Sei sulla pagina 1di 57

PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 1

CLEAN DEVELOPMENT MECHANISM


PROJECT DESIGN DOCUMENT FORM (CDM-PDD)
Version 03 - in effect as of: 28 July 2006

CONTENTS

A. General description of project activity

B. Application of a baseline and monitoring methodology

C. Duration of the project activity / crediting period

D. Environmental impacts

E. Stakeholders’ comments

Annexes

Annex 1: Contact information on participants in the project activity

Annex 2: Information regarding public funding

Annex 3: Baseline information

Annex 4: Monitoring plan


PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 2

SECTION A. General description of project activity

A.1. Title of the project activity:

Title: 20 MW Roura- II Hydro Electric Project by Roura Non Conventional Energy Pvt Ltd
Version: 03
Date: 12/12/2012

A.2. Description of the project activity:

The project activity is a run of river hydro power project on Roura Khad stream located near Village
Yula, Himachal Pradesh, India The project activity will reduce the GHG emission by use of a clean,
renewable (hydro power) source for electricity generation. The project activity will reduce the
dependence on fossil fuel of the integrated NEWNE grid which is dominated by emission intensive fossil
fuel based thermal power plants. The project activity will replace equivalent amount of electricity in the
grid which is majorly fossil fuel based electricity generation. The project is expected to be commissioned
by July 2014. The generated electricity by the project will be supplied to Punjab State Grid through HP
State Grid.

Purpose of the Project

The project will serve the purpose of producing clean electrical energy in a sustainable manner. The
project comprises of 3 units of 6.67 MW each, aggregating to a capacity of 20 MW. The project activity
utilizes hydro power for generation of electricity. The technology consists of conversion of the kinetic
energy available in the water flow to mechanical energy using a hydro turbine and by connecting to a
generator, mechanical energy is converted into electrical energy, which will utilize kinetic energy arising
out of the downstream riparian movement for power generation. Thus, no fossil fuels are involved for
power generation in the project activity. The proposed project activity will, consequently, reduce the
anthropogenic emissions of greenhouse gases into the atmosphere, which, otherwise, would have resulted
from business-as-usual operation of existing/additional fossil fuels-based power plant for the production
of equivalent amount of electricity. The project activity, thus, helps in exploiting the hydro potential,
thereby, leading to a cleaner environment -- through lower greenhouse gas emissions and other pollutants-
- and greater energy security of the nation through lower fuel consumption, fossil fuel conservation for
other activities. The project activity will generate 92460 MWh net electricity per annum resulting
emission reduction of 85,193 tCO2/year.

Pre-project Scenario: No project activity

The proposed project activity is a greenfield project, which means no power generation facility existed at
the project site in the pre-project scenario. Hence, absence of any project activity is a befitting pre-project
scenario at project site; however, export of equivalent amount of electricity into the grid, predominantly
by the existing fossil fuel-based power projects would serve as the business-as-usual scenario.
Baseline Scenario:

The electricity produced by the project activity will be supplied to Punjab State Grid through HP State
Grid, which lies in NEWNE regional grid as prescribed by Central Electricity Authority (CEA), country's
apex power sector planning body, under the federal government of India. The project activity will partly
displace electricity being fed into this regional grid, which is dominated by fossil fuel-fired power plants,
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 3

thereby precluding the emission of greenhouse gases (GHGs) that would resulted in the absence of this
renewable energy-based power project activity. Hence, NEWNE regional grid has been considered for
baseline emission calculations for the proposed project activity.

Evidently, the pre-project scenario is same as the baseline scenario

Contribution of the project activity to sustainable development

Ministry of Environment and Forests, Govt. of India has specified the social well being , economic well
being, environmental well being and technological well being as the four indicators for sustainable
development in the interim approval guidelines of host country approval eligibility criteria for Clean
Development Mechanism( CDM ) Projects .
Social Well Being

The project activity will generate many direct and indirect employment opportunities.
 Contribution to the development of an otherwise underdeveloped area.
 Generation of employment opportunities for local people during various phases of the project
activity.
Economical well being:

 Creation of business opportunities for local stakeholders such as equipment manufacturers,


suppliers, contractors and other vendors.
 Reduction in the load on the national grid by using local renewable source for generating power.
Environmental well being:

 Since, the project uses renewable hydro resources for power generation it does not lead to any
emissions in the environment.
 Avoiding further depletion of the already over-exploited, limited non-renewable sources like coal,
oil, etc.
Technological well being:

 The technology selected for the power project would use well established Horizontal Pelton type
turbines and the project activity would promote the use of such technology

A.3. Project participants:

Name of Party Involved (*) Private and/or Public Kindly Indicate if the Party
(host) indicates a host Entity(ies) Project involved wishes to be
Party) Participants (*) (as Considered
applicable) as Project Participant
(Yes/No)
India (host) M/s Roura Non Conventional No
Energy Pvt. Ltd. ( Private
Entity)
(*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD
public at the stage of validation, a Party involved may or may not have provided its approval. At the
time of requesting registration, the approval by the Party (ies) involved is required.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 4

A.4. Technical description of the project activity:

A.4.1. Location of the project activity:

A.4.1.1. Host Party(ies):

India
A.4.1.2. Region/State/Province etc.:

State: Himachal Pradesh

A.4.1.3. City/Town/Community etc.:

District: Kinnaur, Village: Yula

A.4.1.4. Details of physical location, including information allowing the


unique identification of this project activity (maximum one page):

The physical Location of the project is marked in the maps below1.

1
http://itouchmap.com/latlong.html
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 5

20 MW Roura- II Hydro Electric Project by Roura Non Conventional Energy Pvt. Ltd.
Project Location:

State: Himachal Pradesh


Country: India

Satluj
River

Roura Power House

The Project is located in Kinnaur district of Himachal Pradesh on Roura Khad, a perennial right bank
tributary of Satluj River. The project is located about 200 km distance from Shimla the state Capital of
Himachal Pradesh. The nearest rail head is Kalka and airport is Shimla. The project lies between
geographical co-ordinates of Longitude 78° 08’ 22” East (78.1394° East) and Latitude 31° 32’ 23” North
(31.5397° North).
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 6

A.4.2. Category(ies) of project activity:

The project activity is renewable electricity generation from a 20MW hydro electric power plant. Thus
the applicable category of the project activity is as follows:-
Scope number: 1
Sectoral Scope: Energy Industries- Renewable/ Non renewable source

A.4.3. Technology to be employed by the project activity:

The project is a Small Hydro Power plant designed to generate clean electricity for Grid using available
water resources. The project activity being a Greenfield project, no power generation facility existed in
the pre-project scenario. The project activity is expected to be commissioned in July 2014.

Essentially, the project comprises of 3 units of 6.67 MW each, aggregating to a capacity of 20 MW. The
project activity utilizes hydro power for generation of electricity. The technology consists of conversion
of the kinetic energy available in the water flow to mechanical energy using a hydro turbine and by
connecting to a generator, mechanical energy is converted into electrical energy. In this process there is
no burning of any fossil fuels and hence no emissions. Thus electricity is generated through sustainable
means without causing any negative effect on the environment. The generated power will be evacuated
through the 66 kV transmission line which will be connected to the grid of HPSEB at Karcham Sub-
Station.

The proposed project activity is a greenfield project, which means no power generation facility existed at
the project site in the pre-project scenario. Hence, absence of any project activity is a befitting pre-project
scenario at project site; however, export of equivalent amount of electricity into the grid, predominantly
by the existing fossil fuel-based power projects would serve as the business-as-usual scenario.

Baseline Scenario:

The electricity produced by the project activity will be supplied to Punjab State Grid through HP State
Grid, which lies in NEWNE regional grid as prescribed by Central Electricity Authority (CEA), country's
apex power sector planning body, under the federal government of India. The project activity will partly
displace electricity being fed into this regional grid, which is dominated by fossil fuel-fired power plants,
thereby precluding the emission of greenhouse gases (GHGs) that would resulted in the absence of this
renewable energy-based power project activity. Hence, NEWNE regional grid has been considered for
baseline emission calculations for the proposed project activity.

There are neither any emission sources nor any gases included for the project activity, as explained in
Section B.6.1.
The major components involved in the project are diversion cum trench weir, intake structure, headrace
tunnel, desilting basin, penstock, surge shaft, power house housing 3 turbine-generator sets and tailrace
channel for discharging water back into river.

Brief Technical details of the project are shown below:


PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 7

Brief Technical details of the project design

Parameter Specifications Sources

Hydrology
Gross Head 612.13 m DPR
Net head 601.0 m DPR
Turbine
Type of hydro turbine Horizontal axis Pelton DPR
No. of generating units 3 DPR
Capacity of each generating units 6.67 MW DPR
Generator
Type Synchronous DPR
Rated speed 750 r.p.m. DPR
Generation voltage 11 kV DPR
Power factor 0.85 DPR
Frequency 50 Hz DPR
Power evacuation
Transmission voltage 66 kV DPR
Distance of Substation from site 3 km DPR
Energy (optimum year)
Gross Energy Generation 95,320 MWh DPR
Plant Load factor 54.41% DPR
Average Life time 40 Years DPR

The use of this advanced technology to harness the renewable energy source will avoid emission of
GHGs and other pollutants like CO, SOx, NOx and SPM commonly associated with power generation in
general. Hence, the technology employed is environmentally safe and sound.

Technology transfer from Annex I countries is not involved in the project activity.

A.4.4. Estimated amount of emission reductions over the chosen crediting period:

Fixed crediting period of 10 years has been chosen for the project activity. The estimated emission
reduction over the crediting period is furnished below:-

Years Estimation of annual emission reductions in


tonnes of CO2e
01 July 2014 to 30June 2015 85,193
01 July 2015 to 30June 2016 85,193
01 July 2016 to 30June 2017 85,193
01 July 2017 to 30June 2018 85,193
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 8

01 July 2018 to 30June 2019 85,193


01 July 2019 to 30June 2020 85,193
01 July 2020 to 30June 2021 85,193
01 July 2021 to 30June 2022 85,193
01 July 2022 to 30June 2023 85,193
01 July 2023 to 30June 2024 85,193
Total estimated reductions (tonnes of CO2e) 8,51,930
Total number of crediting years 10
Annual average of the estimated reductions over
85,193
the period (tonnes of CO2e)

A.4.5. Public funding of the project activity:

The project does not involve any diversion of Official Development Assistance (ODA) to the project
activity and does not involve any other public funding.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 9

SECTION B. Application of a baseline and monitoring methodology

B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:

Approved consolidated baseline and monitoring methodology ACM0002: “Consolidated baseline


methodology for grid-connected electricity generation from renewable sources”, Version 13.0.0 (EB 67)2

Tools referenced in this methodology:


 Tool to calculate the emission factor for an electricity system, Version 02.2.13
 Tool for the demonstration and assessment of additionality, Version 07.0.04
 Tool to calculate project or leakage CO2 emissions from fossil fuel combustion, Version 025

B.2. Justification of the choice of the methodology and why it is applicable to the project
activity:

Choice of selected methodology has been justified by showing that the project activity meets each
applicability conditions of the selected methodology in table below.

The project activity is grid-connected renewable power generation from run-of-the-river hydro power
plant.

S. Technology Measures as per ACM0002, version Project Activity Measures


No. 13.0.0

1 This methodology ACM0002 is applicable to grid connected Project activity is an installation


renewable power generation project activities that (a) install of a new power plant at a site
a new power plant at a site where no renewable power plant where no renewable power plant
was operated prior to the implementation of the project was operated prior to the
activity (greenfield plant); (b) involve a capacity addition; (c) implementation of the project
involve a retrofit of (an) existing plant(s); or (d) involve a activity (Greenfield plant). Hence
replacement of (an) existing plant(s). the given condition (a) is
applicable to the project activity.

http://cdm.unfccc.int/filestorage/D/5/W/D5WJ7B6TGLHF8I4XC2RV9YAP0NO1ES/eb67_repan13.pdf?t=VWh8b
WV5aXJ0fDDV3OpCXEPFq7ajWKuzUx2A
3
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-07-v2.2.1.pdf
4

http://cdm.unfccc.int/filestorage/l/i/FJUZLIKOG8NPT4HSCWR1692703A5VX.pdf/eb70_repan08.pdf?t=alN8bWV
5aW0xfDB9QeR8M2aXNszJ8dlqAOm7
5
http://cdm.unfccc.int/methodologies/PAmethodologies/tools/am-tool-03-v2.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 10

2 The project activity is the installation, capacity addition, The project activity is
retrofit or replacement of a power plant/unit of one of the construction and operation of a
following types: hydro power plant/unit (either with a run-of- new run-of-river hydro power
river reservoir or an accumulation reservoir), wind power plant.
plant/unit, geothermal power plant/unit, solar power
plant/unit, wave power plant/unit or tidal power plant/unit;

3 In the case of capacity additions, retrofits or replacements The project activity is a


(except for wind, solar, wave or tidal power capacity addition Greenfield project and not
projects which use Option 2: on page 10 to calculate the capacity additions, retrofits or
parameter EGPJ,y): the existing plant started commercial replacements of the existing
operation prior to the start of a minimum historical reference plant. Thus, this condition is not
period of five years, used for the calculation of baseline applicable.
emissions and defined in the baseline emission section, and
no capacity expansion or retrofit of the plant has been
undertaken between the start of this minimum historical
reference period and the implementation of the project
activity.
4 In case of hydro power plants: The proposed project activity is
 The project activity is implemented in an existing run-of-river based hydro
reservoir, with no change in the volume of reservoir. electricity generation, which does
 The project activity is implemented in an existing not require building of a
reservoir, where the volume of reservoir is increased and the reservoir. Hence, the given
power density of the project activity, as per definitions given condition is not applicable to the
in the Project Emissions section, is greater than 4 W/m2. project activity.
The project activity results in new reservoirs and the power
density of the power plant, as per definitions given in the
Project Emissions section, is greater than 4 W/m2.
5 In case of hydro power plants using multiple reservoirs where The proposed project activity is
the power density of any of the reservoirs is lower than 4 run-of-river based hydro
W/m2 after the implementation of the project activity all of electricity generation, which does
the following conditions must apply: not require building of a
 The power density calculated for the entire project reservoir. Hence, the given
activity using equation 5 is greater than 4W/m2; condition is not applicable to the
 All reservoirs and hydro power plants are located at project activity.
the same river and where are designed together to
function as an integrated project that collectively
constitute the generation capacity of the combined
power plant;
 The water flow between the multiple reservoirs is not
used by any other hydropower unit which is not a
part of the project activity;
 The total installed capacity of the power units, which
are driven using water from the reservoirs with
power density lower than 4 W/m2, is lower than
15MW;
 The total installed capacity of the power units, which
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 11

are driven using water from reservoirs with power


density lower than 4 W/m2, is less than 10% of the
total installed capacity of the project activity from
multiple reservoirs.
6 The methodology is not applicable to the following: The proposed project activity is
 Project activities that involve switching from fossil fuels run-of-river based hydro
to renewable energy sources at the site of the project electricity generation, which does
activity, since in this case the baseline may be the not require building of a
continued use of fossil fuels at the site; reservoir. Hence, the given
 Biomass fired power plants; condition is not applicable to the
 Hydro power plants that result in new single reservoir or project activity.
in the increase in an existing single reservoir where the
power density of the reservoir is less than 4 W/m2.

B.3. Description of the sources and gases included in the project boundary:
The project activity is construction and operation of a new 20 MW run-of-the-river hydro power plant.
According to ACM0002, Version 13.0.0, for the baseline emission factor, “The spatial extent of the
project boundary includes the project power plant and all power plants connected physically to the
electricity system6 that the CDM project power plant is connected to.”

Thus, the project boundary is the spatial extent of the 20 MW Roura Hydro Electric Power Project and
the Integrated NEWNE grid.

Source GHGs Included? Justification/Explanation


CO2 emissions from CO2 Yes Main emission source
Baseline
scenario

electricity generation in CH4 No Minor emission source


fossil fuel fired power
plants that are displaced N2O No Minor emission source
due to the project activity
The project activity is renewable energy
CO2 No project which will not create any CO2
emissions itself
Project scenario

The project activity is renewable energy


project which will not create any
20 MW run-of-the-river
emissions itself. The project is run-of-river
Hydro Electric Power CH4 No
based and does not involves any reservoir.
Project
Thus, no methane emissions need to be
considered
The project activity is renewable energy
N2O No project which will not create any emissions
itself.

6
Refer to the latest approved version of the “Tool to calculate the emission factor for an electricity system” for
definition of an electricity system.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 12

Project boundary is shown in the diagram below:

Diversion Weir
Project Boundary

Trench Weir

Intake Structure

Desilting Chamber

Forebay Tank

Penstock

Turbine

Generator

Transformer Energy output =95,320 MWh


415V/11KV
3% of
Net sellable Energy 95320
EGPJ,y = 92460 11kV/66kV MWh Auxiliary Consumption
MWh + Losses
NEWNE HBSEB Substation at Karcham
66kV
Grid Main Meter/ Check Meter
Parameter Monitored: EGPJ,y

B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 13

According to Section II of ACM0002, Version 13.0.0, if the project activity is the installation of a new
grid-connected renewable power plant/unit, the baseline scenario is the following:
Electricity delivered to the grid by the project activity would have otherwise been generated by the
operation of grid-connected power plants and by the addition of new generation sources, as reflected in
the combined margin (CM) calculations described in the “Tool to calculate the emission factor for an
electricity system”.
Since the project activity is the installation of a new grid-connected renewable power plant, run of the
river hydro power project, the baseline would be the electricity delivered to the grid that would have been
otherwise generated by the operation of grid-connected power plants.

Baseline emissions
Baseline emissions include only CO2 emissions from electricity generation in fossil fuel fired power
plants that are displaced due to the project activity. The methodology assumes that all project electricity
generation above baseline levels would have been generated by existing grid-connected power plants and
the addition of new grid-connected power plants. The baseline emissions are to be calculated as follows:

BE y  EG PJ,y  EFgrid,CM, y

Where:

BEy = Baseline emissions in year y (tCO2)


EGPJ,y = Quantity of net electricity generation that is produced and fed into the grid as a result
of the implementation of the CDM project activity in year y (MWh)
EFgrid,CM,y = Combined margin CO2 emission factor for grid connected power generation in year y
calculated using the latest version of the “Tool to calculate the emission factor for an
electricity system” (tCO2/MWh)

The baseline emission factor (EFgrid,CM,y) is calculated as a combined margin (CM), consisting of the
combination of operating margin (OM) and build margin (BM) factors calculated according to the
version 02.2.1 of “Tool to calculate the emission factor for an electricity system”, using the following
six steps:

STEP 1. Identify the relevant electricity systems;


STEP 2. Choose whether to include off-grid power plants in the project electricity system (optional);
STEP 3. Select a method to determine the operating margin (OM);
STEP 4. Calculate the operating margin emission factor according to the selected method;
STEP 5. Calculate the build margin (BM) emission factor;
STEP 6. Calculate the combined margin (CM) emission factor.

STEP 1. Identify the relevant electricity systems:

The tool defines the project electricity system as the spatial extent of the power plants that are
physically connected through transmission and distribution lines to the project activity and that can be
dispatched without significant transmission constraints. Keeping this into consideration, the Central
Electricity Authority (CEA), Government of India has divided the Indian electricity system into two
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 14

regional grids, viz. NEWNE and Southern grid. Each grid covers several states (see table below).

NEWNE Grid Southern Grid


Northern Western Eastern North - Eastern Southern
Chandigarh Chhatisgarh Bihar Arunachal Pradesh Andhra Pradesh
Delhi Gujarat Jharkhand Assam Karnataka
Haryana Daman & Diu Orissa Manipur Kerala
Dadar & Nagar
Himachal Pradesh West Bengal Meghalaya Tamil Nadu
Haveli
Jammu & Kashmir Madhya Pradesh Sikkim Mizoram Pondicherry
Punjab Maharashtra Andaman - Nicobar Nagaland Lakshadweep
Rajasthan Goa Tripura
Uttar Pradesh
Uttranchal

As the regional grids are interconnected, there is inter-state and inter-regional exchange. A small power
exchange also takes place with neighboring countries like Bhutan and Nepal. Power generation and
supply within the regional grid is managed by Regional Load Dispatch Centre (RLDC). The Regional
Power Committees (RPCs) provide a common platform for discussion and solution to the regional
problems relating to the grid. Each state in a regional grid meets its demand with its own generation
facilities and also with allocation from power plants owned by the Central Sector such as NTPC and
NHPC etc. Specific quotas are allocated to each state from the Central Sector power plants. Depending on
the demand and generation, there are electricity exports and imports between states in the regional grid.
The regional grid thus represents the largest electricity grid where power plants can be dispatched without
significant constraints and thus, represents the “project electricity system” for the project activity. As the
project activity is connected to the NEWNE regional electricity grid, the NEWNE grid is the “connected
electricity system”.

STEP 2. Choose whether to include off grid power plants in the project electrical system:

Project Participants may choose between the following two options to calculate the operating margin
and built margin:

Option I: Only grid power plants are included in the calculation


Option II: Both grid power plants and off-grid power plants are included in the calculations.

Option II requires collecting data on off-grid power generation. Off grid data is not available publically;
Therefore Project Participants have opted for option I.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 15

STEP 3. Select a method to determine the operating margin (OM) method.

The calculation of the operating margin emission factor (EFOM,y) is based on one of the following
methods:
(a) Simple OM, or
(b) Simple adjusted OM, or
(c) Dispatch data analysis OM, or
(d) Average OM.

The simple OM method (Option a) can only be used if low-cost/must-run resources constitute less than
50% of total grid generation in: 1) average of the five most recent years, or 2) based on long-term
averages for hydroelectricity production.

Share of Must-Run (Hydro/Nuclear) (% of Net Generation)


Year 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
NEWNE 18.0% 18.5% 19.0% 17.4% 15.9% 17.6%
South 27.0% 28.3% 27.1% 22.8% 20.6% 21.0%
India 20.1% 20.9% 21.0% 18.7% 17.1% 18.4%
Reference: Baseline Carbon Dioxide Emission Database Version 7.07

The above data clearly shows that the percentage of total grid generation by low cost/must run plants (on
the basis of average of five most recent years) for the NEWNE and Southern grids are less than 50 % of
the total generation. Thus, simple OM method (Option a) has been used to calculate the operating margin
emission factor (EFOM,y).

The “Simple operating margin” has been calculated as per the weighted average emissions (in
tCO2e/MWh) of all generating sources serving the system, excluding hydro, geo-thermal, wind, low-cost
biomass, nuclear and solar generation. The data has been sourced from Baseline Carbon Dioxide
Emission Database Version 7.0, published by the Central Electricity Authority, which is India's apex
power sector planning body, under the federal government of India.

In the project activity, the PP has chosen the an ex ante option for calculation of the OM with the full
generation-weighted average for the most recent 3 years, based on most recent data available at the time
of submission of CDM PDD to the DOE for validation, without requirement to monitor and recalculate
the emission factor during the crediting period. It is, therefore, confirmed that ex-ante vintage is
considered in the project activity and cannot be changed during the crediting period.

7
http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 16

STEP 4. Calculate the operating margin emission factor according to the selected method.

The simple OM emission factor is calculated as the generation-weighted average CO2 emissions per
unit net electricity generation (tCO2/MWh) of all generating power plants serving the system, not
including low-cost / must-run power plants / units. It may be calculated as:

Option A: Based on the net electricity generation and a CO2 emission factor of each power unit; or
Option B: Based on the total net electricity generation of all power plants serving the system and the
fuel types and total fuel consumption of the project electricity system.

Option B can only be used if:

(a) The necessary data for Option A is not available; and

(b) Only nuclear and renewable power generation are considered as low-cost/must-run power sources
and the quantity of electricity supplied to the grid by these sources is known; and

(c) Off-grid power plants are not included in the calculation (i.e., if Option I has been chosen in Step 2)

CEA data base has been prepared based on Option A.

The operating margin emission factor has been calculated using a 3 year data vintage (latest available at
the time of PDD submission for the validation) as follows:

Net Generation in Operating Margin (MWh) (Source: CEA database version 7)

Year MWh (NEWNE Grid)


2008-2009 421802632.89
2009-2010 458043084.55
2010-2011 476986721.34

Simple Operating Margin (tCO2/MWh) (incl. Imports) (Source: CEA database version 7)

Year tCO2/MWh (NEWNE Grid)


2008-2009 1.0065
2009-2010 0.9777
2010-2011 0.9706

Simple Operating Margin = Generation weighted average of the simple operating Margin
=((1.0065 * 421802632.89) + ( 0.9777 * 458043084.55) + (0.9706 *
476986721.34)) / (421802632.89 + 458043084.55 + 476986721.34)
= 0.9842 (tCO2/MWh)
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 17

STEP 5. Calculate the build margin emission factor (EFgrid, BM, y)

In terms of vintage of data, project participants can choose between one of the following two options:

Option 1:

For the first crediting period, calculate the build margin emission factor ex ante based on the most recent
information available on units already built for sample group m at the time of CDM-PDD submission to
the DOE for validation. For the second crediting period, the build margin emission factor should be
updated based on the most recent information available on units already built at the time of submission of
the request for renewal of the crediting period to the DOE. For the third crediting period, the build margin
emission factor calculated for the second crediting period should be used. This option does not require
monitoring the emission factor during the crediting period.

Option 2:

For the first crediting period, the build margin emission factor shall be updated annually, ex post,
including those units built up to the year of registration of the project activity or, if information up to the
year of registration is not yet available, including those units built up to the latest year for which
information is available. For the second crediting period, the build margin emissions factor shall be
calculated ex ante, as described in Option 1 above. For the third crediting period, the build margin
emission factor calculated for the second crediting period should be used.

The project participants have chosen option-1 for vintage of the data.

The sample group of power units m used to calculate the build margin consists of either:

(a) The set of five power units that have been developed most recently; or

(b) The set of power capacity additions in the electricity system that comprise 20% of the system
generation (in MWh) and that have been built most recently.

According to the CEA Baseline Database, for this project, the sample group of power units m used to
calculate the build margin consists of the set of power capacity additions in the electricity system that
comprise 20% of the system generation (in MWh) and that have been built most recently. The CEA
Baseline Database Version 7 has been calculated as per" Tool to calculate the emission factor for an
electricity system" Version 2.2.1 and the details of the key assumptions considered to calculate the figure
can be found in the User Guide of the same.

The Build Margin (BM) emissions factor is the generation-weighted average emission factor
(tCO2/MWh) of all power units m during the most recent year y for which power generation data is
available, calculated as follows:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 18

EFgrid, BM, y = ∑mEGm,y x EFEL,m,y / ∑m EGm,y

Where,
EFgrid, BM,y = Build Margin CO2 Emission Factor in year y (tCO2e/MWh).
EGm, y = Net quantity of electricity generated and delivered to the grid by power unit m in
year y (MWh)
EFEL, m,y = CO2 emission factor of power unit m in year y (tCO2 e /MWh)
m = Power units included in the build margin
y = Most recent historical year for which power generation data is available

As per the CEA CO2 Baseline Database Version 7, the BM for the 2010-11 has been calculated to be:

Grid 2010-11

NEWNE 0.8587

Build Margin (tCO2e/MWh) for NEWNE8 = 0.8587

STEP 6. Calculate the combined margin (CM) emissions factor

The calculation of the combined margin (CM) emission factor (EFgrid,CM,y) is based on one of the
following methods:

(a) Weighted average CM; or


(b) Simplified CM.

Since the weighted average CM method (option a) should be used as the preferred option, PP has chosen
this method to calculate combined margin emission factor.

As per this method, the combined margin emissions factor, CM, can be calculated as:

EFgrid, CM, y = EFgrid, OM, y x WOM + EFgrid, BM, y x WBM

Where:
EFgrid, BM, y = Build Margin CO2 emission factor in the year y (tCO2/MWh)
EFgrid, OM, y = Operating Margin CO2 emission factor in the year y (tCO2/MWh)
WOM = Weighting of operating margin emission factor (%)
WBM = Weighting of build margin emission factor (%)

8
http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 19

As per the Tool, the default values for hydro projects are as follows:
WOM = 50% and WBM = 50%.

In the project activity, combined margin has been chosen as the baseline emission factor for grid
emission factor. The value chosen is taken from relevant official sources and is publicly available9.

Parameter Value10 (tCO2/MWh)

Operating Margin Emission Factor (EFgrid,OM,y ) 0.9842

Build Margin Emission Factor (EFgrid,BM,y ) 0.8587

Combined Margin Emission Factor (EFgrid,CM,y ) 0.9214

Thus, the Combined Margin Emission Factor (EFgrid,CM, y) for the project has been calculated to be EFgrid,
CM, y = 0.9214 tCO2/MWh and is fixed ex-ante for the entire crediting period.

B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessment
and demonstration of additionality):

The project activity is construction and operation of a hydro electric power plant. In absence of the
project activity, the equivalent amount of electricity would have been generated in the existing and future
power plants in the NEWNE grid. Thus, the project activity avoids the emission of equivalent amount of
GHGs associated with the current fuel mix in the grid.

Relevant activities of project implementation:

Date Project Implementation Proof of action

DPR Prepared by Roura Non


August 2010 Detailed Project Report
Conventional Energy Private Limited
Techno Economic Clearance from
15 January 2011 Techno Economic Clearance
Government of Himachal Pradesh11

June 2011 Technical Review Report for the project Technical Review Report

9
http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm
10
As a conservative measure, the final values have been considered to be upto two decimal places
11
Based on submission of DPR. In this process DPR was duly approved by Directorate of Energy (DOE),
Government of Himachal Pradesh.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 20

prepared by Indo Canadian Consultancy (


Contracted third party Engineering
company)

8 August 2011 Loan sanctioned by State Bank of India Loan sanction letter

Minutes of Meeting of Board


30 August 2011 Date of investment decision
of Directors
LSM Newspaper advertisement
28 September 2011 Local Stake Holders Meeting
and other Documents

The project activity is not yet started. CDM validation has started before the starting date of the project
as the CDM registration is a major criterion for approval12.
Additionality:

As required by the approved methodology, the additionality of the project activity shall be
demonstrated and assessed using the latest version of the Tool for the demonstration and assessment
of additionality, Version 07.0.013 EB 70, Annex 08.

According to the "Tool for the demonstration and assessment of additionality, Version 07.0.0”
the steps that need to be followed to determine the additionality:

Step 0: Demonstration whether the proposed project activity is the first-of-its-kind;

Proposed project activity is not the first-of-its-kind project.

Step 1: Identification of alternatives to the project activity consistent with current laws and regulations

Sub-step la: Define alternatives to the project activity:

In this step all the realistic and credible alternative(s) available to the project participants or similar
project developers that provide outputs or services comparable with the proposed CDM project
activity need to be identified.

Since identified methodology ACM0002 prescribes baseline, following plausible alternatives to the
project activity are identified.

1. The proposed project activity not undertaken as a CDM project activity:

Construction of a new renewable run of river hydroelectric project connected to the grid,

12
http://cdm.unfccc.int/Projects/Validation/DB/ZPC7NTI1LX6WM99L8252VOQI2H4LSO/view.html
13

http://cdm.unfccc.int/filestorage/l/i/FJUZLIKOG8NPT4HSCWR1692703A5VX.pdf/eb70_repan08.pdf?t=alN8bWV
5aW0xfDB9QeR8M2aXNszJ8dlqAOm7
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 21

implemented without considering CDM revenues.


This alternative is in compliance with all applicable legal and regulatory requirements and may be a
part of the baseline. However, in absence of CDM revenue it would have been difficult for the
project proponent to implement the project activity on account financial unviability (please refer to
Step 2: Investment Analysis in the following section for details). Hence it cannot be a part of the
baseline scenario.

2. Continuation of power generation in existing and new grid connected thermal power stations:

In this alternative the project activity would not have been implemented and an equivalent amount
of energy (power) would have been produced by the project grid electricity system through its
currently running power plants and by new capacity addition to the grid i.e. Continuation of current
situation.

Outcome of Step 1a: Both alternatives identified are studied further.

Sub-step 1b: Consistency with mandatory laws and regulations:

The implementation of project activity is a voluntary initiative and it is not mandatory or a


legal requirement. For power generation, the Electricity Act 2003 does not restrict or empower any
authority to restrict the fuel choice, the applicable environmental regulations do not restrict the use of
hydro energy and there is no legal requirement on the choice of a particular technology.

Outcome of Step 1b: Thus, both the alternatives are in line with the applicable legal and regulatory
requirements. These are studied further.

Step 2: Investment analysis

Sub-step 2a: Determine appropriate analysis method


This step requires the project proponent to determine the financial analysis method that needs to be
applied to carry out the investment analysis for the feasibility of the project activity. The options
available with the project proponent include:

1. Simple Cost Analysis


2. Investment Comparison Analysis
3. Benchmark Analysis

The option chosen to prove additionality is Option III – “Benchmark Analysis”, as the only plausible
investment decision for Roura Non Conventional Energy Pvt. Ltd. is whether or not to develop the
proposed project activity.

Sub-step 2b: Option III. Apply benchmark analysis

As per the Guidance on the Assessment of Investment Analysis, Version 05, EB62, Annex 514 “In cases
where a benchmark approach is used the applied benchmark shall be appropriate to the type of IRR
calculated. Local commercial lending rates or weighted average costs of capital (WACC) are

14
http://cdm.unfccc.int/Reference/Guidclarif/reg/reg_guid03.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 22

appropriate benchmarks for a project IRR. Required/expected returns on equity are appropriate
benchmarks for equity IRR. Benchmarks supplied by relevant national authorities are also appropriate
if the DOE can validate that they are applicable to the project activity and the type of IRR calculation
presented”.

Moreover, Guidance 13 of this Annex states that, "In the cases of projects which could be developed by
an entity other than the project participant the benchmark should be based on parameters that are
standard in the market." Since such projects could also be developed by entities other than the PP,
benchmark has been calculated using parameters standard in the market.

Now, as per Guidance 15 of this Annex, “If the benchmark is based on parameters that are standard in
the market, the cost of equity should be determined either by: (a) selecting the values provided in
Appendix A; or by (b) calculating the cost of equity using best financial practices, based on data
sources which can be clearly validated by the DOE, while properly justifying all underlying factors”.

Notably, the guideline on using default values for calculating cost of equity were introduced in July
2010, while the decision making date of the current project activity is August 2011; hence, PP has
calculated the cost of equity on the basis of option (a), by selecting the values provided in Appendix A.
The proposed project activity falls under Group 1 category, mentioned in paragraph 5 of this Appendix.
The default cost of equity (real) for Indian Group I projects is 11.75%. However, as per paragraph 7 of
the Appendix A “In situations where an investment analysis is carried out in nominal terms, project
participants can convert the real term values provided in the table below to nominal values by adding
the inflation rate. The inflation rate shall be obtained from the inflation forecast of the central bank of
the host country for the duration of the crediting period.”

As the analysis has been carried out in nominal terms, the default value of expected return on equity
(given in real terms in EB 62 Annex 13) has been adjusted with the inflation. For this purpose, a 10-year
inflation forecast of 5.4%15 by the Reserve Bank of India (RBI), the country’s central bank, has been
used, as the above guideline states that the inflation rate shall be obtained from the inflation forecast of
the central bank of the host country for the duration of the crediting period.

The cost of equity has been calculated using Fisher's equation16as follows:

Nominal return = {(1+ real return)*(1+expected inflation rate) – 1}


= {(1+11.75%)*(1+5.4%) – 1}
= 17.78%

The benchmark, therefore, works out to be 12.76%, which has been tabulated below:

Project Return Cost Income Debt Equity Benchmark


owner on equity of tax rate weightage weightage (WACC)

15
http://www.rbi.org.in/scripts/PublicationsView.aspx?id=13360. Although the mean WPI and CPI inflation rate
published by RBI are 5.40% and 6.3%, PP has, conservatively, selected 5.40%.
16
Fisher's equation available at http://en.wikipedia.org/wiki/Fisher_equation
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 23

(%) debt (%) (%) (%) (%)


(%)
Roura Non
Conventional
17.78 13.2517 19.9318 70 30 12.76
Energy Pvt
Ltd

An investment analysis of the project activity was conducted considering the Project IRR (post-tax) as
the most suitable financial indicator. The project IRR of the project activity has been computed over a
period of 20 years as 7.72% and then compared against the benchmark return of 12.76%.

Sub-step 2c: Calculation and comparison of financial indicators:

IRR is the most common financial indicator used by bankers as well as investors to check the financial
viability of the project. The Project IRR (post-tax) has been computed by taking into account the ash
outflows (capital investment in the project) and cash inflows comprising profit after tax, depreciation,
interest on term loan and salvage value (in the terminal year). The Project IRR is compared with local
commercial lending rates to prove that the proposed CDM project activity is unlikely to be financially
attractive without CER revenue.

1. Various technical and financial parameters used for the calculation of the project IRR are as given
below:

Parameter Values Source


DPR/Technical Review Report by
Installed Capacity ( MW) 20.00
Indo-Canadian Consultancy Limited
PLF 54.41% Calculated
DPR/Technical Review Report by
Annual Operational Days 365
Indo-Canadian Consultancy Limited
No. of operational hours in each DPR/Technical Review Report by
24
working day Indo-Canadian Consultancy Limited
DPR/Technical Review Report by
Gross Annual generation (MWh) 95320.00
Indo-Canadian Consultancy Limited
Total Losses ( 1% Auxiliary
DPR Pg. XV - 1/Technical Review
Consumption & Transformation
3.00% Report by Indo-Canadian
losses+ 2% Transmission Losses, ) As
Consultancy Limited
per DPR
Net Annual saleable generation (MWh) 92460.40 Calculated
http://www.cercind.gov.in/2011/June/
Transmission losses in CTU 2.00% sigend_Order_on_POC_29.6.2011.pd
f

17
Loan sanction letter available at the time of decision making
18
http://www.deloitte.com/assets/Dcom-India/Local%20Assets/Documents/Business_Tax_Alert.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 24

SLDC/Operating Charges
0.73 www.hperc.org/rules/oa1011.doc
(Rs.Million/year) @ Rs. 2000/day
Transmission Charges Rs/kWh
0.17 www.hperc.org/rules/oa1011.doc
(64967.43 Rs/MW/Month)
http://www.cercind.gov.in/2011/June/
CTU Charges Rs/ kWh
0.17 sigend_Order_on_POC_29.6.2011.pd
(66515 Rs/MW/Month)
f
http://peda.gov.in/eng/Data/Commissi
Selling price per kWh (Rs/kWh) 3.65
on/PSERC_Order_-_3092010.pdf
Net Power tariff per kWh 3.31 Calculated
DPR//Technical Review Report by
O & M costs including Insurance 2.00%
Indo-Canadian Consultancy Limited
DPR//Technical Review Report by
Yearly Increase on O & M Cost 8.32%
Indo-Canadian Consultancy Limited
DPR Pg. XV -1//Technical Review
Royalty charges for first 12 years 16% Report by Indo-Canadian
Consultancy Limited
DPR Pg. XV -1//Technical Review
Royalty charges from 13th year
22% Report by Indo-Canadian
(applicable to 30th year)
Consultancy Limited
Interest on Term Loan 13.25% Loan sanction letter
Interest on working capital 14.75% Local commercial lending rates
DPR//Technical Review Report by
Loan repayment period (quarters) 40
Indo-Canadian Consultancy Limited
DPR//Technical Review Report by
Moratorium Period (quarters) 12
Indo-Canadian Consultancy Limited
http://www.deloitte.com/assets/Dcom
-
Minimum Alternate Tax ( MAT) 19.93%
India/Local%20Assets/Documents/Bu
siness_Tax_Alert.pdf
Corporate tax 33.99% IT Act
CEA ver.7-
http://cea.nic.in/planning/c%20and%2
Emission Factor(tCO2/GWh) 921.5
0e/Government%20of%20India%20w
ebsite.htm
CER price Euro/Ton 9.37 CER spot price as on August 29, 2011
Conversion rate for the month of July
Exchange rate Euro=INR 63.49
2011
Incentives
http://law.incometaxindia.gov.in/DIT/
File_opener.aspx?page=ITAC&schT=
Tax holiday (years) 10 &csId=ace9ceec-63d0-4855-a1bd-
496c62307e16&rdb=sec&yr=75996b
99-a798-4098-bca8-
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 25

e66ee23fe426&sec=80IA&sch=&title
=Taxmann - Direct Tax Laws
Subsidy (Rs. Million) (To be released
directly into bank loan account 6 http://www.mahaurja.com/PDF/PG_S
77
months after the commissioning of the HP_Cent_Po.pdf
project)

The project cost has been tabulated below:

COST OF THE PROJECT Rs.Million


Land 64.754
Civil Works 758.484
Electro Mechanical Equipment 493.909
Transmission works 27.545
Sub total 1344.692
Escalation 29.637
Interest During Construction 177.883
Financial Charges 16.298
LADA Charges @ 1.5% of project cost 23.53
Margin money for working capital 11.613
TOTAL 1603.651

Roura Non Conventional Energy Pvt. Ltd intends to sell the generated power outside the state of
Himachal Pradesh i.e. to Punjab (PSEB). In India any IPP/Generator who intends to sell power outside
the state has to pay following charges and losses of the intervening transmission systems.

i) Transmission charges and losses of intra-state grid i.e. HPSEB/HPTCL grid in which the generator is
located.
ii) SLDC/Operating Charges of intra-state grid i.e. HPSEB/HPTCL grid
iii) Inter-state transmission charges of inter-state grid i.e. CTU grid.
iv) Inter-state transmission losses of inter-state grid i.e. CTU grid.

a) Now for transfer of power from generation interconnection point with Himachal Pradesh grid up to
interstate point, the transmission charges applicable is 0.17 Rs/unit.19
b) SLDC/Operating Charges @ Rs. 2000/day20 i.e. 0.73 Rs. Million/year
c) The transmission charges of CTU grid used in transfer of power from inter-state point of Himachal
Pradesh to inter-state point of Punjab are 17 paisa/unit.21

19
www.hperc.org/rules/oa1011.doc
20
www.hperc.org/rules/oa1011.doc
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 26

d) The transmission losses in CTU in transfer of power from inter-state point of Himachal Pradesh to
inter-state point of Punjab is 2%22

Sub-step 2d: Sensitivity analysis:

A sensitivity analysis has been carried out to provide an analysis of variations in important parameters
affecting the project financially, and their impact on the project IRR. The results of the analysis for both
the project participants are as mentioned in table below:

IRR w/o
Parameter Increase 10% Decrease 10% Benchmark
CDM
Project Cost 8.58% 12.16%
Net generation 11.76% 8.63%
10.26% 12.76%
Tariff 11.76% 8.63%
O&M Cost 9.93% 10.56%

As evident from the table above, the Project IRR is unable to cross the benchmark even with a 10%
increase in the gross generation or tariff or with a 10 % reduction in the project cost or O &M cost.

Outcome of Step 2

The project activity has lower returns than the conservative benchmark returns calculated at the time of
investment decision. Even the 10% increase or decrease in the important parameters that affects the
returns on the project does not make project financially viable in the absence of the CDM revenue.
Thus, the CDM revenue is critical for the financial viability of the project activity.

Step 3: Barrier Analysis

According to the “Tool for the demonstration and assessment of additionality, Version 07.0.0”, Project
participants can use either investment analysis or barrier analysis step. Therefore, PP has chosen
investment analysis.

Step 4: Common Practice analysis

The Project is a newly built hydropower generation project connected with Grid, which belongs to
measures that are listed in paragraph 6: (b) Switch of technology with or without change of energy source
(including energy efficiency improvement as well as use of renewable energies) of the Methodological
tool “Demonstration and assessment of additionality” Version 07.0.0., therefore we are proceeding to
Sub-step 4a.

Sub-step 4a: The proposed CDM project activity(ies) applies measure(s) that are listed in the
definitions section above:

21
http://www.cercind.gov.in/2011/June/sigend_Order_on_POC_29.6.2011.pdf
22
http://www.cercind.gov.in/2011/June/sigend_Order_on_POC_29.6.2011.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 27

Common practice analysis has been carried out as per the latest version of the “Guidelines on common
practice” Version 02, EB 69 Annex 8. The step by step approach of the common practice analysis is
illustrated below:

I. Definition

1. Applicable Geographical area covers entire host country as a default. As per the guidelines host
country i.e. India is considered as the applicable geographical area.
2. Measure (for emission reduction activity): Project activity falls under the option 6 (b) of the measures
i.e. switch of technology with or without change of energy source.
3. Output: Goods or services with comparable quality, properties and application areas. As per the
definition “electricity”, which is a service, is considered as output of the project activity.
4. Different technologies: As per guidelines technologies that deliver same output (i.e. electricity) and
differ by following conditions are considered as different technology for the common practice analysis:

Since the Tool provides five alternatives to distinguish the technologies, out which atleast one should be
used, PP has chosen the investment climate in the date of the investment decision (option d) to establish
the common practice analysis.

II. Stepwise approach to common practice analysis

Step 1: Calculate applicable output range as +/-50% of the design output or capacity of the proposed
project activity.

The installed capacity of the Project is 20 MW. As a result, projects between 10 MW and 30 MW are
defined as the applicable output range for common practice analysis.

Step 2: In the applicable geographical area, identify all plants that deliver the same output or capacity,
within the applicable output range calculated in Step 1, as the proposed project activity and have started
commercial operation before the start date of the project. Note their number Nall.. Registered CDM
project activities and projects activities undergoing validation shall not be included in this step.

As per para 1 of EB 69, Annex 8 applicable geographical area covers the entire host country as default,
therefore PP has chosen the entire host country “India” as applicable geographical area.

Proposed project activity is still in planning stage; the expected start date is January 2012. Project design
document (PDD) had been published for global stakeholder consultation on 17 April 2012, before the
project activity start date Thus, power generation projects started commercial operation before April,
2012 need to be considered.

All plants that deliver the same output or capacity within the applicable output range calculated in Step 1
(10MW – 30MW) have been listed in Appendix-1. They are numbered at 234. However, this database is
updated with data latest till March 31, 2011. During 2011-2012, the total hydro-based capacity addition
was pegged at 1423 MW23. Out of the addition, not even a single plant matched our capacity range.

23
http://www.cea.nic.in/reports/monthly/executive_rep/mar12/19-25.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 28

Thereafter, hydro capacity additions in the same small scale range, during the same period, were
analysed. It was observed from the CEA monthly reports24 that there were increments in the Renewable
Energy Sources (RES), which include biomass, wind solar and small hydro, among others, no capacity
addition was observed for the small-scale hydro power projects.

In effect, Nall = 234 (As per CEA database Version 7 Baseline Carbon Dioxide Emission Database
Version 7.0 – LATEST).

Step 3: Within plants identified in Step 2, identify those that apply technologies different that the
technology applied in the proposed project activity. Note their number Ndiff.

It should be noted that Electricity Act, 200325 was a landmark legislation in India that aimed at
transforming the country's power sector. More precisely, the Act is a move towards creating a market-
based regime in the Indian power sector and consolidates the laws relating to generation, transmission,
distribution, trading and use of electricity. The Central Electricity Regulatory Commission (CERC) being
the principle regulator in the Electricity Sector took the lead in moving forward to implement the various
provisions of the new Law in letter and spirit. Keeping the spirit of the Act, the Commission has
emphasized the need to move away from the cost plus regulatory regime to a new regime of lighter
regulation. With this in mind, first ever tariff regulations were unveiled by CERC in April 200426, which
effectively regulated the prices of the power projects in the country, thus, altering the investment climate
altogether. This is because in the period prior to 2003, tariff were considered on project-to-project basis,
whereas a blanked approach was followed by CERC in its detailed procedure to compute tariff based on
capital cost, depreciation, income tax, interest rate etc. As a result, the investment environment of power
production projects in the Host Country changed significantly in 2003, and projects developed before
2003 cannot be considered similar to the proposed Project.” The aforesaid can be categorized under
“different investment climate at the time of investment decision” as per the latest version of the
“Guidelines on common practice” Version 02, EB 69 Annex 8.

According to Definitions of Different Technologies, the projects commissioned before April 2004 can be
considered as applying technologies different that the technology applied in the proposed project activity.
Such plants are numbered at 228. Now, out of the remaining 6 plants (234-228), 2 plants are of capacity
10 MW each while another 2 plants have a capacity of 15 MW each. These 4 plants can, therefore, be
categorized into small scale power plants as per their size of installation, in line with para 4 (c) (ii) of the
EB 69, Annex 8. Thus, we conclude that the total number of plants that can be accounted under different
technologies are 232 (228+4). Thus, Ndiff = 232

Step 4: Calculate factor F=1-Ndiff/Nall representing the share of plants using technology similar to the
technology used in the proposed project activity in all plants that deliver the same output or capacity as
the proposed project activity.

Now, F = 1- Ndiff/Nall
= 1- (232/234) = 0.008

24
http://www.cea.nic.in/executive_summary.html. Within this link click on years, and navigate to serial number 7 in
the table with heading "All India installed capacity of power utilities - sector & mode wise" for specific month.
25
http://www.powermin.nic.in/acts_notification/electricity_act2003/preliminary.htm
26
http://www.cercind.gov.in/Archive2004.html
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 29

and,

Nall - Ndiff = 234 - 232 =2


Therefore,

Nall - Ndiff = 2

As per the tool the proposed project activity is a “common practice” within a sector in the applicable
geographical area if both the following conditions are fulfilled:

(a) The factor F is greater than 0.2, and


(b) Nall-Ndiff is greater than 3.

For the current project activity, it comes out that:

i) F < 0.2, since it is equal to 0.008


ii) Nall-Ndiff < 3, since it is equal to 2

Notably, the project will only be considered a common practice if "both" the conditions are true. Since
both the conditions are false for the current project activity, it can be concluded that the proposed project
activity is not a common practice.

Outcome of Step 4:

In conclusion, the proposed Project is deemed to be additional according to ACM0002 and the
methodological tool – “Demonstration and assessment of additionality”, version 7.0.0.

B.6. Emission reductions:

B.6.1. Explanation of methodological choices:


>>
As per the applied methodology ACM0002, Version 13.0.0, The emission reductions attributable to the
proposed project activity during any given year are calculated as the difference between the Baseline
Emissions ( BEy), the Project Emissions( PEy) and the Leakage ( LEy), in that year.
Baseline emissions

As per section II of ACM0002, Version 13.0.0

BE y  EG PJ,y  EFgrid,CM, y

Where:
BEy = Baseline emissions in year y (tCO2/yr)
EGPJ,y = Quantity of net electricity generation that is produced and fed into the grid as a result
of the implementation of the CDM project activity in year y (MWh/yr)
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 30

EFgrid,CM,y = Combined margin CO2 emission factor for grid connected power generation in year y
calculated using the latest version of the “Tool to calculate the emission factor for an
electricity system” (tCO2/MWh)
Calculation of EGPJ,y
The calculation of EGPJ,y is different for (a) greenfield plants, (b) retrofits and replacements, and
(c) capacity additions. These cases are described next:
(a) Greenfield renewable energy power plants
If the project activity is the installation of a new grid-connected renewable power plant/unit at a site
where no renewable power plant was operated prior to the implementation of the project activity, then:

EG PJ,y  EG facility,y

Where:
EGPJ,y = Quantity of net electricity generation that is produced and fed into the grid as a result
of the implementation of the CDM project activity in year y (MWh/yr)
EGfacility,y = Quantity of net electricity generation supplied by the project plant/unit to the grid in
year y (MWh/yr)

The project activity is a Greenfield project. Hence, the baseline emissions would be computed as:

BE y  EG PJ,y  EFgrid,CM, y

Project Emissions

As per ACM002, Version 13.0.0, For most renewable power generation project activities, PEy = 0.
However, some project activities may involve project emissions that can be significant. These emissions
shall be accounted for as project emissions by using the following equation:

PEy  PEFF,y  PEGP,y  PEHP,y


Where:
PEy = Project emissions in year y (tCO2e/yr)
PEFF,y = Project emissions from fossil fuel consumption in year y (tCO2/yr)
PEGP,y = Project emissions from the operation of geothermal power plants due to the release of
non-condensable gases in year y (tCO2e/yr)
PEHP,y = Project emissions from water reservoirs of hydro power plants in year y (tCO2e/yr)

The project activity doesn’t involve emissions from any of the sources mentioned above.

Thus, PEy = 0

Leakage emissions
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 31

No leakage emissions are considered. The main emissions potentially giving rise to leakage in the
context of electric sector projects are emissions arising due to activities such as power plant construction
and upstream emissions from fossil fuel use (e.g. extraction, processing, transport). These emissions
sources are neglected.
Emission reductions
Emission reductions are calculated as follows:

ER y  BE y  PE y

Where:
ERy = Emission reductions in year y (t CO2e/yr)
BEy = Baseline emissions in year y (t CO2/yr)
PEy = Project emissions in year y (t CO2e/yr)

B.6.2. Data and parameters that are available at validation:

Data / Parameter: EFgrid,OM,y


Data unit: tCO2/MWh
Description: Simple Operating margin baseline emission factor of the NEWNE grid
Source of data used: CEA's Baseline Carbon Dioxide Emissions from Power Sector - Version 07
Value applied: 0.9842
Justification of the The simple OM emission factor (EFOM,y) is calculated as the generation
choice of data or weighted average emissions per electricity unit (tCO2/MWh) of all
description of generating sources serving the grid, not including low-operating cost and
measurement methods must-run power plants. The value is the three year average for, 2008-2009,
and procedures actually 2009-2010 and 2010-2011. Data obtained from "Baseline Carbon Dioxide
applied : Emissions from Power Sector - Version 7.0" published by the CEA.
Any comment: The value is fixed ex-ante

Data / Parameter: EFgrid,BM,y


Data unit: tCO2/MWh
Description: Build Margin baseline emission factor of the NEWNE grid
Source of data used: CEA's Baseline Carbon Dioxide Emissions from Power Sector - Version 07
Value applied: 0.8587
Justification of the
choice of data or The BM emission factor (EFBM,y) is calculated as the emissions per
description of electricity unit (tCO2/MWh) of the power plant capacity additions that
measurement comprise of 20% of the system generation for the period 2010-2011 . Data
methods and obtained from "Baseline Carbon Dioxide Emissions from Power Sector -
procedures actually Version 7.0" published by the CEA
applied :
Any comment: The value is fixed ex-ante

Data / Parameter: EFgrid,CM,y


Data unit: tCO2/MWh
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 32

Description: Combined margin baseline emission factor.


Source of data used: Calculated
Value applied: 0.9214
Justification of the
choice of data or The baseline emission factor (EFy) is calculated as the weighted average of the
description of simple OM emission factor (EFOM,y) and the BM emission factor (EFBM,y). By
measurement default, both margins have equal weights (50%). Data obtained from
methods and "Baseline Carbon Dioxide Emissions from Power Sector - Version 7.0"
procedures actually published by the CEA. The baseline emission factor is fixed ex ante for the
applied : duration of the crediting period.

Any comment: The value is fixed ex-ante

B.6.3. Ex-ante calculation of emission reductions:

The calculation has been done by assuming the parameters that, the gross head of 612.13 m which is
being utilized to generate 95320 MWh of gross energy annually. The value of gross energy generation
has been sourced from the DPR. After considering the total losses, the net available energy for export
to grid is 92460 MWh/annum.

Auxiliary consumption & Losses (Transformation +Transmission) = 3% (sourced from the DPR)

Net Electricity Generation (EGPJ,y) = 95320– (95320 * 3%)


= 92460 MWh/annum

Combined margin baseline emission factor:


Combined margin baseline emission factor (EFgrid,CM,y) is calculated as the weighted average of the
simple OM emission factor (EFOM,y) and the BM emission factor (EFBM,y). By default, both margins
have equal weights (50%). Data obtained from "Baseline Carbon Dioxide Emissions from Power Sector
- Version 7.0" published by the CEA. The baseline emission factor is fixed ex ante for the duration of
the crediting period.

EFgrid,CM,y = 0.9214 tCO2/MWh

Baseline Emission
BE y  EG PJ,y  EFgrid,CM, y

= 92460 * 0.9214
=85,193tCO2

Project emissions

PEy = 0
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 33

Leakage

No leakage emissions are considered.


Emission reductions
Emission reductions are calculated as follows:

ER y  BE y  PE y
= 85,193-0
= 85,193 tCO2

B.6.4 Summary of the ex-ante estimation of emission reductions:

Estimation Estimation of
Estimation of
of project overall
baseline Estimation of
activity emission
Year emissions leakage
emissions reductions
(tonnes of CO2 (tonnes of CO2e)
(tonnes of (tonnes of CO2
CO2 e) e)
e)
01 July 2014 to 30June 2015 0 85,193 0 85,193
01 July 2015 to 30June 2016 0 85,193 0 85,193
01 July 2016 to 30June 2017 0 85,193 0 85,193
01 July 2017 to 30June 2018 0 85,193 0 85,193
01 July 2018 to 30June 2019 0 85,193 0 85,193
01 July 2019 to 30June 2020 0 85,193 0 85,193
01 July 2020 to 30 June 2021 0 85,193 0 85,193
01 July 2021 to 30June 2022 0 85,193 0 85,193
01 July 2022 to 30June 2023 0 85,193 0 85,193
01 July 2023 to 30June 2024 0 85,193 0 85,193
Total
(tonnes of 0 8,51,930 0 8,51,930
CO2 e)

B.7. Application of the monitoring methodology and description of the monitoring plan:

B.7.1 Data and parameters monitored:

Data / Parameter: EGfacility,y


Data unit: MWh
Description: Net Electricity supplied to Grid by Project Activity
Source of data to be Onsite measurement
used:
Value of data applied 95320 MWh
for the purpose of
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 34

calculating expected
emission reductions
in section B.5
Description of The electricity will be monitored through state-of-the-art sealed and tested energy
measurement meters.
methods and The energy exported and imported by the project activity would be measured by
procedures to be 0.2s class energy meter installed at the grid interconnection point every month
applied: and would be recorded. The readings can be verified by check meter installed at
the grid inter connection point.

Net electricity supplied to the grid by the project activity = Energy exported by
project activity – Energy imported by project activity.
This will be recorded in the monthly joint meter reports.
The quantity of net electricity supplied can be cross checked with the invoices
raised for the sale of electricity.
measurement process – electronic logging of the hourly meter reading calibration
procedure – National Test House or equivalent – third party testing
Accuracy of the measurement - ±0.2%
Responsible person for measurement – Recording by electrical operator, daily log
sheet to be signed by supervisor
Measurement interval – Continuous monitoring and monthly record
QA/QC procedures to The meters used for recording of power supplied will be calibrated annually by
be applied: competent agencies. The measurement records will be cross-checked with
records of sold electricity. Records to this effect shall be maintained for future
verification..
Any comment: Monitoring Frequency :Continuous monitoring and monthly recording
Data will be archived on eelectronically. Archived data will be kept during the
crediting period plus 2 years or the last issuance of CERs for this project
activity, whichever occurs later.

B.7.2. Description of the monitoring plan:

This monitoring plan is developed in accordance with the modalities and procedures for large-scale CDM
project activities and is proposed for grid-connected hydroelectric project being implemented in Himachal
Pradesh in India. The monitoring plan, which will be implemented by the project proponent describes
about the monitoring organisation, parameters to be monitored, monitoring practices, quality assurance,
quality control procedures, data storage and archiving.

Monitoring Organisation

The Project Activity will be managed by a Board of Directors. The board will appoint a full time
General Manager who will be assisted by a Manager (Operations), in-charge of all technical aspects and
Manager (Finance) who looks after financial matters of the company. The Manager (Operations) who
will be responsible for the hydro project will have under him one Asst. Manager for the hydro project.

The authority and responsibility for registration, monitoring, measurement, reporting and reviewing of
the data rests with the Board of Directors. The Board March delegate the same to a competent person
identified for the purpose. The identified person will be the in charge of GHG monitoring activities and
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 35

prepare necessary audit reports for review by the management i.e. Board of Directors or its Committee
for review.

The identified person in charge will be assisted by a team of experienced personnel in disciplines such
as mechanical and electrical with experience in plant operation, measurements and management. The
primary responsibility of the team is to collect, measure, monitor, record and reports the information on
various data items to the person in charge and the General Manager, in accordance with the applicable
standards. Annual calibration of various instruments used in the monitoring of the data and record
keeping of the same also will be the responsibility of the team.

The responsibility of storage and archiving of information in good condition also lies with the
designated person in charge. The person in charge will undertake periodic verifications and onsite
inspections to ensure the quality of the data collected by the team.
The company may introduce an internal audit system for the GHG compliance. Internal auditing will be
carried out as per the monitoring schedule and whenever necessary.

The monitoring plan includes monitoring of energy supplied to the grid system. Emission reductions
resulted from the project activity will be calculated based on the energy supplied to the grid system in
accordance with the calculations illustrated in Section B.6.3 of the PDD. Emission reductions generated
by the project shall be monitored at regular intervals. The crediting period chosen for the project activity
is 10 years.

Monitoring equipment comprises of energy meters, which will monitor the energy fed by the plant to
Northern grid system by the proposed project. Project proponents have to install two energy meters one
is main meter and the other is check meter. Both the meters will be calibrated. Project proponent will
appoint a Designated Operational Entity (DOE) for verification of emission reductions and leakages
resulted by the project activity at regular intervals.

Also as per the requirements of the Indian DNA, 2% of the CER revenue will be spent every year on
sustainable development activities like Scholarships to students, Maintenance and up gradation of schools
in the area, Conducting medical camps, Support in operation of the public health centres, Maintenance of
bathing ghats, Conducting sport events and any other socio-development activities as requested by the
villagers.

A separate account for the revenue spent on these activities will be maintained. The revenue spent on
these activities will be reflected in the audited balance sheet of the company every year.

Leakage Monitoring

The proposed 20 MW hydroelectric project is renewable energy type and it utilizes flowing water for
power generation and it does not involve any GHG emission. No leakage is involved in the proposed
activity.

Data Recording and Storage

The net energy fed to the grid system by the project activity will be recorded by project proponents
using either of the two meters (main meter and check meter). The document which will contain all
details such as the equipment data, calibration status, previous reading, current reading, export, import,
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 36

net billable units, date and time of recording etc. This document will be used as a basic document for
monitoring and verification of the net energy exported to the grid.

The above document will be preserved for verification of emission reductions from the project, in safe
storage. Supporting documents such as receipts of payments released will also be preserved in safe
storage for later verification by an independent third party.

B.8. Date of completion of the application of the baseline study and monitoring methodology and
the name of the responsible person(s)/entity(ies):

The baseline study and monitoring methodology have been completed as on 22/03/2012

Mr. Pushpinder Singh


M/s Roura Non Conventional Energy Pvt. Ltd
Sector - 34A SCO-140-141,
Chandigarh
India.
The entity is project participant.

Mr. Ali Imran Naqvi, Ms. Shivya Singhal


Gensol Consultants Pvt. Ltd.
205-206, Sarthik-II, Opp. Rajpat Club,
S.G Highway, Ahmedabad-380015, Gujarat, India
The entity is not a project participant.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 37

SECTION C. Duration of the project activity / crediting period

C.1. Duration of the project activity:

C.1.1. Starting date of the project activity:

Project activity is still in planning stage; the expected start date is 31st January 2013.

C.1.2. Expected operational lifetime of the project activity:

40Years

C.2. Choice of the crediting period and related information:

Fixed crediting period of 10 years has been chosen.

C.2.1. Renewable crediting period:

C.2.1.1. Starting date of the first crediting period:

NA

C.2.1.2. Length of the first crediting period:

NA

C.2.2. Fixed crediting period:

C.2.2.1. Starting date:

01/07/2014 or the effective date of registration, whichever is later.

C.2.2.2. Length:

10 Years
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 38

SECTION D. Environmental impacts

D.1. Documentation on the analysis of the environmental impacts, including transboundary


impacts:

As per the prevailing regulations of the Host Party i.e. India represented by the Ministry of Environment
and Forests (MoEF), Govt. of India, EIA Notification 2006, Hydro projects of less than 25 MW capacity
do no required EIA to be conducted27.

Proposed project will not result in displacement of any population at the project site. The scheme does
not involve any submergence of land and therefore, no rehabilitation activity is needed.
There shall be no adverse impact on forest, wildlife or aquatic life due to implementation of this project.
There is neither any reserved forest area nor any wild life reserved area near to this project. Construction
of this project will thus not interfere with any reserved forest land nor reserved wild life area.

Local population will be greatly benefitted and living conditions will improve as local people will be
engaged during the construction as well as during operation and maintenance of the project activity.
From the above discussions, it is evident that the proposed project is not likely to have any significant
adverse environmental effects during execution or after commissioning.

D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:

Environment impacts are not significant due the project activity and also as stated above as per the EIA
Notification 2006; Hydro projects with less than 25 MW capacity need not conduct EIA. However the
project proponent has obtained the clearances from the following departments:
 District Forest Officer (MOEF);
 Director Fisheries;
 Irrigation and Public Health;
 Gram Panchayat;
 Techno-Economical Viability;
 State Pollution Control Board.

27
http://envfor.nic.in/legis/eia/so1533.pdf
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 39

SECTION E. Stakeholders’ comments

E.1. Brief description how comments by local stakeholders have been invited and compiled:

In order to get the views of the local stakeholders and respond to their concerns (if any), a local
stakeholder meeting was organized by the project proponent. A Notice in the local newspaper was given
and personal invitation letters were given to some of the identified Local Stakeholders. The meeting was
held on 28/09/2011 at the Project site.

Stakeholder consultation procedure was done as below:

 Description of the Hydro project and the associated benefits by project proponent.
 Question and Answer session between the project proponent and the stakeholders
 Vote of thanks
 Signing of the attendance sheet

Following people attended the stakeholder consultation meet:

 Project Proponent
 Consultant
 Representative of Irrigation and Public Health Department
 Local people living near and around the project area.

Consultant welcomed all the stakeholders and briefed them about the agenda for the meeting.

The Project Proponent made a presentation on the phenomenon of CDM in the local language (Hindi). He
gave the non technical description of the project activity. The impacts of the project activity on the
environment and its contribution to the improvement in country’s power situation. He also explained how
the GHG emissions would have occurred in the absence of the project activity.

Gram Pradhan presented his view on the project and supported such type of activities.

The Project Proponent invited the stakeholders to come up with their queries or concerns that they may
have.

E.2. Summary of the comments received:

Positive feedback for the project in the form of letters from the villagers and the local governing bodies
were received. The stakeholders were unanimously in favor of the project and had the opinion that it
would bring prosperity to the area.
The specific concerns expressed by the participants are summarized below along with
clarifications provided on such concerns:

Stakeholder Name and


Answer / clarifications
concerns / question
Mr. Roop Kishor The natural flow of the river is used to generate electricity. This
kind of project activity is built up on rivers which are having a
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 40

consistent and steady flow of water.


Run of river hydro projects do not require impoundment of water
like large reservoir hydro project. The water from the run of
river water is diverted from a river, and sent into a pipe called a
What is a run-off-the-river system? penstock. The penstock feeds the water downhill to the power
station's turbines. The natural force of gravity creates the energy
required to spin the turbines that in turn generate electricity. The
water leaves the generating station and is returned to the river
without altering the existing flow or water levels.
Mr. Rai Bahadur
What is the step towards the The project proponent will plant more trees for every tree cut
biodiversity conservation which will down in construction and is doing the same activity on
be damaged due to the project continuation basis..
activity?
Mr. Medhu Ram Project has no impact on the irrigation in its vicinity as it utilizes
Will this project affect irrigation in only the energy of flowing water and is released back to the river
its vicinity?
Mr. Jang Bahadur Villagers will be given employment during the construction
Will villagers get any financial help phase of the project based on their skills.

The comments received from the local stake holders for the project are:
a) Employment opportunities for the local people will increase.
b) Infrastructure facilities of the locality will improve.
c) As this is a clean source of energy, no pollution is involved due to the project activity.
d) The project activity leads to saving in the fossil fuels.

E.3. Report on how due account was taken of any comments received:

No adverse comments were received. Only minor queries were raised which were satisfactorily
answered.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 41

Annex 1

CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY

Organization: M/s Roura Non Conventional Energy Pvt. Ltd.


Street/P.O.Box:
Building: SCO-140-141, Sec34A
City: Chandigarh
State/Region: Chandigarh
Postcode/ZIP: 160022
Country: India
Telephone: +91-172-5059999
FAX: +91-172-2602863
E-Mail: pushpindersingh68@gmail.com
URL:
Represented by:
Title:
Salutation: Mr.
Last name:
Middle name: Singh
First name: Pushpinder
Department: Hydel
Mobile: +91-9779450009
Direct FAX: +91-172-2602863
Direct tel:
Personal e-mail: pushpindersingh68@gmail.com
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 42

Annex 2

INFORMATION REGARDING PUBLIC FUNDING

The project does involve any diversion of Official Development Assistance (ODA) to the project
activity and does not involve any other public funding.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 43

Annex 3

BASELINE INFORMATION

As Explained in Section B.4


PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 44

Annex 4

MONITORING INFORMATION

As Explained in Section B.7.2.

-----
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 45

Appendix-1

Extracts from CEA Baseline Database Version 7


(http://www.cea.nic.in/reports/planning/cdm_co2/cdm_co2.htm)

These 234 hydro power plants have been filtered from the database on the basis of capacity range of 10-
30 MW. This data covers capacity additions as on March 31, 2011.

CAPAC
ITY MW
UNIT_N DT_ REGI
S_NO NAME AS ON STATE SECTOR SYSTEM TYPE
O COMM ON
31/03/2
011

27 KOSI 0 20 CR BIHAR STATE BSEB HYDRO


30 E.G. CANAL 0 15 CR BIHAR STATE BSEB HYDRO
33 MAITHON 1 28-Oct-57 20 CR BIHAR CENTER DVC HYDRO
33 MAITHON 2 21-May-58 20 CR BIHAR CENTER DVC HYDRO
33 MAITHON 3 12-Dec-58 23.2 CR BIHAR CENTER DVC HYDRO
36 HIRAKUD-I 3 18-Dec-56 24 CR ORISSA STATE OHPC HYDRO
36 HIRAKUD-I 4 13-May-57 24 CR ORISSA STATE OHPC HYDRO
36 HIRAKUD-II 8 15-Jul-62 24 CR ORISSA STATE OHPC HYDRO
36 HIRAKUD-II 9 26-Nov-62 24 CR ORISSA STATE OHPC HYDRO
36 HIRAKUD-II 10 1-Feb-64 24 CR ORISSA STATE OHPC HYDRO
WEST
41 RAMMAM 1 5-Sep-95 12.5 CR BENGAL STATE WBSEB HYDRO
WEST
41 RAMMAM 2 28-Sep-95 12.5 CR BENGAL STATE WBSEB HYDRO
WEST
41 RAMMAM 3 13-Jan-96 12.5 CR BENGAL STATE WBSEB HYDRO
WEST
41 RAMMAM 4 28-Jan-96 12.5 CR BENGAL STATE WBSEB HYDRO
LOWER
43 LAGYAP 0 12 CR SIKKIM STATE SIKKIM HYDRO
46 RANGIT-III 1 5-Feb-00 20 CR SIKKIM CENTER NHPC HYDRO
46 RANGIT-III 2 5-Feb-00 20 CR SIKKIM CENTER NHPC HYDRO
46 RANGIT-III 3 5-Feb-00 20 CR SIKKIM CENTER NHPC HYDRO
KYREDEMK MEGHALAY
63 ULAI 1 26-Jan-79 30 CR A STATE MEGEB HYDRO
KYREDEMK MEGHALAY
63 ULAI 2 30-Mar-79 30 CR A STATE MEGEB HYDRO
MEGHALAY
64 UMIAM IV 7 16-Sep-92 30 CR A STATE MEGEB HYDRO
MEGHALAY
64 UMIAM IV 8 11-Aug-92 30 CR A STATE MEGEB HYDRO
MEGHALAY
65 UMTRU 0 11.2 CR A STATE MEGEB HYDRO
MEGHALAY
66 KHANDONG 1 7-Mar-84 25 CR A CENTER NEEPCO HYDRO
MEGHALAY
66 KHANDONG 2 2-May-84 25 CR A CENTER NEEPCO HYDRO
KOPILI ST.-
67 II 5 31-Dec-03 25 CR ASSAM CENTER NEEPCO HYDRO
68 DOYANG 1 8-Jul-00 25 CR NAGALAND CENTER NEEPCO HYDRO
68 DOYANG 2 5-Jul-00 25 CR NAGALAND CENTER NEEPCO HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 46

68 DOYANG 3 29-Jun-00 25 CR NAGALAND CENTER NEEPCO HYDRO


TRIPUR
70 GUMTI 0 15 CR TSECL STATE A HYDRO
NAGAL
71 LIKIM RO 0 24 CR NAGALAND STATE AND HYDRO
105 GANGUWAL 1 23-Jan-62 29.25 CR PUNJAB CENTER BBMB HYDRO
105 GANGUWAL 2 2-Jan-55 24.2 CR PUNJAB CENTER BBMB HYDRO
105 GANGUWAL 3 2-Jan-55 24.2 CR PUNJAB CENTER BBMB HYDRO
106 KOTLA 1 14-Jul-61 29.25 CR PUNJAB CENTER BBMB HYDRO
106 KOTLA 2 23-May-56 24.2 CR PUNJAB CENTER BBMB HYDRO
106 KOTLA 3 27-Aug-56 24.2 CR PUNJAB CENTER BBMB HYDRO
118 BASSI 1 13-Sep-70 15 CR HIMACHAL STATE HPSEB HYDRO
118 BASSI 2 24-Dec-70 15 CR HIMACHAL STATE HPSEB HYDRO
118 BASSI 3 15-Jul-71 15 CR HIMACHAL STATE HPSEB HYDRO
118 BASSI 4 3-Feb-81 15 CR HIMACHAL STATE HPSEB HYDRO
119 GIRI BATA 1 16-Apr-78 30 CR HIMACHAL STATE HPSEB HYDRO
119 GIRI BATA 2 30-Jun-78 30 CR HIMACHAL STATE HPSEB HYDRO
120 GHANVI 1 7-Dec-00 11.25 CR HIMACHAL STATE HPSEB HYDRO
120 GHANVI 2 30-Jul-00 11.25 CR HIMACHAL STATE HPSEB HYDRO
121 ANDHRA 0 16.95 CR HIMACHAL STATE HPSEB HYDRO
122 BANER 0 12 CR HIMACHAL STATE HPSEB HYDRO
123 GAJ 0 10.5 CR HIMACHAL STATE HPSEB HYDRO
UPPER JAMMU &
129 SINDH-I 1 20-Nov-73 11.3 CR KASHMIR STATE JKEB HYDRO
UPPER JAMMU &
129 SINDH-I 2 9-Jul-74 11.3 CR KASHMIR STATE JKEB HYDRO
GANDHARB JAMMU &
130 AL 0 15 CR KASHMIR STATE JKEB HYDRO
136 SHANAN 1 10-Mar-32 15 CR PUNJAB STATE PSEB HYDRO
136 SHANAN 2 10-Mar-32 15 CR PUNJAB STATE PSEB HYDRO
136 SHANAN 3 10-Mar-32 15 CR PUNJAB STATE PSEB HYDRO
136 SHANAN 4 10-Mar-32 15 CR PUNJAB STATE PSEB HYDRO
U.B.D.C.
137 ST.-I PH-1 1 30-Aug-71 15 CR PUNJAB STATE PSEB HYDRO
U.B.D.C.
137 ST.-I PH-2 2 24-May-72 15 CR PUNJAB STATE PSEB HYDRO
U.B.D.C.
137 ST.-I PH-3 3 12-Apr-73 15 CR PUNJAB STATE PSEB HYDRO
U.B.D.C.ST-
137 II PH-1 4 6-Jul-89 15.45 CR PUNJAB STATE PSEB HYDRO
U.B.D.C.ST-
137 II PH-2 5 6-Jul-91 15.45 CR PUNJAB STATE PSEB HYDRO
U.B.D.C.ST-
137 II PH-3 6 29-Dec-91 15.45 CR PUNJAB STATE PSEB HYDRO
138 MUKERIAN-I 1 20-Oct-83 15 CR PUNJAB STATE PSEB HYDRO
138 MUKERIAN-I 2 14-Oct-83 15 CR PUNJAB STATE PSEB HYDRO
138 MUKERIAN-I 3 26-Nov-83 15 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 II 4 5-May-88 15 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 II 5 3-Jun-88 15 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 II 6 28-Feb-89 15 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 III 7 28-Feb-89 19.5 CR PUNJAB STATE PSEB HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 47

MUKERIAN-
138 III 8 24-Feb-89 19.5 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 III 9 11-Mar-89 19.5 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 IV 10 2-Mar-89 19.5 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 IV 11 8-Mar-89 19.5 CR PUNJAB STATE PSEB HYDRO
MUKERIAN-
138 IV 12 25-Mar-89 19.5 CR PUNJAB STATE PSEB HYDRO
MAHI
143 BAJAJ-I 1 22-Jan-86 25 CR RAJASTHAN STATE RRVUNL HYDRO
MAHI
143 BAJAJ-I 2 6-Feb-86 25 CR RAJASTHAN STATE RRVUNL HYDRO
UTTAR
149 MATATILLA 1 28-Feb-65 10.2 CR PRADESH STATE UPHPC HYDRO
UTTAR
149 MATATILLA 2 30-Jun-65 10.2 CR PRADESH STATE UPHPC HYDRO
UTTAR
149 MATATILLA 3 30-Sep-65 10.2 CR PRADESH STATE UPHPC HYDRO
UTTAR
150 KHARA 1 29-Dec-92 24 CR PRADESH STATE UPHPC HYDRO
UTTAR
150 KHARA 2 29-Dec-92 24 CR PRADESH STATE UPHPC HYDRO
UTTAR
150 KHARA 3 29-Dec-92 24 CR PRADESH STATE UPHPC HYDRO
UTTARAKH
153 KHODRI 1 29-Jan-84 30 CR AND STATE UJVNL HYDRO
UTTARAKH
153 KHODRI 2 9-Feb-84 30 CR AND STATE UJVNL HYDRO
UTTARAKH
153 KHODRI 3 30-Mar-84 30 CR AND STATE UJVNL HYDRO
UTTARAKH
153 KHODRI 4 28-Feb-84 30 CR AND STATE UJVNL HYDRO
UTTARAKH
154 DHAKRANI 1 15-Nov-65 11.25 CR AND STATE UJVNL HYDRO
UTTARAKH
154 DHAKRANI 2 31-Mar-66 11.25 CR AND STATE UJVNL HYDRO
UTTARAKH
154 DHAKRANI 3 10-Jan-70 11.25 CR AND STATE UJVNL HYDRO
UTTARAKH
155 DHALIPUR 1 10-Dec-65 17 CR AND STATE UJVNL HYDRO
UTTARAKH
155 DHALIPUR 2 25-Mar-66 17 CR AND STATE UJVNL HYDRO
UTTARAKH
155 DHALIPUR 3 31-Mar-70 17 CR AND STATE UJVNL HYDRO
UTTARAKH
156 KULHAL 1 11-Apr-75 10 CR AND STATE UJVNL HYDRO
UTTARAKH
156 KULHAL 2 26-Sep-75 10 CR AND STATE UJVNL HYDRO
UTTARAKH
156 KULHAL 3 24-Dec-75 10 CR AND STATE UJVNL HYDRO
MANERI UTTARAKH
157 BHALI 1 14-Dec-84 30 CR AND STATE UJVNL HYDRO
MANERI UTTARAKH
157 BHALI 2 19-Nov-84 30 CR AND STATE UJVNL HYDRO
MANERI UTTARAKH
157 BHALI 3 30-Oct-84 30 CR AND STATE UJVNL HYDRO
UTTARAKH
159 PATHRI 0 20 CR AND STATE UJVNL HYDRO
UTTARAKH
162 KHATIMA 1 30-Apr-55 13.8 CR AND STATE UJVNL HYDRO
UTTARAKH
162 KHATIMA 2 2-Apr-56 13.8 CR AND STATE UJVNL HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 48

UTTARAKH
162 KHATIMA 3 3-Aug-56 13.8 CR AND STATE UJVNL HYDRO
GANDHI MADHYA
218 SAGAR 1 19-Nov-60 23 CR PRADESH STATE MPGPCL HYDRO
GANDHI MADHYA
218 SAGAR 2 19-Nov-60 23 CR PRADESH STATE MPGPCL HYDRO
GANDHI MADHYA
218 SAGAR 3 19-Nov-60 23 CR PRADESH STATE MPGPCL HYDRO
GANDHI MADHYA
218 SAGAR 4 15-Aug-63 23 CR PRADESH STATE MPGPCL HYDRO
GANDHI MADHYA
218 SAGAR 5 9-Nov-66 23 CR PRADESH STATE MPGPCL HYDRO
BANSAGAR MADHYA
222 (II) 1 18-Feb-02 15 CR PRADESH STATE MPGPCL HYDRO
BANSAGAR MADHYA
222 (II) 2 1-Sep-02 15 CR PRADESH STATE MPGPCL HYDRO
BANSAGAR MADHYA
223 (III) 1 26-Nov-00 20 CR PRADESH STATE MPGPCL HYDRO
BANSAGAR MADHYA
223 (III) 2 25-Aug-01 20 CR PRADESH STATE MPGPCL HYDRO
BANSAGAR MADHYA
223 (III) 3 2-Sep-02 20 CR PRADESH STATE MPGPCL HYDRO
BIRSINGHP MADHYA
224 UR 1 1-Nov-91 20 CR PRADESH STATE MPGPCL HYDRO
RAJGHAT MADHYA
225 (MP) 1 15-Oct-99 15 CR PRADESH STATE MPGPCL HYDRO
RAJGHAT MADHYA
225 (MP) 2 29-Sep-99 15 CR PRADESH STATE MPGPCL HYDRO
RAJGHAT MADHYA
225 (MP) 3 3-Nov-99 15 CR PRADESH STATE MPGPCL HYDRO
MADHYA
226 TAWA 0 13.5 CR PRADESH PVT HEGL HYDRO
MAHARASH MAHAG
228 KOYNA DPH 13 3-Oct-80 18 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
228 KOYNA DPH 14 16-Mar-81 18 CR TRA STATE ENCO HYDRO
KHADAVAS MAHARASH MAHAG
232 LA I&II 0 16 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
233 ELDARI 0 22.5 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
235 BHATGARH 1 2-Aug-77 16 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
236 PAITHON 1 20-Nov-84 12 CR TRA STATE ENCO HYDRO
BHANDARD MAHARASH MAHAG
237 HARA 1 27-Mar-86 10 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
238 PAWANA 1 11-Jun-88 10 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
240 BHATSA 1 28-Sep-91 15 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
242 UJJAINI 1 2-May-94 12 CR TRA STATE ENCO HYDRO
MAHARASH MAHAG
246 WARNA 0 16 CR TRA STATE ENCO HYDRO
DUDH MAHARASH MAHAG
247 GANGA 1 27-Feb-00 12 CR TRA STATE ENCO HYDRO
DUDH MAHARASH MAHAG
247 GANGA 2 31-Mar-00 12 CR TRA STATE ENCO HYDRO
MAHARASH TATA
248 BHIRA 1 1-Jan-27 25 CR TRA PVT MAH. HYDRO
MAHARASH TATA
248 BHIRA 2 1-Jan-27 25 CR TRA PVT MAH. HYDRO
MAHARASH TATA
248 BHIRA 3 1-Feb-27 25 CR TRA PVT MAH. HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 49

MAHARASH TATA
248 BHIRA 4 1-Mar-27 25 CR TRA PVT MAH. HYDRO
MAHARASH TATA
248 BHIRA 5 1-May-27 25 CR TRA PVT MAH. HYDRO
MAHARASH TATA
248 BHIRA 7 31-Jan-49 25 CR TRA PVT MAH. HYDRO
MAHARASH TATA
249 BHIVPURI 1 31-Mar-98 24 CR TRA PVT MAH. HYDRO
MAHARASH TATA
249 BHIVPURI 2 29-Sep-98 24 CR TRA PVT MAH. HYDRO
MAHARASH TATA
249 BHIVPURI 3 24-Sep-99 24 CR TRA PVT MAH. HYDRO
MAHARASH TATA
250 KHOPOLI 1 13-Feb-02 24 CR TRA PVT MAH. HYDRO
MAHARASH TATA
250 KHOPOLI 2 25-Mar-03 24 CR TRA PVT MAH. HYDRO
MAHARASH TATA
250 KHOPOLI 3 2-Mar-01 24 CR TRA PVT MAH. HYDRO
MADHIKHE MADHYA
252 DA 1 28-Aug-06 20 CR PRADESH STATE MPGCL HYDRO
MADHIKHE MADHYA
252 DA 2 9-Sep-06 20 CR PRADESH STATE MPGCL HYDRO
BANSAGAR MADHYA
253 (IV) 1 20-Aug-06 10 CR PRADESH STATE MPGPCL HYDRO
BANSAGAR MADHYA
253 (IV) 2 30-Aug-06 10 CR PRADESH STATE MPGPCL HYDRO
ANDHRA APGENC
47 MACHKUND 1 14-Aug-55 17 SR PRADESH STATE O HYDRO
ANDHRA APGENC
47 MACHKUND 2 12-Dec-55 17 SR PRADESH STATE O HYDRO
ANDHRA APGENC
47 MACHKUND 3 26-Jun-56 17 SR PRADESH STATE O HYDRO
ANDHRA APGENC
47 MACHKUND 4 15-Jan-59 21.25 SR PRADESH STATE O HYDRO
ANDHRA APGENC
47 MACHKUND 5 7-Aug-59 21.25 SR PRADESH STATE O HYDRO
ANDHRA APGENC
47 MACHKUND 6 8-Aug-59 21.25 SR PRADESH STATE O HYDRO
N_SAGAR ANDHRA APGENC
51 RBC 1 24-Feb-83 30 SR PRADESH STATE O HYDRO
N_SAGAR ANDHRA APGENC
51 RBC 2 20-Sep-83 30 SR PRADESH STATE O HYDRO
N_SAGAR ANDHRA APGENC
51 RBC EXTN. 3 10-Sep-90 30 SR PRADESH STATE O HYDRO
N_SAGAR ANDHRA APGENC
52 LBC 1 27-Sep-92 30 SR PRADESH STATE O HYDRO
N_SAGAR ANDHRA APGENC
52 LBC 2 27-Mar-92 30 SR PRADESH STATE O HYDRO
ANDHRA APGENC
53 DONKARAYI 1 4-Oct-83 25 SR PRADESH STATE O HYDRO
POCHAMPA ANDHRA APGEN
56 D 0 27 SR PRADESH STATE CO HYDRO
NIZAM ANDHRA APGEN
57 SAGAR 0 10 SR PRADESH STATE CO HYDRO
PENNA ANDHRA APGENC
58 AHOBELAM 1 10-Jan-94 10 SR PRADESH STATE O HYDRO
PENNA ANDHRA APGENC
58 AHOBELAM 2 23-Jan-94 10 SR PRADESH STATE O HYDRO
ANDHRA APGEN
59 SINGUR 0 15 SR PRADESH STATE CO HYDRO
LIGANAMAK KARNATAK
64 KI 1 8-Jul-79 27.5 SR A STATE KPCL HYDRO
LIGANAMAK KARNATAK
64 KI 2 15-Mar-80 27.5 SR A STATE KPCL HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 50

KARNATAK
66 BHADRA (L) 2 21-Jun-63 12 SR A STATE KPCL HYDRO
KARNATAK
66 BHADRA (L) 3 9-Apr-63 12 SR A STATE KPCL HYDRO
GHAT KARNATAK
67 PRABHA 1 8-Oct-92 16 SR A STATE KPCL HYDRO
GHAT KARNATAK
67 PRABHA 2 16-Dec-92 16 SR A STATE KPCL HYDRO
ALMATTI KARNATAK
73 DAM 1 26-Mar-04 15 SR A STATE KPCL HYDRO
KARNATAK
74 JOG 1 15-May-01 13.2 SR A STATE KEB HYDRO
KARNATAK
74 JOG 2 15-Dec-49 13.2 SR A STATE KEB HYDRO
KARNATAK
74 JOG 3 19-Dec-49 13.2 SR A STATE KEB HYDRO
KARNATAK
74 JOG 4 20-Oct-50 13.2 SR A STATE KEB HYDRO
KARNATAK
74 JOG 5 15-Jun-52 21.6 SR A STATE KEB HYDRO
KARNATAK
74 JOG 6 17-Jul-52 21.6 SR A STATE KEB HYDRO
KARNATAK
74 JOG 7 16-Sep-52 21.6 SR A STATE KEB HYDRO
KARNATAK
74 JOG 8 30-Oct-02 21.6 SR A STATE KEB HYDRO
SHIMSAPU KARNATAK
76 RA 0 17.2 SR A STATE VVNL HYDRO
MUNIRABA KARNATAK
77 D 0 28.3 SR A STATE VVNL HYDRO
MUNIRABA KARNATAK
77 D 3 27-Nov-65 10.3 SR A STATE KEB HYDRO
KARNATAK BHORU
78 SHIVAPURA 0 18 SR A PVT KA HYDRO
NARAYANP KARNATAK MYSOR
81 UR 0 11.6 SR A PVT E PC HYDRO
82 KUTTIADI 1 11-Sep-72 25 SR KERALA STATE KSEB HYDRO
82 KUTTIADI 2 1-Nov-72 25 SR KERALA STATE KSEB HYDRO
82 KUTTIADI 3 28-Nov-72 25 SR KERALA STATE KSEB HYDRO
87 KAKKAD 1 13-Oct-99 25 SR KERALA STATE KSEB HYDRO
87 KAKKAD 2 22-Jul-99 25 SR KERALA STATE KSEB HYDRO
88 SHOLAYAR 1 9-May-56 18 SR KERALA STATE KSEB HYDRO
88 SHOLAYAR 2 26-Jan-68 18 SR KERALA STATE KSEB HYDRO
88 SHOLAYAR 3 14-May-68 18 SR KERALA STATE KSEB HYDRO
89 SENGULAM 1 30-May-54 12 SR KERALA STATE KSEB HYDRO
89 SENGULAM 2 26-Jul-54 12 SR KERALA STATE KSEB HYDRO
89 SENGULAM 3 5-Dec-01 12 SR KERALA STATE KSEB HYDRO
89 SENGULAM 4 30-Nov-01 12 SR KERALA STATE KSEB HYDRO
NARIMANG
90 LAM 1 27-Jan-61 15 SR KERALA STATE KSEB HYDRO
NARIMANG
90 LAM 2 9-Apr-61 15 SR KERALA STATE KSEB HYDRO
NARIMANG
90 LAM 3 11-May-63 15 SR KERALA STATE KSEB HYDRO
PORINGALK
93 UTTU L 1 20-Mar-99 16 SR KERALA STATE KSEB HYDRO
94 PANNIAR 1 19-Dec-63 15 SR KERALA STATE KSEB HYDRO
94 PANNIAR 2 20-Nov-01 15 SR KERALA STATE KSEB HYDRO
95 KALLADA 0 15 SR KERALA STATE KSEB HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 51

Carboru
98 MANIYAR 0 12 SR KERALA PVT ndum HYDRO
KUTHUNGA
99 L 0 21 SR KERALA PVT INDSIL HYDRO
TAMIL
100 KUNDAH-I 1 8-Jul-60 20 SR NADU STATE TNEB HYDRO
TAMIL
100 KUNDAH-I 2 21-Jul-60 20 SR NADU STATE TNEB HYDRO
TAMIL
100 KUNDAH-I 3 1-Apr-64 20 SR NADU STATE TNEB HYDRO
TAMIL
100 KUNDAH-V 14 30-Oct-64 20 SR NADU STATE TNEB HYDRO
TAMIL
100 KUNDAH-V 15 28-Sep-88 20 SR NADU STATE TNEB HYDRO
PARSEN_S TAMIL
101 VALLE 1 29-Mar-00 30 SR NADU STATE TNEB HYDRO
METTUR TAMIL
102 DAM 1 13-Jun-37 10 SR NADU STATE TNEB HYDRO
METTUR TAMIL
102 DAM 2 21-Aug-37 10 SR NADU STATE TNEB HYDRO
METTUR TAMIL
102 DAM 3 21-Jan-38 10 SR NADU STATE TNEB HYDRO
METTUR TAMIL
102 DAM 4 28-Oct-46 10 SR NADU STATE TNEB HYDRO
SHOLAYAR- TAMIL
105 II 3 29-Mar-71 25 SR NADU STATE TNEB HYDRO
TAMIL
106 PYKARA 4 28-Aug-39 11 SR NADU STATE TNEB HYDRO
TAMIL
106 PYKARA 5 30-May-54 14 SR NADU STATE TNEB HYDRO
TAMIL
106 PYKARA 6 11-Jun-54 14 SR NADU STATE TNEB HYDRO
SARKARPA TAMIL
108 THY 1 14-Aug-66 30 SR NADU STATE TNEB HYDRO
PAPANASA TAMIL
109 M 0 28 SR NADU STATE TNEB HYDRO
TAMIL
110 MOYAR 1 10-Apr-52 12 SR NADU STATE TNEB HYDRO
TAMIL
110 MOYAR 2 19-Sep-52 12 SR NADU STATE TNEB HYDRO
TAMIL
110 MOYAR 3 6-Jan-53 12 SR NADU STATE TNEB HYDRO
TAMIL
112 SERVALAR 1 23-Mar-86 20 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-1 1 11-Aug-88 15 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-1 2 12-Aug-88 15 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-2 3 26-Aug-88 15 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-2 4 27-Aug-88 15 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-3 5 4-Jan-88 15 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-3 6 30-Sep-87 15 SR NADU STATE TNEB HYDRO
LOWER
METTUR TAMIL
113 PH-4 7 18-Sep-89 15 SR NADU STATE TNEB HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 52

LOWER
METTUR TAMIL
113 PH-4 8 28-Dec-88 15 SR NADU STATE TNEB HYDRO
VAIGAI TAMIL
114 DAM 0 13.5 SR NADU STATE TNEB HYDRO
BHAWANI
KATTALAI TAMIL
119 BARRAGE 1 1-Aug-06 15 SR NADU STATE TNEB HYDRO
BHAWANI
KATTALAI TAMIL
119 BARRAGE 2 22-Sep-06 15 SR NADU STATE TNEB HYDRO
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 53

Appendix-2

Commitment of sharing 2% of the Certified Emission Reduction (CERs) for the development of the local
communities (Exclusively for large scale projects)

Basic purpose of this commitment is to share 2% of the CERs revenue to support the local communities
in achieving their developmental goal. It may be done in different ways:

 Project Proponent (PP) may directly share the amount with respective village Panchayats and
monitor their developmental activities;
 PP may develop a plan and implement it for the betterment of the villages;
 PP may involve villagers and plan and implement it jointly; or
 PP may decide other means and ways;

For the public knowledge about its support, PP should discuss it with the villagers and inform details to
the Village Panchayat, block and tehsil office and it should be part of discussion during the stakeholder
consultation.

a. Project details

Project Title 20 MW Roura- II Hydro Electric Project by Roura Non Conventional Energy
Pvt Ltd

Project Proponent Roura Non Conventional Energy Pvt. Ltd.


Project Location Village: Yula, District: Kinnaur, State: Himachal Pradesh
Latitude: 31° 32’ 23” North, Longitude 78° 08’ 22” East

Project ID Project Type Project Size CERs generation per year


872/11/2011 Large Scale Project 20MW 85,202 tCO2

b). Estimation of 2% of CERs available

Project Life (in years) 40 years


Estimation of 2% of CERs per year 1704.04 tCO2
Approximate market value of CERs (INR) 816 Rs./CER
Approx amount of money available per year (INR) 1390496.64

c). Identification of villages surrounding the project/installations and key developmental issues faced by
them

Identified Villages Total Population Key issues for development


Yula 575 Better sanitation and welfare, medical aids
Meeru 875 Proper fooding, clothing, shelter and education

d). Plan for sharing 2% of the CERs revenues (village wise)


PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 54

List the activities/support PP like provide to the identified villages


S No Village Name Activities/Support proposed over the Approximate amount in INR
project life time
1 Yula Medical Facilities to workers/Farmers; 695248
Assisting school education & providing
2 Meeru funds to school; Providing fooding, clothing
and shelter to workers/farmers,
infrastructure development like roads, 695248
drinking water facilities and common
lavatories

e). Implementation of the plan (provide details as applicable)

How it will be implemented Who will implement the plan


PP Villagers Villagers and PP Others

If PP implements the activities


of its own, it has to be
discussed with the villagers a NA
local contact of PP has to be
established
If Money is given to village
Panchayats for developing it by
Funds will be disbursed to the Village Panchayat with the
villagers. PP has to discuss the
responsibility of their further diversion to the villagers and/or for
money transfer mechanism
concerned local development activities. Village Panchayat will
with the Villagers and have a
implement the local development plan.
local contact office for the
purpose.
If activities are done by
villagers and pp jointly, how
activities will undertaken and
NA
how money will be channelised
for the activities and what will
be local contact for PP
If others arrangements are
preferred by PP, what will be
the arrangement and how
money will be chanelised to the NA
villages and how villagers will
be informed

f) Monitoring arrangement
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 55

In general, PP has to develop a monitoring committee involving villagers, representative of PP and a local
government official /reputed person of the area. Monitoring parameters and frequency has to be defined.

Monitoring Committee
Gram Pradhan, Himurja Project Officer & Director of Roura Non
Conventional Energy Pvt. Ltd. (RNCEPL)
Monitoring Parameters RNCEPL Management will undertake formal discussions with the
Gram Pradhan & Himurja Project Officer about the area that are more
concern to the local population. On the basis of the actual price and
exchange rate, RNCEPL will allocate 2 % of the revenue for
sustainable development activities in the local areas through the annual
review process.
Monitoring Frequency As part of the annual review, RNCEPL management commits that an
official will be appointed to verify the activities towards sustainable
development and to ensure that the activities are undertaken and
concluded in a timely manner each year.

e) Making the Implementation plan public

Implementation plan including local contact, money transfer mechanism and monitoring Committee has
to be finalised and discussed with the villagers. Once it is agreed it has to be submitted to Village
Panchayts/ Block office/ Tehsil Office and District Collector Office.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 56

Reporting Template

Project Name: 20 MW Roura- II Hydro Electric Project by Roura Non Conventional Energy Pvt Ltd
Project Location: Village: Yula, District: Kinnaur, State: Himachal Pradesh
Latitude: 31° 32’ 23” North, Longitude 78° 08’ 22” East

Commitment of the Project Proponent

The project proponent Roura Non Conventional Energy Pvt. Ltd. has committed to share 2%
(1390496 approximate amount in INR per year) of its Certified Emission Reduction (CERs) in connection
with his/her CDM project based on the issuance and transaction of the CERs.

2. The committed amount of money will be utilized for addressing the identified issues in the
following villages:

Identified Villages Total Population Key issues for development


Yula 575 Medical Aid, diseases and other health
Meeru 875 problems
Higher illiteracy level
Civilization, absence of enrich
traditional values

3. Accordingly, the project proponent has identified the activities/ support for the following villages:

S No Village Name Activities/Support proposed over the Approximate amount


project life time in INR
1 Yula Medical Facilities to workers/Farmers 695248
2 Meeru Assisting school education & 695248
providing funds to school
Imparting Cultural Activities to the
workers/farmers

4. The implementation details along with local contact and money transfer mechanism are as
follows:

RNCEPL Management will undertake formal discussions with the Gram Pradhan & Himurja Project
Officer about the area that are more concern to the local population. Accordingly, funds will be
disbursed to the Village Panchayat for area development
Local contact of project proponent Money transfer mechanism

Mr. S D Kamath Funds will be disbursed to Village Panchayat

5. Details of monitoring arrangement


PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03

CDM – Executive Board

page 57

Monitoring Committee
Gram Pradhan, Himurja Project Officer & Director of Roura Non
Conventional Energy Pvt. Ltd. (RNCEPL)
Monitoring Parameters RNCEPL Management will undertake formal discussions with the
Gram Pradhan & Himurja Project Officer about the area that are more
concern to the local population. On the basis of the actual price and
exchange rate, RNCEPL will allocate 2 % of the revenue for
sustainable development activities in the local areas through the annual
review process.
Monitoring Frequency As part of the annual review, RNCEPL management commits that an
official will be appointed to verify the activities towards sustainable
development and to ensure that the activities are undertaken and
concluded in a timely manner each year.

Date: 12/07/2012
Place: Chandigarh
Signature of the project proponent
Mr. Pushpinder Singh
M/s Roura Non Conventional Energy Pvt. Ltd.

Potrebbero piacerti anche