F31 Rate Comparison

Description Unit SCSB Rate Incepsion Recommendation

Excavation of earth at borrow pit of F31 and fill


to areas of filling at P30 & P31 including
transport, placing, spreading, levelling, storage,
compacting in layers as per specification to the m³ 15.30 12.17
required formation level including slope
formation using Contractor's own lorry as shown
in the drawings.

Cost of excavation and loading at borrow area 4.10 3.19


Transportation cost 6.50 5.32
Levelling and compaction 4.70 3.66

Excavation of earth at borrow pit of F31 and fill


to areas of filling at P30 & P31 including
transport, placing, spreading, levelling, storage,
compacting in layers as per specification to the m³ 18.75 15.42
required formation level including slope
formation using licensed lorry as shown in the
drawing.

Cost of excavation and loading at borrow area 4.10 3.19


Transportation cost 9.95 8.57
Levelling and compaction 4.70 3.66