19 Misc & Other Work 0
DC04.7.8.3.4 Station AMbedkar Nagar 0
DC04.7.8.3.4.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.4.6 Barricading Work 0
DC04.7.8.3.4.2 Utilities Identification Work 0
DC04.7.8.3.4.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.4.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.4.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.4.5 Clearing and Grabbing work 0

Actual Level of Effort Remaining Work Milestone Page 4 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
DMRC_DC04- Construction Schedule THREE MONTH ROLLING PROGRAMME
Activity ID Activity Name Original Duration Start Finish Qtr 1, 2020 Qtr 2, 2020
Jan Feb Mar Apr
DC04.7.8.3.4.8 Installation of working piles 0
DC04.7.8.3.4.9 Construction of Pile Caps 0
DC04.7.8.3.4.22 Construction of Pier 0
DC04.7.8.3.4.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.4.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.4.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.4.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.4.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.4.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.4.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.4.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.4.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.4.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.4.18 Misc cast in situ concrete work 0
DC04.7.8.3.4.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.4.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.4.14 Entry Structure 1 0
DC04.7.8.3.4.15 Entry Structure 2 0
DC04.7.8.3.4.16 Cable tray & OHE Insert 0
DC04.7.8.3.4.17 Expansion Joint 0
DC04.7.8.3.4.20 Anti Carbonation paint 0
DC04.7.8.3.4.19 Misc & Other Work 0
DC04.7.8.3.2 Station Saket G 0
DC04.7.8.3.2.1 Hindrance free Area handing over by DMRC 0
DC04.7.8.3.2.6 Barricading Work 0
DC04.7.8.3.2.2 Utilities Identification Work 0
DC04.7.8.3.2.3 Utility Diversion Work ifany byYFC 0
DC04.7.8.3.2.7 Utility Diversion Work ifany by DMRC 0
DC04.7.8.3.2.4 Dismantling Work i.e.Light Poles, Road Median,Railing etc. 0
DC04.7.8.3.2.5 Clearing and Grabbing work 0
DC04.7.8.3.2.8 Installation of working piles 0
DC04.7.8.3.2.9 Construction of Pile Caps 0
DC04.7.8.3.2.22 Construction of Pier 0
DC04.7.8.3.2.23 Construction of Pier - 1st lift up to Concourse 0
DC04.7.8.3.2.24 Precast work of Cross Arm Beam @ Concourse Level 0
DC04.7.8.3.2.25 Erection of Cross ArmBeam@ Concourse Level 0
DC04.7.8.3.2.11 Precast work of Π Girder@ Concourse Level 0
DC04.7.8.3.2.12 Erection of Π Girder @ Concourse Level 0
DC04.7.8.3.2.10 Construction of Pier - 2nd lift up to Platform Level 0
DC04.7.8.3.2.28 Precast work of Π Girder@ Platform Level 0
DC04.7.8.3.2.27 Erection of Cross ArmBeam@ Platform Level 0
DC04.7.8.3.2.26 Precast work of Cross Arm Beam @ Platform Level 0
DC04.7.8.3.2.29 Erection of Π Girder @ Platform Level 0
DC04.7.8.3.2.18 Misc cast in situ concrete work 0
DC04.7.8.3.2.21 Lift Shaft @Concourse to Platform 0
DC04.7.8.3.2.13 Escalator Pit @Concourse to Platform 0
DC04.7.8.3.2.14 Entry Structure 1 0
DC04.7.8.3.2.15 Entry Structure 2 0
DC04.7.8.3.2.16 Cable tray & OHE Insert 0
DC04.7.8.3.2.17 Expansion Joint 0
DC04.7.8.3.2.19 Misc & Other Work 0
DC04.7.8.3.2.20 Anti Carbonation paint 0
DC04.2 Completion and Handing Over 0

DC04.2.1 Completion Work 0


DC04.2.1.1 Cleaning Work 0
DC04.2.3 Inspection 0
DC04.2.2 Handing Over 0

Actual Level of Effort Remaining Work Milestone Page 5 of 5 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation

Potrebbero piacerti anche