Sei sulla pagina 1di 105

INFORMATION TO USERS

This manuscript has been reproduced from the microfilm master. UMI
films the text directly from the original or copy submitted. Thus, some
thesis and dissertation copies are in typewriter face, while others may
be from any type of computer printer.

The quality of this reproduction is dependent upon the quality of the


copy submitted. Broken or indistinct print, colored or poor quality
illustrations and photographs, print bleedthrough, substandard margins,
and improper alignment can adversely afreet reproduction.

In the unlikely event that the author did not send UMI a complete
manuscript and there are missing pages, these will be noted. Also, if
unauthorized copyright material had to be removed, a note will indicate
the deletion.

Oversize materials (e.g., maps, drawings, charts) are reproduced by


sectioning the original, beginning at the upper left-hand comer and
continuing from left to right in equal sections with small overlaps. Each
original is also photographed in one exposure and is included in
reduced form at the back of the book.

Photographs included in the original manuscript have been reproduced


xerographically in this copy. Higher quality 6" x 9" black and white
photographic prints are available for any photographs or illustrations
appearing in this copy for an additional charge. Contact UMI directly
to order.

University Microfilms International


A Bell & Howell Information Company
300 North Zeeb Road, Ann Arbor. Ml 48106-1346 USA
313/761-4700 800/521-0600

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Order Number 1346951

Study of factors causing variability in project estim ate

Hastak, Makarand, M.S.


University of Cincinnati, 1991

Copyright © 1991 by H astak, M akarand. A ll rights reserved.

UMI
300N.ZeebRd.
Ann Arbor, MI 48106

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
UNIVERSITY OF CINCINNATI

March 5, 1991

I hereby recommend that the thesis prepared under


my supervision by Makarand Hastak____________
entitled Study o f factors cousins variability in project
estimate

be accepted asfu lfillin g this part o f the requirements fo r


the degree o f Master o f Science_______________

Approved by:

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
STUDY OF FACTORS CAUSING VARIABILITY

IN PROJECT ESTIMATE

A thesis submitted to the

Department of Civil and Environmental Engineering

College of Engineering

Division of Graduate Studies

UNIVERSITY OF CINCINNATI

in partial fulfillment of the

requirements for the degree of

MASTER OF SCIENCE

1991

by

MAKARAND HASTAK

B.E., Civil Engineering, Nagpur University,

Nagpur, India, 1987.

Committee Chair: Dr. Issam A. Minkarah

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
ABSTRACT

This thesis presents a new model for evaluating

percentage cost escalation in estimated project costs. This

PWPCE model takes into account all attributes that have a

potential for project cost escalation. It is based on an

intricate influence pattern generated by complex

interdependencies among the attributes. The model allows the

contractor to utilize his experience in evaluating the

probable weighted percentage cost escalation in the estimated

project cost. Additionally it calculates the probability of an

attribute occurring as a variable. The probability and

percentage cost escalation values obtained by using this model

can help a contractor to identify risk attributes.

Furthermore, the output of this model and the resulting

knowledge of risk attributes can be used as an effective cost

control measure. One of the outputs are, minimum and maximum

values for the probable cost escalation in the estimated

project cost by the end of a project. This information can be

used by contractors in appropriating contingency funds for a

project. The input required from the user is the conditional

probability that an attribute will occur as a variable, given

that its preceding attribute has occurred as a variable. Also

the probability and percentage cost escalation values for the

starting attributes are required as an input. Contractors can

easily provide these values based on their experience.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
© Copyright Makarand Hastak 1991.

All rights reserved.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
ACKNOWLEDGEMENTS

I would like to. express my sincere gratitude to Prof.

Issam Minkarah for his constructive advise and guidance

throughout this research. I am also thankful to the members of

my committee Prof. Andrew Bodocsi, Prof. Prahlad D. Pant and

Prof. George Suckarieh for their valuable support. Prof. Paul

Horn of the UC mathematics department, helped clarify certain

important mathematical aspects of the model. A special note of

thanks is due to Mr. John W. Slomba of Belcan Engineering

Services, Inc. for providing access to literature from which

this research has benefitted greatly.

ii

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
TABLE OF CONTENTS

CHAPTER PAGE

ABSTRACT i

ACKNOWLEDGEMENTS ii

TABLE OF CONTENTS iii

LIST OF FIGURES v

LIST OF TABLES vi

I INTRODUCTION

1.1 General Background. 01

1.2 Thesis Objective. 04

II THE ESTIMATING PROCESS AND ESTABLISHED VARIABLES 06

2.1 The Estimating Process. 06

2.1.1 Type of Estimates. 08

2.2 Estimating Techniques. 10

2.3 Opinion of Researcher's on Potential 15

Variables.

III RESEARCH APPROACH ANDMETHODOLOGY 22

3.1 Identification of Variables. 23

3.2 The Influence Pattern of the Variables. 23

3.3 The Probable Weighted Percentage Cost 42

Escalation Model.

3.4 Impact of Attributes on the Estimated 53

Cost Of the Project.

iii

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
IV CONCLUSION 57

4.1 Phases of Research. 58

4.2 Scope and limitations. 61

4.3 Conclusion. 62

4.4 Suggestions for further study. 63

LIST OF REFERENCE 64

ADDITIONAL READINGS 66

APPENDIX

Sample Project. 68

iv

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
LIST OF FIGURES

FIGURES PAGE

Figure-1. Influence pattern of Attributes. 07

Figure-2. Actual Equipment Cost. 36

Figure-3. Actual Labor Cost. 37

Figure-4. Project Management Cost & Construction 38

Support Indirect Cost.

Figure-5. Actual Material Cost. 39

Figure-6. Total Cost of Project/End of Work. 40

Figure-7. The Estimating Process. 41

Figure-8. Probability of Occurring as a Variable. 44

Figure-9. Normalized Weights. 49

Figure-10. Minimum and Maximum Percentage cost 52

Escalation in Estimated Project Cost.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
LIST OF TABLES

TABLE PAGE

Table-I List of Attributes (Group-1) 24

Table-II List of Attributes (Group-2) 25

Table-Ill Precedence Chart of Attributes (Group-1) 27

Table-IV Precedence Chart of Attributes (Group-2) 29

vi

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER 1

INTRODUCTION

1.1 General Background

There is no business skill more important to the

construction industry than estimating. The success or failure

of a project depends to a great extent on the accuracy of

estimating at every stage of the project, may it be a

feasibility estimate, design estimate or a detailed contractor

estimate.

The accuracy of an estimate is equally important to the

project owner, his design team and the contractor. An accurate

estimate makes or breaks a contractor. Although contractors

put in a lot of time and effort in preparing a detailed

estimate, it is a common experience that the total cost of a

given project invariably differs from the previously estimated

cost of that project. Most of the times contractors/owners

have to face a cost overrun rather than a cost underrun. This

cost growth is sometimes in the range of 1.8 - 4.0 times the

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
initial estimate, especially in new technology plants.1 Was

there an error in quantity take-off or was the productivity of

resources not assessed properly? Are natural causes to be

blamed or the owner for his frequent changes? It is of concern

therefore, to study the factors which cause this variation in

a project-cost estimate.

While evaluating the cost of the new project, the

contractor's estimator usually consults the available data

bank of previously executed projects. Using this data bank, he

appropriates various factors like schedule and labor/equipment

productivity for the new project. However, without questioning

the completeness of the available data, the probabilistic

nature of these factors and their interrelationship with

numerous other factors cannot be neglected. For example, the

schedule of a project, apart from productivity of

labor/equipment, depends on many other factors like project

management, weather, change orders, error/rework, regulatory

approvals, etc. These factors in turn depend on many others

like the owner, management, nature of work, etc. As each

project differs, the exclusive use of the available data bank

cannot be justified.2 Thus the usual practice is to add a

1 James J. Diekmann, "Probabilistic Estimating: Mathematics


and Applications," Journal of Construction Engineering and
Management 109, no. 3 (September 1983): p. 306.

2 James J. Adrian, Construction Estimating: An Accounting and


Productivity Approach (Reston, Virginia: Reston Publishing
Co.,1982): p. 154.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
contingency factor to the baseline estimate.3 Estimators after

calculating the cost of the project add a contingency factor

from their own side. This factor is called "engineering

contingency". It is added to increase the confidence level of

their estimate, such that, the probability of a cost overrun

or underrun is 50 percent (0.5). This estimate is then

submitted to the management for approval where a "management

contingency" is added to it to further increase the confidence

level.4 An estimator defines a contingency fund as

[a]n assessment, made by a professional, of the amount of


funds which, when added to the line item estimate, will
reflect the most likely final cost of the project given
relative stability of the scope and assumptions upon
which the estimate is based.5
One important point that is illustrated by the definition

of contingency fund is that the evaluation of this fund is

based on certain constraints and assumptions. Even if, the

scope of work is fixed before the initiation of the project,

the assumptions might vary. Furthermore, there are many other

factors which are relatively independent of the base line

estimate but have a potential of tremendous impact on the

overall cost of the project. Some examples of this would be

3 Patricia A. Owen and John K. Nabors, "Quantifying Risks in


Capital Estimates," 1983 Transactions of the AACE (1983): pp. B.5.1
- B.5.7.
4 K.T. Yeo, "Risk, Classification of Estimates, and
Contingency Management," Journal of Management in Engineering 6,
no.4. (October 1990): pp. 458 - 470.

5 John R. Healy, "Contingency Funds Evaluation," 1982


Transactions of the AACE (1982): p. B.3.1.
[Underlining were in the original].

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
inflation, regulatory approvals, wastage, weather conditions,

project management, etc. All these factors are potential

variables and might occur with different probabilities and

weights in different projects. A decision on a contingency

fund without a systematic consideration of all factors, their

interrelationships and their relative impact on the overall

cost of the project, is bound to be fallacious and

inconsistent. Therefore a new approach to the problem needs to

be taken, one that would account for the whole range of

possible variables that might lead to a cost overrun. The

objective of this thesis is to establish the factors that

cause variation in the estimated cost of a project, their

interrelationships and their effect on the overall cost of the

project.

1.2 Thesis Objective

In order to provide contractors and their estimators with

a more reliable way of estimating their projects, this thesis

aims at achieving the following objectives:

1. To ascertain the variables that cause project cost

escalation.

2. To establish the interdependencies of these variables.

3. To formulate the relationship of these variables with

respect to their probability of occurrence, weight

accredited to each of them and the percentage cost

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
escalation each variable causes on the total cost of the

project.

4. To study the overall impact of these variables on the cost

of the project.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER 2

THE ESTIMATING PROCESS AND ESTABLISHED VARIABLES

In the field of construction, estimating has been defined

as a technique to approximately forecast the most probable

cost of the elements and efforts involved in a project with a

well defined scope.6 The probabilistic nature of an estimate

prevents it from being 100% accurate, no matter what is done

to improve the estimating process to gain a higher confidence

level in the estimate.

2.1 The Estimating Process

The estimating process in general can be illustrated as

in fig-1.7 A request for bids is placed by the owner or his

architect/engineer after evaluating a feasibility or

preliminary estimate of the project. The contractors,

6 Kenneth K. Humphereys, Jelen's Cost and Optimization


Engineering. 3rd. ed.(New York, NY: McGraw-Hill 1991): p.363; James
J. Adrian, Construction Estimating: An Accounting and Productivity
Approach (Reston, VA: Reston Publishing Co. 1982): p.2.

7 Adrian, p.152, Fig. 6.3.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C O N TR AC T
D O C U M E N TS

Q U A N T IT Y
T A Z E -O F F

P R IC IN G O F D E T E R M IN A T IO N OF
S U B -C O N T R A C T O R
D IR E C T LA B O R E Q U IP M E N T COST ESTIMATES
A N D M A T E R IA L

D E T E R M IN A T IO N O F D E T E R M IN A T IO N O F
JOB OVERHEAD COMPANY OVERHEAD

A D D IT IO N O F
P R O F IT

B ID

F IG U R E -!: THE ES TIM A TIN G PROCESS

(James J. Adrian, CONSTRUCTION ESTIMATING: An Accounting and


Productivity Approach, 01982, p.152. Reproduced by permission
of Prentsca-Hatt, /«&, Englewood Cliffs, NJ 07632)

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
interested in bidding for the project, purchase the contract

document and prepare a detailed or a conceptual cost estimate

of the project. The contractors' cost estimate includes

quantity take-off, pricing of direct labor and material,

determination of equipment cost, subcontractor estimates,

determination of job overhead, determination of company

overhead, addition of profit, and finally the compilation of

a bid.
The accuracy of the contractors bidding task, i.e., to

find the actual amount of his bid proposal can make or break

him. If the contractors team underestimates the cost of the

project, he might win the bid but it may be unprofitable as

the actual cost of the project might exceed his estimated

cost. The relative accuracy of the cost estimate also depends

to a certain extent on the type of estimate used to evaluate

the project. However, the definitive type of estimate prepared

by the contractors is by far the most accurate.

2.1.1 Type of Estimates

The selection of an estimating type depends to a

considerable extent on the purpose of the estimate, available

information, and on time demands.8 The American Association

of Cost Engineers classifies the estimate in three types,

based on their method of preparation and on their probable

8 Humphreys, p.368.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
accuracies.9

1. Order of Magnitude: Cost-capacity curves, scale-up or down

factors, or ratio estimating techniques are often used to

prepare this type of estimate. However, detailed

engineering data is mostly not used. Probable accuracy:

-30 % to +50 %.10

2. Budget (Conceptual): Equipment details, flow sheets and

layouts are used to prepare this type of estimate. This

type does not refer to the budget as a project control

document but as an owner's budget. Probable accuracy:

-15 % to +30 %.11

3. Definitive: A complete set of specifications and a very

finely defined engineering data is used to prepare this

type of estimate. Probable accuracy: -5 % to +15 %.12

These different types of estimates are generally grouped

into two main categories: preliminary and detailed. The

"order-of-magnitude type" and "budget or conceptual type" of

estimate are included in the preliminary estimate category,

whereas the "definitive" type is included in the category of

detailed estimate. Definitive type is sometimes divided into

9 John R. Healy, "Contingency Funds Evaluation," 1982


Transactions of the American Association of Cost Engineers (1982):
p.B.3.3

10 David J. Peeples, "Capital Cost Estimates: Sensitivity to


Schedule," 1984 Transactions of the AACE (1984): pp. B.1.1 - B.1.5

11 Ibid.

12 Ibid.

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
semi-definitive (-15 % to +25 %), definitive (-10 % to +15 %)

and check (-5 % to +10 %).13 Estimates are not only used for

bidding but are also used for budget establishment,

feasibility study, obtaining government approvals, legal

claims, etc., therefore the degree of accuracy required in the

estimate varies from one purpose to another. For example, a

preliminary estimate might serve the purpose of an owner,

whereas a contractor requires a more precise estimate and

would therefore prefer to use a detailed estimate.

2.2 Estimating Techniques

Diverse estimating techniques are used by estimators to

come up with their desired type of estimate. To arrive at a

preliminary project cost estimate, the most commonly used

techniques are:14

1. Feasibility estimate.

2. Unit cost estimate.

3. Parameter estimating.

4. Factor estimating.

5. Range estimating.

6. Probabilistic estimating.

Feasibility estimate or owner's estimate, as the name

suggests, is prepared to determine the feasibility of building

13 Humphreys, p.369, Table 14.2.

14 For the following see: Adrian, p.101-149.

10

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
the project, irrespective of the financing. It helps the owner

to evaluate the benefits and costs involved in the project at

its conception. The most important concepts in a feasibility

estimate are life-cycle costs, depreciation costs, and debt

service. As at this stage the project drawings or even the

preliminary plans are not available, the accuracy of a

feasibility estimate primarily depends on the ability of the

estimator. The feasibility estimator should have a good

knowledge of project design, life of construction material,

pricing and should be well versed with accounting and related

tax laws.

Unit cost estimates are based on the unit cost of a

functional element such as cost-per-student, cost-per-bed or

cost-per-parking space. It is a measure of the cost of the

building relative to its function. It is very easy and fast to

work with. The cost-per-square-foot estimate is the most

prominent example of this type of estimate. The unit cost is

based on historical data and when multiplied by the total

area, gives the total cost of the project. Cost-per-cubic-foot

is sometimes used as a function, however, it is not very

reliable.

Parameter estimating is a relatively new technique. It

provides the owner with an approximate cost of the project.

Parameter cost estimates were first published by Engineering

News Record in 1966 and since then the periodical has expanded

the concept further. This technique allows an estimator to

11

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
allocate lump-sum cost to the various activities or attributes

of a project. Parameter measures, like gross enclosed floor

area, total basement floor area, number of floors including

basement, area of face brick, interior partitions, parking

area, etc., are selected and are then allocated to the various

activities/attributes of the project, one parameter to an

activity/attribute. Cost ratios are then calculated relative

to the parameter measure. For example, if a gross enclosed

floor area is the selected parameter with a value of 500,000

sf., and if the general conditions and fee for the project was

$1,645,000 then the cost ratio or the parameter cost would be

3.29. The parameter costs can be easily established by an

estimator from a previously executed project of a similar

nature or he can directly use published parameter costs. These

cost ratios or parameter costs can then be used to evaluate

the cost of the new project. This technique can be suitably

used by estimators to evaluate contractor bids.

Factor estimating is a technique in which a factor of 1.0

is assigned to a predominant activity cost and other

activities are then assigned factors proportionate to the cost

of that activity. For example, if in a project a factor of 1.0

is assigned to the cost of concreting with a projected cost of

$400,000, then the factor assigned to excavation with a

projected cost of $280,000 would be 0.7. These factors can

then be used by an estimator to evaluate the cost of a similar

new project.

12

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Range estimating, as the name suggests, is the technique

in which a range is established for the unit cost and

quantities of the critical activities. Critical activities are

defined as those having a potential of causing a cost

variation of at the least 0 . 5 % in the conceptual and0.2 % in

the detailed estimate. The percentage variation is considered

over the total estimated cost of the project. If however,

profit is considered then activities causing variation of 5 %

and 2 % respectively are considered critical. All critical

activities are considered to be mutually independent.15

After finalizing the critical activities and their target

quantities, a probability that actual value will be equal to

or less than the target, is assigned to each activity. The

literature, however, does not clarify the use of this

probability in the subsequent computations. For each critical

activity, a lowest expected and a highest expected value is

ascertained, thus defining a range. There are no established

criteria for deciding on the lowest and the highest expected

value for an activity. The estimator here, has to rely on his

instinct or that of his col leagues/superiors. Then a model is

prepared to establish the mathematical relationship between

the quantities, unit costs and the total cost of the project.

When Monte Carlo simulation is conducted on the accumulated

data, using a personal computer 1000 scenarios are generated,

15 Michael W. Curran, "Range Estimating: Reasoning with Risk,"


1988 Transactions of the American Association of Cost Engineers
(1988): pp. N.3.1 - N.3.9

13

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
each giving a bottom line cost. These results when plotted in

the form of a graph, with cost along y-axis and percentage

probability of overrun along the x-axis, one gets an s-curve

with a practical maximum and minimum. This graph can be

suitably used to evaluate the amount of contingency required

to reduce the probability of a cost overrun.

Range estimating is promoted as a decision technology, to

be used in conjunction with the conventional estimating,

rather than a new estimating technique.

Probabilistic estimating is a relatively new technique.

The point estimates commonly prepared may or may not indicate

the most probable value of the estimate. The future cost of

most of the elements is usually unknown in an estimate. These

cost elements can therefore be considered as random variables.

In probabilistic estimating these variables are assumed to

have a probability distribution function which is continuous,

unimodal, non-negative and real valued. Direct analytical

techniques, the central limit theorem, approximation for a

general function and simulation are some of the probabilistic

estimating procedures.16

A contractor's detailed estimate or definitive estimate

is one of the most important types of estimate, governing the

actual cost of building the project. A detailed estimate is

prepared by careful evaluation and pricing of the quantities

of work, material, labor and equipment involved in the

16 James E. Diekmann, pp.297-308.

14

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
project. A contractor usually sublets part of the work to

specialty contractors or sub-contractors. The general

contractor (or prime contractor) collects the estimates

prepared by the sub-contractors, adds them to his own, then

after including the job and company overhead comes up with his

estimated cost of the project. Addition of profit to this

estimate completes a contractor's bid.

The various estimating types vary in accuracy and detail.

The contractor's detailed estimate is by far the most accurate

in predicting the line item costs. Range estimating also

provides quite an accurate projection of a line-item cost

overrun. However it only considers the critical line items and

does not account for certain other factors, which have a

potential for tremendous impact on the total cost of the

project.

2.3 Opinion of Researcher's on Potential Variables

Herbsman17 and Stukhart18 have pointed out the adverse

effect of inflation on project cost. Herbsman has suggested a

forecasting model whereas Stukhart suggests that the increase

17 Zohar Herbsman, "Long-Range Forecasting Highway Construction


Costs," Journal of Construction Engineering and Management 109, no.
4. (December 1983): pp. 423-434.

18 George Stukhart, "Sharing the Risks of the Cost of


Inflation," 1982 Transactions of the American Association of Cost
Engineers (1982): pp. M.1.1 - M.1.7

15

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
in cost due to inflation should be shared equally by the

parties involved in the project. Inflation causes an upward

change in the cost of labor, material and equipment and thus

adversely affects the estimated cost of a project.

A detailed project estimate is based on a predetermined

schedule for that project. The total cost of the project,

particularly with large, long-term projects, is significantly

affected by changes in schedule and project plans. Changes in

a schedule can also have a considerable impact on worker

morale, equipment cost, job overhead, project management cost

or construction support indirect cost, company overhead and

labor cost. Peeples has pointed out that, due to inflation and

interest rate the value of every dollar in a capital cost

estimate depends on its expenditure in time. Therefore, every

cost element can be considered to be schedule dependent.19

Parisi and Schlunt have divided the time sensitive costs

into three groups, displacement cost, disruption cost and

extended cost. Displacement cost has been defined as the cost

incurred due to, execution of work in a time frame other than

originally anticipated, e.g., effect of inflation on labor and

material cost and additional cost of performing work in an

unfavorable seasonal condition. Disruption cost relates to

costs incurred due to change in work strategy, e.g., poor

planning, change orders, overtime, acceleration and suspension

of work, etc. Extended cost has been defined as the time

19 Peeples, p.B.1.2.

16

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
dependent fixed cost, e.g., job site overhead and home office

overhead.20 Parisi and Schlunt have classified construction

delays into three types, excusable/compensable, excusable/non-

compensable, and non-excusable. Excusable/compensable type are

usually owner-caused delays like, failure to obtain a building

permit, failure to prepare building site, etc. Excusable/non-

compensable type are the delays caused by unforseen events

beyond the contractor's control. They are, unusual weather,

fire, etc. Under these circumstances the contractor is excused

for the delay but is not paid for it. The third category of

non-excusable delays are contractor caused delays like,

improper work management, delay in performance by

subcontractors, failure to procure material and equipment on

time, etc. The contractor is neither compensated for them nor

excused.21 Yeo has also mentioned schedule changes as one of

the major causes of cost overrun.22

Stukhart and Adrian have illustrated the probabilistic

nature of labor, equipment and material cost and its impact

on the total estimated cost of the project. Adrian illustrates

the point that, labor and material costs form the major

portion of a contractor's project cost estimate. Therefore it

is important that due consideration should be given to the

20 Ronald F. Parisi and Robert J. Schlunt, "Construction Delay


Claims: Treatment of Extended overhead," 1983 Transactions of the
AACE (1983): pp. C.2.1 - C.2.7.

21 Ibid.

22 Yeo, p.459.

17

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
accuracy of these costs. However, these costs depend on many

other factors which are probabilistic in nature. Labor cost

directly depends on labor productivity, whereas productivity

in turn can be related to variables like worker morale, crew

balance, prior training of workers, prior experience of

workers, age of workers, weather conditions, degree of

management leadership, repetitive nature of work and

difficulty of work.23 Depending on the type of project,

equipment cost can be a considerable portion of the project

cost estimate. Sometimes "application process" is used to

calculate the equipment cost. In this process the labor and

material costs is multiplied by a factor to come up with the

equipment cost, however, the accuracy of this method is

doubtful.24 Equipment cost also depends on equipment planning

and productivity.25 Stukhart has explained the importance of

materials management for construction industry. He has pointed

out certain problem areas in materials management which can

adversely effect the project cost. They are, slow placement of

purchase orders, poor supplier performance, poor site

distribution at job site, poor quality control, poor inventory

control at job site, incomplete specifications and changes by

23 Adrian, p. 154.

24 Ibid, p. 155.

25 George Stukhart, "Materials Management Report: Business


Roundtable Construction Industry Cost Effectiveness Project
(CICE)," 1983 Transactions of AACE (1983): pp. K.6.1 - K.6.6.

18

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
engineering.26 Adrian has provided a list of factors that

affect material cost. They are supply of material, demand for

material, quantity purchased, location of material purchased,

need of storage of material, quality of material needed and

materials management.27

Herbsman has discussed the influence of "Bidding Volume

Index" on the total cost of the project. Bidding volume index

is defined as the total volume of work in a certain area at a

certain time span. If bidding volume is high for a particular

year, more jobs are created and as a result costs are also

high, on the other hand costs are forced down if bidding

volume is low for that year. Herbsman also pointed out the

effect of rising cost of material, labor, equipment and

subcontracting work on the total cost of the project.28

Owen and Nabors have pointed out the effect of variables

like productivity, schedule, labor rates, escalation,

regulatory approval and weather uncertainty on the project

cost. They pointed out that the productivity of union workers

was influenced by the unemployment rate in that specific area.

The higher the unemployment rate the harder the workers would

work.29 In an earlier article, Nabors has discussed the

26 Ibid.

27 Adrian, p. 155.

28 Zohar Herbsman, "Long-Range Forecasting Highway Construction


Costs," Journal of Construction Engineering and Management 109, no.
4. (December 1983): pp. 423-434.

29 Patricia A. Owen and John K. Nabors, pp. B.5.1-B.5.7.

19

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
adverse impact of changes on the construction cost and

schedule. He has cited a project in which 700 change orders

were processed. To solve the problem, econometric techniques

were used. A time series model was developed to predict the

future behavior of a variable. In such a model, the influence

of other factors on the variable is not considered.30 This

was again the topic of the April, 1990 Construction Industry

Institute report.31 The ClI report suggests that any

additional costs resulting directly or indirectly from the

change, should be borne by the owner. In other words, if the

owner issues a change order, then the direct or indirect

impact of this change on the project activity and its cost

shall be evaluated and then reimbursed to the contractor.

However, a proper record of change orders is not always

maintained. Change orders might thus result in a loss for the

contractor.

Bullis has described some major reasons for field cost

variance. They are design changes, insufficient manpower

supply high turnover of force, poor supervision, poor

craftsmen, poor productivity, labor relations problem,

weather, unanticipated soil conditions, underground

30 John K. Nabors, "Forecasting Final Project Cost With


Econometric Techniques," 1982 Transactions of the AACE (1982): pp.
A.4.1-A.4.5.

31 Cost/schedule Controls Task Force of the Construction


Industry Institute, ed., The Impact of Changes on Construction Cost
and Schedule (Austin, TX: Bureau of Engineering Research at the
University of Texas, 1990).

20

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
obstruction, unanticipated interferences, error, rework and

equipment and material and schedule/quality problem.32

Other important factors that can cause variations in

project cost estimates are wastage during handling/delivery

and execution, mathematical errors, omissions at the stage of

quantity take-off, estimators experience, site management,

misinterpretation of specifications or drawings and the

manhours the estimator put in preparing • the estimate.

Furthermore, the interdependency of these variables also play

a major role in influencing the final cost of the project.

Peter J. Bullis, "Practical Cost Control: Techniques and Timing,"


1984 Transactions of the AACE (1984): p. A.1.3, Table-4.

21

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER-3

RESEARCH APPROACH AND METHODOLOGY

In the previous chapters it has been shown that the

accuracy of an estimate is of prime importance to the

contractor. Although estimates are prepared with meticulous

care, no comprehensive approach is available to account for

all the variables that influence the total cost of the

project. Some further research is therefore required to

understand the precise behavior of these variables in the

estimating process. The objective of this research is to

identify these variables, to establish the influence pattern

of these variables with respect to the estimating process and

to understand their collective impact on the project cost

estimate.

This chapter explains the methodology and procedure

followed in carrying out this study. The research was carried

out in four stages.

22

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
3.1 Identification of variables

It is of importance to properly identify the attributes

that occur as variables and cause project cost escalation. In

this research, potential variables were ascertained by using

the available literature. As these variables come into play at

different stages in the life of a project, they were arranged

into two groups. The attributes (potential variables), that

influence the project before it has started, were included in

group-one. Group-two included the attributes that come into

play after the project has started. The project cost estimate

was considered as the dividing line between the two groups. A

complete list of attributes in the two groups was thus

prepared (Table-I and Table-II). However, this thesis deals

with group-two only, i.e., the attributes which come into play

after the project has commenced.

3.2 The Influence pattern of the Attributes

Available literature not only helped in identifying the

potential variables but also to understand the

interrelationship among the attributes. It was found that the

attributes are highly interdependent and an intricate

influence pattern is obtained. The results have been

summarized in Table-Ill and Table-IV.

To a considerable extent, the management or project team,

23

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

TABLE - I (GROUP - 1)

S. NO. ABBR, DESCRIPTION OF ATTRIBUTE


1. A INTERPRETATION OF SPECIFICATIONS & DRAWINGS
2. A1 SCOPE OF WORK
3. B QUANTITY TAKE-OFF
4. B1 MATHEMATICAL ERROR
5. B2 OMISSION
6. B3 ESTIMATOR'S EXPERIENCE
7. B4 ESTIMATING TECHNIQUE USED
8. . B5 MANHOURS AVAILABLE TO PREPARE THE ESTIMATE
9. B6 AVAILABLE DATA BANK
10. B7 COSTING OF DIRECT LABOR/MATERIAL/EQUIPMENT
11. C MANAGEMENT OR PROJECT TEAM
12. Cl JOB PLANNING
13. C2 EQUIPMENT SELECTION
14. C3 SCHEDULE & DURATION OF PROJECT
15. C4 PROJECT MGMT. COST/CONST.SUPPORT INDIRECT COST/FINANCE COST
16. C5 SUB-CONTRACTOR ESTIMATE
17. C6 SUB-CONTRACTOR SELECTION
18. D TOTAL ESTIMATED COST OF THE PROJECT
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

TABLE - II (GROUP - 2)

S.NO. AfiBR* DESCRIPTION OF ATTRIBUTE

1 c Management or Project team.


2 Cl Job Planning.
3 C2 Proper selection of equipment.
4 C3 Schedule and Duration of Project.
5 C4 Project management cost/Const, support indirect cost.
6 E Actual Equipment cost.
7 El Actual Equipment Productivity.
8 F Change orders.
9 G Regulatory approvals.
10 H Unanticipated soil conditions/Interferences/Underground obstructions.
11 I General environment.
12 J Error and Rework.
13 L Actual Labor cost.
14 LI Actual Labor Productivity.
15 L2 Worker morale
16 L3 Crew balance.
‘CONTD. ..
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

S. HO* ABBR. DESCRIPTION OP ATTRIBUTE*

17 L4 Prior experience/training of workers.


18 L5 Repetitive nature of work.
19 L6* Difficulty of work.
20 L7 Weather conditions.
21 M Actual Material cost.
22 Ml Demand and supply of material/equipment at site.
23 M2 Quantity of material purchased.
24 M3 Location of material purchased.
25 M4 Need of storage of material.
26 M5 Quality of material needed.
27 0 Owner/A&E.
28 R Availability of Resources.
29 S Site management.
30 SI Site location.
31 0 Labor Union.
32 V Bidding Volume Index.
33 w Wastage.
34 T Total cost of Project/End of work.
TABLE - III (GROUP-1)
S.NO. ABBR. DESCRIPTION OF ATTRIBUTE PRECEDING FOLLOWING
ATTRIBUTE ATTRIBUTE
1. A INTERPRETATION OF SPECIFICATIONS & B3 A1
DRAWINGS
2. A1 SCOPE OF WORK A B
3. B QUANTITY TAKE-OFF A1 D
4. B1 MATHEMATICAL ERROR B3 D
5. B2 OMISSION B3 D
6. B3 ESTIMATOR'S EXPERIENCE START (ST) B1,B2,B4,B7,A
7. B4 ESTIMATING TECHNIQUE USED B3 D
8. B5 MANHOURS AVAILABLE TO PREPARE THE C b
ESTIMATE
9. B6 AVAILABLE DATA BANK START B7
10. B7 COSTING OF DIRECT B3,B6 D
LABOR/MATERIAL/EQUIPMENT
11. C MANAGEMENT OR PROJECT TEAM START B5,Cl ,C2 ,C3 ,C
6
12. Cl JOB PLANNING C D
13. C2 EQUIPMENT SELECTION C D
14. C3 SCHEDULE & DURATION OF PROJECT c C4
CONTD...
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

S. HO. ABBR. DESCRIPTION OF ATTRIBUTES PRECEDING FOLLOWING


ATTRIBUTE ATTRIBUTE
15. C4 PROJECT MGMT. COST/CONST.SUPPORT C3 D
INDIRECT COST/FINANCE COST
16. C5 SUB-CONTRACTOR ESTIMATE C6 D
17. C6 SUB-CONTRACTOR SELECTION C C5
18. D TOTAL ESTIMATED COST OF THE PROJECT B,B1,B2,
64,65,67,01,02,
C4,C5 1

to
09
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

TABLE ~ IV (GROUP - 2)
S.NO. ABBR. DESCRIPTION OF ATTRIBUTE PRECEDING ATTRIBUTE FOLLOWING
ATTRIBUTE
1. c MANAGEMENT OR PROJECT TEAM START(ST) Cl,C2,S ,R
2. Cl JOB PLANNING C El, LI
3. C2 PROPER SELECTION OF EQUIPMENT C El
4. C3 SCHEDULE & DURATION OF PROJECT F,G,J,R L,E,C4
5. C4 PROJECT MGMT. COST/CONST. SUPPORT C3,H T
INDIRECT COST
6. E ACTUAL EQUIPMENT COST El,C3 T
7- . El ACTUAL EQUIPMENT PRODUCTIVITY Cl,C2,L2,L3,L4,L5,L6, E
L7
8. F CHANGE ORDERS 0,S C3
9. G REGULATORY APPROVALS O C3
10. H UNANTICIPATED SOIL START C4
CONDITIONS/INTERFERENCES/UNDERGROU
ND OBSTRUCTIONS
11. I GENERAL ENVIRONMENT START T
12. J ERROR AND REWORK S C3,M
13. L ACTUAL LABOR COST L1,C3 T
14. LI ACTUAL LABOR PRODUCTIVITY Cl,L2,L3,L4,L5,L6,L7 L
CONTD...
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

S.NO. fcBBR. DESCRIPTION OF ATTRIBUTE PRECEDING ATTRIBUTE FOLLOWING


ATTRIBUTE
15. L2 WORKER MORALE. S Ll,El
16. L3 CREW BALANCE S LI, El
17. L4 PRIOR EXPERIENCE/TRAINING OF u Ll,El
WORKERS
18. L5 REPETITIVE NATURE OF WORK START Ll, El
19. L6 DIFFICULTY OF WORK SI Ll,El
20. L7 WEATHER CONDITIONS SI Ll, El
21. M ACTUAL MATERIAL COST W ,R ,J ,M2,M3,M4,M5 T
U> 22. Ml DEMAND AND SUPPLY OF S R,M2,M4
o
MATERIAL/EQUIPMENT AT SITE
23. M2 QUANTITY OF MATERIAL PURCHASED Ml,SI M
24. M3 LOCATION OF MATERIAL PURCHASED SI M
25. M4 NEED OF STORAGE OF MATERIAL Ml, SI M
26. M5 QUALITY OF MATERIAL NEEDED 0 M
27. 0 OWNER/A&E START M5,F,G
28. R AVAILABILITY OF RESOURCES Ml,S1,U,C C3,M
29. S SITE MANAGEMENT C,U L2,L3,M1,F,W,
J
CONTD...
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

S. NO. ABBR. DESCRIPTION OF ATTRIBUTE PRECEDING ATTRIBUTE FOLLOWING


ATTRIBUTE
30. SI SITE LOCATION START L6,L7,R ,
M2,M3,M4
31. U • LABOR UNION V L4,R,S
32. V BIDDING VOLUME INDEX START U
33. w WASTAGE S M
34. T TOTAL COST OF THE PROJECT/END OF M, E, C4 ,1,L ---
WORK
influences the availability of resources on site, site

management, job planning and proper selection of equipment for

the project. Managements' laxity in making the required

resources available at site on time can have an adverse effect

on the schedule and duration of the project. Lack of resources

can also have an incremental effect on the material cost of

the project. Many decisions on site require confirmation from

the head office or the management/project team. An error or

delay in taking these decisions might affect a cost sensitive

attribute, resulting into a possible cost escalation. Proper

job planning and selection of equipment is very important for

the success of a project, mismanagement in these aspects can

have a considerable impact on the equipment productivity. Low

equipment productivity would directly influence the equipment

cost.

Many factors, other than lack of resources, can be held

responsible for the change in schedule and duration of a

project, such as, error and rework, change orders and

regulatory approvals.33 Error and rework can be attributed to

improper site management, whereas management of regulatory

approvals is often handled by the owner. Change orders are

either issued by the owner to the contractor or by the

contractor to the sub-contractor.

33 Peeples.

32

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Change in a project schedule has an adverse effect on the

worker morale, thereby affecting labor productivity. As every

cost element in an estimate is schedule dependent, a change in

schedule has a negative effect on the equipment cost, labor

cost, job overhead, finance cost, company overhead, project

management cost and construction support indirect cost.34

Actual labor and equipment cost, i.e., the total cost of labor

or equipment incurred by the end of the project, also depends

on actual labor and equipment productivity. Actual labor and

equipment productivity is defined as the actual productivity

achieved during the course of the project. This productivity

value might be different than the value assumed during the

estimating stage. The variability in productivity can be

attributed to factors like worker morale, crew balance, prior

training of workers, repetitive nature of work, difficulty of

work, weather conditions, job planning and proper selection of

equipment.35 Repetitive nature of work would depend on the

scope, as defined in the contract document. Nothing much can

be done about the effect of weather on productivity, however,

all other factors affecting productivity can be controlled to

a considerable extent by the management or site team.

The management decides on the degree of site

34 Ibid.

35 Adrian, p. 154.

33

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
investigation required for the project, however, this decision

influences the probability of facing unanticipated soil

conditions, unanticipated under ground obstructions and

interferences. If faced, these unanticipated conditions can

have an incremental effect on the project management cost and

construction support indirect cost, which add up to increase

the total cost of the project.

Site management is one of the major factors. It

influences a large number of attributes other than what have

been mentioned earlier like supply of material, demand for

material, quantity of material purchased, location of material

purchased, need of storage of material, wastage and

error/rework. Wastage increases the actual material cost

whereas material cost and error or rework add up to increase

the total cost of the project.36 Quantity of material

purchased, location of material purchased and need of storage

of material are attributes influenced by the location of site.

Site location also influences the difficulty of work. Weather

condition at site can be approximated with respect to the site

location.

Labor union is much influenced by the bidding volume

index, which is defined as the volume of work available in an

area in a specific time span. Bidding volume index for a

36 Adrian, p. 155.

34

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
particular area is governed by factors like political

situation, unemployment, stock market behavior, etc., and is

thus beyond the scope of this research. Labor union influences

factors like prior training/experience of workers,

availability of resources and site management. There are

certain factors which are beyond the control of the management

or the owner such as, recession in a country, war, world

situation, inflation, etc. These factors have.been clubbed

under general environment.

Finally the total cost of the project depends on five

attributes. They are, actual material cost, actual labor cost,

actual equipment cost, general environment and the project

management cost/construction support indirect cost. Actual

material cost, actual equipment cost and actual labor cost

indicates the total cost of material, equipment and labor

respectively, i.e., the cost experienced by the end of the

project. The intricate influence pattern of the attributes as

described, is illustrated graphically in Fig.-2.

Figures 3 to 6 show the influence pattern of attributes

actual equipment cost (E), actual labor cost (L), project

management cost and construction support indirect cost (C4)

and actual material cost (M) respectively. Whereas, Fig.-7

illustrates the attributes influencing the end-of-the-project

cost.

35

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
OF ATTRIBUTES
PATTERN
FIG UR E-2: INFLUENCE
START

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
COST
EQUIPMENT
FIGURE-3: ACTUAL

<o START

/ 1

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
✓ N.

38

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
L, Ki

o
o

39

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
COST
MATERIAL
FIG U R E S : ACTUAL

START

"40

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
WORK
OF
COST OF PROJECT/END

o
FIGURE-7: TOTAL

.41

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
3.3 The Probable Weighted Percentage Cost Escalation Model

The Probable Weighted Percentage Cost Escalation model

was developed based on:

(1) The probability that an attribute will act as a variable,

i.e., the probability that over the course of the project, the

cost or status of an attribute will differ from what was

assigned to it at the estimating stage. For example, the labor

productivity obtained during the course of the project might

differ from what was assumed at the estimating stage.

Similarly, at the estimating stage a non-variable status might

be assigned to the attribute, management or project team.

However, there is a possibility that during the course of the

project the management or project team might make a decision

error, influencing many other attributes. This would change

the non-variable status of the attribute, management or

project team, to a variable. The probability of this event

cannot be neglected.

To determine the probability associated with each

attribute, three assumptions were made:

(1) If an attribute is influenced by a set of attributes,

containing more than one element, then the attributes in

that set are considered to be independent.

(2) All the attributes are conditionally dependent on their

preceding attribute(s ).

42

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
(3) There is a probability that, although an attribute has

occurred as a variable, the attributes influenced by it

might not occur as variables, i.e., if attributes, B and

C are influenced by an attribute A then it is possible

that [ l - p ( B U C ) ] * 0 , B and C being independent.

To satisfy assumptions (2) and (3) conditional

probabilities are required at every step in the influence

pattern of the attributes. These conditional probabilities can

be generalized for all the projects. The author proposes to

conduct an extensive questionnaire survey to collect data on

conditional probabilities of attributes, weight accredited to

the members of a group of attributes influenced by a common

attribute and the percentage cost escalation due to them.

However for the sample project, conditional probabilities were

assigned using an educated judgement. The conditional

probabilities were then used to calculate the global

probabilities of the attributes, with respect to the

probability of their preceding attribute. In order to

calculate the probability of an attribute influenced by more

than one attribute, the following steps were taken,

(1) conditional probabilities were calculated for the

attribute, with respect to all its preceding attributes.

(2) a union of these conditional probabilities would then

provide the probability of the attribute. The example in

Fig.-8 illustrates this point.

43

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C4

C3

Ml
P R O B A B IL IT Y PRO BA­ F O L L O W IN G ATTRIBUTE
PREC­ B IL IT Y
A T T R I­ E D IN G D U E TO
OF A T T R I­ C O N D I­ PROBA­
BUTE PR E C E ­ T IO N A L
ATTR­ S U M PRO D­ BUTE B IL IT Y
A TTR I­
IB U T E D IN G
A T T R I­ UCT PROBA­
BUTE B IL IT Y
BUTE
F 0.084 L 0.90 0.159

G 0.023
C3 0.189 0.012 0.177
E 0.80 0.142
J 0.037

R 0.045 C4 0.90 0.159

F IG U R E -8:P R O B A B IL ITY OF OCCURING AS A VARIABLE

44

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Attribute, schedule and duration of project (C3), is

influenced by attributes regulatory approval (G), change

orders (F), error and rework (J) and availability of resources

(R). Attributes G and F are influenced by attribute, owner/A&E

(0), whereas, F and J are influenced by attribute, site

management (S). Attribute R is influenced by attributes,

demand and supply of material/equipment at site (Ml), site

location (SI), labor union (U) and, management or project team

(C). For C3 to act as a variable it is sufficient for either

G, F, J or R to act as a variable. With the information that

either G, F, J or R can occur as a variable conditional

probabilities for C3 were calculated, i.e.,

p(C3 ! G), p(C3 | F), p(C3 | J) and p(C3 | R)

These conditional probabilities were then multiplied with

the probability of G, F, J and R respectively to calculate the

global probabilities associated with C3. In other words the

intersection of C3 with G, F, J and R was calculated.

Conditional probability of C3, given G has occurred as a

variable, is defined as,37

37 J. R. Benjamin and C. A. Cornell, Probability. Statistics,


and Decision for Civil Engineers (New York, N.Y.: McGraw-Hill Book
Co., 1970): pp. 44-50.

45

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
p(C3 I G) = p(C3 n G) t p(G)

•* p(C3 n G) = p(C3 i G) X p(G)

p(C3 | G) is undefined if p(G) = 0

Therefore the probability of C3, given G, F, J and R have

occurred as variables would be the union of global

probabilities of C3 with respect to G, F, J and R, i.e.,

p(C3) = p[(C3 n g ) u (C3 n f ) u (C3 n j) u (C3 nr )]

however, from assumption (1) it is known that G, F, J and R

are independent, i.e.,

P[(C3 n G) | (C3 n F)] = p(C3 n g)

p(c3 n, g ) n p(C3 n f) -f p(c3 n f) = p(c3 n g )

-> p(c3 n g) n p(c3 n f) = p(C3 n g) x p(C3 n f)

Therefore using the independence of G, F, J and R

p(C3) = p(C3 n G) + p(C3 n f) + p(C3 n j) + p(C3 n r )

- [{p(C3 n G) x p(C3 n F)} + {p(C3 n G) x p(C3 n J)}

+ {p(C3 n g ) x p(c3 n r )} + {p(c3 n f ) x p(C3 n j)}

+ {p(C3 n f) x p(C3 n R)} + {p(c3 n j) x p(C3 n R)}]

+ [{p(C3 n g) x p(c3 n F) x p(c3 n j)} + {p(c3 n g)

x p(C3 n F) x p(c3 n R)} + {p(c3 n F) x p(C3 n j) x

46

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
p(C3 n R)} + {p(C3 n G) x p(C3 n j) x p(C3 n r) }]

- [p(C3 n G) x p(c3 n F) x p(C3 n j) x p(C3 n r)]

However, if the accuracy of computing the probability is

only required up to three significant digits then the

following equation is sufficient.

p(C3) = p(C3 n G) + p(C3 n f ) + p(C3 n j) + p(C3 n r )

- [{p(C3 n G) x p(C3 n F)} + {p(C3 n G) x p(.C3 n J)}

+ {p(C3 n G) x p(C3 n R)} + {p(C3 n F) x p(C3 n J)}

+ {p(C3 n F) x p(c3 n r)} + {p(c3 n j) x p(c3 n r)}]

The probability of attributes with more then one

preceding attribute can be similarly calculated. Once the

probability that C3 will occur as a variable is known, the

conditional probabilities of its following attributes can be

calculated. The attributes influenced by C3 are actual labor

cost (L), actual equipment cost (E) and project management

cost and construction support indirect cost (C4) . The

conditional probabilities [p(L C3)] and the global

probabilities [p(L fl C3)] of L, E and C4 as calculated are

shown in column six of the table in Fig.-8.

The probabilities associated with all the attributes of

a sample project are illustrated in the Appendix. To calculate

these probabilities it is necessary to make an educated guess

47

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
for the probabilities of the starting attributes. This can be

done based on the prior experience of the firm. The starting

attributes are management or project team (C), unanticipated

soil conditions, interferences or underground obstructions

(H), general environment (I), repetitive nature of work (L5),

owner/A&E (0), site location (SI), and bidding volume index

(V).

(2) Weighted percentage cost escalation in the estimated

project cost due to each attribute, assuming that the

attribute occurs as a variable. It can be said that, the

percentage cost escalation in the estimated project cost

because of an attribute would be, the cumulative percentage

cost escalation due to the attributes influenced by it. This

point has been illustrated in the example in Fig.-9. The

attributes, job planning (Cl), proper selection of equipment

(C2), site management (S) and, availability of resources (R)

are influenced by the attribute, management or project team

(C). If for some reason attribute C occurs as a variable then

there is a possibility that its following attributes Cl, C2,

S and R might occur as variables. But if Cl, C2, S and R occur

as variables then they have an independent capacity to cause

certain percentage cost escalation in the estimated project

cost. Therefore it can be said that, the percentage cost

escalation due to the attribute C would be the cumulative

48

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C2

F O L L O W IN G ATTR IB U TE

P A IR W IS E C O M P A R IS IO N R E LA TIV E N O R M A L IZ E D
A T T R - A RRT1-
FO R % COST ESCALATION W E IG H T W E IG H T
B U TE BUTE
M IN MAX M IN MAX M IN MAX

1.0 1.0 1.0 1.0 0 .2 3 0.2 2


Cl
|
0 .7 5 1.0 o!<5 1.0 0.75 0.6 0 .1 7 0 .1 3
C2
C 1 1
1 1
S 1.0 2.0 1.0 3.0 1.50 1.8 0 .3 4 0.4 0
t |
1
R 0 .7 5 0.6 1.13 1.1 0 .2 6 0 .2 5

TOTAL 4.38 4.5 1 .0 0 1.00

FIG U R E -9: N O R M ALIZED WEIGHTS

49

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
percentage cost escalation due its following attributes Cl,

C2, S and R. The proportion in which Cl, C2, S and R influence

the percentage cost escalation due to C can be calculated by

assigning weights to each one of them. However, as a range of

values should be considered for the percentage cost escalation

due to each attribute, the same proportion might not apply for

both minimum and maximum values. Therefore separate weights

were assigned for the minimum and maximum percentage cost

escalation due to the following attributes. To calculate the

weights, a temporary weight of 1.0 was assigned to Cl and it

was then compared with C2, similarly a pairwise comparison was

done between C2 and S and S and R. In the following step,

relative weights were calculated for Cl, C2, S and R with

respect to Cl. These relative weights were then normalized to

add up to one. As explained earlier, two sets of weights were

assigned to the following attributes, one for maximum and the

other for minimum percentage cost escalation. The calculation

has been illustrated in the example in Fig.-9. The calculation

of normalized weights for all the attributes in the sample

project has been illustrated in the Appendix (Normalized

Weights).

To calculate the weighted percentage cost escalation due

to each attribute it is necessary to assign minimum and

maximum percentage cost escalation values to the starting

attributes. This would vary from firm to firm and thus should

50

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
be done based on the prior experience of the firm. For the

sample project an educated guess was made to ascertain the

maximum and minimum percentage cost escalation due to the

starting attributes. Once the percentage cost escalation due

to the starting attributes has been ascertained, the

percentage cost escalation due to the following attributes can

be calculated based on their normalized weights. This process

has been illustrated through an example in Fig.-10. Attribute,

availability of resources (R) is influenced by attributes,

demand and supply of material/equipment at site (Ml), site

location (SI), labor union (U) and management or project-team

(C). Furthermore, attribute R influences attributes, schedule

and duration of project (C3) and actual material cost (M). The

percentage cost escalation due to R would then be the sum of

individual cost escalations in R due to its preceding

attributes Ml, SI, U and C, i.e., cost escalation in R if each

one of its preceding attributes independently occur as a

variable. The percentage cost escalation due to C3 and M,

given R has occurred as a variable, would be the product of

their normalized weights and the total percentage cost

escalation due to R. The weighted percentage cost escalation

due to each attribute in the sample project has been

illustrated in the Appendix (Minimum and Maximum Weighted

Percentage Cost Escalation).

Once the probability of occurring as a variable and the

51

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C3

Ml

P R EC E D IN G A TTR IB U TE
A T T R I­
FO LLO W IN G ATTRIBUTE
ATTRIBUTE % C.E
BUTE
% COST
A T T R IB U T E ESC A LA ­ N O R M A L IZ E D * COST
M IN M A X ATTR1 W E IG H T
E S C A L A T IO N
T IO N
BUTE
M IN MAX M IN MAX M IN MAX

Ml 0.4 9 0 .6 7

C3 0 .5 7 0 .6 7 3.33 9.1

SI l.IS 2 .8 0
R 5.84 1 3 .56

u 1.60 3 .84
M 0 .43 0.33 2 .5 1 4 .4 6

c 2 .6 0 6 .2 6

F IG U R E -1 0 :M IN IM U M & M A X IM U M PERCENTAGE COST ESCALATION

I N ESTIMATED PROJECT COST

52

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission
minimum and maximum weighted percentage cost escalation due to

all the attributes is ascertained, the probable weighted

percentage cost escalation can be calculated by multiplying

the probability and cost for each attribute. This has been

illustrated in the Appendix (Probable weighted Percentage Cost

Escalation).

3.4 Impact of Attributes on the Estimated Cost of the Project

The PWPCE model was tried on a sample project. The

probable weighted percentage cost escalation in the estimated

project cost was calculated for the attributes including the

attribute end-of-the-project. The probable weighted percentage

cost escalation in the estimated project cost due to an

attribute is defined as the weighted percentage cost

escalation in the estimated project cost, if and only if the

attribute occurs as a variable, given all the attributes

preceding it have occurred as variables.

In the sample project, probabilities were assigned to the

starting attributes, management or project team (C, 0.10),

unanticipated soil condition, interferences and underground

obstructions (H, 0.05), general conditions (I, 0.15),

repetitive nature of work (L5, 0.06), owner/A&E (O, 0.05),

site location (SI, 0.04) and bidding volume index (V, 0.06)

and it was found that the probability that the end of the

53

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
project cost (T) would vary from the estimated project cost

was 0.60. The major contributors to this high probability were

the five end attributes, actual material cost (M, 0.216),

actual equipment cost (E, 0.210), project management cost and

construction support indirect cost (C4, 0.201), general

conditions (I, 0.135) and finally the actual labor cost (L,

0.240). The figures in brackets indicate attribute and its

probability of occurring as a variable. A few other attributes

which indicated a high probability of occurring as a variable

were, labor union (U, 0.06), site management (S, 0.102),

Availability of resources (R, 0.075), labor productivity- (LI,

0.096), change orders (F, 0.084), equipment productivity (El,

0.079) and schedule and duration of project (C3, 0.177).

As per the definition of PWPCE model, the probable

weighted percentage cost escalation associated with an

attribute holds true only if it occurs as a variable, given

that all attributes preceding it have occurred as variable.

PWPCE for an attribute is the product of the probability

associated with the attribute and the cumulative weighted cost

escalation in it, expressed as a percentage of the estimated

project cost. For example in the sample project, the PWPCE

associated with the attribute total cost of the project or

end-of-work cost (T) is minimum 21.60 % and maximum as 43.12

%, this escalation in cost is true only if the probability

that T would occur as a variable is 0.60. In other words it is

54

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
the sum of 60 % of individual cost escalation in T due to its

preceding attributes, M, E, C4, I and L. However it would be

noticed that the sum of PWPCE associated with M, E, C4, I and

L is not equal to the PWPCE associated with T. This comes from

the definition of PWPCE model that the PWPCE value indicates

the percentage escalation in cost associated with an

attribute, if and only if it occurs as a variable, given that

its preceding attributes have occurred as variables. For

example PWPCE associated with E is derived from the product of

the probability that it occurs as a variable given its

preceding attributes equipment productivity (El), and schedule

and duration of project (C3) have occurred as variables and

the sum of the weighted percentage cost escalation in E

because of the variability in El and C3. From this it implies

that their is no direct relation between the PWPCE associated

with an attribute and the PWPCE value associated with its

preceding attribute(s ).

Multiple iterations can be performed by giving different

probability values to the starting attributes and obtaining

the probability of T occurring as a variable. However, as

there are seven starting attributes it would be highly

laborious to perform multiple iterations. The author proposes

to computerize the PWPCE model so that it becomes possible to

study the changes in cost due to various iterations. Multiple

iterations and the probabilities of attributes generated

55

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
thereof can help the management in pin-pointing the attributes

which have a high probability of occurring as a variable. The

knowledge of high risk attributes can help the management in

controlling the project cost by maintaining tighter control on

these attributes. Furthermore the PWPCE value associated with

the end-of-the-project cost would enable management to take a

sound decision on the contingency fund for the project.

56

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER 4

CONCLUSION

The accuracy of a project cost estimate is very important

for the success of a project. Contractors and owners take

meticulous care in preparing an estimate, however, it is

rarely seen that the total project cost equals this estimate.

The most common approach taken to counter this problem is the

addition of a contingency fund to the estimated project cost.

So far, no comprehensive approach has been available to

account for all attributes that influence the total cost of a

project.

The objective of this study has been to identify the

attributes which have a potential to occur as variables and

thus cause a project cost escalation. Furthermore this study

ascertained their influence pattern and finally established a

mathematical relationship between these attributes.

57

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
4.1 Phases of Research

The study was carried out in four stages. First, all

attributes that have a potential for causing a project cost

escalation were identified through an extensive literature

survey. These variables were arranged in two groups, according

to their emergence at different stages of the project. The

potential variables like quantity take-off, mathematical

error, omission, estimator's experience, costing of direct

labor/material/equipment, etc., which come into play before

the project has started, were included in group one. Group two

includes the potential variables which influence the project

after it has started.

In the second stage, the influence pattern of attributes

was determined with the help of available literature. It was

observed that all the attributes were highly interdependent.

As a result an intricate influence pattern was obtained. Seven

attributes were categorized as starting attributes and the

influence pattern was developed from them.

In the third stage of the study, a four tier model was

developed to establish the mathematical relationship between

the attributes. The PWPCE model provides the probable weighted

percentage cost escalation value for the last attribute (i.e.,

the total cost of the project/end of work) and also for all

other attributes. In the first tier of the model, normalized

58

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
weights are calculated for all the attributes following a

common attribute. These values of normalized weight were used

later in the third tier to determine the percentage cost

escalation due to various attributes. The normalized weights

were calculated for minimum and maximum percentage cost

escalation. This provides a relationship between the ranges of

percentage cost escalation due to attributes which have a

common preceding attribute in the influence pattern.

The probability of an attribute occurring as a variable

is calculated in the second tier of the model. This

probability of an attribute to occur as a variable is

calculated based on the knowledge that its preceding attribute

has occurred as a variable. Probability values are assigned to

the starting attributes based on past experience of the user.

The user also has to provide the conditional probabilities for

the following attributes. These conditional probabilities are

converted into global probabilities by multiplying them with

the probability of the preceding attribute. The global

probabilities thus collected from all preceding attributes,

are then used to calculate the probability of that attribute.

Similar calculations are carried throughout the influence

pattern, arriving at the probability of the total cost of the

project.

If the attributes occur as variables, they have a

potential to cause a certain percentage cost escalation in the

59

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
estimated project cost. This escalation is calculated in the

third tier of the model. Minimum and maximum percentage cost

escalation values are assigned to the starting attributes

based on the user's experience. The normalized weights

calculated in the first tier, are then used to appropriate the

percentage cost escalation due to all other attributes in the

influence pattern. The minimum and maximum values thus

obtained indicate the percentage cost escalation in the

estimated project cost if an attribute occurs as a variable.

In the fourth and last tier of the model, the probability

obtained in the second tier and the minimum and maximum

percentage cost escalation obtained in the third tier are

multiplied to obtain the probable weighted percentage cost

escalation in the estimated project cost. The PWPCE value thus

obtained is different for all attributes. There is no direct

relationship between the PWPCE value of an attribute and the

PWPCE value of its preceding attribute. The PWPCE value

obtained is unique for each attribute. This is because the

PWPCE value associated with an attribute, indicates the

probable weighted percentage cost escalation in the estimated

project cost due to that attribute, if, and only if, all its

preceding attributes have occurred as variables. Due to the

intricate influence pattern of the attributes, most of them

have different preceding attribute(s ). The influence of an

attribute on each of its following attributes is also

60

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
different.

In the final stage of the study, the PWPCE model was

applied to a sample project in order to study its

effectiveness. Normalized weights were calculated and an

educated judgement was made to assign probability and

percentage cost escalation values to the starting attributes.

It should be noted that the PWPCE values obtained are

dependent on the normalized weights, conditional probabilities

and the values assigned to the starting attributes. Therefore

care needs to be taken in assigning these values.

4.2 Scope and Limitations

The scope of this model is manyfold. It provides the

probability of an attribute occurring as a variable during the

course of the project. It also provides the weighted

percentage cost escalation in the estimated project cost due

to an attribute, if it occurs as a variable. Finally, the

model provides the probable weighted percentage cost

escalation in the estimated project cost due to each variable.

There are a few limitations of this model. The user will

have to provide the values for probability and percentage cost

escalation for the starting attributes. Also the conditional

probabilities for attributes have to be provided, given that

their preceding attribute has occurred as a variable. Finally,

61

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
the accuracy of the model depends on the values supplied by

the user. However, these limitations can be overcome if the

user takes due care in providing the values. The values

required from the user relate to past experiences of the firm.

Furthermore, these values might differ from project to project

and from situation to situation.

4.3 Conclusion

The output of this model can be used beneficially by

contractors and estimators in evaluating the contingency fund

for a project. The minimum and maximum PWPCE values associated

with the total cost of the project will enable the management

to take a sound decision on the contingency fund. The

probabilities associated with the attributes can be used to

isolate the risk attributes. From this model, two kinds of

risk attributes can be identified: (1) the attributes that

have a high probability of occurring as a variable but cause

a low percentage cost escalation, and (2) the attributes that

have a low probability of occurring as a variable but can

cause a considerable percentage cost escalation in the

estimated project cost. Furthermore, the knowledge of risk

attributes will be beneficial to the management for effective

project control. The output of this model can also be used as

a cost control document. The project cost can be kept under

62

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
check by keeping a tighter control on the functions of the

risk attributes.

4.4 Suggestions for Further Study

The effectiveness of this model can be improved further

by standardizing the conditional probabilities for the

attributes. This objective can be achieved by. conducting a

national survey, sending a suitable questionnaire to the top

500 construction firms.

As the model requires lengthy calculations, it is tedious

to perform multiple iterations manually. It will therefore be

beneficial to computerize the model. Results thus obtained can

be used to study the behavior of attributes against each

other. If presented graphically, these behavior patterns can

be used directly by contractors and estimators.

63

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
LIST OF REFERENCES

Adrian, James J. Construction Estimating: An Accounting and


Productivity Approach. Reston, Virginia: Reston
Publishing Co., 1982.

Benjamin, J.R. and C.A. Cornell. Probability. Statistics, and


Decision for Civil Engineers. New York, N.Y.: McGraw-Hill
Book Co., 1970.

Bullis, Peter J. "Practical Cost Control: Techniques and


Timing." In: 1984 AACE Transactions, pp. A.1.1 - A.1.8.
Morgantown, WV: American Association of Cost Engineers,
1984.
Curran, Michael W. "Range Estimating: Reasoning with Risk."
In: 1988 AACE Transactions. pp. N.3.1 - N.3.9.
Morgantown, WV: American Association of Cost Engineers,
1988.
Cost/Schedule Controls Task Force of the Construction Industry
Institute, ed. The Impact of Changes on Construction Cost
and Schedule. Austin, TX: Bureau of Egineering Research
at the University of Texas, 1990.

Diekmann, James J. "Probabilistic Estimating: Mathematics and


Applications." Journal of Construction Engineering and
Management 109 No. 3 (September 1983): pp. 297 - 308.

Healy, John R. "Contingency Funds Evaluation." In: 1982 AACE


Transactions. pp. B 3.1. - B.3.4. Morgantown, WV:
American Association of Cost Engineers, 1982.

Herbsman, Zohar. "Long-Range Forecasting Highway Construction


Costs." Journal of Construction Engineering and
Management 109 No. 4 (December 1983): pp. 423 - 434.

Humphereys, Kenneth K. Jelen's Cost and Optimization


Engineering. Third ed. New York, NY: McGraw-Hill, 1991.

Nabors, John K. "Forecasting Final Project Cost With


Econometric Techniques." In: 1982 AACE Transactions, pp.
A.4.1 - A.4.5. Morgantown, WV: American Association of
Cost Engineers, 1982.

Owen, Patricia A. and John K. Nabors. "Quantifying Risks in


Capital Estimates." In: 1983 AACE Transactions, pp. B.5.1
- B.5.7. Morgantown, WV: American Association of Cost
Engineers, 1983.

64

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Parisi, Ronald F. and Robert J. Schlunt. "Construction Delay
Claims: Treatment of Extended Overhead." In: 1983 AACE
Transactions. pp. C.2.1 - C.2.7. Morgantown, WV: American
Association of Cost Engineers, 1983.

Peeples, David J. "Capital Cost Estimates: Sensitivity to


Schedule." In: 1984 AACE Transactions, pp. B.1.1 - B.1.5.
Morgantown, WV: American Association of Cost Engineers,
1984.

Stukhart, George. "Sharing the Risks of the Cost of


Inflation." In: 1982 AACE Transactions, pp. M.1.1 -
M.1.7. Morgantown, WV: American Association of Cost
Engineers, 1982.
________________ . "Materials Management Report: Business
Roundtable Construction Industry Cost Effectiveness
Project (CICE)." In: 1983 AACE Transactions, pp. K.6.1 -
K.6.6. Morgantown, WV: American Association of Cost
Engineers, 1983.

Yeo, K.T. "Risk, Classification of Estimates, and Contingency


Management." Journal of Management in Engineering 6 N o .
4 (October 1990): pp. 458 - 470.

65

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Additional Readings

Ahuja, Hira N. and Michael A. Walsh. Successful Methods in


Cost Engineering. New York: John Wiley & Sons, 1983.

Assaf, Sadi and Abdulmohsen Al-Hammad. "The Effect of Economic


Changes on Construction Cost." In: 1988 AACE
Transactions. pp. L.1.1 - L.1.4. Morgantown, WV: American
Association of Cost Engineers, 1988.

Bacher, Lawrence C. "Contingency Evaluation in Capital Cost."


In: 1984 AACE Transactions. pp. B.6.1 - B.6.4.
Morgantown, WV: American Association of Cost Engineers,
1984.

Bees ton, Derek T. Statistical Methods for Building Price Data.


New York, NY: Spon Ltd., 1983.

Bell, Lansford C. and Gazanfer A. Bozai. "Preliminary Cost


Estimating for Highway Construction Projects;" In: 1987
AACE Transactions. pp. C.6.1 - C.6.4. Morgantown, WV:
American Association of Cost Engineers, 1987.

Bent, James A. and Albert Thumann. Project Management for


Engineering and Construction. Lilburn, GA: The Fairmont
Press, 1989.

Bentil, Kweku K. "A Uniform Method of Estimating Quantities."


In: 1987 AACE Transactions. pp. C.7.1 - C.7.4.
Morgantown, WV: American Association of Cost Engineers,
1987.

Birrell, George S. "Cyclic Linkage Between Cost Control and


Estimating." In: 1987 AACE Transactions, pp. P.5.1 -
P.5.9. Morgantown, WV: American Association of Cost
Engineers, 1987.

Brown, Joseph A. "Government Estimating vs. General Contractor


Estimating." In: 1989 AACE Transactions, pp. L.1.1 -
L.1.8. Morgantown, WV: American Association of Cost
Engineers, 1989.

Calder, Granville. The Principles and Technioues of


Engineering Estimating. Elmsford, NY: Pergamon Press,
1976.

Carlsson, Christer and Yevgeny Kochetkov, eds. Theory and


Practice of Multiple Criteria Decision Making. New York,
NY: North-Holland Publishing Company, 1983.

66

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Clough, Richard H. Construction Contracting. 4th ed., New
York, NY: John Wiley & Sons, 1981.

Conforto, Sergio L. "Preliminary Cost Estimate: Guidelines for


Elaboration." In: 1988 AACE Transactions, pp. E.2.1 -
E.2.4. Morgantown, WV: American Association of Cost
Engineers, 1988.

Cook, Paul J. Bidding for the General Contractor. Kingston,


MA: R. S. Means Company, 1985.

Cooke, William P. Quantitative Methods for Management


Decisions. New York, NY: McGraw-Hill Book Company, 1985.

Curran, Michael W. "Range Estimating Operating and


Manufacturing Costs." In: 1986 AACE Transactions, pp.
F.1.1 - F.1.8. Morgantown, WV: American Association of
Cost Engineers, 1986.
_________________ . "Range Estimating: Contingencies with
Confidence." In: 1989 AACE Transactions, pp. B.7.1 -
B.7.4. Morgantown, WV: American Association of Cost
Engineers, 1989.
_________________ . "Range Estimating Reduces Iatrogenic Risk."
In: 1990 AACE Transactions. pp. K.3.1 - K.3.3.
Morgantown, WV: American Association of Cost Engineers,
1990.
Dagostino, Frank R. Estimating in Building Construction. 2nd
ed., Reston, Virginia: Reston Publishing Company, 1978.

Davis, K. Roscoe, Patrick G. McKeown and Terry R. Rakes.


Management Science an Introduction. Boston, MA: Kent
Publishing Company, 1986.

Dickinson, Charles H. "Project Cost Analysis Using Range


Estimating." In: 1986 AACE Transactions, pp. E.8.1 -
E.8.5. Morgantown, WV: American Association of Cost
Engineers, 1986.

English, J. Morley, ed. Cost-Effectiveness: The Economic


Evaluation of Engineered Systems. New York, NY: John
Wiley & Sons, 1968.

Frost, David A. "The Value of Precision in Cost Estimates."


In: 1984 AACE Transactions, pp. B.5.1 - B.5.10.
Morgantown, WV: American Association of Cost Engineers,
1984.

67

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Hackney, John W. "Determining Overrun Probabilities." In: 1986
AACE Transactions. pp. E.4.1 - E.4.7. Morgantown, W V :
American Association of Cost Engineers, 1986.

Hackney, John W., Kay Hudson and Lesley Gasperow. "Parametric


Cost Estimating - a Guide." In: 1987 AACE Transactions,
pp. C.3.1 - C.3.8. Morgantown, WV: American Association
of Cost Engineers, 1987.

Haimes, Yacov Y., Kyosti Tarvainen, Takashi Shima and Jacob


Thadathil. Hierarchical Multiobiective Analysis of Large-
Scale Systems. New York, NY: Hemisphere Publishing
Corporation, 1990.

Hardie, Glenn M. Construction Estimating Techniques. Englewood


Cliffs, NJ: Prentice-Hall, 1987.

Helstrom, Carl W. Probability and Stochastic Processes for


Engineers. New York, NY: Macmillan Publishing Company,
1984.

Henderson, Thomas R. and Paul J. Buckholtz. "Comparative Cost


Estimates for Project Control." In: 1989 AACE
Transactions. pp. C.4.1 - C.4.7. Morgantown, WV: American
Association of Cost Engineers, 1989.

Hermes, Raad H. "Cost-Schedule Integration: Alternatives." In:


1982 AACE Transactions, pp. E.5.1 - E.5.4. Morgantown,
WV: American Association of Cost Engineers, 1982.

Jackson, Richard Lee, John W. Kinsey, Wayne E. Cotton and


Susan K. Moore. "The Why and How of Contingency
Management." In: 1985 AACE Transactions, pp. N.0.1 -
N.0.5. Morgantown, WV: American Association of Cost
Engineers, 1985.

Kreps, Rollin A. and John W. Slomba. "Conceptual Estimating


Systems and their Benefits." In: 1990 AACE Transactions,
pp. K.2.1 - K.2.5. Morgantown, WV: American Association
of Cost Engineers, 1990.

McMohan, Leonard A. "Estimating and Negotiating Change


Orders." In: 1984 AACE Transactions, pp. C.5.1 - C.5.5.
Morgantown, WV: American Association of Cost Engineers,
1984.

Mendel, Tom G. "Case History - Parametric Estimating System."


In: 1989 AACE Transactions. pp. B.1.1 - B.1.6.
Morgantown, WV: American Association of Cost Engineers,
1989.

68

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Mlakar, Paul F. and Larry M. Bryant. "Direct Range Cost
Estimating." In: 1990 AACE Transactions, pp. K.4.1 -
K.4.4. Morgantown, WV: American Association of Cost
Engineers, 1990.

Mueller, Frederick W. "Cost Engineering, Estimating and


Construction Management." In: 1986 AACE Transactions, pp.
E.6.1 - E.6.7. Morgantown, WV: American Association of
Cost Engineers, 1986.

Noble, William. "Conceptual Estimation and Budget Control."


In: 1987 AACE Transactions, pp. C.ll.l - C.11.8.
Morgantown, WV: American Association of Cost Engineers,
1987.

Ostwald, Phillip F. Cost Estimating for Engineering and


Management. Englewood Cliffs, NJ: Prentice-Hall, 1974.

Payne, Thomas A. Quantitative Techniques for Management: A


Practical Approach. Reston, Virginia: Reston Publishing
Company, 1982.
Peurifoy, R. L. and G. D. Oberlender. Estimating Construction
Costs. 4th ed., New York, NY: McGraw-Hill Book Company,
1989.
Pilcher, Roy. Appraisal and Control of Project Costs.
Maidenhead, England: McGraw-Hill Book Company Ltd., 1973.

Poulton, Charles G. "The Dangers of Early Estimates." I n :


1989 AACE Transactions, pp. A.3.1 - A.3.3. Morgantown,
WV: American Association of Cost Engineers, 1989.

Querns, Wesley R. "What is Contingency, Anyway?" In: 1989 AACE


Transactions. pp. B.9.1 - B.9.5. Morgantown, WV: American
Association of Cost Engineers, 1989.

Rapier, C. Peter. "How to Deal with Accuracy and Contingency."


In: 1990 AACE Transactions. pp. K.8.1 - K.8.8.
Morgantown, WV: American Association of Cost Engineers,
1990.

Sanders, Steve R. and Tom Cooper. "Factors Affecting


Contractor Profitability." In: 1990 AACE Transactions,
pp. K.9.1 - K.9.7. Morgantown, WV: American Association
of Cost Engineers, 1990.

Skitmore, Martin. "Factors Affecting Accuracy of Engineers'


Estimates." In: 1988 AACE Transactions, pp. B.3.1 -
B.3.8. Morgantown, WV: American Association of Cost
Engineers, 1988.

69

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Stevenson, James J. "Escalation Modeling, Forecasting and
Tracking." In: 1984 AACE Transactions, pp. F.3.1 - F.3.7.
Morgantown, WV: American Association of Cost Engineers,
1984.

Stevene, G. and T. Davis. "How Accurate are Capital Cost


Estimates?" In: 1988 AACE Transactions, pp. B.4.1 -
B.4.5. Morgantown, WV: American Association of Cost
Engineers, 1988.

Stewart, Rodney D. and Ann L. Stewart. Microestimatinq for


Civil Engineers. New York, NY: McGraw-Hill Book Company,
1986.

Stukhart, George. "Cost Management Report: The Business


Roundtable Project." In: 1984 AACE Transactions, pp.
C.1.1 - C.1.5. Morgantown, WV: American Association of
Cost Engineers, 1984.

True, Newton F. "Determining the Accuracy of a Cost Estimate."


In: 1988 AACE Transactions. pp. T.2.1 - T.2.8.
Morgantown, WV: American Association of Cost Engineers,
1988.
Wright, P. A. and T. V. Hill. "Cost Estimating-Dealing with
Uncertainty." In: 1986 AACE Transactions, pp. E.5.1 -
E.5.8. Morgantown, WV: American Association of Cost
Engineers, 1986.

Yokoyama, Kurazo and Takeshi Tomiya. "The Integrated Cost


Estimating Systems Technique for Building Cost." In: 1988
AACE Transactions. pp. B.6.1 - B.6.6. Morgantown, WV:
American Association of Cost Engineers, 1988.

70

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
M
in CM

CM

w
22 SI 25 O »-f
o o esa
OHPiH
CM
I
0*
& gg
o
05 |m CO rH CM
X0 < H

H
►J
n M
A
H
H
>
CM
A
o
GO
A
0
a
ftp
o
a
o
Pm
O
M
&
H
H (N oo r> in
n o rH
A
a
o
06
P<

n
•W

71

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
M
n n CM
rH

in
rH

<n

m
CM

OJ
©
0* D

CM

!a

CM <n
rH

72

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CO CM

in

rH rH

Hf, <«.%
o
WMM
o

in tH rH CM

r> rH CM n

tft

73

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
<o
eg CM

H
iH

(N

M
VO CO
CO

on
eg

M co co
eg

eg co rH

m Hf co
So

iH CO
eg eg

74

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CO rH
CN V£> rH CN n

W
CO <J\ in rH <N n
rH

n n

H
M
CN
rH

CN

CO CN
CN rH

vo
CN CN

75

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
;.
>*
M
■J
« M
C9
rH vo CM o VO vo o CM CM in rH
«§: s ■«r o H rH rH rH CM rH rH vo \o
o o O O O O O O O o o © l
• • • • • • • • • I
* O o o o o o o o o o o o 1
i i
fO £4 O'
i 8 2 2 % . O in o in o o o o o in
i
H
ssss
O h c u h
■V rH CO CM Hf ■V in CM CM
• • •
o O o O o o o o o

r- o
o rH
o

rH
l
l
l

i «
l
vo c*» CM co HJ* l
bs »o ►J J « £ £ £ J 05 cn d £ l
^ S ; V

!§&&
>* ites
fri W tern
ǥ&ȴ
:H t*
i 1-3 5

issS ® £K -
mm
SS’
/fr*: ^
rH co
VO VO o
o o vo
• • •
A '
° o o o
°
; i ‘ a\
Cv
is
. ^M4a 25£\ •■■■>
i
i
i
1
1
1
1
1
1
1
1
1
CO

O

CM
*■* ;
w 1 as
5 O
A : <0 i 1 1 1 o
;:$w ■ i 1 1 1 •
S^ffi ;. i 1 1 1 rH

'■■{&
aJ ^ v.
h .^*,,.w.,i■'T■O•;s’wSs^,
kS.:,
~ .,-' i , <
A‘Xf>iw)iy
rH VO o rH in
* r t l o t t f l VO VO rH rH O CO
i o I O CM CM CM rH
i | 5 g f i • 1 • •
Q O < a < a i o 1 o O o O O

« A
^Ofltw
m S S£ t * f *
mZ h h p EH Eh O'
* * a 3S» 00 > 00 CO £ w O H

* M
IJS
^3Ei>
.'m4'•OSy£''••*/■■*.-0
•• -<\y $■
< 2 ♦ $£+$&
D > s Eh ■
0&


• • • • •
r o H CM « •M
*
« m n cn n cn

76

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

J
H
I
1
<
S
Pt
CONDIT­
PROBAB­

§
IONAL

ILITY

;*

z
ATTR­
IBUTE

t* w

3s!

ft

D
>*

M s
(0
s *
1
fits :
g£ A
0.240

>
S •*
> ••
S S S H S
Q0*a<a
*
t

:
ml iJ

EtsA
f

i
«*
SllSi^P

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CM m
CM CM co
H

vo rH
cn CO

co

CM

co
rH r> CM co
rH CO
(GROUP-2)

M
WEIGHTS

in
NORMALIZED

co

78

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
M
m
n
rH

rH

OJ rH rH

hi

n m rH

CO

79

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission
CM CM
n
rH
H.

CO n cn
to cn in in CM co

vo
CM CM

M co
CM

rH

cn CM

iH

in

tn
M

CM

rH
co
CM CM

80

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
co co
co co

CM CM rH CM CM rH

rH rH

CO

rH rH CM rH

CO

CM

CM
rH CM

H rH
«*
l-f

rH

rH

co

CM CM CM CM CO

81

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
00 rH
CM CM CM iH

tH

cn cn
CM rH

cn
cm cn CM

M
CM

in
cn

H
W

in
rH rH CM

CM
cn cn

82

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission
CM
d d
CM n
rH
d CM

CM CM
VO
M
rH CM

n
CM cn
ESCALATION

M a fs
d 'S'
M d CM n

CM
I
COST

P<
a
o
PS < w
(9
PERCENTAGE

Eh Of n
CO
O
O • CM in n CM •rH
Eh
O
W
►a d
WEIGHTED

CM
O
PS
Pt rH
Q
W
Eh
& MAXIMUM

W d
Eh
CO
H
CM
S d d
H
CM d d d CM
MINIMUM

Ht

d.

83

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
vO
OV CM CM

cn
CM CM CO

cn
cn
rH

cn
M

cn

CM
vo CO
CM'
CM in «-*

K in

cn CM

CO
CM cn co
H
CN <n cn

co VO
rH CM
CM CM

cn CM cn

rH

CM cn
rH

84

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
X io
cn CM

rH

vo
cn cn cn cn

cn cn
cn
er
55.
M
cn cn
cn cn

iH rH

CO cn

cn
cn cn cn cn CM
H H
03 £♦ CM cn

M cn cn cn
CM rH

Hr

CM in

cn

85

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
1
z

15.94
0. 35
0.50
in in in

0.49
0.40
E+S £ vo CO r- H
CO B* • • • *
o o rH CM
8 §
ATTRIBUTE

8 z o <3* VO r* CO o CO in
oi M CM CO CM co CM CO CO H
« • • «
z o O O o o O O rH

o o VO CM VO CM
« in in o CM CO o o
N &H • • «
H X ■g o o o r-4 O o O rH rH
FOLLOWING

>4 O

y-Z VO r~ CO

cn O
I * M in in O CM CO o o
s • • • •
o o o H O o o rH rH

liptijiM
.....

H rH rH CM
■< M 63 4 63 e* (X X X £ £
»:■- rr
O Q\ in
Cl in rH
a in •
o rH rH rH CM
5 63
S o
Ci z o r* CO m
% X VO CO O CO rH
< • •
o r- rH o rH

>t o o\ O tn <Tl CM in
&
si <n
o
pH CO
CM
H
rH rH CM
in in in
CM rH r-H
n
o
M*
rH
rH

CM

a.

. -> w
«
z
M
z
o
VO
in 0\ CO in in
in in CO CO H
• •
o O
• •
cn
CM
O in
VO H

o o CM O o rH H H rH o o rH
z. 61
i a
n
H

:
$
'
S rH
cn s (X *2
CM CO
£ £ £ £
in
CO
rH
X
H H
cn CO

:i
#<a > rH CM CO
4 . s 23 s £
■ ♦
o
z • • • •
o H CM CO <3*
©X CM CM CM CM CM

86

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
co CM in
CM rH rH

OS Hf
rH rH CM CM rH rH

co
rH rH CM
rH
H!
co pH
CM CM
rH

co CM

CM CM CO
o
CO
CM

rH 10

CO

CO

to CO

87

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
rH CM
rH cn

f-f
rH rH

CO VO
rH cn

CM cn cn cn
M CM

CM cn
< H

o
o rH
r4 CM

CO CM
cn

CM
V>

cn cn cn

88

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
II
1

1
||

||
||
fi'
8;
44
OX H m 00

tt-°

10*0
0 .0 5
3 .7 5
m o H O CO r*

2 .4 1

0 .5 6
0.7 7

0.0 7

4 .2 3
0 .25

0 .0 1
2 .5
' • • « •
■:■.■■.■.•.•.•..v.v,- O cn rH o

3KO
, M,
(GROUP-2)

;3 “
aa s.
w-
S X
O'
oz If) C T 'I rH rH
1 .5 6

10 .1 0
0 .2 5
0 .0 5
0 .0 3

1 .5 6
0 .3 9

0 .4 2
04,, ^' o CM o O O
1 .0

• • •
o H d H o o
ESCALATION

1.
1

*%
^ «■'*
I*
g
XYH

2 1 .1 9

1 1 .9 9
14.38

17.62
21 cn
COST

2 5 .0

2.80

12.0
9.72

4.25

1.29
6.64

0.64
in in 5.0
o
• • •
in cn GO
PERCENTAGE

:
4f >:wwKwrt;
\w >/

tsj S'
as
10.0

4.95

0.90
8.83

5.62
7.42

4.35
7.09

0.55
H n o o o o 1.0
« • • •
WEIGHTED

> cm rH cn CM CM CO
pt &
H H S
3 § < i
3 g « g
PROBABLE

rH
0.015

0.201
0.210
0.177

0.025
0.079

0.096
0.084

s o < 2£ in M* CM
0.10

0.02

10 . 1 5

0.01
0.24

o © O
• • •
0.0 o o o

o-'n
!?
?%-ws
3 '
C4.

n
El
ID

CD
C2

L2
LI

1 U w O s H l-D ■4
i
i
V*?/ .•/><*'sw,

• • • •
16. "

• • • • • • • o H CM cn in
H CM cn in IS CO (Ji pH rH rH rH rl rH

89

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CN cn
cn
is pH

rH CN CN AO
CN CN

rH
cn
rH CN CO rH CO CO

cn CN ;,Q
co
rH

CN
cn VO
CN rH

0*0

in

co as rH cn CN
CN CN CN cn cn

90

Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.

Potrebbero piacerti anche