Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
MATERIAL LABOR
ITEM DESCRIPTION QTY UNIT TOTAL AMOUNT
UNIT AMOUNT UNIT AMOUNT
Standard size site office for 1-CM, Architects, Owners, Representative 1-Conference Room. Complete with Office
3.03 1.00 lot 100,351.42 100,351.42 - - 100,351.42
Equipment, Internet Connection & Supplies for the entire duration of the Project. Refer to Instruction to Bidders.
4.00 Warehouse for Contractor and Owner Supplied Materials 1.00 lot 21,503.88 21,503.88 - - 21,503.88
5.00 Security/Safety 1.00 lot 143,359.17 143,359.17 - - 143,359.17
6.00 Permits and Clearance 1.00 lot 630,780.35 630,780.35 - - 630,780.35
6.01 Building Permit
6.02 Barangay Permit
6.03 Electrical Permit
6.04 Sanitary Permit
6.05 Fire Protection Permit
6.06 Mechanical Permit
6.07 Bussiness Tax
6.08 Contractors tax
6.09 Occupancy Permit
6.10 ECC Permit 1.00 lot
7.00 Bonds and Insurance
7.01 Guarantee Bond (10%) 1.00 lot - - - - -
7.02 CARI (100%) 1.00 lot - - - - -
7.03 Surety Bond (Performance) (20%) 1.00 lot - - - - -
8.00 As-Built Plans including E-File 1.00 lot 43,007.75 43,007.75 - - 43,007.75
9.00 Housekeeping 1.00 lot 6,683.40 6,683.40 33,098.77 33,098.77 39,782.17
10.00 Material Testing 1.00 lot 37,273.38 37,273.38 - - 37,273.38
11.00 Rentals of Service Vehicles/Tools & Equipment 1.00 lot 1,044,835.72 1,044,835.72 202,276.42 202,276.42 1,247,112.14
12.00 Safety Net Protection 1.00 lot 191,314.59 191,314.59 27,966.87 27,966.87 219,281.45
13.00 Contractors Field Office and Barracks and Temporary Fence 1.00 lot 460,963.72 460,963.72 4,773.86 4,773.86 465,737.58
14.00 Hauling and Disposal 1.00 lot - - 22,937.47 22,937.47 22,937.47
15.00 Site Engineers Staff - -
15.01 Survey Works 1.00 lot - - 57,343.67 57,343.67 57,343.67
15.02 Supervision & Contingencies 1.00 lot - - 1,081,438.50 1,081,438.50 1,081,438.50
16.00 Others: (Please specify below)
II SITE WORKS
1.00 Excavation 433.16 cu.m. - - 521.54 225,912.02 225,912.02
2.00 Backfill/Compaction 246.61 cu.m. - - 286.85 70,739.74 70,739.74
3.00 Hauling of Excess Soil 1.00 lot - - 261,642.76 261,642.76 261,642.76
4.00 Soil Poisoning - -
a. Pre - Construction Treatment 284.77 sq.m. 192.68 54,869.61 48.17 13,718.12 68,587.72
5.00 Moisture Barrier 284.77 sq.m. 78.23 22,278.01 26.08 7,426.00 29,704.02
6.00 Gravel Bedding 28.48 cu.m. 1,238.67 35,273.52 391.16 11,139.01 46,412.53
7.00 Dewatering 1.00 lot 85,033.90 85,033.90 40,816.27 40,816.27 125,850.17
8.00 Filling Materials cu.m. - - - - -
11.00 Water Stop 326.00 lm. 456.35 148,770.44 195.58 63,758.76 212,529.20
12.00 Trimming of Trees and Plants 1.00 lot 981,160.34 981,160.34 - - 981,160.34
13.00 Others: (Please specify below)
1.02 Parking
a. Column 5,392.16 kgs. 45.00 242,647.40 6.00 32,352.99 275,000.39
b. Slab on Fill 28,029.10 kgs. 45.00 1,261,309.57 6.00 168,174.61 1,429,484.18
c. Stiffener Columns 562.08 kgs. 45.00 25,293.41 6.00 3,372.46 28,665.87
d. Lintel Beam 537.64 kgs. 45.00 24,193.70 6.00 3,225.83 27,419.53
e. Stirrups / Ties 7,652.52 kgs. 45.00 344,363.26 6.00 45,915.10 390,278.36
f. Tie Wires 963.19 kgs. 80.00 77,055.58 - 77,055.58
2.00 FORMWORKS
2.01 Foundation
a. Mat Foundation 217.26 sq.m. 420.00 91,249.20 442.00 96,028.92 187,278.12
b. Column included sq.m.
2.02 Parking
a. Column 201.60 sq.m. 420.00 84,672.00 280.00 56,448.00 141,120.00
b. Slab on Fill 21.73 sq.m. 420.00 9,126.60 442.00 9,604.66 18,731.26
c. Stiffener Columns 28.06 sq.m. 420.00 11,783.57 280.00 7,855.71 19,639.28
d. Lintel Beam 47.60 sq.m. 420.00 19,990.24 280.00 13,326.82 33,317.06
- -
2.03 Ground Floor - -
a. Column 201.6 sq.m. 420.00 84,672.00 280.00 56,448.00 141,120.00
b. Beams and Girder 917.93 sq.m. 420.00 385,530.60 280.00 257,020.40 642,551.00
c. Suspended slab 788.62 sq.m. 420.00 331,220.40 280.00 220,813.60 552,034.00
d. Stair Case 16.71 sq.m. 420.00 7,018.26 280.00 4,678.84 11,697.10
e. Stiffener Columns 58.64 sq.m. 420.00 24,630.20 280.00 16,420.13 41,050.33
f. Lintel Beam 99.49 sq.m. 420.00 41,783.90 280.00 27,855.93 69,639.84
g. Ramp 113.30 sq.m. 420.00 47,586.99 280.00 31,724.66 79,311.66
3.02 Parking
a. Column 34.70 cu.m. 5,450.00 189,115.00 500.00 17,350.00 206,465.00
b. Slab on Fill 185.56 cu.m. 5,450.00 1,011,302.00 500.00 92,780.00 1,104,082.00
c. Stiffener Columns 3.02 cu.m. 5,450.00 16,479.85 500.00 1,511.91 17,991.76
d. Lintel Beam 3.16 cu.m. 5,450.00 17,225.59 500.00 1,580.33 18,805.92
IV ARCHITECTURAL WORKS
5.00 DOORS
5.01 Ground Floor
a. Swing Type Flush Door with 6mm THK Glass Panel 2.00 set/s 12,600.00 25,200.00 750.00 1,500.00 26,700.00
b. Swing Type Flush Door with 6mm THK Glass Panel 7.00 set/s 12,600.00 88,200.00 750.00 5,250.00 93,450.00
c. Swing Type Waterproof MDF Flush Door 2.00 set/s 14,100.00 28,200.00 750.00 1,500.00 29,700.00
d. Swing Type Waterproof MDF Flush Door 4.00 set/s 14,100.00 56,400.00 750.00 3,000.00 59,400.00
e. Double Swing Type Steel Door with Louver 1.00 set/s 19,470.00 19,470.00 1,200.00 1,200.00 20,670.00
7.00 GRANITE LAVATORY COUNTERS INCLUDING SPLASH BOARDS AND CASHIER/RECEPTION/DISPENSING COUNTER
7.01 Ground Floor
a. Lavatory Counter at PWD Male/Female Toilet 3.68 sq.m. 2,500.00 9,200.00 - - 9,200.00
SUB-TOTAL: GRANITE LAVATORY COUNTERS INCLUDING SPLASH BOARDS AND CASHIER/RECEPTION/DISPENSING COUNTER 15,900.00
INDIRECT COSTS
TOTAL BID COST PROPOSAL STRUC'L & ARCH'L WORKS (DIRECT + INDIRECT COSTS) 129,453,993.11
Prepared by:
John C. Calansingin and Associates
Construction Manager and Works Engineer