PROFORMA ESTIMATE
Mandal : UPPALAGUPTAM
RADESH
EPARTMENT
ATE
Specification report to accompany the Proforma estimte for the the work "Providing Appoach road to
Ap Torism Canteen inS.Yanam.
.
Esst:5.0 Laks
The work " Providing Approach road to AP Tourism canteen in S.Yanam (V) of
Uppalaguptam Mandal is prepared for Rs 5.0 Lakhs as per instructions Sri P.Viswaroop, Honourable
Minister for Social welfare Department,Govt of AP , for according Adnistrative sanction from CSR funds.
The proposed road is very essential for tourists and S.yanam people for approach to
apTourisam canteen. The existing surface of the road is Gravel track 3.6 m length and 3.40 m wide. Hence it
is proposed to Sub base using Quarry rubbish to 360 m length and 3.3 wide and 150 mm thick ,CC 360 m
length ,170 mm thick and 3.00 m wide and Sand filling 300 mm provided, Selected earth side berms to a
length of 360 mm
of All Engineering Departments in Andhra Pradesh and the work will be carriedout as per standards
of APDSS.
P.Viswaroop, Honourable
Cum Cum
Cum 1 Cum
Measure
No. ments in
S.No Description of item Mts. Contents Rate/Per Amount
Length Breadth Depth
5 Filling Selected earth for side berms as per drawing and technical specification
Clause 305.3.9 MORD & 304 MORTH
for Side berms 1 360.00 0.30 0.20 21.60
Cum 1 Cum
1226789
#REF!
8 Provision for QC Charges @ 0.50% #REF!
9 Provision for GST Charges @ 12.00% #REF!
10 Provision for Supervisor Charges @ 3.00% #REF!
11 Provision for NAC Carpus fund @ 0.10% #REF!
#REF!
Name of work: "Providing Approach Road to AP Tourism canteen in S.Yanam Estt. Rs.5.0 Lakhs
.
1 2 3 4 5 6 7 8 9 10 11 12 13
3 40mm HBG Metal (SS5) Katheru 103 1044.00 608.00 75.00 70.00 1,797.00
4 20mm HBG Metal (SS5) Katheru 103 1044.00 1,016.00 75.00 70.00 254.00 2,459.00
5 10mm HBG Metal (SS5) Katheru 103 1044.00 680.00 75.00 70.00 170.00 2,039.00
6 5-7mm HBG Stone chips Katheru 103 1044.00 480.00 75.00 70.00 120.00 1,789.00
7 2.36-5mm HBG Chips Katheru 103 1044.00 350.00 75.00 70.00 87.50 1,626.50
2.36mm size below HBG
8 Katheru 103 1044.00 350.00 75.00 0.00 0.00 1,469.00
Stone chips
9 Quarry Rubbish Vemagiri 86 884.20 84.75 30.00 998.95
Certified that the leads and rates adopted in the estimate are correct to the best of my knowledge and belief.
1 2 3 4 5 6
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 500.00 2,500.00
Mason (2nd class) day 5.00 460.00 2,300.00
Mazdoor (unskilled) day 150.00 420.00 63,000.00
Mazdoor(skilled) day 6.00 420.00 2,520.00
Surveyor day 2.00 750.00 1,500.00
Mazdoor (semi-skilled) day 6.00 420.00 2,520.00
Black smith for cutting of dowel bars including removal of burrs, day 1.00 0.00 0.00
fabrications & fixing of dowel bars
74340.00
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 mixers) with weight batcher Hr 36.00 524.70 18,889.20
and suitable capacity calibrated water tank
Needle vibrator Hr 9.00 209.10 1,881.90
Screed vibrator Hr 9.00 59.10 531.90
Plate vibrator Hr 9.00 59.10 531.90
Water tanker 6 Kl. Capacity Hr 5.00 655.20 3,276.00
Air compressor ( 1hour initial + 1 hour final) Hr 2.00 566.20 1,132.40
Concrete cutting machine ( R&B Dept) Hr 4.00 220.00 880.00
27,123.30
c) Material
(I) Crushed stone coarse aggregates, grading will be as per clause
1501.2.4.1 (Table 1500.1) of specifications @ 0.90 Cum/cum of concrete
Crushed stone aggregate of 20mm size @ 0.60 cum per 1 cum of Cum 44.55 2083.00 92,797.7
concrete
Crushed stone aggregate of 10mm size @ 0.30 cum per 1 cum of Cum 22.95 1663.00 38,165.85
concrete
(ii) Sand as per IS:383 and conforming to clause 1500.2.4.2. @ 0.45 cum of cum 33.75 1158.00 39,082.50
concrete
(iii) Cement @ 330 Kg/cum of concrete t 24.75 3750.00 92,812.50
1 2 3 4 5 6
Rate per Cum = (a+b+c+d)/75 5227.70
2 Filling Selected Earth for side berms as per drawing and technical specification Clause 305.3.9 MORD &
304 MORTH
Selected earth filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 420.00 130.20
b) Material
Selected earth cum 1.00 1000.20 1000.20
1130.40
Basic rate of Granular sub base for 300 cum 613830.00
3 Filling Sand in Foundation trenches as per drawing and technical specification Clause 305.3.9 MORD &
304 MORTH
Sand Filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 420.00 130.20
b) Material
Sand cum 1.00 556.80 556.80
687.00
4 Earth work Excavation for Kerb wall, it protect from sliding of the soil in road besides as per specification
305 MORD/304 MORTH(RSSR)
Unit=1cum
Taking Output=1
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 420.00 130.20
130.20
5 Plain Cement concrete (M 20) Nominal Mix using 20mm metal using concrete mixer - for
Kerb walls
Unit : 1cum
A. MATERIALS:
Cement Kgs 330.00 3.7500 1237.50
Coarse aggregate 20mm graded Cum 0.90 2459.00 2213.10
Fine aggregate (Sand) Cum 0.45 1199.80 539.91
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity Hrs 1.00 524.70 524.70
C. LABOUR:
Mason 1st class Day 0.10 500.00 50.00
Mazdoor (unskilled) Day 1.39 420.00 583.80
5149.01
Add 3% centering charges 154.4703
Grand Total 5303.48
S No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
7 CC 00 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work upto plinth level. -- for
Foundation concrete
Unit = 1cum
a) Materials
Cement kg 162.00 3.75 607.50
Fine aggregate (Sand) cum 0.45 1199.80 539.91
40 mm aggregate cum 0.90 1797.00 1617.30
b) Labour
Mason ( 1st Class) day 0.10 500.00 50.00
Mazdoor (unskilled) day 1.39 420.00 583.80
c) Machinary
Mechanical concrete mixer 0.4/0.28 cum capacity hour 0.400 524.70 209.88
3608.39
(d) Formwork @ 3% on material, labour and machinery 108.25
3716.64
6 Construction of Sub Grade using barrowed useful approved Selected earth LL and PL not exceeding 50%
and 25% respectively, spreading uniform layers using Tractor with grader and consolidation with Static /
Vibrator roller of 80 to 100 Kn capacity to acheive the desired density compacted as per technical
specifications clause 303 MORD including cost and conveyance of all materials and all labour charges, hire
charges of machinery, royalties all taxes etc.,complete for finished item of work.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.040 420.00 436.80
Add 20% M A on labour 0.00
b) Machinery
Tractor with grader @ 25 cum per hour hour 4.00 423.60 1,694.40
Static / Vibrator roller hour 1.43 1285.40 1,838.12
Water tanker with 6 kl capacity hour 2.00 655.20 1,310.40
c) Material
Selected earth cum 100.000 1000.20 100,020.00
Rate per 100 Cum 105299.72
Rate per 1 Cum 1053.00
6 Supply and Collection of Granular sub-base/base/surface course with local materials(Quarry rubbish) (Table
400.13) by mix in place method normal Construction of granular sub-base by providing local material
spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with
rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per
Clause 401.4 as per Technical Specification Clause 408 MORD.
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 2.400 420.00 1,008.00
Mazdoor (Unskilled) day 10.000 420.00 4,200.00
Add 20% M A on labour 0.00
b) Machinery
Static / Vibrator roller hour 30.00 1285.40 38,562.00
Tractor with grader @ 25 cum per hour hour 4.00 423.60 1,694.40
Water tanker with 6 kl capacity hour 5.00 655.20 3,276.00
c) Material
quarry rubbish cum 360.000 998.95 359,622
Rate per 300 Cum 408362.00
Rate per 1 Cum 1361.21
S No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6