Sei sulla pagina 1di 4

Protection Check-List Rev-NR2- Dated 07 June’18

Name: Status Remarks


Month and Year of Commissioning (OK/Not
Element Description Ok)
Main-I/Main-II Check the settings values Parameters with
respect to the template updated with latest
in-feed values

Check the Signal Matrix/PSL/Application


Configuration/Masking with respect to the
Input and Output assignment as per scheme
Check the Logic for DT send
Check the Logic for 86A and 86B trip
Check the Logic for single phase tripping
Check the Logic for LBB Initiations
Check the Logic for A/R starts
Check the Logic of STUB protection & Line
Isolator open status ( to be enable for one &
Half CB scheme having no Line side CT and to
be disable for DMT scheme & having Line
side CT)
Check that the wiring of Line Isolator open is
connected at correct input for Stub
Protection
Check the Logic for SOTF protection
Check that OV protection is analog (Voltage)
as well as time graded for Double
Ckt/Parallel lines
Check that the VT fail shall block the tripping
Check the current, and voltage and angle in
the relay
Check for mutual compensation wiring (if
applicable) and Check setting and
configuration according to wiring.
Whether all relays are accessible from
remote dedicated PC for setting & DR
extraction in control room

Whether Main-I & Main-II protections of all


line are time synchronised with GPS based
time synchronised equipment.

PLCC Check the healthiness of PLCC protection


panels
Check alarm during OUT position of Carrier
IN/OUT Switch in Control room as well as in
RTAMC/NTAMC

Auto Reclosure Check the logic and configuration of the AR


Start and Block
Protection Check-List Rev-NR2- Dated 07 June’18

Check the dead time and reclaim time


settings
Check the Logic and Configuration of the AR
Lockout
Check the logic & wiring for Priority Ckt in
one & Half CB scheme.
Whether priority scheme is working
properly. ( check previous A/R DR)

LBB relay/PU relay Check the relay settings (particularly, pick-up,


retrip time and back-trip time)
Check that single phase initiation is wired and
configured correctly for lines

Check the logic that retrip trips the same


breaker
Check the Signal Matrix/PSL/Application
Configuration with respect to the Input and
Output assignment as per scheme
Check the logic that back-trip trips the
associated bus-bar(for Main-CB LBB) OR both
the Main-CB (for Tie CB LBB )
In case of half dia, check that the Tie Bay LBB
instantaneously trips the Bus connected to
future bay( also check the wiring)
For bays commissioned in the extension
projects have Tie-LBB wiring changed from
“Tripping the bus” to “Tripping the Main CB”
Dead Zone/ End zone Protection is disabled;
Topology is independent of switch status in
One and Half CB scheme
Check/measure phase wise current in LBB/PU
relay

Reactor/Transfor Check the differential current and bias current


mer Differential in the relay
Check the relay settings as per the template
Check the relay configuration for proper input
and output contact assignment.
Check the tripping logic wrt the scheme.
In case of single phase transformer with spare,
check the correct implementation of spare
selection in trip logic
REF protection Check the current in the relay
Check the relay settings as per the template
Check the relay configuration for proper input
and output contact assignment.
Check the tripping logic wrt the scheme.
In case of single phase transformer with spare,
Protection Check-List Rev-NR2- Dated 07 June’18

check the correct implementation of spare


selection in trip logic
Check for the CT selection scheme and logic

Back-up Check the current and voltage in the relay


impedance
Check the VT selection logic in BCU/relay
panel
Check that at a time only one bus VT is
selected

Check the relay settings as per the template


Check the relay configuration for proper input
and output contact assignment.
Check the tripping logic wrt the scheme.
Check that VT fail blocks the tripping
Check for implementation of NGR protection
scheme
CSD Check whether CSD installed with ICT/Reactor
is working properly as per its requirement. (
Check recent graph/DR)

Check provision of bypassing of CSD is


provided
Check DR trigging of other relay on Manual
operation of CB in case CSD is not having the
provision of extraction of DR/graph.

General Check that the two trippings of PRD, Buchlz


etc are wired to two separate relays
Check that the relays powered by DC-1 are
supervised by relays powered by DC-2 and
Vice-versa
Check Relay Failure and Relay disconnected
alarms for all the relays.
Check for time-sync status of the relay
Check the DR channel standardisation
Check pre-commissioning test reports
(whether print-outs of DR and EL enclosed)
Check the logic of Bus earth switch interlock
Check the auto download of DR
Check for implementation of relevant CC-AM
circulars

Check the single point earthing of CT


secondary core on sample basis.
Check the earthing interconnecting link/strip
connected in inter panel/adjacent panel Commented [01]: Only Corner panels is earthed with external
earthing grid and remaining adjacent panels interconnected with
copper stripped.
During protection audit of one substation it was found that inter
panel earthing links/strip is not connected in many panels.
Protection Check-List Rev-NR2- Dated 07 June’18

Bus Bar Protection Whether duplicate bus bar protection


provided in 400 & 765 kV Bus bar Commented [02]: In few s/s only one bus bar relay is still exist
in 400 kV Bus

Check the topology of both the CUs


Check the Diff current and restrain current
Check /Measure the Spill current in bus-bar
relay
Check that CB status is permanently shorted in
one and half CB scheme
Check the operation of the selector switch and
correct alarms in SCADA
Check the settings and Configuration of the CU
Simulate PU disconnected and check for Bus
Bar Block
Check the setting of CT supervision/CT fail/CT
circuitry fault alarm
Check logic for LBB initiation on bus bar trip

Check the logic for BUS Bar Tripping on SF6


Gas compartment zone trip in case of GIS
Station. Commented [03]: This is very important to check this logic for
GIS station. Wrong logic may lead mal-operation/GIS equipment
damages.

SAS As per Annexure-I (SAS Checklist)


Alarms Simulate the alarms as per Annex-II for at least
20% bays, Minimum 6 bays.
DC System Check DC voltage at the farthest point in the
switchyard (+ to Earth, - to earth)
AC system Check auto operation of DG set
FFPH Check auto operation of HVW and Diesel
driven pump
Smoke detection Simulate smoke detection in any kiosk and
system check for alarm