This document provides a protection check-list for various relay systems and components at a substation. It includes checks for settings, configurations, logic, wiring, measurements, and alarms for main protections, auto-reclosure, line backup, busbar protection, and other relay systems. General checks include testing interconnections, supervision, time synchronization, and implementing relevant guidelines. The goal is to verify correct implementation and operation of all relay protections and systems.
This document provides a protection check-list for various relay systems and components at a substation. It includes checks for settings, configurations, logic, wiring, measurements, and alarms for main protections, auto-reclosure, line backup, busbar protection, and other relay systems. General checks include testing interconnections, supervision, time synchronization, and implementing relevant guidelines. The goal is to verify correct implementation and operation of all relay protections and systems.
This document provides a protection check-list for various relay systems and components at a substation. It includes checks for settings, configurations, logic, wiring, measurements, and alarms for main protections, auto-reclosure, line backup, busbar protection, and other relay systems. General checks include testing interconnections, supervision, time synchronization, and implementing relevant guidelines. The goal is to verify correct implementation and operation of all relay protections and systems.
Month and Year of Commissioning (OK/Not Element Description Ok) Main-I/Main-II Check the settings values Parameters with respect to the template updated with latest in-feed values
Check the Signal Matrix/PSL/Application
Configuration/Masking with respect to the Input and Output assignment as per scheme Check the Logic for DT send Check the Logic for 86A and 86B trip Check the Logic for single phase tripping Check the Logic for LBB Initiations Check the Logic for A/R starts Check the Logic of STUB protection & Line Isolator open status ( to be enable for one & Half CB scheme having no Line side CT and to be disable for DMT scheme & having Line side CT) Check that the wiring of Line Isolator open is connected at correct input for Stub Protection Check the Logic for SOTF protection Check that OV protection is analog (Voltage) as well as time graded for Double Ckt/Parallel lines Check that the VT fail shall block the tripping Check the current, and voltage and angle in the relay Check for mutual compensation wiring (if applicable) and Check setting and configuration according to wiring. Whether all relays are accessible from remote dedicated PC for setting & DR extraction in control room
Whether Main-I & Main-II protections of all
line are time synchronised with GPS based time synchronised equipment.
PLCC Check the healthiness of PLCC protection
panels Check alarm during OUT position of Carrier IN/OUT Switch in Control room as well as in RTAMC/NTAMC
Auto Reclosure Check the logic and configuration of the AR
Start and Block Protection Check-List Rev-NR2- Dated 07 June’18
Check the dead time and reclaim time
settings Check the Logic and Configuration of the AR Lockout Check the logic & wiring for Priority Ckt in one & Half CB scheme. Whether priority scheme is working properly. ( check previous A/R DR)
LBB relay/PU relay Check the relay settings (particularly, pick-up,
retrip time and back-trip time) Check that single phase initiation is wired and configured correctly for lines
Check the logic that retrip trips the same
breaker Check the Signal Matrix/PSL/Application Configuration with respect to the Input and Output assignment as per scheme Check the logic that back-trip trips the associated bus-bar(for Main-CB LBB) OR both the Main-CB (for Tie CB LBB ) In case of half dia, check that the Tie Bay LBB instantaneously trips the Bus connected to future bay( also check the wiring) For bays commissioned in the extension projects have Tie-LBB wiring changed from “Tripping the bus” to “Tripping the Main CB” Dead Zone/ End zone Protection is disabled; Topology is independent of switch status in One and Half CB scheme Check/measure phase wise current in LBB/PU relay
Reactor/Transfor Check the differential current and bias current
mer Differential in the relay Check the relay settings as per the template Check the relay configuration for proper input and output contact assignment. Check the tripping logic wrt the scheme. In case of single phase transformer with spare, check the correct implementation of spare selection in trip logic REF protection Check the current in the relay Check the relay settings as per the template Check the relay configuration for proper input and output contact assignment. Check the tripping logic wrt the scheme. In case of single phase transformer with spare, Protection Check-List Rev-NR2- Dated 07 June’18
check the correct implementation of spare
selection in trip logic Check for the CT selection scheme and logic
Back-up Check the current and voltage in the relay
impedance Check the VT selection logic in BCU/relay panel Check that at a time only one bus VT is selected
Check the relay settings as per the template
Check the relay configuration for proper input and output contact assignment. Check the tripping logic wrt the scheme. Check that VT fail blocks the tripping Check for implementation of NGR protection scheme CSD Check whether CSD installed with ICT/Reactor is working properly as per its requirement. ( Check recent graph/DR)
Check provision of bypassing of CSD is
provided Check DR trigging of other relay on Manual operation of CB in case CSD is not having the provision of extraction of DR/graph.
General Check that the two trippings of PRD, Buchlz
etc are wired to two separate relays Check that the relays powered by DC-1 are supervised by relays powered by DC-2 and Vice-versa Check Relay Failure and Relay disconnected alarms for all the relays. Check for time-sync status of the relay Check the DR channel standardisation Check pre-commissioning test reports (whether print-outs of DR and EL enclosed) Check the logic of Bus earth switch interlock Check the auto download of DR Check for implementation of relevant CC-AM circulars
Check the single point earthing of CT
secondary core on sample basis. Check the earthing interconnecting link/strip connected in inter panel/adjacent panel Commented [01]: Only Corner panels is earthed with external earthing grid and remaining adjacent panels interconnected with copper stripped. During protection audit of one substation it was found that inter panel earthing links/strip is not connected in many panels. Protection Check-List Rev-NR2- Dated 07 June’18
Bus Bar Protection Whether duplicate bus bar protection
provided in 400 & 765 kV Bus bar Commented [02]: In few s/s only one bus bar relay is still exist in 400 kV Bus
Check the topology of both the CUs
Check the Diff current and restrain current Check /Measure the Spill current in bus-bar relay Check that CB status is permanently shorted in one and half CB scheme Check the operation of the selector switch and correct alarms in SCADA Check the settings and Configuration of the CU Simulate PU disconnected and check for Bus Bar Block Check the setting of CT supervision/CT fail/CT circuitry fault alarm Check logic for LBB initiation on bus bar trip
Check the logic for BUS Bar Tripping on SF6
Gas compartment zone trip in case of GIS Station. Commented [03]: This is very important to check this logic for GIS station. Wrong logic may lead mal-operation/GIS equipment damages.
SAS As per Annexure-I (SAS Checklist)
Alarms Simulate the alarms as per Annex-II for at least 20% bays, Minimum 6 bays. DC System Check DC voltage at the farthest point in the switchyard (+ to Earth, - to earth) AC system Check auto operation of DG set FFPH Check auto operation of HVW and Diesel driven pump Smoke detection Simulate smoke detection in any kiosk and system check for alarm