1 GIRDER AT SUPPORT

0.63
No 1.000
a3 0.000 a1 0.625 1.750 1.09
a2 0 a2 0.463 0.00 0.00
a3 0.625 0.00 0.00
1.09
1.75 0.3
1.750
a1

0.625
2 GIRDER AT MID SPAN

0.63
No 1.000
a5 0.00 a1 0.625 0.25 0.16
a4 0.000 a2 0.463 0.20 0.09
a3 0.300 1.300 0.39
0.3 a4 0.463 0.00 0.00
1.75 1.300 a5 0.625 0.00 0.00
a3 0.64

a2 0.20
a1 0.25

0.625

For 1 Span
Nos Length Area Qnty

Support 4 1.4 1.09 6.125


length =
Taper 4 1.8 0.87 6.237
length =
Narrow 4 16.20 0.64 41.391
length =
19.40 53.753
268.77

3 END DIAPHRAGM
500 500
a 250

250 c 250 a 0.00 Sqm


c 0.41 Sqm
1630 0.41 Sqm
1380

300
4 INTERMEDIATE DIAPHRAGM

a 250

c a 0.00 Sqm
c 0.41 Sqm
1630 0.41 Sqm
1380
300
DETAILED ESTIMATE OF MAJOR BRIDGE AT CH 32 / 370
General data
Chainage 7/830 kM
Overall length of span 19.96 m
Centre to centre of span 20.00 m
No of span 5.00 nos
No of deck slab over one abutment & pier 1.00 m
Width of deck slab 14.00 m
Type of superstructure RCC Girder
Depth of slab 0.25 m
Depth of girder 1.75 m
Deck level 227.524 m
Bearing + Pedestal 0.398 m
Depth of foundation for abutment A1= 3.50 m
Depth of foundation for abutment A2= 3.50 m
Depth of foundation for pier = 1.80 m
Thickness of wearing coat = 0.075 m
No of Abutment = 2.00 nos
No of Pier = 4.00 nos
Length of retaining wall = 0.00 m
Approcah slab 3.50 m
Levelling course below approach slab 3.60 m
Total number of girders per span 5.00 nos
End girder 2.00 nos
Intermediate Girder 3.00 nos
End Diaphragm 2.00 nos
Intermediate Diaphragm 1.00 nos
Spacing of Girder 3.00 m
Support section 0.70 m
Tapered section 0.90 m
Length of mid span section 16.20 m

Struct PCC Top of Bottom of Top of


Ground Formation
ure Avg. GL Bottom Abutment / Abutment Abutment /
level level
Name level Pier shaft / Pier shaft Pier cap

A1 221.164 221.164 219.174 224.249 221.124 227.524 225.049


A2 220.578 220.578 219.174 224.249 221.124 227.524 225.049
P1 220.634 220.634 219.049 224.049 220.999 227.524 224.849
P2 220.647 220.647 219.049 224.049 220.999 227.524 224.849
P3 220.332 220.332 219.049 224.049 220.999 227.524 224.849
P4 220.098 220.098 219.049 224.049 220.999 227.524 224.849

DETAIL ESTIMATE OF BRIDGE AT CH - 7/830 kM


SUBSTRUCTURE & FOUNDATION
No Length Breadth Depth Volume

1 Earth work in excavation of pile cap in all kinds of soil as per drawing and technical specification,
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom and backfilling with approved material. as per clause 304 of
MORTH specification for Road and Bridge works (5th revision) and as directed by the Engineer in
charge
A1 1 12.30 6.30 1.990 154.21
A2 1 12.30 6.30 1.404 108.80
P1 1 5.80 5.40 1.585 49.64
P2 1 5.80 5.40 1.598 50.05
P3 1 5.80 5.40 1.283 40.18
P4 1 5.80 5.40 1.049 32.85
Launching apron 2 44.18 sqm 1.000 88.36

Total = 524.09 Cum

2 Supplying, Providing & laying Plain cement concrete M-15 grade (cast-in-situ) in nominal mix
below pile cap with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days as levelling course as per
drawing and technical specification section 1000, 1500 & 2100 of MORTH specification for Road &
Bridge works (5th revision) as directed by Engineer in charge

A1 1 16.70 9.50 0.150 23.80


A2 1 16.70 9.50 0.150 23.80
P1 1 9.50 5.90 0.150 8.41
P2 1 9.50 5.90 0.150 8.41
P3 1 9.50 5.90 0.150 8.41
P4 1 9.50 5.90 0.150 8.41
Total = 81.23 Cum
Providing supplying and laying Design Mix Reinforced Cement Concrete with grade M35 in pile cap
3 complete as per Drawing and Technical Specifications as per approved drawings and sections 1000,
1500, 1600, 1700 and 2100 of MORTH specifications for road and bridge works(5th revision)
excluding the cost of reinforcement complete as directed by Engineer in charge

Abutment
2 16.40 9.20 1.800 543.17

Pier 4 9.20 5.60 1.800 370.94

Total = 914.11 Cum

4 Supplying, decoiling, straightening, cutting, bending, placing in position and tying the grills of HYSD
steel reinforcement Fe 500 conforming to IS-1786, 2008 in position binding with galvanized binding
works of 18 gauge complete for all RCC works in pile cap & pile as per working drawing and
technical specification section 1000,1500,1600, 2300 of MORTH specification for Road & Bridge
works (5th revision) as directed by Engineer in charge.

Qty. vide Item no. 5 ∏ /4 x (1.2 x 1.2) x 427.04 933.053 cum 933.05 qtl
Qty. vide Item no. 3 914.11 cum 1 Qntl/cum 914.1 qtl
Total = 184.720 MT

Bored cast-in-situ M 35 grade R.C.C. Pile of 1200m dia excluding Reinforcement complete as per
5 Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000
m.
In abutment AL 1 15 15.0 225.0
In abutment AR 1 15 15.0 225.0
In pier P1 1 6 15.0 90.0
P2 1 6 15.0 90.0
P3 1 6 15.0 90.0
P4 1 6 15.0 90.0
Test Pile 1 1 15.0 15.0
Total = 825 Rm

6 Abutment / pier Shaft - RCC M 30

A1 1 14.00 1.5 3.125 65.63


A2 1 14.00 1.5 3.125 65.63
Pier
P1 1 6.80 1.2 3.050 24.89
1 1.13 3.050 3.45
P2 1 6.80 1.2 3.050 24.89
1 1.13 3.050 3.45
P3 1 6.80 1.2 3.050 24.89
1 1.13 3.050 3.45
P4 1 6.80 1.2 3.050 24.89
1 1.13 3.050 3.45

Total = 244.60 Cum

7 Return Wall in Abutment - RCC M 30

Return wall
A1 2 1.83 0.5 6.325 11.57
A2 2 1.83 0.5 6.325 11.57
fly wing 4 3.4 sqm 0.300 4.10

Total = 27.24 Cum

8 Cap & corbel - RCC M 30

Abutment
Rectangular Portion 2 14.00 1.70 0.500 23.80
Trapezoidal Portion 2 14.00 1.60 0.300 13.44
Pier
Rectangular Portion 8 11.60 2.00 0.500 92.80
Trapezoidal Portion 8 8.60 1.65 0.500 56.76

Total = 186.80 Cum

9 Dirt Wall in Abutment - RCC M 30


A1 & A2 2 14 0.40 2.15 24.08

Total = 24.08 Cum


10 HYSD Fe 500 for substructure
i Shaft 244.600 cum 2.00 Qntl/cum 489.20
ii Cap 186.800 cum 2.00 Qntl/cum 373.60
iii Return wall 27.240 cum 1.50 Qntl/cum 40.86
iv Dirt Wall 24.080 cum 1.50 Qntl/cum 36.12
v Pedestal 10.680 cum 1.00 Qntl/cum 10.68

950.46 Qntl
95.05 MT
11 Weep holes
In abutment
A1 29 1.502 43.55
A2 29 1.502 43.55
In return wall
A1 16 0.501 8.01
A2 16 0.501 8.01

Total = 103.13 Rm

12 Filter media behind abutment

A1 1.00 13.000 0.6 6.325 49.34


A2 1.00 13.000 0.6 6.325 49.34

behind Returnwall
For A1 2 1.23 0.6 6.325 9.34
For A2 2 1.23 0.6 6.325 9.34

Total = 119.37 Cum

13 Back filling
Abutment 2 11.80 1.23 6.325 183.60 cum

Total = 183.60 cum

14 Bearing
Elastomeric bearing 50 50 36 9.60 864000.00
864000.00 cc
Total = 864000.00 cc
15 Pedestal - RCC M 40
72 0.80 0.62 0.299 10.68

Total = 10.68 Cum


SUPERSTRUCTURE

16 End Girder & central Girders RCC M 30

Area of support section of Girder 1.094 Sqm


Area of mid section of Girder 0.64 Sqm

Area of Intermediate section of Girder 1.094 Sqm


Area of mid section of Girder 0.64 Sqm

Volume of end & intermediate girder 13.438 cum


Volume per span (16.207*4) 67.191 cum
For 9 spans Total volume = 335.96 cum

17 Cross Diaphragm - RCC M 30


End Diaphragm 0.414 Sqm
Intermediate 0.414 Sqm
Length of intermediate diaphragm 7.050 m
Length of end diaphragm 7.050 m

Volume of intermediate diaphragm per span 2.919 Cum


Volume of end diaphragm per span 5.837 Cum
For 9 spans Total volume = 43.78 cum

18 Deck Slab - RCC M 30


5 19.96 14.00 0.250
Total volume = 349.30 cum

19 HYSD Fe500 for superstructure

i Girder & cross Girder 379.740 cum 2 Qntl/cum 759.48


ii Deck Slab 349.300 cum 2 Qntl/cum 698.60
1458.08
Total 145.81 MT

20 Wearing Coat - RCC M 30


Qty per span 1 12.50 19.96 0.075 18.71
Total qty 5 NOS 93.55
Total = 93.55 cum
21 Providing and laying of compression seal expansion joint
6 14 84.00 rm

22 Utility Duct 150mm PVC pipe


2 107.00 214.00 rm

23 Drainage spout
40 40.00 nos

24 Drainage Pipe 100mm


100mm dia PVC pipes
Vertical drop
40 2.15 86.00 rm

25 Crash barrier - RCC M 40


214.00 rm

26 PCC M15 Grade leveling course below approach slab


2 13.00 3.6 0.150 14.04 cum

27 Approach Slab - RCC M 30


2 13.00 3.5 0.250 22.75 cum
28 Guard posts
400 400.00 nos

29 Providing and applying 2 coats of water based cement paint


Crash barrier outer side 1 214 1.050 224.70
Total = 224.70 sqm
30 Painting Two Coats on New Concrete Surfaces
Guard posts 400 0.424
Crash barrier inner side 1 214 0.975 208.65
Total = 208.65 sqm
32 RCC Railing
107.00 rm
RETAINING WALL
31 Earth work in excavation of foundation of structure in all kind of soil
2 60.00 3.60 2.150 928.80 cum
Total = 928.80 cum

32 P.C.C M15 Retaining wall


2 60.00 3.60 0.150 64.80 cum
Total = 64.80 cum
33 R.C.C in foundation

Rectangular 2 60.00 3.40 0.500 204.00 cum


Trapezoidal 2 60.00 2.10 0.500 126.00 cum
Total = 330.00 cum

34 HYSD Fe 500 in foundation

330.00 cum 1.00 Qtl/Cum 330.00

Total = 33.00 MT

35 Retaining wall Shaft


2 60.00 0.625 5.000 375.00 cum
Total = 375.00 cum

36 HYSD Fe 500 in substructure


375.00 cum 1.00 Qtl/Cum 375.00

Total = 37.50 MT

37 Providing Filter Media behind Retaining wall


2 60.00 0.60 3.200 230.40 cum

Total = 230.40 cum


38 Providing weep Holes
336.00 0.63 210.00 m
Total = 210.00 rm
39 Granular material below slope pitching
(pi() x (13.200/2) x 14.75) 4 306.001 0.150 183.60 cum

40 Side slope stone pitching


(pi() x (13.200/2) x 14.75) 4 306.001 0.300 367.20 cum
Launching apron 2 44.18 sqm 1.000 88.36 cum
Total = 455.56 cum