Description Unit SCSB Rate Incepsion Recommendation
Excavation of earth at borrow pit of F31 and fill
to areas of filling at P30 & P31 including transport, placing, spreading, levelling, storage, compacting in layers as per specification to the m³ 15.30 12.17 required formation level including slope formation using Contractor's own lorry as shown in the drawings.
Cost of excavation and loading at borrow area 4.10 3.19
Transportation cost 6.50 5.32 Levelling and compaction 4.70 3.66
Excavation of earth at borrow pit of F31 and fill
to areas of filling at P30 & P31 including transport, placing, spreading, levelling, storage, compacting in layers as per specification to the m³ 18.75 15.42 required formation level including slope formation using licensed lorry as shown in the drawing.
Cost of excavation and loading at borrow area 4.10 3.19
Transportation cost 9.95 8.57 Levelling and compaction 4.70 3.66