ASIGNATURA:
INGENIERIA DE LA CONSTRUCCION I
TEMA:
METRADOS
ESTUDIANTE:
DOCENTE:
TARAPOTO- CACATACHI
2018 - II
ÍNDICE
INTRODUCCIÓN ........................................................................................................................ 3
1. OBJETIVOS ........................................................................................................................ 4
2. MARCO TEÓRICO ............................................................................................................. 6
3. RESULTADOS ................................................................................................................. 12
4. CONCLUSIONES: ........................................................................................................... 96
BIBLIOGRAFÍA Y REFERENCIAS PERSONALES ............................................................ 97
INTRODUCCIÓN
Los resultados obtenidos en este metrado, nos servirán como base para
poder realizar el presupuesto de obra.
1. OBJETIVOS
Principal:
Secundarios:
Edificación
En conformidad con el Reglamento Nacional de Edificaciones, es una
obra de carácter permanente, cuyo destino es albergar actividades
humanas. Comprende las instalaciones fijas y complementarias adscritas
a ella.
Metrado
En conformidad con el Reglamento de la Ley de Contrataciones del
Estado, es el cálculo o la cuantificación por partidas de la cantidad de obra
a ejecutar.
Partida
Cada uno de los productos o servicios que conforman el presupuesto de
una Obra.
Limpieza de terreno
Esta partida comprende los trabajos que deben ejecutarse para la
eliminación de basura, elementos sueltos, livianos y pesados existentes
en toda el área del terreno, así como de maleza y arbustos de fácil
extracción. No incluye elementos enterrados de ningún tipo.
Movimiento de tierras
Comprende las excavaciones, cortes, rellenos y eliminación del material
excedente, necesarios para alcanzar los niveles proyectados del terreno
en la ejecución de la edificación y sus exteriores; así como dar cabida a
los elementos que deban ir enterrados y subterráneos, tales como
cimentaciones, tuberías, etc.
Nivelado apisonado
Se medirá el área del terreno a nivelar, indicándose en el metrado la altura
promedio de corte y relleno, así como la clase de material. Para el caso
de nivelado apisonado, se indicara el número de capas por apisonar para
efectos de cálculos de costos.
Excavaciones simples
Es el tipo de excavación que por su condición se ejecuta preferentemente
con la utilización de mano de obra y/o equipos.
Rellenos
Comprende la ejecución de trabajos tendientes a rellenar zanjas (como es
el caso de colocación de tuberías, cimentaciones enterradas, etc.) o el
relleno de zonas requeridas por los niveles de pisos establecidos en los
planos.
Zapatas
Constituyen el cimiento de las columnas. Su ubicación y dimensiones
están determinadas en los planos respectivos.
Se denominan zapatas aisladas, a las que soportan una sola columna,
zapatas combinadas, a las que sirven de soporte de dos o más columnas
y zapatas conectadas, a las que son unidas por una o más vigas de
cimentación.
Vigas de cimentación
Generalmente se diseñan para conectar a las zapatas, de manera que
trabajen en conjunto, pudiendo actuar como cimiento.
Columnas
Son elementos de apoyo aislado, generalmente verticales con medida de
altura muy superior a las transversales.
En edificios de uno o varios niveles con losas de concreto, la altura de las
columnas se considerará:
- En primer nivel, distancia entre las caras superiores de la cimentación
(no incluye sobrecimiento) y la cara superior del entrepiso (techo).
- En niveles superiores, será la distancia entre las caras superiores de
los entrepisos que lo limitan.
Vigas
Son los elementos horizontales o inclinados, de medida longitudinal muy
superior a las transversales. La longitud a considerarse para la longitud
de vigas será su longitud entre caras de columnas.
En los elementos que se crucen se medirá la intersección una sola vez.
En el encuentro de losas con vigas, se considerará que la longitud de cada
losa termina en el plano lateral o costado de la viga, por consiguiente la
altura o peralte de la viga incluirá el espesor de la parte empotrada de la
losa.
La partida comprende las vigas principales, vigas secundarias, vigas de
amarre y dinteles.
Escaleras
Son estructuras diseñadas para vincular planos de distintos niveles, están
conformados por una serie de pasos o peldaños y eventuales descansos.
3. RESULTADOS
PRESUPUESTO DE OBRA
OBRA ::VIVIENDA
AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 01 DE 5
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
FECHA : : ABRIL
DICIEMBRE
DEL 2009
DEL 2018 REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
2.0 ESTRUCTURAS
2.1.0 MOVIMIENTO DE TIERRAS
2.1.1 Nivelación del terreno
2.1.1.1 Nivelación M2 160
2.1.1.2 Nivelado apisonado M2 160
2.1.2 Excavaciones
2.1.2.1 Excavación simple ( de zanjas ) M3 160
2.1.4 Rellenos
2.1.4.1 Relleno con material propio M3 10.89
2.1.4.2 Relleno con material de préstamo M3 10.89
2.1.5 Nivelación interior y apisonado M3 142.54
2.1.6 Eliminación de material excedente M2 44.95
3.0 ARQUITECTURA
3.1 MUROS Y TABIQUES DE ALBAÑILERIA
3.1.2 Muros de ladrillo corriente de arcilla
3.1.2.1 De Soga M2 162.11
PRESUPUESTO DE OBRA
OBRA ::VIVIENDA
AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 02 DE 5
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
FECHA : : ABRIL
DICIEMBRE
DEL 2009
DEL 2018 REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
3.3 CIELORRASOS
3.3.3 Cieloraso con mezcla M2 94.63
3.9 CERRAJERIA
3.9.1 Bisagras
3.9.1.1 Aluminizadas Unid. 40.00
3.9.2 Cerraduras
3.9.2.1 Para puerta principal de sobreponer 2 golpes, llave exterior Unid. 3.00
3.9.2.2 Para puertas interiores y baño, seguro interior de perilla Unid. 10.00
3.9.4 Accesorios de cierre
3.9.4.1 Picaportes de sobreponer Unid. 9.00
3.9.4.2 Agarraderas Unid. 1.00
OBRA ::VIVIENDA
AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 03 DE 5
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
FECHA : : ABRIL
DICIEMBRE
DEL 2009
DEL 2018 REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
3.11 PINTURA
3.11.1 De Cielorrasos, Vigas, Columnas y Paredes
3.11.1.1 Cielorrasos al temple M2 94.63
3.11.1.2 Vigas al temple M2 89.15
3.11.1.3 Columnas al Temple M2 46.65
3.11.1.4 Muros interiores al temple M2
3.11.2 Pintura de Puertas al Barniz M2 36.88
3.11.3 Pintura de Ventanas al Barniz M2 26.70
OBRA ::VIVIENDA
AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 04 DE 5
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO HECHO POR : MARIA JEYSSI SALDAÑA MENDOZA
FECHA : : ABRIL
DICIEMBRE
DEL 2009
DEL 2017 REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
4.5.2 Accesorios
4.5.2.1 Codos ø 2" x 90° Unid.
4.5.2.2 Codos ø 2" x 45° Unid.
4.5.2.3 Sumideros 2" Unid.
OBRA ::VIVIENDA
AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 05 DE 5
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO HECHO POR : MARIA JEYSSI SALDAÑA MENDOZA
FECHA : : ABRIL
DICIEMBRE
DEL 2009
DEL 2017 REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
5.5 ARTEFACTOS
5.5.1 Lámparas Unid.
COSTOS DIRECTO
GASTOS GENERALES FIJOS (............. % ) -
GASTOS GENERALES VARIABLES (............. % ) -
UTILIDAD (............. % ) -
SUB TOTAL S/. -
I.G.V. ( 18,00 % ) -
OBRA : VIVIENDA
: AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 01 DE 50
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : IS-01
U-01,E-01
FECHA : DICIEMBRE
: ABRIL DEL
DEL
2009
2018 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
TRABAJOS PRELIMINARES
FACIL EXTRACCION
2.0 ESTRUCTURAS
2.1.2 EXCAVACIONES
ZAPATAS
2.1.4 RELLENOS
INGRESO
1 1.00 0.30 - 0.30
55.84 10.89
OBRA : VIVIENDA : AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 10
01 DE
DE 50
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : IS-01
E-01
FECHA : DICIEMBRE
: ABRIL
DELDEL
2018
2009 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
EJE 9-9(/A y C)
1 2.45 0.50 0.80 0.98
EJE 9-9(/C y E) 2.43
1 0.50 0.80 0.97
EJE 9-9(/E y F) 3.13
1 0.50 0.80 1.25
EJE 8-8(/A y C) 2.45 0.50
1 0.80 0.98
EJE 8-8(/C y E) 2.78 0.50
1 0.80 1.11
EJE 8-8(/E y F) 4.23 0.50
1 0.80 1.69
EJE 7-7(/E y F) 3.43 0.50
1 0.80 1.37
EJE 6-6 (/C-E) 1.75 0.50
1 0.80 0.70
EJE 5-5(/A y C) 2.45 0.50
1 0.80 0.98
EJE 5-5(/C y E) 2.43 0.50
1 0.80 0.97
EJE 5-5(/E y F) 3.13 0.50
1 0.80 1.25
C1 0.25 0.25
1 0.80 -0.05
EJE 4-4(/E y F) 3.43 0.50
1 0.80 1.37
C1 0.25 0.25
1 0.80 -0.05
EJE 3-3(/E y F) 4.58 0.50
1 0.80 1.83
C1 0.25 0.25
1 0.80 -0.05
EJE 2-2(/A y C) 1 2.45 0.50 0.80 0.98
2.2.6 SOBRECIMIENTO
EJE 9-9(/A y E)
2 4.35 - 0.60 5.22
OBRA : VIVIENDA
: AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N°1304DE
DE50
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : E-01
-01, E-01
FECHA : DICIEMBRE
: ABRIL
DELDEL
2018
2009 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
2 - 0.15
0.60 0.18
EJE 5-5(/E y F) 2 2.75 -
0.60 3.30
2 - 0.15
0.60 0.18
EJE 4-4(/E y F) 2 2.00 -
0.60 2.40
2 - 0.15
0.60 0.18
EJE 3-3(/E y F) 2 2.00 -
0.60 2.40
2 - 0.15
0.60 0.18
EJE 2´-2´(/A y D) 2 3.60 -
0.60 4.32
2 - 0.15
0.60 0.18
EJE 2´-2´(/E y F) 2 2.10 -
0.60 2.52
2 - 0.15
0.60 0.18
EJE 1-1/A y C) 2 1.00 -
0.60 1.20
2 - 0.15
0.60 0.18
EJE 1-1/(E y F) 2 0.28 -
0.60 0.33
2 - 0.15
0.60 0.18
2 0.18 -
0.60 0.21
2 - 0.15
0.60 0.18
EJE A-A(/9 y 8)
2 2.65 - 0.60 3.18
OBRA : VIVIENDA
: AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 04
14 DE 50
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : -01,
E-01E-01
FECHA : DICIEMBRE
: ABRIL
DELDEL
2018
2009 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
2 - 0.15
0.60 0.18
EJE D-D(/3 y 2´) 2 0.80 -
0.60 0.96
2 - 0.15
0.60 0.18
EJE D-D(/2´ y 2) 2 1.05 -
0.60 1.26
2 - 0.15
0.60 0.18
EJE E-E(/9 y 8) 2 1.80 -
0.60 2.16
2 - 0.15
0.60 0.18
2 1.65 -
0.60 1.98
2 - 0.15
0.60 0.18
2 0.80 -
0.60 0.96
2 - 0.25
0.60 0.30
EJE E-E(/7 y 5) 2 2.45 -
0.60 2.94
2 - 0.25
0.60 0.30
EJE E-E(/5 y 3)
2 2.30 - 0.60 2.76
OBRA : VIVIENDA
: AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 15
04 DE
DE 50
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : -01,
E-01E-01
, A- 01
FECHA : DICIEMBRE
: ABRIL
DELDEL
2018
2009 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
1 3.90 2.95 -
11.505
1 2.30 0.15 -
0.345
1 2.75 0.10 -
0.275
SH.1 1 0.90 0.10 - 0.09
OBRA : VIVIENDA
: AMPLIACION
MULTIFAMILIAR
CASA HABITACION HOJA N° 16
04 DE
DE50
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : E-01
-01, E-01
, A- 01
FECHA : DICIEMBRE
: ABRIL
DELDEL
2018
2009 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
1 0.75 0.10 -
0.08
1 2.00 1.85 -
3.70
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
C-1-ZAPATA 3 0.25 0.25 3.00 0.56 1.00 3.00 9.00 1/2" 4.00 4.05 48.60
C-2-ZAPATA 1 0.25 0.25 3.00 0.19 1.00 3.00 3.00 1/2" 4.00 4.05 16.20
C-1-(centro) 1 0.25 0.25 2.70 0.17 1.00 2.70 2.70 1/2" 4.00 4.05 16.20
C-2-(borde) 13 0.25 0.25 3.00 2.44 1.00 3.00 39.00 1/2" 4.00 4.35 226.20
C-2-(centro) 1 0.25 0.25 2.70 0.17 1.00 2.60 2.60 1/2" 4.00 4.05 16.20
C-3-(borde) 3 0.40 0.15 2.70 0.49 1.10 2.70 8.91 1/2" 6.00 4.35 78.30
C-4-(centro) 2 0.30 0.15 2.70 0.24 0.90 2.70 4.86 1/2" 4.00 4.75 38.00
TOTAL ( Kgs )
962.75 684.41 33.04 1680.20
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
C-4-(borde) 2 0.30 0.15 2.90 0.26 0.90 2.90 5.22 1/2" 4.00 4.02 32.16
C-5-(borde) 8 0.25 0.15 6.00 1.80 0.8 6.00 38.40 1/2" 4.00 4.75 152.00
C-5-(centro) 2 0.25 0.15 5.1 0.38 0.8 5.11 8.18 1/2" 4.00 4.05 32.40
C-5 1 0.25 0.15 2.9 0.11 0.8 2.9 2.32 1/2" 4.00 4.02 16.08
(1 piso) 3/8" 22.00 0.90 19.80
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
1 PISO
VS-01(1) 1 8.00 0.25 0.20 0.40 8.00 0.20 1.60 1/2" 2.00 8.12 16.24
VA-1(4) 1 8.00 0.25 0.20 0.40 6.70 0.25 1.68 1/2" 2.00 8.12 16.24
VB(8) 1 3.30 0.15 0.20 0.10 0.90 0.15 0.14 1/2" 2.00 3.42 6.84
VB(6) 1 1.40 0.15 0.20 0.04 0.95 0.15 0.14 1/2" 2.00 1.52 3.04
VB(15) 1 3.85 0.15 0.20 0.12 3.85 0.15 0.58 1/2" 2.00 3.97 7.94
TOTAL ( Kgs )
392.73 640.47 103.15 56.82 1193.17
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
VA-1(12) 1 8.00 0.25 0.20 0.40 4.60 0.25 1.15 1/2" 2.00 8.12 16.24
4.75 0.20 0.95 1/2" 2.00 8.12 16.24
VA-1(13) 1 3.25 0.25 0.20 0.16 2.75 0.25 0.69 1/2" 2.00 3.37 6.74
VB(14) 1 3.25 0.15 0.20 0.10 3.25 0.15 0.49 1/2" 2.00 3.37 6.74
VS-1(2) 1 2.65 0.25 0.40 0.27 3.15 0.40 1.26 1/2" 2.00 3.57 7.14
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
VB-5 1 2.45 0.15 0.20 0.07 2.45 0.15 0.37 1/2" 3.00 2.97 8.91
VP-16 1 4.20 0.15 0.40 0.25 4.20 0.15 0.63 1/2" 2.00 4.97 9.94
4.20 0.20 0.84 1/2" 2.00 4.97 9.94
VB-7 1 1.80 0.15 0.20 0.05 1.80 0.15 0.27 1/2" 3.00 2.32 6.96
1.80 0.20 0.36 1/2" 3.00 2.32 6.96
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
VS-02(1 piso) 1 0.35 0.15 0.20 0.01 0.20 0.15 0.03 1/2" 2.00 7.22 14.44
5.60 0.15 0.40 0.34 0.20 0.15 0.03 1/2" 2.00 7.02 14.04
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
2.3.9.2 LOSA ALIGERADAS 8.28 4.45 3.15 14.02 1/2" 6 1.325 7.95
TOTAL ( Kgs )
136.85 402.42 26.96 1145.48
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
N° L A H ( M3 ) L A(H) ( M2 ) ( PULG.) C/Ø 16
TOTAL ( Kgs )
0.00 0.00 0.00
VOLUMEN DE CONCRETO
L A TOTAL(M2)
AREA 1 4.25 2.65 11.2625
AREA 2 2.75 2.65 7.2875
AREA 3 2.45 1.1 2.695
AREA 4 4.25 0.85 3.6125
AREA 5 1.8 0.9 1.62
AREA 6 2.75 2.3 6.325
AREA 7 3.45 0.8 2.76
AREA 8 4.45 3.1 13.795
AREA 9 3.1 2.75 8.525
AREA 10 4.45 2.5 11.125
AREA 11 4.45 1.85 8.2325
AREA 12 2.85 1.85 5.2725
AREA 13 3.9 2.85 11.115
AREA 14 2.85 0.35 0.9975
94.625
CANTIDAD LADRILLO
= 94.625 x 10
= 946.25 = 947 LAD
VOL. LADRILLO
= 946.25 x (0.15x0.30x0.25)
= 10.6453125 m3
VOL. CONCRETO
= 18.925 - 10.65
8.28 m3
FORMATO DE METRADO DE CONCRETO ARMADO
1 1.00 0.50 1.60 0.80 15.00 0.18 2.64 3/8" 6 3.150 18.90
1 1.00 0.20 0.18 0.03 3.33 1.00 3.33 3/8" 6 1.920 11.52
1 1.00 0.85 0.18 0.15 3.33 0.30 1.00 3/8" 10 0.950 9.50
5 1.00 0.25 0.18 0.22 0.53 42.00 22.05 N°16 36 0.300 10.8
1 1.00 0.25 0.18 0.04 0.85 0.18 0.15 3/8" 6 2.700 16.20
1 3.33 1.00 0.15 0.50 1.05 0.18 0.19 3/8" 7 0.950 6.65
1 1.05 1.00 0.18 0.18 N°16 42 0.300 12.6
TOTAL ( Kgs )
62.32 35.52 1.78 99.61
FORMATO DE METRADO
1°PISO 5.31 M2
EJE 1-1(/A y C) 1 1.00 - 2.50 2.50
EJE 1-1(/C y E) 1 2.30 - 2.50 5.75 P-1(1) - 2.30 2.20 5.06
1 1.00 - 2.50 2.50 P-2(1) - 1.00 2.20 2.20
EJE 1-1(/E y F) 1 2.75 - 2.50 6.88 P-3(1) - 2.30 2.20 5.06
FORMATO DE METRADO
46.65 M2
3.2.5 TARRAJEO EN COLUMNAS
46.65 M2
1° PISO
EJE 9-9 1 0.80 - 2.50 2.00
89.15 M2
3.2.5 TARRAJEO EN VIGAS
89.15 M2
1° PISO
EJE 9-9(/A y C) 1 2.20 0.10 - 2.20
1° PISO 48.95 Ml
3.3 CIELORRASO
1 PISO
94.63
4.25 2.65 - 11.26
1 PISO
ESTUDIO
1 0.90 0.15 - 0.135
INGRESO
1 1.00 0.30 - 0.30
3.4.2.11 MAYOLICA
ESTUDIO
1 0.90 0.15 - 0.135
INGRESO
1 1.00 0.30 - 0.30
ALISADO Y COLOREADO
1 PISO
ESTUDIO
1 0.90 0.15 - 0.135
INGRESO
1 1.00 0.30 - 0.30
INGRESO
1 1.00 0.30 - 0.30
1 7.00 - - 7.00
1 1.15 - - 1.15
1 3.35 - - 3.35
2 0.90 - - 1.80
1 1.05 - - 1.05
1 0.90 - - 0.90
1 - - 0.10
0.10
1 - - 0.70
0.70
1 2.85 - - 2.85
1 0.90 - - 0.90
1 0.15 - - 0.15
1 3.90 - - 3.90
1 0.9 - - 0.90
1 0.60 - - 0.60
1 2.95 - - 2.95
1 0.25 - - 0.25
FORMATO DE METRADO
1 PISO
3.5.1 ZOCALO
3.5.2 CONTRAZOCALO
ESPESOR=0.10 m
2 1.8 - - 3.60
2 0.9 - - 1.80
1 0.80 - - 0.80
1 2.20 - - 2.20
1 2.75 - - 2.75
1 0.80 - - 0.80
1 3.20 - - 3.20
1 3.10 - - 3.10
1 1.05 - - 1.05
1 0.15 - - 0.15
1 0.10 - - 0.10
1 2.40 - - 2.40
1 0.25 - - 0.25
1 2.85 - - 2.85
FORMATO DE METRADO
3.7.1 PUERTAS
1 PISO
3.7.2 VENTANA
1 PISO 9.00 ML
V1 1 - - - 1.00
V2 3 - - - 3.00
V3 1 - - - 1.00
V5 3 - - - 3.00
V8 1 - - - 1.00
3.90 CERRADURAS
1 PISO
3.9.1.1. ALUMINIZADAS
P1 3 - - - 3.00
P2 3 - - - 3.00
P3 3 - - - 3.00
P4 3 - - - 3.00
P5 3 - - - 3.00
P6 3 - - - 3.00
P7 3 - - - 3.00
P8 3 - - - 3.00
FORMATO DE METRADO
V1(1) 4 - - - 4.00
V2(1) 2 - - - 2.00
V3(1) 3 - - - 3.00
V5(1) 3 - - - 3.00
V8(1) 4 - - - 4.00
3.9.2.1
PARA PUERTA PRINCIPAL DE SOREPONER 2 GOLPES, LLAVE EXTERIOR 3.00 UND
P1 1 - - - 1.00
P2 1 - - - 1.00
P3 1 - - - 1.00
P4 1 - - - 1.00
P5 5 - - - 5.00
P6 1 - - - 1.00
P7 2 - - - 2.00
P8 1 - - - 1.00
V1(1) 1 - - - 1.00
V2(1) 3 - - - 3.00
V3(1) 1 - - - 1.00
V5(1) 3 - - - 3.00
V8(1) 1 - - - 1.00
3.11 PINTURA
1 PISO
1° PISO
EJE 9-9(/A y C) 1 2.20 0.10 - 2.20
46.65 M2
1° PISO
EJE 9-9 1 0.80 - 2.50 2.00
INGRESO
1 1.00 0.30 - 0.30
1°PISO
EJE A-A (/6 y 5) 1 0.63 - 2.30 1.45
EJE A-A (/5 y 4) 1 3.10 - 2.30 7.13
EJE A-A (/4 y 3) 1 2.50 - 2.30 5.75
EJE A-A (/3 y 2) 1 1.05 - 2.30 2.42
EJE E-E (/9 y 8) 2 0.80 - 2.30 3.68
EJE E-E (/7 y 5) 2 2.45 - 2.30 11.27
EJE E-E (/5 y 4) 2 3.10 - 2.30 14.26 P-8(2) - 0.80 2.00 3.20
EJE E-E (/4 y 3) 2 2.5 - 2.30 11.50 V-2(2) - 1.00 0.30 0.60
EJE 9-9(/A y C) 1 2.45 - 2.50 6.13
EJE 9-9(/C y E) 1 2.43 - 2.50 6.08
2 1.65 - 2.50 8.25
EJE 9-9(/E y F) 1 3.13 - 2.50 7.83
EJE 8-8 (/A y C) 2 2.20 - 2.50 11.00 V-5 (2) - 1.60 1.70 5.44
EJE 8-8 (/C y E) 2 1.10 - 2.50 5.50 P-5(2) - 0.90 2.00 3.60
2 0.90 - 2.50 4.50
EJE 8-8 (/E y F) 2 1.6 - 2.50 8.00 V-5 (2) - 1.60 1.70 5.44
2 0.9 - 2.50 4.50 P-5(2) - 0.90 2.00 3.60
EJE 7-7 (/E y F) 2 1.6 - 2.50 8.00 V-5 (2) - 1.60 1.70 5.44
2 0.9 - 2.50 4.50 P-5(2) - 0.90 2.00 3.60
EJE 6-6 (/C y E) 2 0.95 - 2.50 4.75
EJE 5-5 (/A y E) 2 3.45 - 2.50 17.25 V-8 (2) - 3.45 1.70 11.73
EJE 5-5 (/E y F) 2 2.75 - 2.50 13.75
EJE 4-4 (/E y F) 2 2.00 - 2.50 10.00 V-3(2) - 1.60 1.40 4.48
P-7(2) - 0.75 2.00 3.00
EJE 3-3 (/E y F) 2 2.75 - 2.50 13.75 V-2(2) - 1.00 0.30 0.60
- P-7(2) - 0.75 2.00 3.00
EJE 2-2(/A y C) 2 3.35 - 2.50 16.75 V-1(2) - 2.45 1.70 8.33
FORMATO DE METRADO
1 PISO
1 PISO 26.70 ML
1 PISO 33.94
1 PISO
ESTUDIO
1 0.90 0.15 - 0.135
INGRESO
1 1.00 0.30 - 0.30
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
C-1-ZAPATA 3 0.25 0.25 3.30 0.62 1.00 3.30 9.90 1/2" 4.00 3.66 43.92
C-2-ZAPATA 1 0.25 0.25 3.30 0.21 1.00 3.30 3.30 1/2" 4.00 3.66 14.64
C-1-(centro) 1 0.25 0.25 2.40 0.15 1.00 2.40 2.40 1/2" 4.00 3.66 14.64
C-2-(borde) 13 0.25 0.25 3.30 2.68 1.00 3.30 42.90 1/2" 4.00 3.66 190.32
C-2-(centro) 1 0.25 0.25 2.20 0.14 1.00 2.20 2.20 1/2" 4.00 2.72 10.88
C-3-(borde) 3 0.40 0.15 3.30 0.59 1.10 3.30 10.89 1/2" 6.00 3.66 65.88
C-4-(centro) 2 0.30 0.15 3.30 0.30 0.90 3.30 5.94 1/2" 4.00 2.72 21.76
TOTAL ( Kgs )
927.02 508.69 24.55 1460.27
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
C-5-(borde) 8 0.25 0.15 3.30 0.99 0.8 3.30 21.12 1/2" 4.00 3.66 117.12
C-5-(centro) 2 0.25 0.15 2.4 0.18 0.8 2.4 3.84 1/2" 4.00 2.72 21.76
TOTAL ( Kgs )
OBRA : VIVIENDA MULTIFAMILIAR HOJA N° : 03 DE 30
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : E-02 , E-03
FECHA : DICIEMBRE
: JULIO DE
DEL2017
2018 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
2 PISO
VS-01(1) 1 8.00 0.25 0.20 0.40 8.00 0.20 1.60 1/2" 2.00 8.12 16.24
4.35 0.25 1.09 1/2" 2.00 8.12 16.24
VA-1(4) 1 8.00 0.25 0.20 0.40 6.70 0.25 1.68 1/2" 2.00 8.12 16.24
VB(8) 1 3.30 0.15 0.20 0.10 0.90 0.15 0.14 1/2" 2.00 3.42 6.84
VB(15) 1 3.85 0.15 0.20 0.12 3.85 0.15 0.58 1/2" 2.00 3.97 7.94
TOTAL ( Kgs )
506.744 645.444 103.1459 62.77 1318.10
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
VA-1(11) 1 8.00 0.25 0.20 0.40 4.50 0.25 1.13 1/2" 2.00 8.12 16.24
VA-1(12) 1 8.00 0.25 0.20 0.40 4.60 0.25 1.15 1/2" 2.00 8.12 16.24
VA-1(13) 1 3.25 0.25 0.20 0.16 2.75 0.25 0.69 1/2" 2.00 3.37 6.74
VB(14) 1 3.25 0.15 0.20 0.10 3.25 0.15 0.49 1/2" 2.00 3.37 6.74
VS-1(2) 1 2.65 0.25 0.40 0.27 3.15 0.40 1.26 1/2" 2.00 3.57 7.14
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
VB-5 1 2.45 0.15 0.20 0.07 2.45 0.15 0.37 1/2" 3.00 2.97 8.91
VP-16 1 4.20 0.15 0.40 0.25 4.20 0.15 0.63 1/2" 2.00 4.97 9.94
VB-7 1 1.80 0.15 0.20 0.05 1.80 0.15 0.27 1/2" 3.00 2.32 6.96
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
VS-02(2 piso) 1 0.85 0.15 0.20 0.03 0.20 0.15 0.03 1/2" 2.00 7.72 15.44
5.60 0.15 0.40 0.34 0.20 0.15 0.03 1/2" 2.00 7.52 15.04
13.86
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
4.90 0.25 0.40 0.49 0.25 0.20 0.05 1/2" 2.00 22.82 45.64
13.83
TOTAL ( Kgs )
FORMATO DE METRADO DE CONCRETO ARMADO
DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL Ø CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N°
TOTAL ( Kgs )
138.6 413.06 27.58 579.24
OBRA : VIVIENDA MULTIFAMILIAR HOJA N° : 09 DE 30
PROPIETARIO : Sr. ELBANO MIRANDA DELGADO PLANO N° : E-01
FECHA : DICIEMBRE
: JULIO DE
DEL2017
2018 HECHO POR : JAIME SAMIR RAMIREZ PIZARRO
REVISADO POR : ING° M.Sc. VICTOR SAMAME ZATTA
TOTAL ( Kgs )
VOLUMEN DE CONCRETO
L A TOTAL(M2)
AREA 1 4.25 2.65 11.2625
AREA 2 2.75 2.65 7.2875
AREA 3 2.45 1.1 2.695
AREA 4 4.25 0.85 3.6125
AREA 5 1.8 0.9 1.62
AREA 6 2.75 2.3 6.325
AREA 7 3.45 0.8 2.76
AREA 8 4.45 3.1 13.795
AREA 9 3.1 2.75 8.525
AREA 10 4.45 2.5 11.125
AREA 11 4.45 1.85 8.2325
AREA 12 2.85 1.85 5.2725
AREA 13 3.9 2.85 11.115
AREA 14 2.85 0.85 2.4225
96.05
CANTIDAD LADRILLO
= 96.05 x 10
= 960.5 = 961 LAD
VOL. LADRILLO
= 960.5 x (0.15x0.30x0.25)
= 10.805625 m3
VOL. CONCRETO
= 19.21 - 10.81
8.40 m3
FORMATO DE METRADO DE CONCRETO ARMADO
DE SOGA 158.5 M2
EJE 9-9(/A y C) 1 2.45 - 2.50 6.13
EJE 9-9(/C y E) 1 2.43 - 2.50 6.08
1 1.65 - 2.50 4.13
EJE 9-9(/E y F) 1 3.13 - 2.50 7.83
EJE 8-8 (/A y C) 1 2.20 - 2.50 5.50 V-5 (1) - 1.60 1.70 2.72
EJE 8-8 (/C y E) 1 1.10 - 2.50 2.75 P-5(1) - 0.90 2.00 1.80
1 0.90 - 2.50 2.25 0.00
EJE 8-8 (/E y F) 1 1.60 - 2.50 4.00 V-5 (1) - 1.60 1.70 2.72
1 0.90 - 2.50 2.25 P-5(1) - 0.90 2.00 1.80
EJE 7-7 (/E y F) 1 1.60 - 2.50 4.00 V-5 (1) - 1.60 1.70 2.72
1 0.90 - 2.50 2.25 P-5(1) - 0.90 2.00 1.80
EJE 6-6 (/C y E) 1 0.95 - 2.50 2.38 0.00
EJE 5-5 (/A y E) 1 3.45 - 2.50 8.63 M-1(1) - 3.45 2.50 8.63
EJE 5-5 (/E y F) 1 2.75 - 2.50 6.88 P-8(1) - 0.80 2.00 1.60
EJE 4-4(/E y F) 1 2.75 - 2.50 6.88 V-3(1) - 1.60 1.40 2.24
EJE 3-3 (/E y F) 1 2.75 - 2.50 6.88 V-2(1) - 1.00 0.30 0.30
EJE 2-2(/A y C) 1 3.35 - 2.50 8.38 V-1(1) - 2.45 1.70 4.17
1 1.15 - 2.50 2.88 V-7(1) - 0.40 1.70 0.68
FORMATO DE METRADO
47.49 M2
3.2.5 TARRAJEO EN COLUMNAS
47.49 M2
2° PISO
EJE 9-9 1 0.60 - 2.50 1.50
67.04 M2
3.2.5 TARRAJEO EN VIGAS
67.04 M2
2° PISO
EJE 9-9(/A y C) 1 2.20 0.10 - 2.20
2 PISO
3.5.1 ZOCALO
3.5.2 CONTRAZOCALO
ESPESOR=0.10 m
2 1.8 - - 3.60
2 0.9 - - 1.80
1 0.80 - - 0.80
1 2.20 - - 2.20
1 2.75 - - 2.75
1 0.80 - - 0.80
1 3.20 - - 3.20
FORMATO DE METRADO
1 3.10 - - 3.10
1 1.05 - - 1.05
1 0.15 - - 0.15
1 0.10 - - 0.10
1 2.40 - - 2.40
1 0.25 - - 0.25
1 2.85 - - 2.85
1 7.00 - - 7.00
1 1.15 - - 1.15
1 3.35 - - 3.35
2 0.90 - - 1.80
1 1.05 - - 1.05
1 0.90 - - 0.90
1 - - 0.10
0.10
1 - - 0.70
0.70
1 2.85 - - 2.85
1 0.90 - - 0.90
1 0.15 - - 0.15
1 3.90 - - 3.90
1 0.9 - - 0.90
1 0.60 - - 0.60
1 2.95 - - 2.95
1 0.25 - - 0.25
3.7.1 PUERTAS
2 PISO
3.7.2 VENTANA
2 PISO 11.00 ML
V2 3 - - - 3.00
V3 1 - - - 1.00
V4 2 - - - 2.00
V5 3 - - - 3.00
V6 1 - - - 1.00
V7 1 - - - 1.00
3.91. BISAGRAS
P5 3 - - - 3.00
P6 3 - - - 3.00
P8 3 - - - 3.00
V2(1) 2 - - - 2.00
V3(1) 3 - - - 3.00
V4(1) 2 - - - 2.00
V5(1) 3 - - - 3.00
V6(1) 3 - - - 3.00
V7(1) 2 - - - 2.00
P5 5 - - - 5.00
P6 2 - - - 2.00
P8 2 - - - 2.00
V2(1) 3 - - - 3.00
V3(1) 1 - - - 1.00
V4(1) 2 - - - 2.00
V5(1) 3 - - - 3.00
V6(1) 1 - - - 1.00
V7(1) 1 - - - 1.00
FORMATO DE METRADO
3.11 PINTURA
2 PSIO
89.15 M2
2° PISO
EJE 9-9(/A y C) 1 2.20 0.10 - 2.20
47.49 M2
3.11.1.3 COLUMNAS AL TEMPLE
47.49 M2
2° PISO
EJE 9-9 1 0.60 - 2.50 1.50
221.85 66.14
FORMATO DE METRADO
181.44 19.286
FORMATO DE METRADO
2 PISO
2 PISO 32.57 ML
2 PISO
pág. 94
FORMATO DE METRADO
DORMITORIO PRINCIPAL
1 2.65 0.10 - 0.27
Los metrados son de suma importancia dentro del campo de ingeniería civil
ya que nos permite saber sobre la cantidad de los materiales y sacar u
presupuesto de la obra o costo en obra.
Es muy importante redimensionar los y metrar una edificación para que este
dure mas y resulte economica
pág. 96
BIBLIOGRAFÍA Y REFERENCIAS PERSONALES
- http://gis.proviasnac.gob.pe/expedientes/2011/LP%20009-
2011/INFORME%2005%20-%20VOL%2003%20-
%20METRADOS.pdf
- https://www.udocz.com/read/informe-de-metrados---metodología-
a-
pág. 97