Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
This manuscript has been reproduced from the microfilm master. UMI
films the text directly from the original or copy submitted. Thus, some
thesis and dissertation copies are in typewriter face, while others may
be from any type of computer printer.
In the unlikely event that the author did not send UMI a complete
manuscript and there are missing pages, these will be noted. Also, if
unauthorized copyright material had to be removed, a note will indicate
the deletion.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Order Number 1346951
UMI
300N.ZeebRd.
Ann Arbor, MI 48106
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
UNIVERSITY OF CINCINNATI
March 5, 1991
Approved by:
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
STUDY OF FACTORS CAUSING VARIABILITY
IN PROJECT ESTIMATE
College of Engineering
UNIVERSITY OF CINCINNATI
MASTER OF SCIENCE
1991
by
MAKARAND HASTAK
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
ABSTRACT
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
© Copyright Makarand Hastak 1991.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
ACKNOWLEDGEMENTS
ii
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
TABLE OF CONTENTS
CHAPTER PAGE
ABSTRACT i
ACKNOWLEDGEMENTS ii
LIST OF FIGURES v
LIST OF TABLES vi
I INTRODUCTION
Variables.
Escalation Model.
iii
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
IV CONCLUSION 57
4.3 Conclusion. 62
LIST OF REFERENCE 64
ADDITIONAL READINGS 66
APPENDIX
Sample Project. 68
iv
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
LIST OF FIGURES
FIGURES PAGE
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
LIST OF TABLES
TABLE PAGE
vi
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER 1
INTRODUCTION
estimate.
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
initial estimate, especially in new technology plants.1 Was
a project-cost estimate.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
contingency factor to the baseline estimate.3 Estimators after
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
inflation, regulatory approvals, wastage, weather conditions,
project.
escalation.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
escalation each variable causes on the total cost of the
project.
of the project.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER 2
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C O N TR AC T
D O C U M E N TS
Q U A N T IT Y
T A Z E -O F F
P R IC IN G O F D E T E R M IN A T IO N OF
S U B -C O N T R A C T O R
D IR E C T LA B O R E Q U IP M E N T COST ESTIMATES
A N D M A T E R IA L
D E T E R M IN A T IO N O F D E T E R M IN A T IO N O F
JOB OVERHEAD COMPANY OVERHEAD
A D D IT IO N O F
P R O F IT
B ID
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
interested in bidding for the project, purchase the contract
a bid.
The accuracy of the contractors bidding task, i.e., to
find the actual amount of his bid proposal can make or break
8 Humphreys, p.368.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
accuracies.9
11 Ibid.
12 Ibid.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
semi-definitive (-15 % to +25 %), definitive (-10 % to +15 %)
and check (-5 % to +10 %).13 Estimates are not only used for
techniques are:14
1. Feasibility estimate.
3. Parameter estimating.
4. Factor estimating.
5. Range estimating.
6. Probabilistic estimating.
10
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
the project, irrespective of the financing. It helps the owner
tax laws.
reliable.
News Record in 1966 and since then the periodical has expanded
11
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
allocate lump-sum cost to the various activities or attributes
area, etc., are selected and are then allocated to the various
sf., and if the general conditions and fee for the project was
new project.
12
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Range estimating, as the name suggests, is the technique
the quantities, unit costs and the total cost of the project.
13
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
each giving a bottom line cost. These results when plotted in
estimating procedures.16
14
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
project. A contractor usually sublets part of the work to
after including the job and company overhead comes up with his
project.
15
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
in cost due to inflation should be shared equally by the
labor cost. Peeples has pointed out that, due to inflation and
19 Peeples, p.B.1.2.
16
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
dependent fixed cost, e.g., job site overhead and home office
for the delay but is not paid for it. The third category of
the point that, labor and material costs form the major
21 Ibid.
22 Yeo, p.459.
17
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
accuracy of these costs. However, these costs depend on many
23 Adrian, p. 154.
24 Ibid, p. 155.
18
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
engineering.26 Adrian has provided a list of factors that
materials management.27
year, more jobs are created and as a result costs are also
volume is low for that year. Herbsman also pointed out the
The higher the unemployment rate the harder the workers would
26 Ibid.
27 Adrian, p. 155.
19
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
adverse impact of changes on the construction cost and
contractor.
20
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
obstruction, unanticipated interferences, error, rework and
21
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER-3
estimate.
22
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
3.1 Identification of variables
play after the project has started. The project cost estimate
with group-two only, i.e., the attributes which come into play
23
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
TABLE - I (GROUP - 1)
TABLE - II (GROUP - 2)
to
09
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
TABLE ~ IV (GROUP - 2)
S.NO. ABBR. DESCRIPTION OF ATTRIBUTE PRECEDING ATTRIBUTE FOLLOWING
ATTRIBUTE
1. c MANAGEMENT OR PROJECT TEAM START(ST) Cl,C2,S ,R
2. Cl JOB PLANNING C El, LI
3. C2 PROPER SELECTION OF EQUIPMENT C El
4. C3 SCHEDULE & DURATION OF PROJECT F,G,J,R L,E,C4
5. C4 PROJECT MGMT. COST/CONST. SUPPORT C3,H T
INDIRECT COST
6. E ACTUAL EQUIPMENT COST El,C3 T
7- . El ACTUAL EQUIPMENT PRODUCTIVITY Cl,C2,L2,L3,L4,L5,L6, E
L7
8. F CHANGE ORDERS 0,S C3
9. G REGULATORY APPROVALS O C3
10. H UNANTICIPATED SOIL START C4
CONDITIONS/INTERFERENCES/UNDERGROU
ND OBSTRUCTIONS
11. I GENERAL ENVIRONMENT START T
12. J ERROR AND REWORK S C3,M
13. L ACTUAL LABOR COST L1,C3 T
14. LI ACTUAL LABOR PRODUCTIVITY Cl,L2,L3,L4,L5,L6,L7 L
CONTD...
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
cost.
33 Peeples.
32
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Change in a project schedule has an adverse effect on the
Actual labor and equipment cost, i.e., the total cost of labor
34 Ibid.
35 Adrian, p. 154.
33
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
investigation required for the project, however, this decision
location.
36 Adrian, p. 155.
34
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
particular area is governed by factors like political
cost.
35
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
OF ATTRIBUTES
PATTERN
FIG UR E-2: INFLUENCE
START
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
COST
EQUIPMENT
FIGURE-3: ACTUAL
<o START
/ 1
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
✓ N.
38
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
L, Ki
o
o
39
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
COST
MATERIAL
FIG U R E S : ACTUAL
START
"40
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
WORK
OF
COST OF PROJECT/END
o
FIGURE-7: TOTAL
.41
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
3.3 The Probable Weighted Percentage Cost Escalation Model
i.e., the probability that over the course of the project, the
cannot be neglected.
preceding attribute(s ).
42
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
(3) There is a probability that, although an attribute has
43
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C4
C3
Ml
P R O B A B IL IT Y PRO BA F O L L O W IN G ATTRIBUTE
PREC B IL IT Y
A T T R I E D IN G D U E TO
OF A T T R I C O N D I PROBA
BUTE PR E C E T IO N A L
ATTR S U M PRO D BUTE B IL IT Y
A TTR I
IB U T E D IN G
A T T R I UCT PROBA
BUTE B IL IT Y
BUTE
F 0.084 L 0.90 0.159
G 0.023
C3 0.189 0.012 0.177
E 0.80 0.142
J 0.037
44
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Attribute, schedule and duration of project (C3), is
45
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
p(C3 I G) = p(C3 n G) t p(G)
46
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
p(C3 n R)} + {p(C3 n G) x p(C3 n j) x p(C3 n r) }]
47
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
for the probabilities of the starting attributes. This can be
(V).
48
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C2
F O L L O W IN G ATTR IB U TE
P A IR W IS E C O M P A R IS IO N R E LA TIV E N O R M A L IZ E D
A T T R - A RRT1-
FO R % COST ESCALATION W E IG H T W E IG H T
B U TE BUTE
M IN MAX M IN MAX M IN MAX
49
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
percentage cost escalation due its following attributes Cl,
due to each attribute, the same proportion might not apply for
Weights).
attributes. This would vary from firm to firm and thus should
50
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
be done based on the prior experience of the firm. For the
and duration of project (C3) and actual material cost (M). The
51
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
C3
Ml
P R EC E D IN G A TTR IB U TE
A T T R I
FO LLO W IN G ATTRIBUTE
ATTRIBUTE % C.E
BUTE
% COST
A T T R IB U T E ESC A LA N O R M A L IZ E D * COST
M IN M A X ATTR1 W E IG H T
E S C A L A T IO N
T IO N
BUTE
M IN MAX M IN MAX M IN MAX
Ml 0.4 9 0 .6 7
C3 0 .5 7 0 .6 7 3.33 9.1
SI l.IS 2 .8 0
R 5.84 1 3 .56
u 1.60 3 .84
M 0 .43 0.33 2 .5 1 4 .4 6
c 2 .6 0 6 .2 6
52
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission
minimum and maximum weighted percentage cost escalation due to
the probability and cost for each attribute. This has been
Escalation).
site location (SI, 0.04) and bidding volume index (V, 0.06)
and it was found that the probability that the end of the
53
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
project cost (T) would vary from the estimated project cost
conditions (I, 0.135) and finally the actual labor cost (L,
54
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
the sum of 60 % of individual cost escalation in T due to its
preceding attribute(s ).
55
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
thereof can help the management in pin-pointing the attributes
56
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CHAPTER 4
CONCLUSION
rarely seen that the total project cost equals this estimate.
project.
57
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
4.1 Phases of Research
the project has started, were included in group one. Group two
the total cost of the project/end of work) and also for all
58
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
weights are calculated for all the attributes following a
project.
59
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
estimated project cost. This escalation is calculated in the
project cost due to that attribute, if, and only if, all its
60
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
different.
61
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
the accuracy of the model depends on the values supplied by
4.3 Conclusion
with the total cost of the project will enable the management
62
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
check by keeping a tighter control on the functions of the
risk attributes.
63
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
LIST OF REFERENCES
64
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Parisi, Ronald F. and Robert J. Schlunt. "Construction Delay
Claims: Treatment of Extended Overhead." In: 1983 AACE
Transactions. pp. C.2.1 - C.2.7. Morgantown, WV: American
Association of Cost Engineers, 1983.
65
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Additional Readings
66
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Clough, Richard H. Construction Contracting. 4th ed., New
York, NY: John Wiley & Sons, 1981.
67
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Hackney, John W. "Determining Overrun Probabilities." In: 1986
AACE Transactions. pp. E.4.1 - E.4.7. Morgantown, W V :
American Association of Cost Engineers, 1986.
68
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Mlakar, Paul F. and Larry M. Bryant. "Direct Range Cost
Estimating." In: 1990 AACE Transactions, pp. K.4.1 -
K.4.4. Morgantown, WV: American Association of Cost
Engineers, 1990.
69
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Stevenson, James J. "Escalation Modeling, Forecasting and
Tracking." In: 1984 AACE Transactions, pp. F.3.1 - F.3.7.
Morgantown, WV: American Association of Cost Engineers,
1984.
70
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
M
in CM
CM
w
22 SI 25 O »-f
o o esa
OHPiH
CM
I
0*
& gg
o
05 |m CO rH CM
X0 < H
H
►J
n M
A
H
H
>
CM
A
o
GO
A
0
a
ftp
o
a
o
Pm
O
M
&
H
H (N oo r> in
n o rH
A
a
o
06
P<
n
•W
71
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
M
n n CM
rH
in
rH
<n
m
CM
OJ
©
0* D
CM
!a
CM <n
rH
72
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CO CM
in
rH rH
Hf, <«.%
o
WMM
o
in tH rH CM
r> rH CM n
tft
73
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
<o
eg CM
H
iH
(N
M
VO CO
CO
on
eg
M co co
eg
eg co rH
m Hf co
So
iH CO
eg eg
74
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CO rH
CN V£> rH CN n
W
CO <J\ in rH <N n
rH
n n
H
M
CN
rH
CN
CO CN
CN rH
vo
CN CN
75
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
;.
>*
M
■J
« M
C9
rH vo CM o VO vo o CM CM in rH
«§: s ■«r o H rH rH rH CM rH rH vo \o
o o O O O O O O O o o © l
• • • • • • • • • I
* O o o o o o o o o o o o 1
i i
fO £4 O'
i 8 2 2 % . O in o in o o o o o in
i
H
ssss
O h c u h
■V rH CO CM Hf ■V in CM CM
• • •
o O o O o o o o o
•
r- o
o rH
o
•
rH
l
l
l
i «
l
vo c*» CM co HJ* l
bs »o ►J J « £ £ £ J 05 cn d £ l
^ S ; V
■
!§&&
>* ites
fri W tern
ǥ&ȴ
:H t*
i 1-3 5
issS ® £K -
mm
SS’
/fr*: ^
rH co
VO VO o
o o vo
• • •
A '
° o o o
°
; i ‘ a\
Cv
is
. ^M4a 25£\ •■■■>
i
i
i
1
1
1
1
1
1
1
1
1
CO
O
•
CM
*■* ;
w 1 as
5 O
A : <0 i 1 1 1 o
;:$w ■ i 1 1 1 •
S^ffi ;. i 1 1 1 rH
'■■{&
aJ ^ v.
h .^*,,.w.,i■'T■O•;s’wSs^,
kS.:,
~ .,-' i , <
A‘Xf>iw)iy
rH VO o rH in
* r t l o t t f l VO VO rH rH O CO
i o I O CM CM CM rH
i | 5 g f i • 1 • •
Q O < a < a i o 1 o O o O O
« A
^Ofltw
m S S£ t * f *
mZ h h p EH Eh O'
* * a 3S» 00 > 00 CO £ w O H
* M
IJS
^3Ei>
.'m4'•OSy£''••*/■■*.-0
•• -<\y $■
< 2 ♦ $£+$&
D > s Eh ■
0&
♦
• • • • •
r o H CM « •M
*
« m n cn n cn
76
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
>«
J
H
I
1
<
S
Pt
CONDIT
PROBAB
§
IONAL
ILITY
;*
z
ATTR
IBUTE
t* w
3s!
1£
ft
D
>*
M s
(0
s *
1
fits :
g£ A
0.240
>
S •*
> ••
S S S H S
Q0*a<a
*
t
:
ml iJ
*«
EtsA
f
i
«*
SllSi^P
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CM m
CM CM co
H
vo rH
cn CO
co
CM
co
rH r> CM co
rH CO
(GROUP-2)
M
WEIGHTS
in
NORMALIZED
co
78
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
M
m
n
rH
rH
OJ rH rH
hi
n m rH
CO
79
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission
CM CM
n
rH
H.
CO n cn
to cn in in CM co
vo
CM CM
M co
CM
rH
cn CM
iH
in
tn
M
CM
rH
co
CM CM
80
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
co co
co co
CM CM rH CM CM rH
rH rH
CO
rH rH CM rH
CO
CM
CM
rH CM
H rH
«*
l-f
rH
rH
co
CM CM CM CM CO
81
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
00 rH
CM CM CM iH
tH
cn cn
CM rH
cn
cm cn CM
M
CM
in
cn
H
W
in
rH rH CM
CM
cn cn
82
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission
CM
d d
CM n
rH
d CM
CM CM
VO
M
rH CM
n
CM cn
ESCALATION
M a fs
d 'S'
M d CM n
CM
I
COST
P<
a
o
PS < w
(9
PERCENTAGE
Eh Of n
CO
O
O • CM in n CM •rH
Eh
O
W
►a d
WEIGHTED
CM
O
PS
Pt rH
Q
W
Eh
& MAXIMUM
W d
Eh
CO
H
CM
S d d
H
CM d d d CM
MINIMUM
Ht
d.
83
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
vO
OV CM CM
cn
CM CM CO
cn
cn
rH
cn
M
cn
CM
vo CO
CM'
CM in «-*
K in
cn CM
CO
CM cn co
H
CN <n cn
co VO
rH CM
CM CM
cn CM cn
rH
CM cn
rH
84
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.
X io
cn CM
rH
vo
cn cn cn cn
cn cn
cn
er
55.
M
cn cn
cn cn
iH rH
CO cn
cn
cn cn cn cn CM
H H
03 £♦ CM cn
M cn cn cn
CM rH
Hr
CM in
cn
85
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
1
z
15.94
0. 35
0.50
in in in
0.49
0.40
E+S £ vo CO r- H
CO B* • • • *
o o rH CM
8 §
ATTRIBUTE
8 z o <3* VO r* CO o CO in
oi M CM CO CM co CM CO CO H
« • • «
z o O O o o O O rH
o o VO CM VO CM
« in in o CM CO o o
N &H • • «
H X ■g o o o r-4 O o O rH rH
FOLLOWING
>4 O
y-Z VO r~ CO
—
cn O
I * M in in O CM CO o o
s • • • •
o o o H O o o rH rH
liptijiM
.....
H rH rH CM
■< M 63 4 63 e* (X X X £ £
»:■- rr
O Q\ in
Cl in rH
a in •
o rH rH rH CM
5 63
S o
Ci z o r* CO m
% X VO CO O CO rH
< • •
o r- rH o rH
>t o o\ O tn <Tl CM in
&
si <n
o
pH CO
CM
H
rH rH CM
in in in
CM rH r-H
n
o
M*
rH
rH
CM
a.
!§
. -> w
«
z
M
z
o
VO
in 0\ CO in in
in in CO CO H
• •
o O
• •
cn
CM
O in
VO H
•
o o CM O o rH H H rH o o rH
z. 61
i a
n
H
:
$
'
S rH
cn s (X *2
CM CO
£ £ £ £
in
CO
rH
X
H H
cn CO
:i
#<a > rH CM CO
4 . s 23 s £
■ ♦
o
z • • • •
o H CM CO <3*
©X CM CM CM CM CM
86
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
co CM in
CM rH rH
OS Hf
rH rH CM CM rH rH
co
rH rH CM
rH
H!
co pH
CM CM
rH
co CM
CM CM CO
o
CO
CM
rH 10
CO
CO
to CO
87
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
rH CM
rH cn
f-f
rH rH
CO VO
rH cn
CM cn cn cn
M CM
CM cn
< H
o
o rH
r4 CM
CO CM
cn
CM
V>
cn cn cn
88
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
II
1
1
||
||
||
fi'
8;
44
OX H m 00
tt-°
10*0
0 .0 5
3 .7 5
m o H O CO r*
2 .4 1
0 .5 6
0.7 7
0.0 7
4 .2 3
0 .25
0 .0 1
2 .5
' • • « •
■:■.■■.■.•.•.•..v.v,- O cn rH o
3KO
, M,
(GROUP-2)
;3 “
aa s.
w-
S X
O'
oz If) C T 'I rH rH
1 .5 6
10 .1 0
0 .2 5
0 .0 5
0 .0 3
1 .5 6
0 .3 9
0 .4 2
04,, ^' o CM o O O
1 .0
• • •
o H d H o o
ESCALATION
1.
1
*%
^ «■'*
I*
g
XYH
2 1 .1 9
1 1 .9 9
14.38
17.62
21 cn
COST
2 5 .0
2.80
12.0
9.72
4.25
1.29
6.64
0.64
in in 5.0
o
• • •
in cn GO
PERCENTAGE
:
4f >:wwKwrt;
\w >/
tsj S'
as
10.0
4.95
0.90
8.83
5.62
7.42
4.35
7.09
0.55
H n o o o o 1.0
« • • •
WEIGHTED
> cm rH cn CM CM CO
pt &
H H S
3 § < i
3 g « g
PROBABLE
rH
0.015
0.201
0.210
0.177
0.025
0.079
0.096
0.084
s o < 2£ in M* CM
0.10
0.02
10 . 1 5
0.01
0.24
o © O
• • •
0.0 o o o
o-'n
!?
?%-ws
3 '
C4.
n
El
ID
CD
C2
L2
LI
1 U w O s H l-D ■4
i
i
V*?/ .•/><*'sw,
• • • •
16. "
• • • • • • • o H CM cn in
H CM cn in IS CO (Ji pH rH rH rH rl rH
89
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
CN cn
cn
is pH
rH CN CN AO
CN CN
rH
cn
rH CN CO rH CO CO
cn CN ;,Q
co
rH
CN
cn VO
CN rH
0*0
in
co as rH cn CN
CN CN CN cn cn
90
Reproduced with permission o f the copyright owner. Further reproduction prohibited without permission.