Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CONTRACTOR/SUPPLIER:
PESTECH SDN BHD
NO.26, JALAN UTARID U5/14, SEKSYEN U5
BANDAR PINGGIRAN SUBANG,
40150 SHAH ALAM, SELANGOR
CONSULTANT:
PROJECT:
SIBIYU 132/33 kV SUBSTATION PROJECT
PROJECT DETAIL:
SIBIYU 132/33 kV SUBSTATION PROJECT
METHOD STATEMENT
STRUCTURAL WORKS
4.2.3 ERECTION
Unless noted otherwise, trusses shall be supported on external load
bearing wall or beam.
Exercise cares and provides erection bracing required to prevent
toppling or domino’s effect of trusses during erection.
Erect trusses with plane of truss webs vertical and parallel to each
other’s, locate at design spacing as indicated in the construction design
documents.
Trusses shall be anchored by L shape steel plate at the specify location. L
shape steel plate should be attached to the reinforced concrete beam
by expansion bolt.
Purlin/batten should attach to the trusses according to the spacing
provided.
Trusses should be placed in accordance with the truss layout plan. No
amendment is allowed without the notification of the Design Engineer.
Building Material like bricks, concrete tiles etc should not under any
circumstances be stacked on the trusses.
Installer should strictly follow the instruction, roof truss layout plan and
shop drawings given by Design Engineer.
Provide proper lifting equipment suited to sizes and types of trusses
required, applied at lift point recommended by truss fabricator. Exercise
care to avoid damage to truss members during erection and keep
horizontal bending of the truss to minimum.
Bracing is to apply sufficient to the plane of the truss to hold every truss
member in the position.
Temporary bracing is used during erection to hold the trusses until
permanent bracing, sheathing and ceiling are in place.
4.3 SHEETING
4.3.1 BUBBLE FOIL AND WIRE MESH INSTALLATION
Prepare and ensure that all equipment is in proper condition, inspected
and approved by Site/Client representative.
Unroll the bubble foil on top of batten and fasters it using self-drilling
screws to batten.
Overlap the insulation seams by 100mm.
Bubble foil shall be cut using hand cutter.
Continue attaching the insulation and sealing the seams until the roof is
completely covered.
1. Project Manager Responsible for overall planning, control and execution of the project in a cost-effective manner.
Julius Jong Overall authority in determination of all quality related matters affecting the project.
Responsible to coordinate and handling with Employers for finalizing project and its related activities.
Responsible to complete the Project within the schedule completion time frame.
2. Construction Manager Managing construction activities to comply with schedule, budget and quality requirements.
Chen Min Sang Supervising and monitoring of all construction activities assisted by site engineer.
To ensure all site staff are clear with the scope of works and time schedule.
Organizing and managing all construction personnel, contractors and subcontractors for smooth execution of the project.
Ensuring that all materials and equipment used in the construction work have passed all tests specified in the contract.
Ensuring the sufficiency of resources to carry out the construction activities.
3. Project Engineer (Civil) Assist the PM to monitor project milestones and updating of project progress schedule together with scheduler.
Mohammad Hadoumi Attend progress meetings with the client and prepare minute of meeting.
Attend technical meetings and assist to resolve technical issues
4. QAQC Engineer Coordination with Construction manager and project engineer on QAQC matters.
(Civil) To carry out stage and final inspection and Preparation of associated reports.
Mohammad Hadoumi To raise NCR and initiate corrective action if the work done is not as per Specification, Method Statement or as per approved
drawing.
Site Engineer (Civil) Ensure that all materials used and work performed are in accordance with the specifications.
Carry out internal inspection and after verifying the work done, raise Inspection for client/consultant Inspection.
To check and ensure that the work done is as per Project Specification, Method Statement and as per approved drawings.
5. Site Supervisor Assisting Site Engineer on Site Supervision and Construction work
Ahmad Fakhruddin Coordinating all the related works between sub-contractors in order to ensure smooth flow of works.
6. Safety and Health Compliance with the Employer's Environment, Health and Safety Policy
Officer Implementation and management of the Contractor's Environment, Health and Safety Management Plan
Robert Kenny Implementation and management of the Contractor's Emergency Planning and Response Plan;
7. Site Safety Supervisor To assist SHO for the following;
Alexander Empam Compliance with the Employer's Environment, Health and Safety Policy
Implementation and management of the Contractor's Environment, Health and Safety Management Plan
Implementation and management of the Contractor's Emergency Planning and Response Plan;
6.0 QUALITY ASSURANCE
6.1 Inspection and Test Plan (ITP)
TEST FREQUENCY OF STANDARD/ ACCEPTANCE PERSONNEL INCHARGE INSPECTION
ACTIVITY RECORD
METHOD TEST CRITERIA TESTED VERIFIED WITNESSED FORM
Off-Site
Off-Site: Roof Truss Visual Per section Shall refer to approved shop Steel C.O.W /
Fabrication Inspection drawings. fabricator QAQC
Cross sectional tolerance should Engineer
not be less than the structural
steel specifications or approved
plan
Tolerance for length of structural
steel member : ±3mm
Tolerance for bolt hole size :
≤ 2mm for bolt diameter <
24mm
≤ 3mm for bolt diameter ≥
24mm
The dry film thickness (painting)
shall be checked
Welding works Visual All welded joint All welds shall follow approved 3rd Party C.O.W /
Inspection welding procedures Tester QAQC
Weld size, length and profile Engineer
shall meet the structural steel
specifications and drawings
Non- 10% of welded BS EN ISO 17637 Non-destructive 3rd Party C.O.W / SEB
Destructive joint testing of welds. Visual testing of Tester QAQC Representative
Examination fusion-welded joints Engineer
(Magnetic
Particle Test)
Sand Blasting Visual 10% of welded
Inspection joint
Protective Coating Per section Inorganic Zinc Silicate Primer - 75
application micron
Polyamide Cured Epoxy with
Natural Micaceous Iron Oxide –
TEST FREQUENCY OF STANDARD/ ACCEPTANCE PERSONNEL INCHARGE INSPECTION
ACTIVITY RECORD
METHOD TEST CRITERIA TESTED VERIFIED WITNESSED FORM
100 micron
Polyamide Epoxy Enamel Paint –
40 micron
Material Receiving Visual Per section Installation as per Drawing
Inspection Inspection
Roof Truss Visual Per section Installation as per Drawing
Installation Inspection
Inspection
Material Delivery
Installation
7.0 ENVIRONMENT, SAFETY AND HEALTH
7.1 Introduction
Occupational injuries and fatalities occur every day in the workplace. These injuries often
occur because employees are not trained in the proper job procedure. One way to
prevent workplace injuries is to establish proper job procedures and train all employees
in safer and more efficient work methods. Establishing proper job procedures is one of
the benefits of conducting a Job Safety Analysis (JSA) – carefully studying and recording
each step of a job, identifying existing or potential job hazards (both safety and health),
and determining the best way to reduce or eliminate these hazards.
Precautions are to be taken for protection of persons and properties from injury or
damage. All site personnel must adhere to safety requirements:
EMERGENGY
COMMANDER
JULIUS JONG
INCIDENT
EVACUATION SAFETY COUNTER & SECURITY CONTROLLER
CONTROLLER/
CONTROLLER FIRST AIDER
HISTORIAN OTHMAN SAHOK
ROBERT KENNY NAUL UNIE BELASAN
ALEXANDER EMPAM
CLEOPATHRA DHIEMAH
MHD. HADOUMI BIN JAMBAI
SALDAN
NAME ANDREW CHAN ROBERT KENNY JULIUS JONG ACTIVITY : ROOFING WORKS
POSITION CIVIL ENGINEER SAFETY & HEALTH OFFICER PROJECT MANAGER REVISION : 0.1
SIGNATURE
DATE
LEGAL REQUIREMENT
SCORE
LEVEL
1. Lay down area for work F NR 1. Slip, Trip and Fall Minor 1. Clear and free water 2 2 4 L - Site Engineer
materials Injury stagnant area. Supervisor
A 2. Barrication with Signage. SHO/SSS
3. Proper PPEs
a. Safety Helmet.
b. Long sleeves cotton clothes.
c. Safety goggles.
d. Rigger Gloves.
e. Safety Shoes.
2. Access / Egress to working F NR 1. Fall form height. Major 1. Provide safe access and 2 3 M L 1. Admin Control. Site Supervisor
platform and areas. 2. Loose Materials. Injury egress. a. Safe work procedure. Foreman
2. Safe Scaffold platform. b. Supervision. SHO/SSS
3. House Keeping. c. Trainings on WOH
4. Secure all loose materials.
5. PPEs.
a. Safety Harness.
b. Life lines.
LEGAL REQUIREMENT
HAZARD IDENTIFICATION RISK ASSESSMENT
CONDITION
STEP SEQUENCE OF BASIC JOB *** RISK CONTROL/ RECOMMENDED PERSON
CURRENT RISK CONTROL RISK IN CHARGE
NO STEP ACTION AND DATE
* ** RANKING
HAZARD EFFECT
LIKE SEV
SCORE
LEVEL
3. Lifting works. F NR 1. Falling object. Major 1. Proper Supervision. 2 3 6 M 1. Engineering control. Site Supervisor
(Roof materials) 2. Hit by lifting Injury 2. Working area barrication. a. Load indicator function. Roofing
A objects. 3. Hard and level ground for Supervisor
3. Crane Topple. crane operation. 2. Admin Control. Crane operator
4. Boom failure. 4. Work worthy crane. a. Safe Work Procedure. SHO/SSS
5. Tag lines. b. Supervision.
6. Signal man. c. Trainings on lifting works.
7. Good weather condition. d. House Keeping.
3. PPEs
a. As per stated.
4. Installing safety mesh to F NR 1. Electrical shock. Major 1. Electrical tools and cords 2 3 6 M 1. Admin Control. Roofing
purlins 2. Hand Injury Injury inspection. a. Safe work procedures and Method Supervisor
A 3. Fall from height. 2. Mesh lifting by crane. statement. Site Supervisor
4. Heat stress 3. Proper Access. b. Supervisions.
5. Falling object. 4. Drinking water. c. Job rotations.
5. Secure loose items. d. Buddy system.
6. And lanyards for tools. e. Housekeeping.
7. Proper PPEs as per stated
above. 2. PPEs.
a. As per stated.
5. Installing Fiber Glass F NR 1. Inhalation. Major 1. MSDS provided. 2 3 6 M 1. Engineering Control Roofing
insulations. 2. Irritation. Injury 2. Working area barricaded. a. Isolation - Do not allow other Supervisor
3. Fall from height. 3. Good weather condition. activities in this area. Site Supervisor.
A 4. Falling objects. 4. Secure all loose items.
5. Proper PPEs. 2. Admin Control.
a. Safe work procedure and Method
Statement.
b. Supervision.
c. House keeping
d. Hygiene - To wash hand
thoroughly before meals.
LEGAL REQUIREMENT
HAZARD IDENTIFICATION RISK ASSESSMENT
CONDITION
STEP SEQUENCE OF BASIC JOB *** RISK CONTROL/ RECOMMENDED PERSON
CURRENT RISK CONTROL RISK IN CHARGE
NO STEP ACTION AND DATE
* ** RANKING
HAZARD EFFECT
LIKE SEV
SCORE
LEVEL
6. Cleaning wools at roof area F NR 1. Falling from Major 1. Stored in plastic bag as 2 3 6 M 1. Admin Control. Site Supervisor
height. Injury schedule waste. a. Safe Work Procedure. Roofing
A 2. Eye Irritation. 2. Proper PPEs. b. Supervision. Supervisor
3. Inhalation c. House Keeping.
2. PPEs
a. As per stated.
7. Arrange and installing roof F NR 1. Fall from height. Major 1. Mechanical means to move 2 3 6 M 1. Admin Control. Site Supervisor
sheets. 2. Electrical shocks. Injury roof sheets. a. Safe work Procedure and Method Roofing
A 3. Manual handling. 2. Hand tools and cords statement. Supervisor
4. Loose Materials inspection. b. Supervision.
5. Heat stress. 3. Secure all loose items. c. Job rotation.
(Roof sheets may fly off due to
strong winds)
4. Proper ergonomic during
manual lifting.
5. Drinking water.
6. Proper PPEs.
8. Installation of down pipes F NR 1. Fall from height. Major 1. Safe working platform. 2 3 6 M 2. Admin Control. Site Supervisor
and gutters. 2. Hand Injury. Injury 2. Inspection on hand tools and d. Safe work Procedure and Method Roofing
A 3. Electrocuted. cords. statement. Supervisor
4. Falling Object. 3. Secure all loose items. e. Supervision.
4. Proper PPEs. f. Job rotation.
9. Human factor A R 1. Fall from height. Major 1. Workers induction. 2 2 4 L - Site
2. Bodily injury. injury 2. Well trained. Management
3. Stress. 3. Discipline.
4. Medical checkup.
5. Promote safety culture.
6. Workers welfare
7. Penalty system.
8. Proper usage of PPEs.
Legends
Conditions
R – routine
NR – non routine
Likelihood (L) Score
Most likely The most likely result of the hazard/ event being realized 5
Where L = Likelihood
S = Severity
Severity (S)
Likelihood (L) 1 2 3 4 5
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
Type of job: Roof Steel Frame Installation
Job Safety Analysis
Date: 18/9/2019
Personal Protective Equipment to be worn: Safety boot, safety vest, safety helmet & hand glove
1. Lay down area for work 1. 1. Slip, Trip and Fall 1. Clear and free water stagnant area.
materials 2. Barrication with Signage.
3. Proper PPEs
4. Safety Helmet.
5. Long sleeves cotton clothes.
6. Safety goggles.
7. Rigger Gloves.
8. Safety Shoes.
2. Access / Egress to working 1. Fall form height. 1. Provide safe access and egress.
platform and areas. 2. Loose Materials. 2. Safe Scaffold platform.
3. House Keeping.
4. Secure all loose materials.
5. PPEs.
6. Safety Harness.
7. Life lines.
3. Lifting works. 1. Falling object. 1. Proper Supervision.
(Roof materials) 2. Hit by lifting objects. 2. Working area barrication.
3. Crane Topple. 3. Hard and level ground for crane operation.
4. Boom failure. 4. Work worthy crane.
5. Tag lines.
6. Signal man.
7. Good weather condition.
4. Installing safety mesh to 1. Electrical shock. 1. Electrical tools and cords inspection.
purlins 2. Hand Injury 2. Mesh lifting by crane.
3. Fall from height. 3. Proper Access.
4. Heat stress 4. Drinking water.
5. Falling object. 5. Secure loose items.
6. And lanyards for tools.
7. Proper PPEs as per stated above.
5. Installing Fiber Glass 1. Inhalation. 1. MSDS provided.
insulations. 2. Irritation. 2. Working area barricaded.
3. Fall from height. 3. Good weather condition.
4. Falling objects. 4. Secure all loose items.
5. Proper PPEs.
6. Cleaning wools at roof 1. Falling from height. 1. Stored in plastic bag as schedule waste.
area 2. Eye Irritation. 2. Proper PPEs.
3. Inhalation
Basic Job Steps Potential Hazards Recommended Action or Procedure
7. Arrange and installing roof 1. Fall from height. 1. Mechanical means to move roof sheets.
sheets. 2. Electrical shocks. 2. Hand tools and cords inspection.
3. Manual handling. 3. Secure all loose items.
4. Loose Materials 4. (Roof sheets may fly off due to strong winds)
5. Heat stress. 5. Proper ergonomic during manual lifting.
6. Drinking water.
7. Proper PPEs.