Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities
During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity
───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name Actual quantity Unit Average daily rate Start Finish 2004 2005 2006
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 Receipt of drawings Thu 14/08/08 Tue 30/09/08
2 Possession of Site Thu 14/08/08 Tue 30/09/08
3 Commencement Date Thu 14/08/08 Thu 14/08/08
Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities
During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity
───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 06 2007 2008 2009
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Construction of First Carriageway
FIRST CARRIAGEWAY
Construction of First Carriageway
PRELIMINARIES 18/04
1 Receipt of drawings 18/07
2 Possession of Site 10/08 22/09
3 Commencement Date 14/08
4 Issuance of Addendum for the Bypass works 18/04
DATE OF COMPLETION
Earthworks
13.8.2009
7 Excavate topsoil 01/11 04/12
8 Excavate in cutting, fill in embankment 02/11 16/02
9 Excavate in cutting, dispose 02/11 16/02
10 Extra over for excavation in rock 06/11 24/12
11 Fill in embankment from borrow pit 02/11 01/04
12 Free draining granular material as protection to embankments 02/11 16/03
13 Grassing on embankment slopes 15/03 06/04
Asphaltic layers
37 Prime coat MC30 11/02
38 75 mm thick bitumen bound base course 13/02
39 Tack coat MC3000 13/02 20/07
40 50 mm thick asphaltic concrete binder course 14/02 05/05
41 40 mm thick asphaltic concrete wearing course
06/05 21/07
Road Furniture
SECOND CARRIAGEW
Construction of Second Carriageway 14/08
PRELIMINARIES 14/08 30/09
Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities
During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity
───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 06 2007 2008 2009
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 Receipt of drawings 14/08 30/09
2 Possession of Site 14/08 30/09
3 Commencement Date 14/08
WORKS
Demolition and site clearance 01/09
4 General clearance 01/09
5 Removal of trees, stumps, timber logs 01/09
Earthworks 02/09
6 Excavate topsoil 02/09
7 Excavate in cutting, fill in embankment 03/09
8 Excavate in cutting, dispose 03/09
9 Extra over for excavation in rock 05/09
10 Fill in embankment from borrow pit 03/09
11 Free draining granular material as protection to embankments 03/09
12 Grassing on embankment slopes 02/02
Pavement works
31 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick 10/06
32 Crushed stone base in carriageway, 200 mm thick 01/10
33 125 x 300 mm kerbstone
34 50 x 225 mm kerbstone
35 80 mm thick paving blocks in busbays and walkways
Asphaltic layers
36 Prime coat MC30 03/01
37 75 mm thick bitumen bound base course 05/01
38 Tack coat MC3000
39 50 mm thick asphaltic concrete binder course
40 40 mm thick asphaltic concrete wearing course
Road Furniture
41 W crash barriers
42 Guardrail reflectors
43 Precast concrete New Jersey Barrier
44 Road signs
45 120 mm wide road marking line
46 150 mm wide road marking line
47 300 - 350 mm wide road marking line
Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities
During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity
───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 2010 2011 2012
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Construction of First Carriageway
DATE OF COMPLETION
13.8.2009
7 Excavate topsoil
8 Excavate in cutting, fill in embankment
9 Excavate in cutting, dispose
10 Extra over for excavation in rock
11 Fill in embankment from borrow pit
12 Free draining granular material as protection to embankments
13 Grassing on embankment slopes
WAY
Construction of Second Carriageway 15/11
PRELIMINARIES
Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities
During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity
───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 2010 2011 2012
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Receipt of drawings
2 Possession of Site
3 Commencement Date
WORKS
Demolition and site clearance 07/12
4 General clearance 24/11
5 Removal of trees, stumps, timber logs 07/12
Earthworks 15/11
6 Excavate topsoil 25/03
7 Excavate in cutting, fill in embankment 10/05
8 Excavate in cutting, dispose 17/04
9 Extra over for excavation in rock 16/04
10 Fill in embankment from borrow pit 20/04
11 Free draining granular material as protection to embankments 10/04
12 Grassing on embankment slopes 15/11
PROGRAMME OF WORKS
DATE OF COMPLETION
AS PER APPROVED
19 Reinforcing steel for drainage structures 20/04
20 Formwork for drainage structures 22/04
12.8.2010
21 Concrete in drainage structures 23/04
22 Precast concrete U drain 60 x 60 cm including covers 15/06
23 Precast concrete U drain 60 x 60 cm without covers 15/06
24 1 m deep manholes 02/11 30/04
25 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover 02/11 30/04
26 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover 02/11 30/04
27 Geotextile membrane 02/11 30/04
28 Rock filled gabions 02/11 30/04
29 Trapezoidal drain, grouted stone pitching 15 cm thick 31/01
30 Stone pitching 31/12
Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities
During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity
───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time