Sub: a) Establishing of 220/66/11kV Gas Insulated Substation with an installed capacity of 2X150MVA,
220/66kV and 1X31.5MVA, 66/11kV transformers at ITI Substation in Bangalore East Taluk, Bangalore Urban
District.
b) Running of 220kV DC, 1000 Sq.mm Copper single core XLPE UG cable for a route length of 2.607 Kms from
220kV Hoody-Hebbal SC line to proposed 220/66/11kV Gas Insulated substation at ITI Substation, Bengaluru
urban district.
c) Running of 66kV SC 1000 Sq.mm Copper single core XLPE UG cable for a route length of 3.64 Kms from
proposed 220/66/11kV ITI substation to 66/11kV NGEF sub-station in Bengaluru East Taluk, Bangalore Urban
District.
d) Construction of 66 kV Cable line Terminal bay at 66/11 kV NGEF Sub-Station in Bengaluru East Taluk, Bangalore
Urban District.
on Partial Turnkey Basis, including the supply of all equipment’s/Materials (Except 11kV Switchgear), Erection
(Including Civil Works), Testing and Commissioning. – Regarding Request for LC for Exist 31.5 MVA
Transformer commissioning.

Ref No:
1) DWA Supply portion: KPTCL/CEE/T&P/220kVGIS/ ITI/ PTK/ TLSS-903/ 3004 dt: 29.11.2017
2) DWA Erection portion: KPTCL/CEE/T&P/220kVGIS/ ITI/ PTK/ TLSS-903/ 3006 dt: 29.11.2017
3) DWA Civil portion: KPTCL/CEE/T&P/220kVGIS/ ITI/ PTK/ TLSS-903/ 3007 dt: 29:11:2017.

Dear Sir,

As we all know that 66 KV GIS Bus charged successfully on dt. 20.11.2019 .we would like to inform
that the Existing 31.5 MVA Transformer is loaded individually as it is not in parallel operation. The
Commissioning of Existing 31.5 MVA Transformer can be carried after the shifting of 1No. Exist
transformer load to the New 31.5 MVA Transformer which to be erected before shifting the load.and
We need minimum 2 weeks shutdown for shifting of RTCC and OLTC panel ,protection and control &
SAS operation of Exist Trafo from old CRP room to NEW CRP Room.
As we all aware that the New 31.5 MVA transformer plinth is fouling on the live Bus PT and the
erection and commissioning can be taken up after shifting the Bus PT and dismantling of Existing live
bagmane 1 &2 bays .
After commissioning

For KEC International Ltd,

[Authorised Signatory]

Registered Office: RPG House, 463, Dr. Annie Besant Road An Company
Worli, Mumbai 400030, CIN: L45200MH2005PLC152061, India.

Potrebbero piacerti anche