1.1 Purpose
1.2 Scope
MACO have full responsibility for the detailed engineering design, procurement
of necessary materials and equipment, fabrication, delivery, erection at site,
construction, cleaning and painting, inspection, testing and commissioning of the
complete system.
In the current project (phase – 1), only 3 pumps will be installed (2 Duty and 1
Stand-by). So, the capacity of the pump-station at the completion of phase – 1
will be more than 60,000m3/day (average). There will be provisions in the pump-
station / electrical room for the future phase – 2 project.
In the future phase – 2 of the project, 3 more pumps will be installed (2 Duty and
1 Stand-by). The capacity of the pump-station at the completion of phase – 2 will
be 100,000m3/day (average).
The design of the pump station is based on the combined phase-1 (this project
and phase-2 (future project) – mechanical, piping, civil, electrical,
instrumentation/communications requirements.
The SWW PS-56A will have a Pump-station building, SEC Interface building, an
Electrical/Control building, Diesel Generator building, Odor Control System,
Building Ventilation & Air Conditioning Systems, Fire Protection Systems.
SECTION 3: REFERENCES
The Works shall be carried out in accordance with the relevant Standards and
Codes. The Codes and Standards listed below shall be considered as an integral
part of the Scope of Work. Where discrepancy / inconsistency exists between
these Codes and Standards, Royal Commission Standards shall govern.
Discrepancy shall be brought to the attention of Marafiq/ILF Representative
prior to start of the activity. MACO shall ensure that the requirements of the
Standards are complied to, and that all applicable material and design
requirements, tests, inspections and other requirements are complied.
4.1 Definitions
Design Control: The verification that design criteria comply with specified
requirements; that design data and methods are valid for the range of
application; and that the completed design satisfies the design criteria.
Hold Point: Inspection or test may not proceed without the QA/QC
organization/and or client representative in attendance.
Witness Point: It defines a point that provides QA/QC organization with the
opportunity to attend the Inspection or Test, at their option.
4.2 Abbreviations
Project Manager
The Project Manager has overall authority and responsibility for all aspects of
the Project. His responsibilities include but are not limited to the following:
The QA/QC Manager directs activities of the Project Quality Organization. His
responsibilities include but are not limited to:
Construction Manager
• Schedule the project in logical steps and budget time required to meet
deadlines.
• Determine labor requirements and dispatch workers to construction
sites.
• Requisition of supplies and materials to complete the construction
project.
• Take actions to deal with the results of delays, bad weather, or
emergencies at construction site.
• Ensure that quality of the works being delivered by the project team is
in compliance with approved project quality plan, procedures, ITP’s
and specifications.
• Assist in developing the Project Quality Management system by
establishing procedures, plans and ITP’s as needed.
• Assumes the job of Acting QA/QC Manager in the absence of QA/QC
Manager.
• Monitor the day to day quality activities of the discipline quality
inspectors. Prepares the daily, weekly and monthly quality reports.
• Implement quality control functions for the project including planning
of quality control inspections as per the approved ITP’s.
Procurement Supervisor
Supervisor
Document Controller
Material Controller
• Examining goods for defects, storing, and keeping track of inbound and
outbound materials.
• Maintains detailed records specifying the shipment or receipt of
materials. Monitoring of careful segregation of quarantined material.
• Assuring the traceability of identified critical materials while materials
are in storage.
• The monitoring and recording of the condition and state of preservation
of materials released from storage for construction.
• To prepare the material issue notes to site as per project
SECTION 7: ORGANIZATION
In this project the subcontractors will perform work under their own Quality
Management System (QMS). QA/QC Manager will review the subcontractor
QMS Manual for conformance to the ISO 9001:2015 - Quality Management
System Requirement, RC Guidelines Section 01450 - Construction Quality
Control requirements, as it applies to the assigned scope of work. QA/QC
Manager will perform an evaluation (MACO-QMP-017 Internal Quality
Audits) of the subcontractor's implementation of their QMS Manual. These
evaluations shall be submitted to MARAFIQ/ILF for review. Reports of such
evaluations will be maintained by QA/QC Manager for the duration of the
project. Any noncompliance will be resolved to the satisfaction of MACO/
MARAFIQ/ILF and records maintained. MARAFIQ/ILF reserves the right to
see the subcontractors’ installations at any time. Approved MACO
Subcontractor Management Plan has to be followed.
MACO-QMP-008 PURCHASING
MATERIAL HANDLING, STORAGE,
MACO-QMP-009 PACKAGING AND DELIVERY
MACO-QMP-018 TRAINING
Inspection and Test Plans (ITP’s) shall be prepared within the contract
conditions to cover each element of the work-scope and must be submitted
to MARAFIQ/ILF for review and approval at least ten working days in
advance of the commencement of the works to which they relate.
Prior to submission, ITP’s shall be signed, dated and authorized by the
MACO QA/QC Manager.
Inspection and Test Plans shall detail in-process activities for which
inspection and tests are required indicating the method, frequency,
inspection / test acceptance criteria and those parties responsible for
witnessing each inspection or test. The final column of the Inspection and
Test form records the verifying document where details of the relevant
inspection / test record for each activity can be found. All parties
responsible for witnessing inspections/tests and /or documentation shall be
included including testing agencies, supplier representatives and third
parties.
MACO shall utilize the standard MARAFIQ ITP template for the
development and implementation of Inspection and Test Plan. (The
template attached in Attachment 3).
8.7.1 General
MACO top management will review the Quality Management System at
least once in every six months to ensure its suitability, adequacy,
effectiveness and alignment with the strategic direction of MACO.
Procurement
• On-time Material delivery
• Product conformance to requirements
• Cost of Material
Construction
• Number of defects
• Number of defects due to workmanship
• Time to rectify defects
• The total cost of rework
• Work Completed Within Specified Time
Safety
• No Fatalities. No Permanent Disability
• Lost Time Incident Frequency (LTIF) (0.15)
• Zero Spill Incident
• ZERO Occupational Health Related Incident.
• Improve the waste management to reduce the total amount of waste by
10 %.
Quality
• Number of site inspections conducted
• The ratio of the number of inspections passed to the total number of
inspections done
• Number of non-compliance records received
• Number of non-compliance records closed
• Total number of non-compliance records rectified
• Compliance to close-out dates of non-compliance reports
• Work Rejection
Commissioning
• Accurate & Reliable Test Equipments
• Approved Commissioning Plan
For more details, please refer to project KPI and PQI procedure.
O&M Manual shall be identified by each volume, front cover and spine,
with typed or printed title "OPERATING AND MAINTENANCE
INSTRUCTIONS," name of Project, Project No., location, Contractor,
date of Substantial Completion and Volume Number and will comply
with Appendix – II Project Turnover Documents.
8.8.1.3 Warranties
• Compacting
• Coating
• Bolt Tensioning
• Welding
• Pipe Laying
• Cable Laying
• Cable Terminations
• Pump Installations
• Electrical Equipment Installations
MACO assures these processes can achieve planned results through:
• Process qualification.
• Equipment and personnel qualification.
• Defined methods and procedures.
• Records will be maintained and revalidation performed
as necessary.
• Applicable Tests specified in the ITP’s.
Applicable construction process procedures identified in Marafiq’s
quality documents, if not included in this Quality Plan, will be
submitted for Marafiq/ILF review at least 30 days prior to start of the
construction activity.
9.8.3.1 General
MACO shall perform all necessary pre-commissioning and
commissioning checks, start-up, initial operation and other tests
on the facilities, installations and equipment to demonstrate that
the requirements of the Contract have been met and that all work
has been performed properly and adequately.
9.8.3.4 Tests
The tests shall be performed by MACO under the surveillance
and to the satisfaction of MARAFIQ/ILF representatives.
MACO shall record test data and maintain records on test data
sheets in an operations log detailing and describing each activity
and change in mode of operation, including the time and date of
each test.
10.1 Objective
10.2 Policies
10.2.2 All Project Team members are responsible for attending risk and value
workshops when requested by Marafiq/ILF and for carrying out and reporting
their agreed follow-up actions.
10.2.3 Risk and value management workshops must involve the personal
contribution and attendance of all relevant stakeholders, as far as practicable.
10.3 Procedure
10.3.1 It is vital that the right information is available for the identification of
the objectives and for clearly understanding the issues, constraints, assumptions
and risks relating to this project.
This will assist in the process of briefing the project team, and in using the
relevant objectives to decide which proposed option is the best solution to
develop further.
All identified project risks must be reported to the Project Manager, who
must make an initial investigation to determine the cause, likelihood of
PR No. 7200039700 Page 35 of 42 QA/QC Manual MACO-QP-039700-001
QA/QC PLAN
NEW PUMP STATION PS 56A AND FORCE
MAIN TO SWTP-9 - JUBAIL
DOC. No. MACO-QP-039700-001 REV. 04
IMPACT
P 1 2 3 4 5
R
O 1 5 10 15 20 25
B
A 2 4 8 12 16 20
B
I 3 3 6 9 12 15
L
I 4 2 4 6 8 10
T
Y 5 1 2 3 4 5
All identified risks shall initially be qualitatively assessed, with the assessment
to take into consideration the probability scoring on a range of 1 through to 5,
and the impact scoring on a range of 1 through to 5.
DOCUMENT TITLE:
ATTACHMENT 1
ORGANIZATIONAL CHARTS
DOCUMENT NO.:
MACO-ORG-039700-001
MACO-ORG-039700-002
DOCUMENT TITLE:
ATTACHMENT 2
ISO CERTIFICATES
DOCUMENT TITLE:
ATTACHMENT 3
ATTACHMENT 4
INDEX FOR
INSPECTION & TEST PLANS
ATTACHMENT 5
INDEX FOR
QUALITY MANAGEMENT PROCEDURES
ATTACHMENT 6