Sei sulla pagina 1di 6

FIRST DIVISION

[G.R. No. 168384. August 7, 2006.]

CHARLES BERNARD H. REYES doing business under the name and


style CBH REYES ARCHITECTS , petitioner, vs . ANTONIO YULO BALDE
II, PAULINO M. NOTO and ERNESTO J. BATTAD, SR., in their
capacities as Arbitrators of the CONSTRUCTION INDUSTRY
ARBITRATION COMMISSION, SPOUSES CESAR and CARMELITA
ESQUIG and ROSEMARIE PAPAS , respondents.

DECISION

YNARES-SANTIAGO , J : p

This Petition for Review on Certiorari under Rule 45 of the Rules of Court assails the
Decision 1 of the Court of Appeals dated February 18, 2005, which sustained the Order 2
dated April 23, 2004 of the Arbitral Tribunal 3 of the Construction Industry Arbitration
Commission (CIAC), denying petitioner's Motion to Terminate Proceedings and its
Resolution 4 dated May 20, 2005 denying petitioner's motion for reconsideration.
The facts of the case are as follows:
On October 20, 2002, respondent-spouses Cesar and Carmelita Esquig entered into
a Design-Build Construction Agreement 5 with petitioner Charles Bernard H. Reyes, doing
business under the name and style of CBH Reyes Architects, for the architectural design
and construction of a 2-storey residence in Tahanan Village, Paranaque City.
In accordance with the contract, spouses Esquig paid the amount of P1,050,000 as
down payment. 6 Thereafter, construction commenced.
The relationship between petitioner and respondent spouses went on smoothly until
sometime in January 2003 when the latter left for the United States and designated their
co-respondent, Rosemarie Papas, as their representative. According to petitioner, Papas
meddled with the construction works by demanding changes and additional works which
entailed additional cost. Papas also refused to pay petitioner's progress billing and the
salary of the laborers. Petitioner thereafter prepared an accounting report of all the
additional works and their corresponding costs, however, Papas denied all the items in the
list and refused to pay the same. Worse, on May 8, 2003, Papas wrote the Board of
Directors of Tahanan Village Homeowner's Association requesting for the cancellation of
the contractor's work permit. EHITaS

Thus, on May 26, 2003, petitioner led a complaint for Accounting, Collection of
Sum of Money, Rescission of Contract with Damages against spouses Esquig and
Rosemarie Papas with the Regional Trial Court of Muntinlupa City which was docketed as
Civil Case No. 03-110. In the complaint, petitioner prayed that an accounting be rendered
to determine the cost of the materials purchased by Papas; that respondents be ordered
to pay the cost of the additional works done on the property; that the Design-Build
Construction Agreement be ordered rescinded because respondents breached the same;
and that respondents be ordered to pay moral and exemplary damages and litigation
CD Technologies Asia, Inc. © 2018 cdasiaonline.com
expenses.
On July 15, 2003, respondents led a motion to dismiss Civil Case No. 03-110 on
the ground that the court has no jurisdiction over the subject matter of the case. They
claimed that the Design-Build Construction Agreement contained an arbitration clause,
thus any dispute arising therefrom should be brought before the CIAC.
On even date, respondents also led a complaint before the CIAC against the
petitioner, docketed as CIAC Case No. 13-2003. Respondents alleged that petitioner
unreasonably delayed the construction and refused to nish the project. Thus, they prayed
that petitioner be ordered to nish the project or, in the alternative, to pay the cost to nish
the same; to reimburse the overpayments made by respondents; and to pay liquidated
damages, attorney's fees and costs of the suit.
Instead of submitting an answer, petitioner led with the CIAC a motion to dismiss 7
on grounds of lack of jurisdiction to hear and decide the case as well as the pendency of
the case before the trial court involving the same subject matter.
In an Order dated October 17, 2003, CIAC denied petitioner's motion to dismiss,
holding that since the Design-Build Construction Agreement contained an arbitration
clause, any dispute arising from said contract is within CIAC's jurisdiction.
Petitioner led a motion for reconsideration which was denied by CIAC in its Order
dated November 27, 2003. Thus, petitioner led his Answer Ad Cautelam. Thereafter, CIAC
constituted the Arbitral Tribunal and directed the same to carry on with the arbitration
proceedings in accordance with CIAC Rules. CDEaAI

Meanwhile, on February 27, 2004, the Regional Trial Court of Muntinlupa City, Branch
203 issued an Order 8 denying the motion to dismiss led by respondents. The trial court
held that it has jurisdiction over the complaint for accounting, rescission of contract and
damages. Petitioner then led with the CIAC a motion to terminate proceedings but the
same was denied 9 in an Order dated April 23, 2004.
Thus, petitioner led a petition for certiorari and prohibition before the Court of
Appeals which was docketed as CA-G.R. SP No. 83816. On February 18, 2005, the Court of
Appeals rendered the assailed Decision dismissing the petition for lack of merit. It held
that CIAC properly acquired jurisdiction over the subject property. Petitioner's motion for
reconsideration was denied hence this petition raising the following issues:
I

THE COURT OF APPEALS ERRED WHEN IT RULED THAT PETITIONER AGREED


TO HAVE THE CASE SUBMITTED FOR VOLUNTARY ARBITRATION.

II

EVEN ASSUMING ARGUENDO THAT PETITIONER AGREED TO HAVE THE


PRESENT CASE SUBMITTED FOR ARBITRATION, THE COURT OF APPEALS
ERRED IN HOLDING THAT THE CIAC MAY TAKE COGNIZANCE OF THE PRESENT
CASE CONSIDERING THAT THE PRESENT CASE INVOLVED ISSUES WHICH ARE
OUTSIDE ITS JURISDICTION.

III

THE COURT OF APPEALS ERRED IN NOT HOLDING THAT ANY PROCEEDING IN


THE CIAC MUST BE TERMINATED SINCE THE RTC ALREADY ASSUMED
CD Technologies Asia, Inc. © 2018 cdasiaonline.com
JURISDICTION OVER THE SUBJECT CONTROVERSY AND HAD NOT
RELINQUISHED THE SAME TO CIAC. 1 0

The primordial issue in the instant case is, which body has jurisdiction over the
present controversy — the Regional Trial Court or the CIAC?
Petitioner contends that the CIAC has no jurisdiction to entertain the case because it
is purely civil in nature and does not involve construction dispute nor require the resolution
of highly technical issues. Moreover, petitioner alleges that the trial court acquired
jurisdiction prior to the CIAC since petitioner's complaint was led earlier thus, rendering
the arbitration clause moot, unenforceable and revocable. IADaSE

The petition lacks merit.


Executive Order (EO) No. 1008 entitled, "Construction Industry Arbitration Law" 1 1
provided for an arbitration mechanism for the speedy resolution of construction disputes
other than by court litigation. It recognized the role of the construction industry in the
country's economic progress as it utilizes a large segment of the labor force and
contributes substantially to the gross national product of the country. 1 2
Section 4 of E.O. No. 1008 provides:
SECTION 4. Jurisdiction. — The CIAC shall have original and exclusive
jurisdiction over disputes arising from, or connected with, contracts entered into
by parties involved in construction in the Philippines, whether the dispute arises
before or after the completion of the contract, or after the abandonment or breach
thereof. These disputes may involve government or private contracts. For the
Board to acquire jurisdiction, the parties to a dispute must agree to submit the
same to voluntary arbitration.

The jurisdiction of the CIAC may include but is not limited to violation of
speci cations for materials and workmanship; violation of the terms of
agreement; interpretation and/or application of contractual provisions; amount of
damages and penalties; commencement time and delays; maintenance and
defects; payment default of employer or contractor and changes in contract cost.

Excluded from the coverage of this law are disputes arising from employer-
employee relationships which shall continue to be covered by the Labor Code of
the Philippines.

In the case of Philrock, Inc. v. Construction Industry Arbitration Commission , 1 3 the


Court has ruled that CIAC has original and exclusive jurisdiction over disputes arising from
or connected with construction contracts entered into by parties that have agreed to
submit their dispute to voluntary arbitration.
Section 1, Article III of the CIAC Rules of Procedure Governing Construction
Arbitration likewise provides that recourse to the CIAC may be availed of whenever a
contract contains a clause for the submission of a future controversy to arbitration, thus:
SECTION 1. Submission to CIAC Jurisdiction. — An arbitration clause in
a construction contract or a submission to arbitration of a construction
dispute shall be deemed an agreement to submit an existing or future
controversy to CIAC jurisdiction , notwithstanding the reference to a different
arbitration institution or arbitral body in such contract or submission. When a
contract contains a clause for the submission of a future controversy to
arbitration, it is not necessary for the parties to enter into a submission agreement
CD Technologies Asia, Inc. © 2018 cdasiaonline.com
before the claimant may invoke the jurisdiction of CIAC. (Emphasis supplied)

We agree with the ndings of the Court of Appeals that the Design-Build
Construction Agreement mutually entered into by the parties contain an arbitration clause,
to wit:
ARTICLE 10. ARBITRATION.
All questions in dispute under the Agreement shall be submitted in
accordance with the provisions of Philippine Law on Arbitration and provided for
in Article 2042 of the New Civil Code of the Philippines and the provisions of
Republic Act No. 876.

Clearly, the presence of the arbitration clause in the parties' contract vests
jurisdiction on the CIAC on all controversies arising from such contract. The arbitral clause
in the agreement is a commitment by the parties to submit to arbitration the disputes
covered therein. Because that clause is binding, they are expected to abide by it in good
faith. 1 4 Where the jurisdiction of CIAC is properly invoked, the failure or refusal of herein
petitioner to arbitrate shall not affect the proceedings. Arbitration proceedings shall
continue notwithstanding the absence or lack of participation of petitioner, and the award
shall be made after receiving the evidence of the claimant. 1 5

With respect to petitioner's contention that the action is purely civil in nature hence,
jurisdiction rests with the Regional Trial Court, the same must fail. Since the action is
rooted on alleged violations of the agreement, it is embraced by the term "construction
dispute". As CIAC aptly ruled: DIEAHc

As regards Respondent's assertion that the claims in the civil case are not
arbitrable, this Commission again begs to digress. A cursory perusal of the claims
in civil case would show that such fall within the scope of CIAC jurisdiction, to wit:
(1) accounting of all payments made for the purchase of construction materials;
(2) cost of additional work; (3) balance on the contract price; (4) interest; (5)
rescission of contract; (6) moral damages; (7) exemplary damages; and (8) cost
of suit. 1 6

Besides, Section 23 of E.O. No. 1008 expressly provides that all provisions of
existing laws, proclamations, decrees, letters of instructions and executive orders contrary
to or inconsistent with E.O. No. 1008 are repealed or modi ed accordingly. E.O. No. 1008
which vests jurisdiction to the CIAC over construction disputes is a special law; hence, it
takes precedence over Batas Pambansa Blg. 129 or the Judiciary Reorganization Act of
1980, a general law which vests jurisdiction to the Regional Trial Courts over civil actions in
which the subject of the litigation is incapable of pecuniary estimation.
Meanwhile, it appears that the Regional Trial Court of Muntinlupa City, Branch 203
rendered judgment on July 29, 2005 1 7 in Civil Case No. 03-110 in favor of herein
petitioner, the dispositive portion of which reads:
WHEREFORE, judgment is rendered declaring a rescission of the Design
Build Construction Agreement dated 20 October 2002; ordering defendants to
render an accounting of all the construction materials they bought for the
construction of the project subject matter of the present case; further ordering
defendants, jointly and severally, to pay plaintiff as follows:

CD Technologies Asia, Inc. © 2018 cdasiaonline.com


a. P840,300.00 representing cost of additional works and changes in
the project plus legal interest until fully paid;
b. P296,658.85 representing balance of the contract price plus legal
interest until fully paid;
c. P500,000.00 as and by way of moral damages;

d. P500,000.00 as and by way of exemplary damages;


e. P500,000.00 as and by way of attorney's fees;

f. Cost of suit.
SO ORDERED. 1 8

On June 29, 2006, the presiding judge ordered the designated sheriff to implement
the writ of execution dated May 17, 2006. Consequently, Sheriff Melvin T. Bagabaldo levied
on the personal properties of respondent Papas. Hence, respondents' manifestation with
prayer for the issuance of a temporary restraining order (TRO). ISHCcT

In the Resolution dated July 12, 2006, we issued a TRO enjoining the Presiding
Judge of Regional Trial Court of Muntinlupa City, Branch 203, from continuing with any of
the proceedings in Civil Case No. 03-110 and from enforcing the Order dated June 29,
2006 ordering the sheriff to implement the writ.
Thus, considering our ndings that the CIAC and not the RTC which has jurisdiction
over the instant controversy, the injunction against the Presiding Judge of the Regional
Trial Court of Muntinlupa City, Branch 203 from further proceeding with Civil Case No. 03-
110 must be made permanent. All the proceedings therein are declared null and void for
lack of jurisdiction. The designated sheriff is enjoined from proceeding with the sale of the
levied personal properties and is ordered to return the same to respondents. Accordingly,
Civil Case No. 03-110 must be dismissed on the ground of lack of jurisdiction.
It bears to stress that being an inexpensive, speedy and amicable method of settling
disputes, arbitration — along with mediation, conciliation and negotiation — is encouraged
by the Supreme Court. Aside from unclogging judicial dockets, arbitration also hastens the
resolution of disputes, especially of the commercial kind. It is thus regarded as the "wave
of the future" in international civil and commercial disputes. Brushing aside a contractual
agreement calling for arbitration between the parties would be a step backward. 1 9
WHEREFORE, in view of the foregoing, the instant petition is DENIED. The Decision of
the Court of Appeals dated February 18, 2005 in CA-G.R. SP No. 83816 which sustained
the Order of the Arbitral Tribunal of the Construction Industry Arbitration Commission
dated April 23, 2004 denying petitioner's Motion to Terminate Proceedings, and its
Resolution dated May 20, 2005 denying petitioner's motion for reconsideration, are
AFFIRMED. The Presiding Judge of the Regional Trial Court of Muntinlupa City, Branch 203
is PERMANENTLY ENJOINED from proceeding with Civil Case No. 03-110 and all the
proceedings therein are DECLARED NULL AND VOID. Sheriff Melvin T. Bagabaldo is
ENJOINED from proceeding with the sale of the levied personal properties and is
ORDERED to return them to the respondents. The Presiding Judge of the Regional Trial
Court of Muntinlupa City, Branch 203 is further DIRECTED to dismiss Civil Case No. 03-110
for lack of jurisdiction.
SO ORDERED.
CD Technologies Asia, Inc. © 2018 cdasiaonline.com
Panganiban, C.J., Austria-Martinez, Callejo, Sr. and Chico-Nazario, JJ., concur.

Footnotes
1. Rollo, pp. 34-48. Penned by Associate Justice Delilah Vidallon-Magtolis as concurred in
by Associate Justices Perlita J. Tria-Tirona and Jose C. Reyes, Jr.
2. Id. at 254-255.
3. Composed of Antonio Yulo Balde II as Chairman, with Paulino M. Noto and Ernesto J.
Battad, Sr. as members.
4. Rollo, p. 50.
5. Id. at 51-55.
6. Id. at 118-119.
7. Id. at 166-174.
8. Id. at 235-238. Penned by Judge Pedro M. Sabundayo, Jr.
9. Id. at 255.
10. Id. at 20.
11. Issued on February 4, 1985.
12. David v. Construction Industry [and] Arbitration Commission, G.R. No. 159795, July 30,
2004, 435 SCRA 654, 660.
13. 412 Phil. 236, 245 (2001).
14. LM Power Engineering Corp. v. Capitol Industrial Construction Groups, Inc., 447 Phil.
705, 716 (2003).
15. See Section 2, Article III of the Rules of Procedure Governing Construction Arbitration.
16. Rollo, p. 189.
17. Id. at 506.
18. Id. at 546.
19. LM Power Engineering Corp. v. Capitol Industrial Construction Groups, Inc., supra note
14 at 714.

CD Technologies Asia, Inc. © 2018 cdasiaonline.com

Potrebbero piacerti anche