Sei sulla pagina 1di 28

SANITARY DATA (2019-20)

Municipal Area Allowance 20%


Overheads and Contractor's profit 13.615%
1 Supplying and laying, jointing and testing SWG SP-1 pipes of ISI make conforming to ISI 651 & 4127 with air tight
cement joints in cm (1½:1) prop, including excavation of trenches and socket pits in any soils (except rock requiring
blasting) up to 914.4 mm (3'0") depth and refilling watering and tamping etc complete for finished item of work

A 101.4 mm (4") dia UNIT 1 Rmt


Material TBSP-A.I-02 1 Rmt 425 1 Rmt 425.00

TBSP-A.III- Applicable Municipal Area 20% 265 53.00


01 Allowance
Applicable Overheads and 13.615% 478.00 65.08
Contractor's profit
Total 543.08
Rate per 1 Rmt Say 543.00

B 152.4 mm (6") dia UNIT 1 Rmt


Material TBSP-A.I-04 1 Rmt 633 1 Rmt 633.00

TBSP-A.III- Applicable Municipal Area 20% 265 53.00


01 Allowance
Applicable Overheads and 13.615% 686.00 93.40
Contractor's profit
Total 779.40
Rate per 1 Rmt Say 779.00

2 Supplying and laying, jointing and testing SWG SP-1 pipes of ISI make conforming to ISI 651 & 4127 with air tight
cement joints in cm (1½:1) prop, including excavation of trenches and socket pits in any soils (except rock requiring
blasting) up to 1524mm (5'.0") depth and refilling watering and tamping etc complete for finished item of work

A 101.6 mm (4") dia UNIT 1 Rmt


Material TBSP-A.I-01 1 Rmt 493 1 Rmt 493.00

TBSP-A.III- Applicable Municipal Area 20% 329.00 65.80


02 Allowance
Applicable Overheads and 13.615% 558.80 76.08
Contractor's profit
Total 634.88
Rate per 1 Rmt Say 635.00

B 152.4 mm (6") dia UNIT 1 Rmt


Material TBSP-A.I-03 1 Rmt 712 1 Rmt 712.00

TBSP-A.III- Applicable Municipal Area 20% 329.00 65.80


02 Allowance
Applicable Overheads and 13.615% 777.80 105.90
Contractor's profit
Total 883.70
Rate per 1 Rmt Say 884.00

C 203.2 mm (8") dia UNIT 1 Rmt


Material TBSP-A.II- Supply 1 Rmt 504 1 Rmt 504.00
03
TBSP-A.III- Labour charges 1 Rmt 329 1 Rmt 329.00
02
TBSP-A.III- Applicable Municipal Area 20% 329.00 65.80
02 Allowance
Applicable Overheads and 13.615% 898.80 122.37
Contractor's profit
Total 1021.17
Rate per 1 Rmt Say 1021.00

7 Supplying & fixing 150 mm x 100 mm SWG gully traps conforming to ISI 651 & 4127 with C.I Grating & constructing
Brick masonry in CM 1:6 prop. over a C.C. (1:5:10) prop. Bed 100mm thick and plastering 12mm thick in CM (1:4)
prop. both inside and outside surfaces and fitted with 304.8 mm x 288.6mm (12" x 9") C.I. frame and hinged cover
of standard make as directed by the Engineer-in-charge including cost & conveyance to site, labour charges, etc.
complete for finished item of work. (APSS No 1326)

UNIT 1 Each
Material TBSP-A.I-09 1 No 622 1 No 622.00

Applicable Overheads and 13.615% 622 84.69


Contractor's profit
Total 706.69
Rate per 1 Each Say 707.00

B MAN HOLES & INSPECTION CHAMBERS - AS PER - IS 4111 : Part 1 :


1986
8 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement
mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing
strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 904 mm (3'-0") in all sorts
of soils (excluding rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4
benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site,cost of excluding seigniorage on all materials and all
incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing
etc., complete for finished item of work as per Standard specification. 3'-0" Depth

A 3'-0" Depth UNIT 1 Each


Material TBSP-B.I-03 1 No 7357 1 No 7357.00

Applicable Overheads and 13.615% 7357.00 1001.66


Contractor's profit
Total 8358.66
Rate per 1 Each Say 8359.00
9 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement
mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing
strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 1524 mm (5'-0") in all sorts
of soils (excluding rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4
benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of excluding seigniorage charges on all materials and all
incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing
etc., complete for finished item of work as per Standard specification. 5'-0" Depth

B 5'-0" Depth UNIT 1 Each


Material TBSP-B.I-04 1 No 11,707.00 1 No 11707.00

Applicable Overheads and 13.615% 11707.00 1593.91


Contractor's profit
Total 13300.91
Rate per 1 Each Say 13301.00

10 Constructing 904.0 mm (3’0”) dia solid block masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using fly-ash blocks of 225 mm thick from approved source having a minimum crushing
strength of 10 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 904 mm (3'-0") in all sorts
of soils (excluding rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4
benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of excluding seigniorage charges on all materials and all
incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing
etc., complete for finished item of work as per Standard specification. 3'-0" Depth

A 3'-0" Depth UNIT 1 Each


Material TBSP-B.I-01 1 No 7375 1 No 7375.00

Applicable Overheads and 13.615% 7375.00 1004.11


Contractor's profit
Total 8379.11
Rate per 1 Each Say 8379.00

11 Constructing 904.0 mm (3’0”) dia solid block masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using fly-ash blocks of 225 mm thick from approved source having a minimum crushing
strength of 10 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 1524 mm (5'-0") in all sorts
of soils (excluding rock) and laying cement concrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4
benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of excluding seigniorage charges on all materials and all
incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing
etc., complete for finished item of work as per Standard specification. 5'-0" Depth

B 5'-0" Depth UNIT 1 Each


Material TBSP-B.I-02 1 No 11752 1 No 11752.00

Applicable Overheads and 13.615% 11752.00 1600.03


Contractor's profit
Total 13352.03
Rate per 1 Each Say 13352.00
12 Constructing 914.4 mm x 457.2 mm (3'0"x1'6") brick in CM 1:6 prop. Masonry Inspection chamber up to 914.4
mm (3'0") and fitted with light weight 914.4 mm x 457.2 mm (3'0"x1'6") C.I frame and cover of 40 Kg.

UNIT 1 Each
Material TBSP-B.II- 1 No 6356 1 No 6356.00
01
Applicable Overheads and 13.615% 6356.00 865.37
Contractor's profit
Total 7221.37
Rate per 1 Each Say 7221.00

13 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber up to 914.4
mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover of 20 Kg.

UNIT 1 Each
Material TBSP-B.II- 1 No 3832 1 No 3832.00
02
Applicable Overheads and 13.615% 3832.00 521.73
Contractor's profit
Total 4353.73
Rate per 1 Each Say 4354.00

C C.I. PIPES & FITTINGS - AS PER - IS 1729:1979


14 Supplying and fixing of Cast Iron pipes & fittings as per IS:1729-1979 of reputed make with cement caulked joints
and fixing all specials such as plug bends, offsets, single junctions, C.I. cowls, double junctions etc., as per site
requirements including painting black with Japan paint and fixing with necessary wooden blocks fixed in the
masonry walls in cement mortar (1½:1)and including fixing of M.S. clamps as per necessity with required no.of
Bombay nails etc., complete at all floor levels including cost & conveyance of all materials, labour charges, etc.
complete for finished item of work (A.P.S.S. Nos. 1302 & 1319)

A 3" dia (76.2 mm) UNIT 3 Rmt


Material TBSP-C.I-01 S&F 3" dia (76.2 mm) Single Socket 3 Rmt 755 1 Rmt 2265.00

TBSP-C.II- Supplying & fixing CI Plain bends Ist 1 No 294 1 No 294.00


01 quality ISI marked - for 3" dia (75
mm)
TBSP-C.II- Supplying & fixing CI Plug (Door) 1 No 365 1 No 365.00
04 bends Ist quality ISI marked - for 3"
dia (75 mm)
TBSP-C.II- Supplying and Fixing of 75mm C.I. 1 No 296 1 No 296.00
19 Offsets Ist quality -for 76.20 mm
(3") C.I. Pipe
TBSP-H.II- 75 mm dia - Vent Cowl - UPVC/SWR 1 No 14 1 No 14.00
53 Pipe fittings
TBSP-C.III- Applicable Municipal Area 20% 774.00 154.80
01 Allowance -Single socket pipe for 3
RM
TBSP-C.III- Applicable Municipal Area 20% 82 16.40
02 Allowance - for Plain bend
TBSP-C.III- Applicable Municipal Area 20% 82 16.40
02 Allowance - for CI Plug (Door)
bends
TBSP-C.III- Applicable Municipal Area 20% 51 10.20
05 Allowance -for C.I. Offsets
Applicable Overheads and 13.615% 3431.80 467.24
Contractor's profit
Rate for 3 Rmt Total 3899.04
Rate per 1 Rmt Say 1300.00

B 4" dia (101.6mm) UNIT 3 Rmt


Material TBSP-C.I-02 4" dia (101.6mm) Single Socket 3 Rmt 993 1 Rmt 2979.00

TBSP-C.II- Supplying & fixing CI Plain bends Ist 1 No 372 1 No 374.00


02 quality ISI marked - for 4" dia
(101.6 mm)
TBSP-C.II- Supplying & fixing CI Plug (Door) 1 No 452 1 No 452.00
05 bends Ist quality ISI marked - for 4"
dia (101.6 mm)
TBSP-C.II- Supplying and Fixing of 75mm C.I. 1 No 414 1 No 414.00
20 Offsets Ist quality -for 101.6 mm
(4") C.I. Pipe
TBSP-H.II- 110 mm dia - Vent Cowl - 1 No 19 1 No 19.00
55 UPVC/SWR Pipe fittings
TBSP-C.III- Applicable Municipal Area 20% 774.00 154.80
01 Allowance -Single socket pipe
TBSP-C.III- Applicable Municipal Area 20% 82.00 16.40
02 Allowance - for Plain bend
TBSP-C.III- Applicable Municipal Area 20% 82.00 16.40
02 Allowance - for CI Plug (Door)
bends
TBSP-C.III- Applicable Municipal Area 20% 51.00 10.20
05 Allowance -for C.I. Offsets
Applicable Overheads and 13.615% 4435.80 603.93
Contractor's profit
Rate for 3 Rmt Total 5039.73
Rate per 1 Rmt Say 1680.00

15 Supplying & fixing CI floor traps 1st quality ISI marked conforming to IS:1729-1979 with C.P. Grating fixing with
white cement as per site requirements with standard practice for nominal dia 75 mm (3") and grating size 100 mm
dia of weight not less than 4.0 Kgs

UNIT 1 Each
Material TBSP-C.II- 1 No 328 1 No 328.00
30
TBSP-C.III- Applicable Municipal Area 20% 67 13.40
06 Allowance
Applicable Overheads and 13.615% 341.40 46.48
Contractor's profit
Total 387.88
Rate per 1 Each Say 388.00

16 Supplying & fixing CI floor traps 1st quality ISI marked with C.P. Grating fixing with white cement as per site
requirements with standard practice for nominal dia 100 mm (4") and grating size 100 mm dia of weight not less
than 6 Kgs
UNIT 1 Each
Material TBSP-C.II- 1 No 656 1 No 656.00
29
TBSP-C.III- Applicable Municipal Area 20% 67 13.40
06 Allowance
Applicable Overheads and 13.615% 669.40 91.14
Contractor's profit
Total 760.54
Rate per 1 Each Say 761.00

D VITREOUS CHINAWARE - SANITARY APPLIANCES as per IS:2556 - 1974


17 Supplying & Fixing Orissa Pan White glazed W.C 1st quality ISI marked conforming to IS:2556-Part-3-1981 with "P"
or "S" trap Hindware/ Parryware/ Neycer - ISI Mark: 580 mm x 440 mm duly providing constructing Brick masonry
seat using 2nd class bricks, CC Squatting plate in P.C.C 1:2:4, S&F PVC Low level system with internal components &
short bend: 10 Litres capacity Single Flush, S&F of 15 mm brass angle stop valve of quarter turn spindle type of
not less than 400 grams weight with internal threaded conforming to IS 8931 and S&F 15 mm nominal size PVC
connection with brass union nut C.P coated including cost and conveyance of all materials and labour charges,
overheads and contractor's profit etc.,. complete as per standard practice for finished item of work.

White UNIT 1 Each


Material TBSP-E.I-03 Supplying & Fixing Orissa Pan white 1 Each 1313 1 Each 1313.00
glazed W.C 1st quality ISI marked
conforming to IS:2556-Part-3-1981
with "P" or "S" trap Hindware/
Parryware/ Neycer - ISI Mark: 580
mm x 440 mm

TBSP-E.I-06 Providing Brick masonry seat for 1 Each 272 1 Each 272.00
Orissa pan/ Indian W.C. using 2nd
class bricks as per standard practice

TBSP-E.I-07 Providing Cement Concrete 1 Each 82 1 Each 82.00


Squatting plate for Orissa pan/
Indian W.C. in P.C.C. 1:2:4 as per
standard practice

TBSP-H.II- Supply & fixing of PVC low level 1 Each 1446 1 Each 1446.00
07 system with internal components &
short bend: 10 Litres capacity Single
Flush

TBSP-F.IV- S&F of 15 mm brass angle stop 1 Each 554 1 Each 554.00


07 valve of quarter turn spindle type of
not less than 400 grams weight with
internal threaded onforming to IS
8931

TBSP-J.I-32 Supplying & Fixing 15 mm nominal 1 Each 102 1 Each 102.00


size PVC connection with
brass union nut C.P coated
TBSP-F.VII- S&F brass body plumber union of 1 Each 63 1 Each 63.00
30 size 31.75 mm dia with
check nut
TBSP-J.I-31 S & F 76.2 x 101.6 mm teak wood 2 Each 24 48.00
block complete
TBSP-E.VIII- Applicable Municipal Area 20% 429 85.80
02 Allowance - FOR Orissa Pan

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - FOR Angle stop cock
Applicable Overheads and 13.615% 3986.40 542.75
Contractor's profit
Total 4529.15
Rate per 1 Each Say 4529.00

17 Supplying & Fixing Orissa Pan COLOUR glazed W.C 1st quality ISI marked conforming to IS:2556-Part-3-1981 with
"P" or "S" trap Hindware/ Parryware/ Neycer - ISI Mark: 580 mm x 440 mm duly providing constructing Brick
masonry seat using 2nd class bricks, CC Squatting plate in P.C.C 1:2:4, S&F PVC Low level system with internal
components & short bend: 10 Litres capacity Single Flush, S&F of 15 mm brass angle stop valve of quarter turn
spindle type of not less than 400 grams weight with internal threaded conforming to IS 8931 and S&F 15 mm
nominal size PVC connection with brass union nut C.P coated including cost and conveyance of all materials and
labour charges, overheads and contractor's profit etc.,. complete as per standard practice for finished item of
work.

COLOUR UNIT 1 Each


Material TBSP-E.I-03 Supplying & fixing approved make 1 Each 1313 1 Each 1313.00
Orissa Pan white glazed W.C 1st
quality ISI marked conforming to
IS:2556-Part-3-1981 with "P" or "S"
trap Hindware/ Parryware/ Neycer -
ISI Mark: 580 mm x 440 mm

For basic rate of 1306- fixing charges


Coloured Orissa pan i.e.,1306-409 = 1057
50% extra for coloured items 50% 884.00 442.00
TBSP-E.I-06 Providing Brick masonry seat for 1 Each 272 1 Each 272.00
Orissa pan/ Indian W.C. using 2nd
class bricks as per standard practice

TBSP-E.I-07 Providing Cement Concrete 1 Each 82 1 Each 82.00


Squatting plate for Orissa pan/
Indian W.C. in P.C.C. 1:2:4 as per
standard practice

TBSP-H.II- Supply & fixing of PVC low level 1 Each 1446 1 Each 1446.00
07 system with internal components &
short bend: 10 Litres capacity Single
Flush

50% extra for coloured items 50% 1446.00 723.00


TBSP-F.IV- S&F of 15 mm brass angle stop 1 Each 554 1 Each 554.00
07 valve of quarter turn spindle type of
not less than 400 grams weight with
internal threaded onforming to IS
8931

TBSP-J.I-32 Supplying & Fixing 15 mm nominal 1 Each 102 1 Each 102.00


size PVC connection with
brass union nut C.P coated
TBSP-J.I-31 S & F 76.2 x 101.6 mm teak wood 2 Each 24 48.00
block complete
TBSP-E.VIII- Applicable Municipal Area 20% 429 85.80
02 Allowance - FOR Orissa Pan

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - FOR Angle stop cock
Applicable Overheads and 13.615% 5088.40 692.79
Contractor's profit
Total 5781.19
Rate per 1 Each Say 5781.00
19 Supplying and fixing approved make wash down European Water Closet of 1st quality conforming to IS:2556-Part-
2- 2004 of white glazed with 'S' trap with CI short Connector & 4" dia CP thimble pipe: 150 mm long, best Indian
make plastic seat and lid for European water closets with rubber or plastic Buffers as per IS 2548-1996, PVC low
level system with internal components & short bend: 10 Litres capacity Single Flush, 15 mm brass angle stop valve
of quarter turn spindle type of not less than 400 grams weight with internal threaded conforming to IS 8931 and
15 mm nominal size PVC connection with brass union nut C.P coated all of approved make, including cost and
conveyance of all materials and labour charges, overheads and contractor's profit etc.,. complete as per standard
practice for finished item of work.

White UNIT 1 Each


Material TBSP-E.II- Supplying and fixing approved make 1 Each 1627 1 Each 1627.00
02 wash down European Water Closet
of 1st quality conforming to
IS:2556-Part-2-
2004 of white glazed with 'S' trap

TBSP-E.V- Supplying and Fixing best Indian 1 Each 738 1 Each 738.00
01 make plastic seat and lid for
European water closets with rubber
or plastic Buffers as per IS 2548-
1996

TBSP-H.II- Supply & fixing of PVC low level 1 Each 1446 1 Each 1446.00
07 system with internal components &
short bend: 10 Litres capacity Single
Flush

TBSP-F.IV- S&F of 15 mm brass angle stop 1 Each 554 1 Each 554.00


07 valve of quarter turn spindle type of
not less than 400 grams weight with
internal threaded onforming to IS
8931

TBSP-J.I-32 Supplying & Fixing 15 mm nominal 1 Each 102 1 Each 102.00


size PVC connection with
brass union nut C.P coated
TBSP-F.VII- S&F 4" dia CP thimble pipe: 150 1 Each 377 1 Each 377.00
32 mm long
TBSP-J.I-31 S & F 76.2 x 101.6 mm teak wood 2 Each 24 48.00
block complete
TBSP-E.VIII- Applicable Municipal Area 20% 301 60.20
06 Allowance - For EWC

TBSP-E.VIII- Applicable Municipal Area 20% 87 17.40


07 Allowance - For SEAT

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - FOR ANGLE Valve
Applicable Overheads and 13.615% 4990.20 679.42
Contractor's profit
Total 5669.62
Rate per 1 Each Say 5670.00
19 Supplying and fixing approved make wash down European Water Closet of 1st quality conforming to IS:2556-Part-
2- 2004 of COLOUR glazed with 'S' trap with CI short Connector & 4" dia CP thimble pipe: 150 mm long, best
Indian make plastic seat and lid for European water closets with rubber or plastic Buffers as per IS 2548-1996, PVC
low level system with internal components & short bend: 10 Litres capacity Single Flush, 15 mm brass angle stop
valve of quarter turn spindle type of not less than 400 grams weight with internal threaded conforming to IS 8931
and 15 mm nominal size PVC connection with brass union nut C.P coated all of approved make, including cost and
conveyance of all materials and labour charges, overheads and contractor's profit etc.,. complete as per standard
practice for finished item of work.

Coloured UNIT 1 Each


Material TBSP-E.II- Supplying and fixing approved make 1 Each 1627 1 Each 1627.00
02 wash down European Water Closet
of 1st quality conforming to
IS:2556-Part-2-
2004 of white glazed with 'S' trap

For Colour; basic rate 1619- fixing charges


of EWC i.e.,1619-287 = 1516
50% extra for coloured items 50% 1326.00 663.00
TBSP-E.V- Supplying and Fixing best Indian 1 Each 738 1 Each 738.00
01 make plastic seat and lid for
European water closets with rubber
or plastic Buffers as per IS 2548-
1996

TBSP-H.II- Supply & fixing of PVC low level 1 Each 1446 1 Each 1446.00
07 system with internal components &
short bend: 10 Litres capacity Single
Flush

50% extra for coloured items 50% 1446.00 723.00


TBSP-F.IV- S&F of 15 mm brass angle stop 1 Each 554 1 Each 554.00
07 valve of quarter turn spindle type of
not less than 400 grams weight with
internal threaded onforming to IS
8931

TBSP-J.I-32 Supplying & Fixing 15 mm nominal 1 Each 102 1 Each 102.00


size PVC connection with
brass union nut C.P coated
TBSP-F.VII- S&F 4" dia CP thimble pipe: 150 1 Each 377 1 Each 377.00
32 mm long
TBSP-J.I-31 S & F 76.2 x 101.6 mm teak wood 2 Each 24 48.00
block complete
TBSP-E.VIII- Applicable Municipal Area 20% 301 60.20
06 Allowance - For EWC

TBSP-E.VIII- Applicable Municipal Area 20% 87 17.40


07 Allowance - For SEAT

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - FOR ANGLE Valve
Applicable Overheads and 13.615% 6376.20 868.12
Contractor's profit
Total 7244.32
Rate per 1 Each Say 7244.00
21 Supply, Installation and commissioning approved make floor mounted Close Coupled wash down EWC conforming
to IS:2556 (Part 8)-2004 suit with 'P' or 'S' trap with dual flush porcelain cistern fixed on wash down EWC with all
internal parts of dual flush cistern, ultra solid seat cover of approved make with rubber buffer and cap & 15 mm
angle stop cock & 450 mm long PVC inter connection pipe wall flanges all of approved make, including cost and
conveyance of all materials, overheads and contractor's profit etc. complete for finished item of work in all
respects: White Colour

UNIT 1 Each
Material TBSP-E.II- 1 Each 8026 1 Each 8026.00
04
TBSP-E.VIII- Applicable Municipal Area 20% 301 60.20
06 Allowance - For EWC

Applicable Overheads and 13.615% 8086.20 1100.94


Contractor's profit
Total 9187.14
Rate per 1 Each Say 9187.00

21 Supply, Installation and commissioning approved make floor mounted Close Coupled wash down EWC conforming
to IS:2556 (Part 8)-2004 suit with 'P' or 'S' trap with dual flush porcelain cistern fixed on wash down EWC with all
internal parts of dual flush cistern, ultra solid seat cover of approved make with rubber buffer and cap & 15 mm
angle stop cock & 450 mm long PVC inter connection pipe wall flanges all of approved make, including cost and
conveyance of all materials, overheads and contractor's profit etc. complete for finished item of work in all
respects: Coloured - Grade - I/ Grade - II

UNIT 1 Each
Material TBSP-E.II- 1 Each 11730 1 Each 11730.00
05
TBSP-E.VIII- Applicable Municipal Area 20% 301 60.20
06 Allowance - For EWC

Applicable Overheads and 13.615% 11790.20 1605.24


Contractor's profit
Total 13395.44
Rate per 1 Each Say 13395.00

21 Supply, Installation and commissioning approved make floor mounted Close Coupled wash down EWC conforming
to IS:2556 (Part 8)-2004 with 'P' or 'S' trap with dual flush porcelain cistern fixed on wash down EWC with all
internal parts of dual flush cistern, ultra solid seat cover of approved make with rubber buffer and cap & 15 mm
angle stop cock & 450 mm long PVC inter connection pipe wall flanges all of approved make etc., including cost
and conveyance of all materials, overheads and contractor's profit etc. complete for finished item of work in all
respects: Special Colour - Grade - III

UNIT 1 Each
Material TBSP-E.II- 1 Each 14940 1 Each 14940.00
06
TBSP-E.VIII- Applicable Municipal Area 20% 301 60.20
06 Allowance - For EWC

Applicable Overheads and 13.615% 15000.20 2042.28


Contractor's profit
Total 17042.48
Rate per 1 Each Say 17042.00
24 Supplying & Fixing Indian make WHITE Flat Back Wash Hand Basin of size 550 x 400 mm with Single C.P. Pillar cock
1st quality conforming to IS:2556-Part-4:1972 with waste fittings like rubber plug, chain, 32 mm nominal size C.P.
Fitting with parallel pipe thread conforming to IS:2963- 1979 and fitted with 15 mm nominal bore Chromium
Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/Senior/ Nice/ Esso or equivalent, 15 mm brass angle
stop valve of quarter turn spindle type of not less than 400 grams weight with internal threaded onforming to IS
8931, 15 mm nominal size PVC connection with brass union nut C.P coated, 30 mm nominal size dia PVC flexible
waste pipe of 914.4 mm length of Ist quality and standard CI brackets including wooden block, including cost and
conveyance of all materials, overheads and contractor's profit etc. complete for finished item of work in all
respects.

UNIT 1 Each
Material TBSP-E.VI- Flat Back Wash Hand Basin 550 x 1 Each 1476 1 Each 1476.00
04 400 mm
TBSP-F.IV- S&F of 15 mm brass angle stop 1 Each 554 1 Each 554.00
07 valve of quarter turn spindle type of
not less than 400 grams weight with
internal threaded onforming to IS
8931

TBSP-J.I-32 Supplying & Fixing 15 mm nominal 1 Each 102 1 Each 102.00


size PVC connection with
brass union nut C.P coated
TBSP-H.II- Supply & fixing 30 mm nominal 1 Each 26 1 Each 26.00
04 sizedia PVC flexible waste pipe of
914.4 mm length of Ist quality
TBSP-E.VIII- Applicable Municipal Area 20% 429 85.80
08 Allowance - For Wash Hand basin

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - FOR ANGLE Valve
Deduct TBSP-J.I- Supplying & Fixing NP chain rubber 1 Each -38 1 Each -38.00
24 and plug for basin
Applicable Overheads and 13.615% 2226.40 303.12
Contractor's profit
Total 2529.52
Rate per 1 Each Say 2530.00

24 Supplying & Fixing Indian make COLOURED Flat Back Wash Hand Basin of size 550 x 400 mm with Single C.P. Pillar
cock 1st quality conforming to IS:2556-Part-4:1972 with waste fittings like rubber plug, chain, 32 mm nominal size
C.P. Fitting with parallel pipe thread conforming to IS:2963- 1979 and fitted with 15 mm nominal bore Chromium
Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/Senior/ Nice/ Esso or equivalent, 15 mm brass angle
stop valve of quarter turn spindle type of not less than 400 grams weight with internal threaded onforming to IS
8931, 15 mm nominal size PVC connection with brass union nut C.P coated, 30 mm nominal size dia PVC flexible
waste pipe of 914.4 mm length of Ist quality and standard CI brackets including wooden block, including cost and
conveyance of all materials, overheads and contractor's profit etc. complete for finished item of work in all
respects.

UNIT 1 Each
Material TBSP-E.VI- Flat Back Wash Hand Basin 550 x 1 Each 1476 1 Each 1476.00
04 400 mm
For basic rate of 1476- fixing charges(TBSP-F.II-01)- pillar cock- chain with rubber
coloured WHB plug(TBSP-J.I-24) i.e.,1476-429-571-38 = 438
50% extra over basic rate for 50% 438.00 219.00
coloured items
TBSP-F.IV- S&F of 15 mm brass angle stop 1 Each 554 1 Each 554.00
07 valve of quarter turn spindle type of
not less than 400 grams weight with
internal threaded onforming to IS
8931

TBSP-J.I-32 Supplying & Fixing 15 mm nominal 1 Each 102 1 Each 102.00


size PVC connection with
brass union nut C.P coated
TBSP-H.II- Supply & fixing 30 mm nominal 1 Each 26 1 Each 26.00
04 sizedia PVC flexible waste pipe of
914.4 mm length of Ist quality
TBSP-E.VIII- Applicable Municipal Area 20% 429 85.80
08 Allowance - For Wash Hand basin

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - FOR ANGLE Valve
Deduct TBSP-J.I- Supplying & Fixing NP chain rubber 1 Each -38 1 Each -38.00
24 and plug for basin

Applicable Overheads and 13.615% 2445.40 332.94


Contractor's profit
Total 2778.34
Rate per 1 Each Say 2778.00

31 Supplying & Fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with internal flushing
rim fixed with screws complete Indian make conforming to IS:2556-1995, fitted with 15 mm brass body CP finish
self closing tap push type conforming to IS 1711 and 30 mm nominal size dia PVC flexible waste pipe of 914.4 mm
length of Ist quality including cost and conveyance of all materials, overheads and contractor's profit etc. complete
for finished item of work in all respects.

UNIT 1 Each
Material TBSP-E.VII- Flat back Bowl urinals of size 440 1 Each 771 1 Each 771.00
01 mm x 265 mm x 315 mm
TBSP-F.III- S&F of 15 mm brass body CP finish 1 Each 247 1 Each 247.00
01 self closing tap push type
conforming to IS 1711
TBSP-H.II- Supply & fixing 30 mm nominal size 1 Each 26 1 Each 26.00
04 dia PVC flexible waste pipe of 914.4
mm length of Ist quality
TBSP-E.VIII- Applicable Municipal Area 20% 171 34.20
11 Allowance - For Urinal

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - stop Valve
Applicable Overheads and 13.615% 1098.80 149.60
Contractor's profit
Total 1248.40
Rate per 1 Each Say 1248.00

31 Supplying & Fixing white glazed flat back half stall urinals 1st quality conforming to IS:2556-1995 with standard
C.P. Spreader fixed with screws complete Indian make : 590 x 375 x 390 mm, fitted with 15 mm brass body CP
finish self closing tap push type conforming to IS 1711 and 30 mm nominal size dia PVC flexible waste pipe of
914.4 mm length of Ist quality including cost and conveyance of all materials, overheads and contractor's profit
etc. complete for finished item of work in all respects.

UNIT 1 Each
Material TBSP-E.VII- Flat back Bowl urinals of size 440 1 Each 2568 1 Each 2568.00
03 mm x 265 mm x 315 mm
TBSP-F.III- S&F of 15 mm brass body CP finish 1 Each 247 1 Each 247.00
01 self closing tap push type
conforming to IS 1711
TBSP-H.II- Supply & fixing 30 mm nominal size 1 Each 26 1 Each 26.00
04 dia PVC flexible waste pipe of 914.4
mm length of Ist quality
TBSP-E.VIII- Applicable Municipal Area 20% 171 34.20
11 Allowance - For Urinal

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - stop Valve
Applicable Overheads and 13.615% 2895.80 394.26
Contractor's profit
Total 3290.06
Rate per 1 Each Say 3290.00

31 Supplying & Fixing COLOURED glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with internal
flushing rim fixed with screws complete Indian make conforming to IS:2556-1995, fitted with 15 mm brass body CP
finish self closing tap push type conforming to IS 1711 and 30 mm nominal size dia PVC flexible waste pipe of
914.4 mm length of Ist quality including cost and conveyance of all materials, overheads and contractor's profit
etc. complete for finished item of work in all respects.

UNIT 1 Each
Material TBSP-E.VII- Flat back Bowl urinals of size 440 1 Each 771 1 Each 771.00
01 mm x 265 mm x 315 mm
For basic rate of 771 - fixing charges
coloured Urinal i.e.,771-171= 600
50% extra over basic rate for 50% 600.00 300.00
TBSP-F.III- coloured
S&F of 15items
mm brass body CP finish 1 Each 247 1 Each 247.00
01 self closing tap push type
conforming to IS 1711
TBSP-H.II- Supply & fixing 30 mm nominal 1 Each 26 1 Each 26.00
04 sizedia PVC flexible waste pipe of
914.4 mm length of Ist quality
TBSP-E.VIII- Applicable Municipal Area 20% 171 34.20
11 Allowance - For Urinal

TBSP-F.VIII- Applicable Municipal Area 20% 103 20.60


02 Allowance - stop Valve
Add for Woden Gutties, nails, black paint etc LS 13.51
Applicable Overheads and 13.615% 1398.80 190.45
Contractor's profit
Total 1602.76
Rate per 1 Each Say 1603.00

E TAPS & FAUCETS


34 S&F of 15 mm brass body CP finish long body bib tap of not less than 400 grams weight with quarter turn spindle
internal / external threaded connection conforming to IS 8931

UNIT 1 Each
Material TBSP-F.I-08 1 Each 697 1 Each 697.00

TBSP-F.VIII- Applicable Municipal Area 20% 53 10.60


01 Allowance
Applicable Overheads and 13.615% 707.60 96.34
Contractor's profit
Total 803.94
Rate per 1 Each Say 804.00

34 S&F of 15 mm brass body CP finish bib tap of not less than 300 grams weight screw type (full turn) with internal /
external threaded conenction conforming to IS 8931

UNIT 1 Each
Material TBSP-F.I-01 1 Each 224 1 Each 224.00

TBSP-F.VIII- Applicable Municipal Area 20% 53 10.60


01 Allowance
Applicable Overheads and 13.615% 234.60 31.94
Contractor's profit
Total 266.54
Rate per 1 Each Say 267.00

34 S&F of 15 mm brass body CP finish bib tap of not less than 300 grams weight with quarter turn spindle with either
internal or external threaded conenction conforming to IS 8931

UNIT 1 Each
Material TBSP-F.I-02 1 Each 546 1 Each 546.00

TBSP-F.VIII- Applicable Municipal Area 20% 53 10.60


01 Allowance
Applicable Overheads and 13.615% 556.60 75.78
Contractor's profit
Total 632.38
Rate per 1 Each Say 632.00

F G.I. PIPES & FITTINGS


36 S & F Bronze Gate/ Globe valve as per IS - 778 Class - I,Indian make heavy type as approved by the Engineer
including cost & conveyance of all materials, labour charges, etc. complete for finished item of work in all floors as
directed by Engineer-in-charge.

15 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 580 1 Each 580.00
01
Applicable Overheads and 13.615% 580.00 78.97
Contractor's profit
Total 658.97
Rate per 1 Each Say 659.00

20 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 782 1 Each 782.00
02
Applicable Overheads and 13.615% 782.00 106.47
Contractor's profit
Total 888.47
Rate per 1 Each Say 888.00

25 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1125 1 Each 1125.00
03
Applicable Overheads and 13.615% 1125.00 153.17
Contractor's profit
Total 1278.17
Rate per 1 Each Say 1278.00

32 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1709 1 Each 1709.00
04
Applicable Overheads and 13.615% 1709.00 232.68
Contractor's profit
Total 1941.68
Rate per 1 Each Say 1942.00

40 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 2308 1 Each 2308.00
05
Applicable Overheads and 13.615% 2308.00 314.23
Contractor's profit
Total 2622.23
Rate per 1 Each Say 2622.00

50 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 3382 1 Each 3382.00
06
Applicable Overheads and 13.615% 3382.00 460.46
Contractor's profit
Total 3842.46
Rate per 1 Each Say 3842.00

65 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 5222 1 Each 5222.00
07
Applicable Overheads and 13.615% 5222.00 710.98
Contractor's profit
Total 5932.98
Rate per 1 Each Say 5933.00

43 Supplying & fixing Bronze Horizontal Check (Non return) Valve as per IS-778 I-class heavy duty as approved by the
Engineer including cost & conveyance of all materials, labour charges, etc. complete for finished item of work in all
floors as directed by Engineer-in-charge.

15 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 428 1 Each 428.00
09
Applicable Overheads and 13.615% 428.00 58.27
Contractor's profit
Total 486.27
Rate per 1 Each Say 486.00

20 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 626 1 Each 626.00
10
Applicable Overheads and 13.615% 626.00 85.23
Contractor's profit
Total 711.23
Rate per 1 Each Say 711.00

25 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 978 1 Each 978.00
11
Applicable Overheads and 13.615% 978.00 133.15
Contractor's profit
Total 1111.15
Rate per 1 Each Say 1111.00

32 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1435 1 Each 1435.00
12
Applicable Overheads and 13.615% 1435.00 195.38
Contractor's profit
Total 1630.38
Rate per 1 Each Say 1630.00

40 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1991 1 Each 1991.00
13
Applicable Overheads and 13.615% 1991.00 271.07
Contractor's profit
Total 2262.07
Rate per 1 Each Say 2262.00

48 Supplying & fixing Bronze Vertical Check (Non return) Valve as per IS-778 I-class heavy duty as approved by the
Engineer including cost & conveyance of all materials, labour charges, etc. complete for finished item of work in all
floors as directed by Engineer-in-charge.

15 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 404 1 Each 404.00
14
Applicable Overheads and 13.615% 404.00 55.00
Contractor's profit
Total 459.00
Rate per 1 Each Say 459.00

20 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 525 1 Each 525.00
15
Applicable Overheads and 13.615% 525.00 71.48
Contractor's profit
Total 596.48
Rate per 1 Each Say 596.00
25 mm Nominal Bore UNIT 1 Each
Material TBSP-G.III- 1 Each 794 1 Each 794.00
16
Applicable Overheads and 13.615% 794.00 108.10
Contractor's profit
Total 902.10
Rate per 1 Each Say 902.00

32 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1093 1 Each 1093.00
17
Applicable Overheads and 13.615% 1093.00 148.81
Contractor's profit
Total 1241.81
Rate per 1 Each Say 1242.00

40 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1322 1 Each 1322.00
18
Applicable Overheads and 13.615% 1322.00 179.99
Contractor's profit
Total 1501.99
Rate per 1 Each Say 1502.00

50 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 2096 1 Each 2096.00
19
Applicable Overheads and 13.615% 2096.00 285.37
Contractor's profit
Total 2381.37
Rate per 1 Each Say 2381.00

54 S & F Bronze Ball valve with SS Ball and SS Spindle as per IS - Class - I, Indian make heavy type as approved by the
Engineer including cost & conveyance of all materials, labour charges, etc. complete for finished item of work in all
floors as directed by Engineer-in-charge.

15 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 189 1 Each 189.00
20
Applicable Overheads and 13.615% 189.00 25.73
Contractor's profit
Total 214.73
Rate per 1 Each Say 215.00

20 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 274 1 Each 274.00
21
Applicable Overheads and 13.615% 274.00 37.31
Contractor's profit
Total 311.31
Rate per 1 Each Say 311.00
25 mm Nominal Bore UNIT 1 Each
Material TBSP-G.III- 1 Each 386 1 Each 386.00
22
Applicable Overheads and 13.615% 386.00 52.55
Contractor's profit
Total 438.55
Rate per 1 Each Say 439.00

32 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 684 1 Each 684.00
23
Applicable Overheads and 13.615% 684.00 93.13
Contractor's profit
Total 777.13
Rate per 1 Each Say 777.00

40 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 942 1 Each 942.00
24
Applicable Overheads and 13.615% 942.00 128.25
Contractor's profit
Total 1070.25
Rate per 1 Each Say 1070.00

50 mm Nominal Bore UNIT 1 Each


Material TBSP-G.III- 1 Each 1415 1 Each 1415.00
25
Applicable Overheads and 13.615% 1415.00 192.65
Contractor's profit
Total 1607.65
Rate per 1 Each Say 1608.00

66 Supplying, laying and jointing Nominal Bore GI pipe Medium Grade properties & weight as per IS 1239 ISI mark
with GI fittings including the cost of pipe & its fittings & labour charges complete, with necessary excavation in
all types of soils (except rock requiring blasting) refilling, chiseling masonry walls and making good the walls and
floors to the original surface, fixing M.S. clamps and T.W. block on walls wherever required, Brick support pillars
on terraces etc including cost & conveyance of all materials, labour charges, etc. complete for finished item of
work as directed by Engineer-in-charge.

15 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 185 1 Rmt 185.00
07
Applicable Overheads and 13.615% 185.00 25.19
Contractor's profit
Total 210.19
Rate per 1 Each Say 210.00

20 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 205 1 Rmt 205.00
08
Applicable Overheads and 13.615% 205.00 27.91
Contractor's profit
Total 232.91
Rate per 1 Each Say 233.00

25 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 269 1 Rmt 269.00
09
Applicable Overheads and 13.615% 269.00 36.62
Contractor's profit
Total 305.62
Rate per 1 Each Say 306.00

32 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 377 1 Rmt 377.00
10
Applicable Overheads and 13.615% 377.00 51.33
Contractor's profit
Total 428.33
Rate per 1 Each Say 428.00

40 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 422 1 Rmt 422.00
11
Applicable Overheads and 13.615% 422.00 57.46
Contractor's profit
Total 479.46
Rate per 1 Each Say 479.00

50 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 454 1 Rmt 454.00
12
Applicable Overheads and 13.615% 454.00 61.81
Contractor's profit
Total 515.81
Rate per 1 Each Say 516.00

65 mm Nominal Bore UNIT 1 Rmt


Material TBSP-G.I- 1 Rmt 806 1 Rmt 806.00
13
Applicable Overheads and 13.615% 806.00 109.74
Contractor's profit
Total 915.74
Rate per 1 Each Say 916.00

G PVC PIPES & FITTINGS


73 Providing & Placing on Terrace (at all floor levels) polyethylene water storage tank with Double layer approved
brand & manufacture with cover and suitable locking arrangement & making necessary holes for inlet & outlets
and over flow pipes but without fittings & base support for tanks, including overheads and contractor's profit
complete for finished item of work.

UNIT 1 Ltr
Material TBSP-H.II- 1 Ltr 7 1 Ltr 7.00
01
Applicable Overheads and 13.615% 7.00 0.95
Contractor's profit
Total 7.95
Rate per 1 Ltr Say 8.00

78 Supplying and fixing of SWR PVC pipes of 4 Kg/Sq.cm. and fixing all specials such as plain bends, off sets, door
bends, single junctions, double junctions as per site requirement, fixing with PVC clamps with required number of
Bombay nails etc with solvent jointing as per standard practice including cost and conveyance of all materials to
site, labour charges, overheads & contractors profit complete for finished item of work at all floor levels . (APSS
No. 1302 1319 & 1326)

A 75mm dia UNIT 3 Rmt


Material TBSP-H.I- 75 mm dia 3 M Double Socket 3 Rmt 285 3 Rmt 285.00
04 PVC/SWR pipe - 4 Kg/sq.cm
Market 75mm clamps 3 No 15 1 No 45.00
TBSP-H.II- 75 mm dia - Door Bend 87.5 Degree 1 No 67 1 No 67.00
13 - UPVC/SWR Pipe
fittings
TBSP-H.II- 75 mm dia - Single Tee with Door - 1 No 72 1 No 72.00
25 UPVC/SWR Pipe fittings
TBSP-H.II- 75 mm dia - Vent Cowl - UPVC/SWR 1 No 14 1 No 14.00
53 Pipe fittings
TBSP-H.IV- Labour charges for laying, fixing and 3 Rmt 79 237.00
01 commissioning the
PVC pipes including couplers/
bends/ tees etc any diameter
including fixing necessary fittings
like bends, plugs,
couplers, junctions, tees, etc with
solvent jointing as per
standard practice

Applicable Municipal Area 20% 237.00 47.40


Allowance
Applicable Overheads and 13.615% 767.40 104.48
Contractor's profit
Total 871.88
Rate per 1 Rmt Say 291

B 110mm dia UNIT 3 Rmt


Material TBSP-H.I- 110 mm dia 3 M Double Socket 3 Rmt 556 3 Rmt 556.00
06 PVC/SWR pipe - 4 Kg/sq.cm
Market 110mm clamps 3 No 18 1 No 54.00
TBSP-H.II- 110 mm dia - Door Bend 87.5 1 No 107 1 No 107.00
15 Degree - UPVC/SWR Pipe
fittings
TBSP-H.II- 110 mm dia - Single Tee with Door - 1 No 129 1 No 129.00
27 UPVC/SWR Pipe fittings
TBSP-H.II- 110 mm dia - Vent Cowl - 1 No 19 1 No 19.00
55 UPVC/SWR Pipe fittings
TBSP-H.IV- Labour charges for laying, fixing and 3 Rmt 79 237.00
01 commissioning the PVC pipes
including couplers/ bends/ tees etc
any diameter including fixing
necessary fittings like bends, plugs,
couplers, junctions, tees, etc with
solvent jointing as per standard
practice

Applicable Municipal Area 20% 237.00 47.40


Allowance
Applicable Overheads and 13.615% 1149.40 156.49
Contractor's profit
Total 1305.89
Rate per 1 Rmt Say 435

81 Supplying & fixing of 4" (101.6 mm ) multi floor trap with Jali- UPVC/SWR Pipe fittings including cost and
conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item of
work.

UNIT 1 Each
Material TBSP-H.II- 1 No 143 1 No 143.00
74
Applicable Overheads and 13.615% 143.00 19.47
Contractor's profit
Total 162.47
Rate per 1 Each Say 162.00

82 Supplying & fixing of 3" (75 mm nominal size ) Nahany Trap with Jali - UPVC/SWR Pipe fittings including cost and
conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item of
work.
UNIT 1 Each
Material TBSP-H.II- 1 No 101 1 No 101.00
73
Applicable Overheads and 13.615% 101.00 13.75
Contractor's profit
Total 114.75
Rate per 1 Each Say 115.00

83 Supplying & fixing of 4" (101.6) multi floor trap with out Jalli- UPVC/SWR Pipe fittings including cost and
conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item of
work.

UNIT 1 Each
Material TBSP-H.II- 1 No 111 1 No 111.00
75
Applicable Overheads and 13.615% 111.00 15.11
Contractor's profit
Total 126.11
Rate per 1 Each Say 126.00

I MISCELLANEOUS ITEMS
84 Chiselling the stone masonry wall for fixing of wooden blocks including finishing as directed by the department
labour charges, including overheads & contractors profit complete for finished item of work.
UNIT 1 Each
Material TBSP-J.I-03 1 No 31 1 No 31.00
Applicable Municipal Area 20% 31.00 6.20
Allowance
Applicable Overheads and 13.615% 37.20 5.06
Contractor's profit
Total 42.26
Rate per 1 Each Say 42.00

85 Chiselling the stone masonry wall and repairs as directed by the department labour charges, including overheads
& contractors profit complete for finished item of work.

UNIT 1 Rm
Material TBSP-J.I-04 1 RM 149 1 RM 149.00
Applicable Municipal Area 20% 149.00 29.80
Allowance
Applicable Overheads and 13.615% 178.80 24.34
Contractor's profit
Total 203.14
Rate per 1 Rm Say 203.00

86 Chiselling the brick masonry wall and repairs as directed by the department labour charges, including overheads &
contractors profit complete for finished item of work.

UNIT 1 Rm
Material TBSP-J.I-05 1 Rm 31 1 Rm 31.00
Applicable Municipal Area 20% 31.00 6.20
Allowance
Applicable Overheads and 13.615% 37.20 5.06
Contractor's profit
Total 42.26
Rate per 1 Rm Say 42.00

87 Cutting holes in C.C; basement & repairs Labour charges only including overheads & contractors profit complete
for finished item of work.
UNIT 1 Each
Material TBSP-J.I-20 1 No 112 1 No 112.00
Applicable Municipal Area 20% 112.00 22.40
Allowance
Applicable Overheads and 13.615% 134.40 18.30
Contractor's profit
Total 152.70
Rate per 1 Each Say 153.00

88 Cutting holes in stone masonry & basement and repairs Labour charges only including overheads & contractors
profit complete for finished item of work.

UNIT 1 Each
Material TBSP-J.I-21 1 No 75 1 No 75.00
Applicable Municipal Area 20% 75.00 15.00
Allowance
Applicable Overheads and 13.615% 90.00 12.25
Contractor's profit
Total 102.25
Rate per 1 Each Say 102.00

89 Cutting holes in Brick masonry & repairs Labour charges only including overheads & contractors profit complete
for finished item of work.

UNIT 1 Each
Material TBSP-J.I-22 1 No 49 1 No 49.00
Applicable Municipal Area 20% 49.00 9.80
Allowance
Applicable Overheads and 13.615% 58.80 8.01
Contractor's profit
Total 66.81
Rate per 1 Each Say 67.00

90 Cutting holes in RCC slab floor & repairs Labour charges only
UNIT 1 Each
Material TBSP-J.I-23 1 No 75 1 No 75.00
Applicable Municipal Area 20% 75.00 15.00
Allowance
Applicable Overheads and 13.615% 90.00 12.25
Contractor's profit
Total 102.25
Rate per 1 Each Say 102.00

91 Constructing Brick masonry support for G.I pipe with C.M 304.8 x 228.6 x228.6 mm size including plastering cost
& conveyance of all materials, labour charges, etc. and overhead & contractor's profit complete for finished item
of work in all floors as directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-B.II- 1 Each 77 1 Each 77.00
04
Applicable Overheads and 13.615% 77.00 10.48
Contractor's profit
Total 87.48
Rate per 1 Each Say 87.00

92 Supply and fixing CP finish brass soap dish of approved make with screws etc., complete for finished item of work
in all floors, including cost & conveyance of all materials, labour charges, etc. and overhead & contractor's profit
complete for finished item of work as directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-F.VII- 1 Each 517 1 Each 517.00
21
Applicable Overheads and 13.615% 517.00 70.39
Contractor's profit
Total 587.39
Rate per 1 Each Say 587.00

93 Supplying and fixingTV shape mirror with plastic frame size 609.6 mm x 457 .2 mm best quality glass mirror with
approved make 1st quality including cost & conveyance of all materials, labour charges, etc. overhead &
contractor's profit complete for finished item of work in all floors as directed by Engineer-in-charge.
UNIT 1 Each
Material TBSP-J.I-35 1 Each 468 1 Each 468.00
Applicable Overheads and 13.615% 468.00 63.72
Contractor's profit
Total 531.72
Rate per 1 Each Say 532.00

94 Supplying & fixing stainless steel sink size 36" x 18" (914.4x457.2mm) 1 mm thick with accessories including cost
& conveyance of all materials, labour charges, etc. overhead & contractor's profit complete for finished item of
work in all floors as directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-E.VI- 1 Each 6255 1 Each 6255.00
13
Applicable Overheads and 13.615% 6255.00 851.62
Contractor's profit
Total 7106.62
Rate per 1 Each Say 7107.00

95 Supplying & fixing SINGLE BOWL stainless steel sink size 24"x18"x8 " (609.6 x 457.2 x 203.2mm) 1 mm thick with
accessories including cost & conveyance of all materials, labour charges, etc. overhead & contractor's profit
complete for finished item of work in all floors as directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-E.VI- 1 Each 4932 1 Each 4932.00
14
Applicable Overheads and 13.615% 4932.00 671.49
Contractor's profit
Total 5603.49
Rate per 1 Each Say 5603.00
96 Supplying & fixing stainless steel sink size 20" x18" x 8 " (508x457.2x203.2mm) 1 mm thick with accessories
including cost & conveyance of all materials, labour charges, etc. overhead & contractor's profit complete for
finished item of work in all floors as directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-E.VI- 1 Each 4470 1 Each 4470.00
15
Applicable Overheads and 13.615% 4470.00 608.59
Contractor's profit
Total 5078.59
Rate per 1 Each Say 5079.00

96 S&F of 15 mm premium variety Chromium plated finish brass body wall mixer with hand shower with a provision
for over head shower with 115 mm long bend pipe on upper side, connecting legs & wall flanges conforming to IS
8931 with 10 years warranty overhead & contractor's profit complete for finished item of work in all floors as
directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-F.V-03 1 Each 3327 1 Each 3327.00

TBSP-F.VIII- Applicable Municipal Area 20% 183 36.60


03 Allowance
Applicable Overheads and 13.615% 3363.60 457.95
Contractor's profit
Total 3821.55
Rate per 1 Each Say 3822.00
96 S&F of Chromium plated finish stainless steel body Tumbler holder with 10 years warranty overhead &
contractor's profit complete for finished item of work in all floors as directed by Engineer-in-charge.
UNIT 1 Each
Material TBSP-F.VII- 1 Each 996 1 Each 996.00
40
Applicable Overheads and 13.615% 996.00 135.61
Contractor's profit
Total 1131.61
Rate per 1 Each Say 1132.00
96 S&F of Chromium plated finish stainless steel body Toilet paper holder with 10 years warranty overhead &
contractor's profit complete for finished item of work in all floors as directed by Engineer-in-charge.

UNIT 1 Each
Material TBSP-F.VII- 1 Each 796 1 Each 796.00
25
Applicable Overheads and 13.615% 796.00 108.38
Contractor's profit
Total 904.38
Rate per 1 Each Say 904.00
96 Supplying & fixing 4 " x 24 " (101.6x609.6mm) white glazed porcelain channel fixed in brick masonry white cement
pointing overhead & contractor's profit complete for finished item of work in all floors as directed by Engineer-in-
charge.

UNIT 1 Each
Material TBSP-E.VII- 1 Each 451 1 Each 451.00
04
Rate per 1 RM 739.83
Applicable Overheads and 13.615% 739.83 100.73
Contractor's profit
Total 840.56
Rate per 1 Rm Say 841.00

CPVC PIPES
97 S&F premium make CPVC Pipes including the cost of pipe & its fittings & labour charges complete including cost of
overheads & contractor profit etc. for finished item of work as directed by Engineer-in-charge

a S&F premium make CPVC Pipes of 15.90mm OD Pipe - SDR 13.5

UNIT 1 Rmt
Material TBSP-J.III- 1 Rmt 129 1 Rmt 129.00
01
Applicable Overheads and 13.615% 129.00 17.56
Contractor's profit
Value Added Tax ( Works Contract 0% 0.00
Tax)
Total 146.56
Rate per 1 RM Say 147.00

b S&F premium make CPVC Pipes of 22.20mm OD Pipe - SDR 13.5


UNIT 1 Rmt
Material TBSP-J.III- 1 Rmt 147 1 Rmt 147.00
02
Applicable Overheads and 13.615% 147.00 20.01
Contractor's profit
Value Added Tax ( Works Contract 0% 0.00
Tax)
Total 167.01
Rate per 1 Each Say 167.00

c S&F premium make CPVC Pipes of 28.60mm OD Pipe - SDR 13.5


UNIT 1 Rmt
Material TBSP-J.III- 1 Rmt 194 1 Rmt 194.00
03
Applicable Overheads and 13.615% 194.00 26.41
Contractor's profit
Value Added Tax ( Works Contract 0% 0.00
Tax)
Total 220.41
Rate per 1 Each Say 220.00

c S&F premium make CPVC Pipes of 34.90mm OD Pipe - SDR 13.5


UNIT 1 Rmt
Material TBSP-J.III- 1 Rmt 264 1 Rmt 264.00
04
Applicable Overheads and 13.615% 264.00 35.94
Contractor's profit
Value Added Tax ( Works Contract 0% 0.00
Tax)
Total 299.94
Rate per 1 Each Say 300.00

c S&F premium make CPVC Pipes of 41.30mm OD Pipe - SDR 13.5


UNIT 1 Rmt
Material TBSP-J.III- 1 Rmt 329 1 Rmt 329.00
05
Applicable Overheads and 13.615% 329.00 44.79
Contractor's profit
Value Added Tax ( Works Contract 0% 0.00
Tax)
Total 373.79
Rate per 1 Each Say 374.00

c S&F premium make CPVC Pipes of 54.00mm OD Pipe - SDR 13.5


UNIT 1 Rmt
Material TBSP-J.III- 1 Rmt 479 1 Rmt 479.00
06
Applicable Overheads and 13.615% 479.00 65.22
Contractor's profit
Value Added Tax ( Works Contract 0% 0.00
Tax)
Total 544.22
Rate per 1 Each Say 544.00

97 S&F of Chromium plated finish brass body quarter turn Bibcock cum Health Faucet with 1m long tube and wall
hook with 10 years warranty
UNIT 1 E
Material TBSP-F.I-07 1 e 2929 1 Rmt 2929.00

Applicable Overheads and 13.615% 2929.00 398.78


Contractor's profit
Total 3327.78
Rate per 1 Each Say 3328.00

97 S & F 25 mm nominal size dia & 609.6 mm long aluminium anodized towel rod with brackets and aluminium screws

UNIT 1 E
Material TBSP-J.I-25 1 e 150 1 Rmt 150.00
Applicable Overheads and 13.615% 150.00 20.42
Contractor's profit
Total 170.42
Rate per 1 Each Say 170.00

97 S & F 19.04 mm dia & 609.6 mm long aluminium anodized towel rod with brackets and aluminium screws

UNIT 1 E
Material TBSP-J.I-26 1 e 130 1 Rmt 130.00
Applicable Overheads and 13.615% 130.00 17.70
Contractor's profit
Total 147.70
Rate per 1 Each Say 148.00

97 S&F CP finish brass wall mounted towel ring


UNIT 1 E
Material TBSP-F.VII- 1 e 563 1 Rmt 563.00
13
Applicable Overheads and 13.615% 563.00 76.65
Contractor's profit
Total 639.65
Rate per 1 Each Say 640.00

31 Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0" x 2' 0" for urinals
including full rounding the edges , fixing in position, polishing, including cost and conveyance of all materials and
labour charges , overheads & contractors profit complete for finished item of work for all floors excluding cost of
seigniorage charges on marble.

UNIT 0.9 x 0.6 0.54


Material TBSC-B.II- Polished Marble slabs of any variety 0.54 sqm 907 1 sqm 489.78
03 and gang saw cut
TBSP-J.I-05 Chiselling the brick masonry wall 0.9 RM 31 1 RM 27.90
and repairs
Applicable Municipal Area 20% 27.90 5.58
Allowance
TBSC-T.I-12 Full Rounding the edges of Marble/ 2.1 RM 480 1 RM 1008.00
Granite
Applicable Municipal Area 20% 403.20 80.64
Allowance (40% labour component)
Labour charges for fixing ( dadooing 0.54 sqm 681.9### sqm 36.82
labour charges )

Applicable Municipal Area 20% 36.82 7.36


Allowance
Applicable Overheads and 13.615% 1656.08 225.48
Contractor's profit
Total 1881.56
Rate per 1 Each Say 1882.00