Sei sulla pagina 1di 6

SONITRA Ltd.

CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)


P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name Actual quantity Unit Average daily rate Start Finish 2004 2005 2006
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Construction of First Carriageway Tue 06/06/06 Tue 15/11/11

Construction of First Carriageway Tue 06/06/06 Tue 25/01/11 06/06


PRELIMINARIES Tue 06/06/06 Wed 18/04/07 06/06
1 Receipt of drawings Tue 06/06/06 Tue 18/07/06 06/06
2 Possession of Site Thu 10/08/06 Fri 22/09/06 1
3 Commencement Date Mon 14/08/06 Mon 14/08/06
4 Issuance of Addendum for the Bypass works Wed 18/04/07 Wed 18/04/07

WORKS Wed 01/11/06 Tue 25/01/11


Demolition and site clearance Wed 01/11/06 Sat 15/03/08
5 General clearance 70 ha 0.28 Wed 01/11/06 Sat 15/03/08
6 Removal of trees, stumps, timber logs 1,550 nr 6 Wed 01/11/06 Sat 15/03/08

Earthworks Wed 01/11/06 Mon 06/04/09


7 Excavate topsoil *81,665 m3 260 Wed 01/11/06 Thu 04/12/08
8 Excavate in cutting, fill in embankment *760,000 m3 **2,050 Thu 02/11/06 Mon 16/02/09
9 Excavate in cutting, dispose *625,000 m3 **1,680 Thu 02/11/06 Mon 16/02/09
10 Extra over for excavation in rock 10,000 m3 35 Mon 06/11/06 Wed 24/12/08
11 Fill in embankment from borrow pit 350,938 m3 860 Thu 02/11/06 Wed 01/04/09
12 Free draining granular material as protection to embankments 4,502 m3 16 Thu 02/11/06 Mon 16/03/09
13 Grassing on embankment slopes 22,250 m2 250 Sat 15/03/08 Mon 06/04/09
Tue 01/01/08 Wed 31/12/08
Drainage and Concrete works Fri 03/11/06 Fri 31/07/09
14 Excavation for drainage structures 12,470 m3 35 Fri 03/11/06 Wed 15/04/09
15 Rock excavation for drainage structures 3,535 m3 13 Sat 04/11/06 Tue 31/03/09
16 Concrete surrounded D600 mm concrete pipe culverts *140 m 1 Mon 06/11/06 Wed 30/04/08
17 Concrete surrounded D900 mm concrete pipe culverts *819 m 3 Mon 06/11/06 Sat 31/01/09
18 Concrete surrounded D1200 mm concrete pipe culverts *646 m 2 Mon 06/11/06 Sat 31/01/09
19 Blinding concrete for drainage structures *100 m3 0.30 Sat 04/11/06 Tue 24/02/09
20 Reinforcing steel for drainage structures 223,765 kg 600 Sat 04/11/06 Wed 25/02/09
21 Formwork for drainage structures 8,850 m2 25 Mon 06/11/06 Thu 26/02/09
22 Concrete in drainage structures *2,500 m3 7 Tue 07/11/06 Sat 28/02/09
23 Precast concrete U drain 60 x 60 cm including covers 1,780 m 8 Thu 01/05/08 Mon 01/06/09
24 Precast concrete U drain 60 x 60 cm without covers 3,000 m 14 Thu 01/05/08 Mon 01/06/09
25 1 m deep manholes 10 nr 0.07 Sat 01/11/08 Mon 01/06/09
26 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover 10 nr 0.07 Sat 01/11/08 Mon 01/06/09
27 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover 5 nr 0.05 Sat 01/11/08 Wed 01/04/09
28 Geotextile membrane 1,000 m2 7 Sat 01/11/08 Fri 01/05/09
29 Rock filled gabions 285 m3 2 Sat 01/11/08 Fri 01/05/09
30 Trapezoidal drain, grouted stone pitching 15 cm thick 2,967 m 13 Thu 01/05/08 Mon 15/06/09
31 Stone pitching 22,250 m2 88 Thu 01/05/08 Fri 31/07/09
Tue 01/01/08 Tue 01/01/08
Pavement works Fri 22/02/08 Tue 25/05/10
32 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick *51,043 m3 **260 Fri 22/02/08 Thu 20/05/10
33 Crushed stone base in carriageway, 200 mm thick 41,600 m3 275 Sat 01/11/08 Sun 23/05/10
34 125 x 300 mm kerbstone 1,100 m 10 Sat 03/01/09 Tue 25/05/10
35 50 x 225 mm kerbstone 200 m 5 Sat 03/01/09 Sat 24/04/10
36 80 mm thick paving blocks in busbays and walkways 500 m2 10 Sat 03/01/09 Fri 30/04/10
Tue 01/01/08 Fri 17/04/09
Asphaltic layers Wed 27/01/10 Sat 11/12/10
37 Prime coat MC30 243,840 lit 3,100 Wed 27/01/10 Sun 30/05/10
38 75 mm thick bitumen bound base course *15,240 m3 200 Thu 18/02/10 Wed 02/06/10
39 Tack coat MC3000 140,160 lit 1,540 Fri 04/06/10 Fri 10/12/10
40 50 mm thick asphaltic concrete binder course 10,160 m3 165 Sat 05/06/10 Fri 05/11/10
41 40 mm thick asphaltic concrete wearing course 4,672 m3 165 Sat 06/11/10 Sat 11/12/10
Tue 01/01/08 Tue 01/01/08
Road Furniture Mon 15/03/10 Sat 15/01/11
42 W crash barriers 4,048 m 25 Mon 15/03/10 Sat 15/01/11
43 Guardrail reflectors 980 nr 15 Fri 15/10/10 Sat 15/01/11
44 Precast concrete New Jersey Barrier 54 m 1 Thu 01/04/10 Thu 15/07/10
45 Road signs 211 nr 5 Sat 20/11/10 Sat 15/01/11
46 120 mm wide road marking line 15,000 m 550 Mon 06/12/10 Sat 15/01/11
47 150 mm wide road marking line 32,000 m 1,200 Mon 06/12/10 Sat 15/01/11
48 300 - 350 mm wide road marking line 1,292 m 55 Thu 16/12/10 Sat 15/01/11

Finishing works and demobilisation Wed 01/12/10 Tue 25/01/11


49 Finishing works Wed 01/12/10 Thu 20/01/11
50 Demobilisation of construction equipment Wed 15/12/10 Sun 23/01/11
51 Notice of Substantial Completion Tue 28/12/10 Tue 28/12/10
52 Completion of the Project Tue 25/01/11 Tue 25/01/11

Construction of Second Carriageway Thu 14/08/08 Tue 15/11/11


PRELIMINARIES Thu 14/08/08 Tue 30/09/08

Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities

During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity

───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name Actual quantity Unit Average daily rate Start Finish 2004 2005 2006
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 Receipt of drawings Thu 14/08/08 Tue 30/09/08
2 Possession of Site Thu 14/08/08 Tue 30/09/08
3 Commencement Date Thu 14/08/08 Thu 14/08/08

WORKS Mon 01/09/08 Tue 15/11/11


Demolition and site clearance Mon 01/09/08 Mon 07/12/09
4 General clearance 26 ha 0.10 Mon 01/09/08 Tue 24/11/09
5 Removal of trees, stumps, timber logs 1,619 nr 6 Mon 01/09/08 Mon 07/12/09

Earthworks Tue 02/09/08 Mon 15/11/10


6 Excavate topsoil 85,000 m3 270 Tue 02/09/08 Thu 25/03/10
7 Excavate in cutting, fill in embankment 800,000 m3 2,150 Wed 03/09/08 Mon 10/05/10
8 Excavate in cutting, dispose 400,000 m3 1,075 Wed 03/09/08 Sat 17/04/10
9 Extra over for excavation in rock 50,000 m3 135 Fri 05/09/08 Fri 16/04/10
10 Fill in embankment from borrow pit 450,000 m3 1,200 Wed 03/09/08 Tue 20/04/10
11 Free draining granular material as protection to embankments 5,500 m3 15 Wed 03/09/08 Sat 10/04/10
12 Grassing on embankment slopes 100,000 m2 500 Mon 02/02/09 Mon 15/11/10

Drainage and Concrete works Wed 03/09/08 Mon 31/01/11


13 Excavation for drainage structures 26,402 m3 70 Wed 03/09/08 Fri 31/12/10
14 Rock excavation for drainage structures 3,535 m3 10 Thu 04/09/08 Fri 31/12/10
Concrete surrounded D600 mm concrete pipe culverts 140 m 1 Sat 01/11/08 Sun 12/09/10
16 Concrete surrounded D900 mm concrete pipe culverts 900 m 3 Sat 01/11/08 Mon 12/04/10
17 Concrete surrounded D1200 mm concrete pipe culverts 761 m 3 Tue 02/12/08 Sun 18/04/10
18 Blinding concrete for drainage structures 82 m3 0.25 Thu 04/09/08 Sat 17/04/10
19 Reinforcing steel for drainage structures 202,632 kg 550 Fri 05/09/08 Tue 20/04/10
20 Formwork for drainage structures 10,426 m2 30 Mon 08/09/08 Thu 22/04/10
21 Concrete in drainage structures 2,249 m3 6 Mon 08/09/08 Fri 23/04/10
22 Precast concrete U drain 60 x 60 cm including covers 1,780 m 7 Mon 16/03/09 Tue 15/06/10
23 Precast concrete U drain 60 x 60 cm without covers 3,000 m 11 Mon 16/03/09 Tue 15/06/10
24 1 m deep manholes 10 nr 0.07 Mon 02/11/09 Fri 30/04/10
25 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover 10 nr 0.07 Mon 02/11/09 Fri 30/04/10
26 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover 5 nr 0.05 Mon 02/11/09 Fri 30/04/10
27 Geotextile membrane 1,000 m2 7 Mon 02/11/09 Fri 30/04/10
28 Rock filled gabions 285 m3 2 Mon 02/11/09 Fri 30/04/10
29 Trapezoidal drain, grouted stone pitching 15 cm thick 10,000 m 30 Thu 15/01/09 Mon 31/01/11
30 Stone pitching 6,000 m2 20 Mon 02/02/09 Fri 31/12/10

Pavement works Sat 22/05/10 Thu 10/03/11


31 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick 50,000 m3 255 Sat 22/05/10 Sun 20/02/11
32 Crushed stone base in carriageway, 200 mm thick 41,600 m3 275 Tue 25/05/10 Wed 23/02/11
33 125 x 300 mm kerbstone 1,100 m 10 Tue 12/10/10 Thu 10/03/11
34 50 x 225 mm kerbstone 200 m 5 Wed 01/12/10 Sat 22/01/11
35 80 mm thick paving blocks in busbays and walkways 500 m2 10 Sun 05/12/10 Thu 10/02/11

Asphaltic layers Sat 11/12/10 Mon 03/10/11


36 Prime coat MC30 243,840 lit 1,600 Sat 11/12/10 Thu 17/03/11
37 75 mm thick bitumen bound base course *15,240 m3 200 Mon 13/12/10 Sat 19/03/11
38 Tack coat MC3000 140,160 lit 1,540 Mon 21/03/11 Sun 02/10/11
39 50 mm thick asphaltic concrete binder course 10,160 m3 165 Tue 22/03/11 Wed 20/07/11
40 40 mm thick asphaltic concrete wearing course 4,672 m3 165 Thu 21/07/11 Mon 03/10/11

Road Furniture Sun 02/01/11 Mon 31/10/11


41 W crash barriers 5,048 m 30 Sun 02/01/11 Mon 31/10/11
42 Guardrail reflectors 980 nr 15 Wed 15/06/11 Mon 31/10/11
43 Precast concrete New Jersey Barrier 60 m 1 Tue 15/02/11 Sat 30/04/11
44 Road signs 216 nr 5 Tue 12/07/11 Mon 31/10/11
45 120 mm wide road marking line 15,500 m 550 Thu 18/08/11 Mon 31/10/11
46 150 mm wide road marking line 32,000 m 1,200 Thu 18/08/11 Mon 31/10/11
47 300 - 350 mm wide road marking line 1,300 m 55 Thu 01/09/11 Mon 31/10/11

Finishing works and demobilisation Thu 15/09/11 Tue 15/11/11


48 Finishing works Thu 15/09/11 Thu 10/11/11
49 Demobilisation of construction equipment Sat 01/10/11 Sun 13/11/11
50 Notice of Substantial Completion Tue 18/10/11 Tue 18/10/11
51 Completion of the Project Tue 15/11/11 Tue 15/11/11

Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities

During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity

───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 06 2007 2008 2009
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Construction of First Carriageway
FIRST CARRIAGEWAY
Construction of First Carriageway
PRELIMINARIES 18/04
1 Receipt of drawings 18/07
2 Possession of Site 10/08 22/09
3 Commencement Date 14/08
4 Issuance of Addendum for the Bypass works 18/04

AS PER APPROVED PROGRAMME OF WORKS


WORKS
Demolition and site clearance 01/11 15/03
5 General clearance 01/11 15/03
6 Removal of trees, stumps, timber logs 01/11 15/03

DATE OF COMPLETION
Earthworks

13.8.2009
7 Excavate topsoil 01/11 04/12
8 Excavate in cutting, fill in embankment 02/11 16/02
9 Excavate in cutting, dispose 02/11 16/02
10 Extra over for excavation in rock 06/11 24/12
11 Fill in embankment from borrow pit 02/11 01/04
12 Free draining granular material as protection to embankments 02/11 16/03
13 Grassing on embankment slopes 15/03 06/04

Drainage and Concrete works 03/11 31/07


14 Excavation for drainage structures 03/11 15/04
15 Rock excavation for drainage structures 04/11 31/03
16 Concrete surrounded D600 mm concrete pipe culverts 06/11 30/04
17 Concrete surrounded D900 mm concrete pipe culverts 06/11 31/01
18 Concrete surrounded D1200 mm concrete pipe culverts 06/11 31/01
19 Blinding concrete for drainage structures 04/11 24/02
20 Reinforcing steel for drainage structures 04/11 25/02
21 Formwork for drainage structures 06/11 26/02
22 Concrete in drainage structures 07/11 28/02
23 Precast concrete U drain 60 x 60 cm including covers 01/05 01/06
24 Precast concrete U drain 60 x 60 cm without covers 01/05 01/06
25 1 m deep manholes 01/11 01/06
26 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover 01/11 01/06
27 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover 01/11 01/04
28 Geotextile membrane 01/11 01/05
29 Rock filled gabions 01/11 01/05
30 Trapezoidal drain, grouted stone pitching 15 cm thick 01/05 15/06
31 Stone pitching 01/05 31/07

Pavement works 22/02


32 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick 22/02 05/05
33 Crushed stone base in carriageway, 200 mm thick 01/11 11/05
34 125 x 300 mm kerbstone 03/01 15/05
35 50 x 225 mm kerbstone 03/01 27/02
36 80 mm thick paving blocks in busbays and walkways 03/01 28/02

Asphaltic layers
37 Prime coat MC30 11/02
38 75 mm thick bitumen bound base course 13/02
39 Tack coat MC3000 13/02 20/07
40 50 mm thick asphaltic concrete binder course 14/02 05/05
41 40 mm thick asphaltic concrete wearing course
06/05 21/07

Road Furniture

SUSPENSION OF PAVEMENT AND ASPHALT


42 W crash barriers 24/12 31/07

REDUCTION OF RATE OF WORK AND

AS PER LETTERS DATED 7, 16.1.2009


43 Guardrail reflectors 16/03 15/07

WORKS DUE TO NON PAYMENT


44 Precast concrete New Jersey Barrier 03/01 16/03
45 Road signs 15/04 15/07
46 120 mm wide road marking line 15/05 27/07
47 150 mm wide road marking line 15/05 25/07
48 300 - 350 mm wide road marking line 01/06 31/07

Finishing works and demobilisation


49 Finishing works 01/07 10/08
50 Demobilisation of construction equipment 28/07 12/08
51 Notice of Substantial Completion 16/07
52 Completion of the Project 13/08

SECOND CARRIAGEW
Construction of Second Carriageway 14/08
PRELIMINARIES 14/08 30/09

Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities

During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity

───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 06 2007 2008 2009
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 Receipt of drawings 14/08 30/09
2 Possession of Site 14/08 30/09
3 Commencement Date 14/08

WORKS
Demolition and site clearance 01/09
4 General clearance 01/09
5 Removal of trees, stumps, timber logs 01/09

Earthworks 02/09
6 Excavate topsoil 02/09
7 Excavate in cutting, fill in embankment 03/09
8 Excavate in cutting, dispose 03/09
9 Extra over for excavation in rock 05/09
10 Fill in embankment from borrow pit 03/09
11 Free draining granular material as protection to embankments 03/09
12 Grassing on embankment slopes 02/02

Drainage and Concrete works 03/09


13 Excavation for drainage structures 03/09
14 Rock excavation for drainage structures 04/09
Concrete surrounded D600 mm concrete pipe culverts 01/11
16 Concrete surrounded D900 mm concrete pipe culverts 01/11
17 Concrete surrounded D1200 mm concrete pipe culverts 02/12
18 Blinding concrete for drainage structures 04/09
19 Reinforcing steel for drainage structures 05/09
20 Formwork for drainage structures 08/09
21 Concrete in drainage structures 08/09
22 Precast concrete U drain 60 x 60 cm including covers 16/03
23 Precast concrete U drain 60 x 60 cm without covers 16/03
24 1 m deep manholes
25 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover
26 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover
27 Geotextile membrane
28 Rock filled gabions
29 Trapezoidal drain, grouted stone pitching 15 cm thick 15/01
30 Stone pitching 02/02

Pavement works
31 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick 10/06
32 Crushed stone base in carriageway, 200 mm thick 01/10
33 125 x 300 mm kerbstone
34 50 x 225 mm kerbstone
35 80 mm thick paving blocks in busbays and walkways

Asphaltic layers
36 Prime coat MC30 03/01
37 75 mm thick bitumen bound base course 05/01
38 Tack coat MC3000
39 50 mm thick asphaltic concrete binder course
40 40 mm thick asphaltic concrete wearing course

Road Furniture
41 W crash barriers
42 Guardrail reflectors
43 Precast concrete New Jersey Barrier
44 Road signs
45 120 mm wide road marking line
46 150 mm wide road marking line
47 300 - 350 mm wide road marking line

Finishing works and demobilisation


48 Finishing works
49 Demobilisation of construction equipment
50 Notice of Substantial Completion
51 Completion of the Project

Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities

During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity

───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 2010 2011 2012
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Construction of First Carriageway

Construction of First Carriageway 25/01


PRELIMINARIES
1 Receipt of drawings
2 Possession of Site
3 Commencement Date
4 Issuance of Addendum for the Bypass works

AS PER APPROVED PROGRAMME OF WORKS


WORKS
Demolition and site clearance
5 General clearance

DUE TO NON PAYMENT OF CERTIFICATES


6 Removal of trees, stumps, timber logs

DATE OF COMPLETION

NEW DATE OF COMPLETION


Earthworks

13.8.2009
7 Excavate topsoil
8 Excavate in cutting, fill in embankment
9 Excavate in cutting, dispose
10 Extra over for excavation in rock
11 Fill in embankment from borrow pit
12 Free draining granular material as protection to embankments
13 Grassing on embankment slopes

Drainage and Concrete works


14 Excavation for drainage structures
15 Rock excavation for drainage structures
16 Concrete surrounded D600 mm concrete pipe culverts
17 Concrete surrounded D900 mm concrete pipe culverts
18 Concrete surrounded D1200 mm concrete pipe culverts
19 Blinding concrete for drainage structures
20 Reinforcing steel for drainage structures
21 Formwork for drainage structures
22 Concrete in drainage structures
23 Precast concrete U drain 60 x 60 cm including covers
24 Precast concrete U drain 60 x 60 cm without covers
25 1 m deep manholes
26 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover
27 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover
28 Geotextile membrane
29 Rock filled gabions
30 Trapezoidal drain, grouted stone pitching 15 cm thick
31 Stone pitching

Pavement works 25/05


32 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick 20/05
33 Crushed stone base in carriageway, 200 mm thick 23/05
34 125 x 300 mm kerbstone 25/05
35 50 x 225 mm kerbstone 24/04
36 80 mm thick paving blocks in busbays and walkways 30/04

Asphaltic layers 27/01 11/12


37 Prime coat MC30 27/01 30/05
38 75 mm thick bitumen bound base course 18/02 02/06
39 Tack coat MC3000 04/06 10/12
40 50 mm thick asphaltic concrete binder course 05/06 05/11
41 40 mm thick asphaltic concrete wearing course 06/11 11/12

Road Furniture 15/03 15/01


42 W crash barriers 15/03 15/01
43 Guardrail reflectors 15/10 15/01
44 Precast concrete New Jersey Barrier 01/04 15/07
AFTER RECEIPT OF PAYMENT

45 Road signs 20/11 15/01


NORMAL WORK RESUMES

46 120 mm wide road marking line 06/12 15/01


47 150 mm wide road marking line 06/12 15/01
48 300 - 350 mm wide road marking line 16/12 15/01
25.1.2010

Finishing works and demobilisation 01/12 25/01


49 Finishing works 01/12 20/01
50 Demobilisation of construction equipment 15/12 23/01
51 Notice of Substantial Completion 28/12
52 Completion of the Project 25/01

WAY
Construction of Second Carriageway 15/11
PRELIMINARIES

Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities

During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity

───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time
SONITRA Ltd. CONTINUATION OF THE REHABILITATION OF ANYINAM - KONONGO ROAD (47 Km)
P.O. BOX 6014
ACCRA-NORTH NKAWKAW BY PASS (FIRST AND SECOND CARRIAGEWAY)
PROGRAMME OF WORKS - REVISED AFTER RECEIPT OF PAYMENT ON 22ND JANUARY 2010
No. Task Name 2010 2011 2012
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 Receipt of drawings
2 Possession of Site
3 Commencement Date

WORKS
Demolition and site clearance 07/12
4 General clearance 24/11
5 Removal of trees, stumps, timber logs 07/12

Earthworks 15/11
6 Excavate topsoil 25/03
7 Excavate in cutting, fill in embankment 10/05
8 Excavate in cutting, dispose 17/04
9 Extra over for excavation in rock 16/04
10 Fill in embankment from borrow pit 20/04
11 Free draining granular material as protection to embankments 10/04
12 Grassing on embankment slopes 15/11

Drainage and Concrete works 31/01


13 Excavation for drainage structures 31/12
14 Rock excavation for drainage structures 31/12
Concrete surrounded D600 mm concrete pipe culverts 12/09

DUE TO NON PAYMENT OF CERTIFICATES


16 Concrete surrounded D900 mm concrete pipe culverts 12/04
17 Concrete surrounded D1200 mm concrete pipe culverts 18/04

PROGRAMME OF WORKS
DATE OF COMPLETION

NEW DATE OF COMPLETION


18 Blinding concrete for drainage structures 17/04

AS PER APPROVED
19 Reinforcing steel for drainage structures 20/04
20 Formwork for drainage structures 22/04

12.8.2010
21 Concrete in drainage structures 23/04
22 Precast concrete U drain 60 x 60 cm including covers 15/06
23 Precast concrete U drain 60 x 60 cm without covers 15/06
24 1 m deep manholes 02/11 30/04
25 1.2 x 1.0 x 2.0 m concrete U drain chamber with cover 02/11 30/04
26 1.05 x 1.4 x 0.925 m concrete U drain chamber with iron cover 02/11 30/04
27 Geotextile membrane 02/11 30/04
28 Rock filled gabions 02/11 30/04
29 Trapezoidal drain, grouted stone pitching 15 cm thick 31/01
30 Stone pitching 31/12

Pavement works 22/05 10/03


31 Gravel sub-base in carriageway, stabilised with crushed stone, 250 mm thick 26/04 22/05 20/02
32 Crushed stone base in carriageway, 200 mm thick 28/04 25/05 23/02
33 125 x 300 mm kerbstone 15/12 15/05 12/10 10/03
34 50 x 225 mm kerbstone 01/12 31/03 01/12 22/01
35 80 mm thick paving blocks in busbays and walkways 03/12 2/04 05/12 10/02

Asphaltic layers 11/12 03/10


36 Prime coat MC30 30/04 11/12 17/03
37 75 mm thick bitumen bound base course 03/05 13/12 19/03
38 Tack coat MC3000 14/02 20/07 21/03 02/10
39 50 mm thick asphaltic concrete binder course 15/02 05/05 22/03 20/07
40 40 mm thick asphaltic concrete wearing course 06/05 21/07 21/07 03/10

Road Furniture 02/01 31/10


41 W crash barriers 02/11 02/08 02/01 31/10
42 Guardrail reflectors 16/03 15/07 15/06 31/10
43 Precast concrete New Jersey Barrier 04/01 16/03 15/02 30/04
44 Road signs 15/04 15/07 12/07 31/10
45 120 mm wide road marking line 17/05 27/07 18/08 31/10
46 150 mm wide road marking line 17/05 27/07 18/08 31/10
47 300 - 350 mm wide road marking line 01/06 02/08 01/09 31/10

Finishing works and demobilisation 15/09 15/11


48 Finishing works 01/07 07/08 15/09 10/11
49 Demobilisation of construction equipment 15/07 10/08 01/10 13/11
50 Notice of Substantial Completion 15/07 18/10 18/10
51 Completion of the Project 12/08 15/11

Project: NKAWKAW BYPASS Task Progress Summary Deadline EOT due to delay of other activities
Date: 03/02/2010 Split Milestone Project Summary EOT due to increase of quantities

During the rainy seasons (May - October) the number of working days per month is assumed to be reduced by 50% * Quantity increased as per actual Site conditions
** Rate increased due to increased quantity

───── Activity at reduced rate ─ ─ ─ ─ ─ Activity as per approved Programme that was suspended EOT = Extention of Time

Potrebbero piacerti anche