NO : 028

DAILY SITE CONSTRUCTION REPORT (On Daily Programmed Activities of Work)


DAY: SUNDAY

Employer: Consultant Contractor DATE: 28 May 2017

High Low
TEMP: 41°C 30°C
Al Salam Medical Service Co. Dar Engineering Project Build Co.
WEATHER: Sunny

Main Contractor’s Work Subcontractor’s Work Combined Work

No. Site Activities Accomplished Quantity Unit Actual Previous Actual Today Location Manpower Engaged Progress Today Over All Progress

1 Dewatering System Site 1 Daily Daily


2 Fibrication of Steel Site 6 Daily Daily
3 House Keeping Site 6 Daily Daily
4 Rebar of Retaining Wall for Basement 371 L.M 230 H.B 0% 62%
5 Formwork of Retaining Wall for Basement 371 L.M 230 H.B 0% 62%
6 Concrete of Retaining Wall for Basement 371 L.M 230 H.B 0% 62%
7 Rebar of Columns for Ground Floor 169 N. 160 H.B 0% 95%
8 Formwork of Columns for Ground Floor 169 N. 160 H.B 0% 95%
9 Concrete for Columns for Ground Floor 169 N. 160 H.B 0% 95%
10 Rebar of Shear Walls for Ground Floor 105 L.M 90 H.B 0% 86%
11 Formwork of Shear Walls for Ground Floor 105 L.M 90 H.B 0% 86%
12 Concrete for Shear Walls for Ground Floor 105 L.M 90 H.B 0% 86%
13 Formwork of Beams for First Floor 2192 L.M 1600 150 H.B 13 7% 80%
14 Rebar of Beams for First Floor 2192 L.M 1500 100 H.B 17 5% 73%
15 Concrete of Beams for First Floor 2192 L.M 790 90 H.B 15 4% 40%
16 Installation of Hollow Core Slab for Ground Floor 7000 M2 1950 450 H.B 13 6% 34%
17 Screed Structure for Ground Floor 7000 M2 1800 150 H.B 15 2% 28%
18 Duct Pipe H.B 15 2% 19%
19 Conduits,Boxes&Cable Tray System H.B 14 3% 27%
20 Fire Fighting Pipes Network H.B 17 2% 16%
21 Lean Concrete (Prepration) 10900 M2 10900 P.B 0% 100%
22 Water Proofing 10900 M2 10900 P.B 0% 100%
23 Screed 10900 M2 10800 50 P.B 6 0% 100%
24 Reinforce Steel Rebar for Raft 400 TON 383 1 P.B 6 0% 96%
25 Excavation & Pipe Instulation P.B 10 1% 98%
26 Raft Concrete 5000 M3 4050 P.B 0% 81%
27 Rebar of Columns for Basement 173 N. 145 P.B 0% 84%
28 Formwork of Columns for Basement 173 N. 145 P.B 0% 84%
29 Concrete for Columns for Basement 173 N. 145 P.B 0% 84%

No. Site Activities Targeted for Next Day Quantity Unit Actual Previous Actual Today Location Estimated Manpower Planned Progress Over All Progress

1 Dewatering System Site 1 Daily Daily


2 Fibrication of Steel Site 6 Daily Daily
3 House Keeping Site 6 Daily Daily
4 Rebar of Retaining Wall for Basement 371 L.M 230 H.B 0% 62%
5 Formwork of Retaining Wall for Basement 371 L.M 230 H.B 0% 62%
6 Concrete of Retaining Wall for Basement 371 L.M 230 H.B 0% 62%
7 Rebar of Columns for Ground Floor 169 N. 160 H.B 0% 95%
8 Formwork of Columns for Ground Floor 169 N. 160 H.B 0% 95%
9 Concrete for Columns for Ground Floor 169 N. 160 H.B 0% 95%
10 Rebar of Shear Walls for Ground Floor 105 L.M 90 H.B 0% 86%
11 Formwork of Shear Walls for Ground Floor 105 L.M 90 H.B 0% 86%
12 Concrete for Shear Walls for Ground Floor 105 L.M 90 H.B 0% 86%
13 Formwork of Beams for First Floor 2192 L.M 1750 250 H.B 13 11% 91%
14 Rebar of Beams for First Floor 2192 L.M 1600 150 H.B 17 7% 80%
15 Concrete of Beams for First Floor 2192 L.M 880 90 H.B 15 4% 44%
16 Installation of Hollow Core Slab for Ground Floor 7300 M2 2400 450 H.B 13 6% 39%
17 Screed Structure for Ground Floor 7300 M2 1950 250 H.B 15 3% 30%
18 Duct Pipe H.B 15 2% 21%
19 Conduits,Boxes&Cable Tray System H.B 14 3% 30%
20 Fire Fighting Pipes Network H.B 17 2% 18%
21 Lean Concrete (Prepration) 10900 M2 10900 P.B 0% 100%
22 Water Proofing 10900 M2 10900 P.B 0% 100%
23 Screed 10900 M2 10850 50 P.B 10 0% 100%
24 Reinforce Steel Rebar for Raft 400 TON 384 1 P.B 6 0% 96%
25 Excavation & Pipe Instulation P.B 10 1% 99%
26 Raft Concrete 5000 M3 4050 P.B 0% 81%
27 Rebar of Columns for Basement 173 N. 145 P.B 0% 84%
28 Formwork of Columns for Basement 173 N. 145 P.B 0% 84%
29 Concrete for Columns for Basement 173 N. 145 P.B 0% 84%

No. Material Delivery to Site / Material Name UOM Quantity Location Ticket No. Date

1 0

No. Health & Safety Issues Action Reason for H/S Issue

No. of Visitors Client Office Consultant Office Contractors Off. Total

Prepared by Contractor (P.E.) Reviewed by Contractor (C.M.) Issued by Contractor (P.M.)

Signature: ……………………… Signature: ………………………… Signature: …………………………

Date/
Time: 28-May-17 04:30:00 PM Date/Time: 28-MAY-17 Date/Time: 28-MAY-17

Page 1/2
AL SALAM HOSPITAL PROJECT 636

DAILY SITE CONSTRUCTION REPORT (On Daily Programmed Activities of Work) 07 January 2019

This section includes reports on Staff, Manpower & Equipment of Main Contractor and all Subcontractor

STAFF Day/Night Shift MANPOWER Day/Night Shift EQUIPMENT Day/Night Shift

S.No. Designation DS N/S S.No. Designation DS N/S Total S.No. Description DS NS Total

1 Project Director 1 1 Civil foreman 13 1 Jack hammer 3


2 Project manager 1 2 Mechanical foreman 6 2 Grinders 20
3 Construction manager 2 3 Electrical foreman 5 3 Vibarator 2
4 Technical Manager 1 4 Store keeper 3 4 Compactor 2
5 Project Engineer 1 5 Drivers 8 1 5 Loader 1
6 Structural Engineer 2 6 Security guard 4 7 6 Tower Crane 3
7 Civil Engineer 3 7 Steel fixer 23 7 Mobile Crane 1
8 Architectural Engineer 4 8 Carpenter 27 8 Bobcat 3
9 Technical Engineer 1 9 Electrician 147 9 Trucks 1
10 Mehanical Manager 1 11 Plumber 56 10 Diana 2
11 Mechanical Engineer 4 12 Plumber Labor 11 11 Fork lift 1
12 Mechanical Supervisor 1 12 Mason 45 3 12 Hilti 2
13 Electrical Manager 1 13 Labour 161 4 13 Excavator 1
14 Electrical Engineer 3 14 Leadman 5 14 Site Concrete Pump 1
15 Finishing Engineer 1 15 Bobcat Operator 3 15 Pick Up 2
16 QA/QC Manager 1 16 Painter 6 16 Bus 3
17 QC Inspector 1 17 Office Boy 4 Total Equipment 48
18 QA/QC Engineer 2 18 Tile Fixer 2 1
19 Planing Engineer 1 19 Equipment operator 7
20 Quality Controller 1 20 Tower Crane Operator 3 1
21 Surveyor 3 21 Rigger 3 1
22 Safety Engineer 1 22 Scaffolder 25
23 Safety officer 4 23 Safety Inspector 1
24 Safety Manager 1 24 Welder 2
25 Document Controller 2 25 Steel Structure Erector 6
26 Autocad operator 3 26 Gypsum Labor 3
27 Admin 1
28 Mechanic 1 Sub Contractors Man Power
29 Accountant 1 1 Structural Workers
Steel fixer 8
Carpenter 5
2 Stone Cladding(Exterior Wall Tiles) 14
3 Fire Fighting 9
4 RHG Staff 4
5 RHG (Duct work) 10
6 Chiller pipe 7
7 Duct Work (ACC) 4
8 MedicalGas 9
9 Mason (Block Work) 4
10 Glass Installer(Almouca) 12
11 GypsumBoard 30
12 False Ceiling 5
13 Plastering
14 Painter 11
15 Water Proofing & Epoxy 8
16 Elec Cable Pulling(Sub Con) 36
17 Bus Bar Work
18 Cable Termination 3
19 GRC 16
20 Steel structural Erector 10 6
21 Ceramic Tiles
22 Demolish work 4
Sub-total 784
Total Day Shift 50 0 Day shift : 834
Total Night Shift 0 0 Night shift: 28

Total Staff on Site 50 TOTAL MANPOWER ON SITE : 862


NIGHT SHIFT START END
PBC 6:00 PM 6:00: AM
DAY SHIFT 6:00 AM 5:00PM
Prepared by Contractor (P.E.) Reviewed by Contractor (C.M.) Issued by Contractor (P.M.)
Signature: ………………………… Signature: ………………………… Signature: …………………………

Date/T
07-Jan-19 4:30pm 07 January 2019
ime:
33 56
37 24
15 60
51 69
60 49
25 29
22 17 25-Aug-16
22 9 1-Mar-17
6 4
6 7
4 2 188
6 1
27 7
10 2
12 3
55 3
21 342
412 55
397
8
405
159
564
24
588
47
635
35
34
49
51
5 52
20
25-Aug-16 21
25-May-19 4
5
1
0 1003 6
4
26
815 10
55
15
36