Abstract This document presents the Market Network Model to be used in the Philippine
Wholesale Electricity Spot Market and associated information as well as the
details on the development of the model.
Document Approval
Author: PEMC Market Operations Group Date: 4/18/2005
06/01/2006
11/14/2006
06/21/06
11/17/06
Line 4.
Reconfiguration of the Tapping of Trans
Asia S/S to the 150 MVA Angat – San Jose
115 kV Line 1.
Update on the parameters of 300 MVA
Dolores Transformer 1.
Updates on Appendices:
Appendix 3a - Market Network Model Resources
Summary
Additional station to reflect the reconfiguration
in the model of the tapping of Trans Asia S/S to
the Angat – San Jose Line 1.
MVA
b. Replacement of230/115 kV San
Jose transformer T2 from 300 MVa to 100
MVA.
Related Document
Document ID Document Title
WESM Rules
Distribution List
MO Subcommittee members
SO Subcommittee members
Table of Contents
1.0 Introduction ...............................................................................................20
1.1 About this Document ............................................................................20
1.2 Purpose ..................................................................................................20
1.3 Scope ......................................................................................................20
1.4 Intended Audience ................................................................................20
1.5 Background ............................................................................................20
2.0 Definition of Terms ...................................................................................22
3.0 Responsibilities ........................................................................................23
4.0 EMS – MMS Data Interchange .................................................................23
5.0 Market Network Data Files .......................................................................23
5.1 Modeling Requirements and Information ...........................................23
5.2 Summary of MNM Revisions ................................................................26
Appendix 1 – Issue 58 Market Network Model of the Luzon Grid Bus
Oriented Single Line Diagram (Copy Attached) ...........................................27
Appendix 2 – Issue 58 Market Network Model of the Visayas Grid Bus
Oriented Single Line Diagram (Copy Attached) ...........................................27
Appendix 3 – Market Network Model Resources, Stations and Parameters
Descriptions .....................................................................................................28
Appendix 3a – Market Network Model Resources Summary
(Luzon/Visayas)................................................................................................28
Appendix 3b – Market Network Model Stations ...........................................29
Appendix 3c – Market Network Model Branch Group Definitions ..............31
Appendix 3d – Luzon Market Network Model Generator Resources .........33
Appendix 3e – Luzon Market Network Model Customer Resources ..........36
Appendix 3f – Visayas Market Network Model Generator Resources .......44
Appendix 3g – Visayas Market Network Model Customer Resource .........46
Appendix 4 – Market Network Model Revision Summary ...........................50
1.0 Introduction
1.1 About this Document
This document presents the Market Network Model (the “MNM”) that will
be used in the Philippine Wholesale Electricity Spot Market for the Luzon
and Visayas Grids and provides the detailed information on its
development. This document also presents the register of market trading
nodes.
1.2 Purpose
This document aims to:
1.2.1 Provide for transparency in developing the WESM Market Network
Model.
1.2.2 Comply with the requirements of the WESM Rules clauses 10.4.4
and 10.4.5 in relation to clause 3.2. and of the WESM Market
Network Model Manual.
1.3 Scope
This document currently covers the market network model for the Luzon
Grid and the Visayas Grid. The Luzon model is being used in the
commercial operations of the WESM in Luzon while the Visayas
commercial version model is being used for the WESM Trial Operations in
the Visayas.
1.4 Intended Audience
This manual is intended for use of the Market Operator, the System
Operator and the Trading Participants.
1.5 Background
The WESM Rules clauses 10.4.4 require the Market Operator to develop
and seek approval from the Philippine Electricity Market Board (the “PEM
Board”) of the Market Network Model that will be used in the WESM, prior
to spot market commencement date. This is implemented in the WESM
Market Network Model (MNM) Manual, which further require that the MNM
to be used for market commercial operations shall be reviewed and
endorsed by the WESM Technical Working Group (now the Rules Change
Committee) to the PEM Board for approval.
Prior to the conduct of the factory acceptance testing (the “FAT”) of the
Market Management System (the “MMS”), the Market Operations group of
PEMC developed and prepared the market network data (the “MND”) files
for the initial market network model based on the National Transmission
Corporation (the “Transco”) System Planning 2003 PSS/E data and was
used for the MMS FAT.
Upon completion of FAT, the market network data files were further
developed in November 2004 based on Transco System Operations
Energy Management System (EMS) transmission model. The resulting
MNM was used in the Site Acceptance Testing (the “SAT”) of the MMS.
Additional enhancements were made in the MNM prior to and during the
Trial Operations Program (TOP) of the WESM (TOP MNM Version 1 & 2).
The enhancements include the modeling of embedded generators with
available Remote Terminal Units (RTU) and sub-transmission system.
During the TOP, additional enhancements in the model were made to
accommodate pumping mode of the pump storage plant, station service
use, revalidation of network parameters from the latest SO PSS/E data
and block unit modeling of some plants. The results of these
enhancements are now incorporated in the Commercial Operations
version (Version 3.0) of the MNM.
Version 3 of the Luzon MNM was endorsed for approval by the interim
Rules Change Committee on January 5, 2006 and was subsequently
approved by the PEM Board on 19 January 2006. This document was
likewise approved by the PEM Board on 19 January 2006.
Subsequently, some generators within Luzon have signified their intention
to have their generating units aggregated in their registration. On the other
hand, the load representation was disaggregated to each feeder in order
to have a more specific load or customer representation in the Market
Network Model. The Luzon MNM was likewise reviewed by Transco
System Operations, with updates on the network parameters used.
These changes are now documented in this document (Issue 2.0) and
reflected in the Version 4 of the Luzon MNM.
Version 5 of the Luzon MNM reflects changes and updates in the Luzon
Grid as advised by the System Operator as well as changes in the
modeling of specific facilities or units requested by the Trading
Participants.
Since the Luzon WESM commercial operation, the Market Network Model
has been continuously updated in accordance with the updates/changes
in the power system grid as advised by System Operations. Appendix 4
shows the details of the changes in the model up to the present.
2.1 Area – refers to the three major power system grids of the Philippines
namely the Luzon Grid, the Visayas Grid and the Mindanao Grid.
2.2 Zone – the geographical location assigned to a particular resource and
station. A numerical prefix is used to all resources and stations name
from 1-9 to identify a particular zone in which they are connected, as
follows: 1 - North Luzon, 2 - Metro Manila, 3 - South Luzon, 4 -
Leyte/Samar, 5 - Cebu, 6 - Negros, 7 - Bohol, 8 - Panay, and 9 -
Mindanao.
2.3 Zone Name – name used to define the particular zone in the MMS
namely: NORT for North Luzon, METR for Metro Manila, SOUT for South
Luzon, LEYT for Leyte/Sama, CEBU for Cebu, NEGR for Negros, BOHO
for Bohol, PANA for Panay, and MIND for Mindanao.
2.4 Load Group Name – name used to define the particular group of loads in
the MMS namely: NORT_LG for North Luzon Load Group, METR_LG for
Metro Manila Load Group, SOUT_LG for South Luzon Load Group,
LEYT_LG for Leyte/Samar Load Group, CEBU_LG, for Cebu Load Group
NEGR_LG for Negros Load Group, BOHO_LG for Bohol Load Group,
PANA_LG for Panay Load Group, and MIND_LG and Mindanao Load
Group.
2.5 Resource Node Name – refers to a particular generating unit or a
particular load/customer. A numerical prefix is use to indicate at which
zone a resource is connected, e.g. 1MAGAT_G01 is generating unit
located in North Luzon; 3LABO_T1L1 is load connected in South Luzon.
2.6 Station Name – name convention assigned to a particular power
substation in which a resource is connected. A numerical prefix is used to
indicate at which zone a station is connected, e.g. 2ARANETA - Araneta
substation located in Metro Manila; 5BANILAD – Banilad substation
located in Cebu.
2.7 Common Name – refers to the actual name of a particular plant.
2.8 Company Name – refers to the owner of a particular plant.
2.9 Customer Name – refers to a distribution company, electric
cooperative or private entity that purchases electricity in the WESM.
2.10 Trading Participant – refers to a person or an entity registered with the
Market Operator as either: (a) a customer; or (b) a generation Company,
3.0 Responsibilities
The Energy Management System (the “EMS”) of the System Operator provides the
power system snapshot to the MMS every five (5) minutes. The EMS snapshot is a
breaker-oriented representation of the power system and provides the injections and
withdrawal of power (i.e., MW and MVAR) and the status of the individual power circuit
breakers connecting the power equipments at all the monitored points in the power
system.
The snapshot essentially provides the latest condition and topology (up to 5 minutes) of
the power system to the MMS. The MMS then translates the breaker-oriented
information EMS model into the bus-oriented Market Network Model. This information is
then used by the MMS in determining the latest system condition and produce
schedules and prices in the electricity market.
Appendix 1 of the MNM Manual details the parameters to be used in defining the
physical power system into its mathematical representation. The parameters defines the
topology of the power system, impedances, thermal limits, line and equipment loss
parameters, generator parameters and High Voltage Direct Current line limits. These
information are taken from the PSS/E Base Case provided by SO to MO.
The following lists the other modeling requirements and information used in defining the
Market Network Model in the MMS:
1. WESM Market Network Model Area definition. For the MMS, three (3) Areas
were defined for the Philippine Power System. These are:
a. Luzon
b. Visayas
c. Mindanao
2. The three areas are further categorized into nine (9) zones. The zones have
been defined based on geographic location. The zones also define the load
group in the network data files.
For examples,
1MAGAT for Magat Substation located in North Luzon
2ARANETA for Araneta Substation located in Metro Manila
3CLACA for Calaca Switchyard located in South Luzon
4ISABEL for Isabel Substation located in Leyte
5BANILAD for Banilad Substation located in Cebu
6AMLAN for Amlan Substation located in Negros
7UBAY for Ubay switchyard located in Bohol
8DINGLE for Dingle Substation located in Panay
9DAVAO for Davao Substation located in Mindanao
5. Names have been provided for each transmission line and transformer circuit.
They are represented by identifying “from” which a line is connected and “to”
which station it connects into as defined in the PSS/E data. e.g.
1HERM_2BAL1 is Line 1 connecting Hermosa Substation located at North
Luzon to Balintawak Substation located at Metro Manila.
11. Power Circuit Breakers have been named based on the Transco existing
breaker coding system and removing the “BKR ” prefix. E.g. BKR 81BT124 of
Transco is equivalent to 81BT124 of MMS. Some dummy breakers are
incorporated in the MNM to accept or pass validation process of the MMS
during uploading. like some generator breakers which are not monitored by
the EMS SCADA. These breakers are always assumed as “CLOSE” status.
E.g. 60ST4 generator breaker of 1T_ASIA_G01.
12. Embedded generating facilities that are not injecting or exporting energy to
the grid and no available real-time unit (RTU) monitoring facilities are not
modeled in the MNM.
Note: A complete list of resources, stations, and other parameters use in the Market
Network Model are listed in Appendix 3 (Market Network Model Resources, Stations
and Parameters Descriptions) of this manual.
Appendix 1 – Issue 58 Market Network Model of the Luzon Grid Bus Oriented
Single Line Diagram (Copy Attached)
Appendix 2 – Issue 58 Market Network Model of the Visayas Grid Bus Oriented
Single Line Diagram (Copy Attached)
Visayas
ZONE STATION ZONE STATION ZONE STATION
LEYT 4BABATNGN CEBU 5COMPSTLA NEGR 6KABANKALAN
LEYT 4STARITA CEBU 5KSPC NEGR 6MABINAY
LEYT 4STARITATAP CEBU 5LAPULAPU NEGR 6NNGPP
LEYT 4ISABEL CEBU 5MANDAUE NEGR 6PGPP1
LEYT 4MAASIN CEBU 5NAGA NEGR 6PGPP2
LEYT 4ORMOC CEBU 5QUIOT BOHO 7UBAY
Visayas
ZONE STATION ZONE STATION ZONE STATION
LEYT 4CENTRAL CEBU 5TOLEDO NEGR 6CADIZ
LEYT 4CALBAYOG CEBU 5CALUNG PANA 8DINGLE
LEYT 4TABANGO CEBU 5DAANBNTAY PANA 8NABAS
LEYT 4TONGONA CEBU 5SAMBOAN PANA 8PANITAN
LEYT 4PARANAS NEGR 6AMLAN PANA 8PEDC
CEBU 5CEBU NEGR 6BACOLOD PANA 8STBARBRA
CEBU 5CEDC
People’s Energy
3NAGA 3BARIT_G01 Barit Hydro
Services Inc. (PESI)
Power Sector Assets
and Liabilities
3CALIRAY 3BOTOCA_G01 Botocan
Management
(PSALM)
3CALACA_G01 SEM-Calaca Power
3CLACA Batangas CFTPP
3CALACA_G02 Corporation (SCPC)
Power Sector Assets
and Liabilities
3CALIRAY 3CALIRY_G01 Caliraya
Management
(PSALM)
3KAL_G01
Power Sector Assets
3KAL_G02 and Liabilities
3KALYAAN CBK (KPSPP)
3KAL_G03 Management
(PSALM)
3KAL_G04
3ILIJAN 3ILIJAN_G01 South Premiere
Ilijan CCPP Power Corporation
3ILIJAN_G02 (SPPC)
3MKBAN-A 3MKBN_A Makban A
AP Renewables, Inc.
3MKBAN-B 3MKBN_B Makban B
(APRI)
3MKBAN-C 3MKBN_C Makban C
Note:
1. Resources whose associated company or customer name has not yet been
determined (or no assigned customers) and those with shared Market Trading
Nodes have been assigned with Company Name as WESMTMP.
d. Inclusion of the newly commissioned Makban S/S in the MNM with the
updated breaker connection and transmission line configuration.
e. Modeling of the newly installed transformer in the Bataan S/S for Petron
feeder.
f. Remodeling of Visayas Network Model in preparation for the commercial
operation of Visayas Market.
g. Modeling of QPPL in the net side (QPPL – Tayabas lines) as per participant
request.
Details of MNM Revision 7.0 (November 09, 2007)
a. Modeling of the new transmission lines between San Esteban-Bakun,
Bacnotan-Bauang, Bakun-Bauang and San Esteban-Bacnotan.
b. Upgraded the transformer limit of Dasmarinas Transformer 5 from 100MVA
to 300MVA.
c. Updated some breaker naming convention in accordance with its actual
name e.g. Trans Asia and Hanjin S/S.
d. Modeling of Trans-Asia in the gross side (generator transformers) as per
participant request.
e. Remodeling of Visayas Network Model in preparation for the commercial
operation of Visayas Market.
f. Revalidation of Market Network Model parameters, configuration,
connection, etc.
Details of MNM Revision 8.0 (February 8, 2008)
a. Modeling of San Jose EHV Transformers as a branch group as per
agreement between the SO-MO coordination meetings.
b. Updated all the transmission lines and transformers parameters base on the
latest PSS/E model
Details of MNM Revision 9.0 (September 12, 2008)
a. Updates on Luzon MNM network parameters incorporating the upgrading of
San Manuel – Concepcion – Mexico line.
Details of MNM Revision 10.0 (September 30, 2008)
a. Updates on San Jose Transformer 2 impedance. The defective San Jose
transformer T02 was replaced by the 600MVA transformer taken from
Kadampat 500kV substation with higher impedance.
Details of MNM Revision 11.0 (October 12, 2008)
a. Transfers of San Manuel – Pantabangan line from Old San Manuel Station to
New San Manuel Station
b. Tapping of San Manuel – Mexico line to Old San Manuel and Mexico Sub-
stations.
a. Updating of the Visayas Network in the Market Network Model for Visayas
WESM.
b. Updates on the Appendix 3: Market Network Model Resources, Stations
and Parameters Descriptions associated with the updates on the Visayas
Market Network Model.
Details of MNM Issue 34.0
a. Modelling of the new 300MVA 230/115 KV 3-Winding Transformer No. 2
(1SNJOS_TR2P & 1SNJOS_TR2S) at San Jose S/S
b. Modelling of Barit HEPP (3BARIT_G01) at Naga S/S
c. Modelling of KSPC station loads (5KSPC_SS1 and 5KSPC_SS2) at KSPC
S/S
d. Modelling of KSPC unit 2 (5KSPC_G02) at KSPC S/S
g. Modelling of KSPC units 1 and 2 station load 25 MVA transformers
(5KSPC_TR3 and 5KSPC_TR4) at KSPC S/S
h. Updates on the Appendix 3: Market Network Model Resources, Stations
and Parameters Descriptions
Details of MNM Issue 35.0 (January 21, 2011)
a. Reconfiguration at Sta. Barbara Station
b. Modeling of of capacitor banks at Sta. Barbara, Bacolod, Cadiz,
Kabankalan, Paranas, Babatngon, and Maasin Stations.
c. Modeling of Ilijan Station Service (disaggregated from Ilijan SS)
Details of MNM Issue 36.0 (February 04, 2011)
a. Installation of additional breaker at Ambuklao Station
b. Changes in naming convention of San Manuel Station circuit breakers
c. Modelling of Casa generator – 8CASA_G01
d. Modelling of Nabas substation
e. Commissioning of Sta. Barbara transformers station service loads
b. Change in breaker names at the San Jose 500 and 230 kV stations to
reflect the Site and Equipment Identification and Labelling (SEIL) naming
convention of NGCP.