Provision of Open Shed in HSE yard and Fencing for Waste storage- Dukhan Fields Provision of Open Shed

Provision of Open Shed in HSE Yard and Fencing for Waste Storage- Dukhan Fields 27-Apr-19 18:25

Activity ID Activity Name Original Duration Start Finish 2019 2020 2021

783 21-Jul-19 20-Jul-21 20-Jul-21, Provision of Open She


Provision of Open Shed in HSE yard and Fencing for Waste storage- Dukhan Fields
783 21-Jul-19 20-Jul-21 20-Jul-21, PROJECT MILESTON
PROJECT MILESTONES
PM-101 Work Site Survey 60 21-Jul-19 14-Sep-19 Work Site Survey
PM-111 Design & Engineering 106 30-Jul-19 05-Nov-19 Design & Engineering
PM-121 Mobilization of Resources 60 30-Jul-19 23-Sep-19 Mobilization of Resources
PM-131 Procurement 336 22-Oct-19 31-Aug-20 Procurement
PM-141 Construction- Open Shed in HSE Yard at Khatiyah Sector 441 28-Nov-19 13-Jan-21 Construction- Open Shed in HSE Yard at Khatiyah S
PM-151 Construction- Fencing and Gates for HSE Solid waste storage area at Fahalil Sector 160 31-Aug-20 27-Jan-21 Construction- Fencing and Gates for HSE Solid wa
PM-161 Project Commissioning 185 27-Jan-21 19-Jul-21 Project Commissioning
PM-171 Completion and Deliverables 146 06-Mar-21 20-Jul-21 Completion and Deliverables
60 21-Jul-19 14-Sep-19 14-Sep-19, WORK SITE SURVEY FOR BOTH OPEN SHED AND FENCING FOR WASTE STORA
WORK SITE SURVEY FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
WSS-101 As-Built Survey of the existing site facilities 15 21-Jul-19 03-Aug-19 As-Built Survey of the existing site facilities
WSS-111 Identification of all existing tie-ins, connection points intended for modification/replacement 8 04-Aug-19 11-Aug-19 Identification of all existing tie-ins, connection points intended for modification/replacement
WSS-121 Scanning of the Underground Services 7 11-Aug-19 17-Aug-19 Scanning of the Underground Services
WSS-131 Geotechnical Investigation 10 18-Aug-19 26-Aug-19 Geotechnical Investigation
WSS-141 Trial pit excavation (Manual) to identify and verify the existing underground services 20 27-Aug-19 14-Sep-19 Trial pit excavation (Manual) to identify and verify the existing underground services
45 21-Jul-19 31-Aug-19 31-Aug-19, PERMIT & DATA FROM QP
PERMIT & DATA FROM QP
PDQP-101 Apply for the Permit to perform the works 10 21-Jul-19 29-Jul-19 Apply for the Permit to perform the works
PDQP-111 Approval of Permit by QP 10 30-Jul-19 07-Aug-19 Approval of Permit by QP
PDQP-121 Obtaining the information/data & drawings from QP 25 08-Aug-19 31-Aug-19 Obtaining the information/data & drawings from QP
106 30-Jul-19 05-Nov-19 05-Nov-19, DESIGN & ENGINEERING FOR BOTH OPEN SHED AND FENCING FOR WAST
DESIGN & ENGINEERING FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
DE-101 Submission & Approval of Contractor Execution Plan 10 30-Jul-19 07-Aug-19 Submission & Approval of Contractor Execution Plan
DE-111 Submission & Approval of Design Basis Memorandum 21 08-Aug-19 27-Aug-19 Submission & Approval of Design Basis Memorandum
DE-121 Submission and Approval of AFC/Shop Drawings by the Contractor 60 27-Aug-19 22-Oct-19 Submission and Approval of AFC/Shop Drawings by the Contractor
DE-131 Submission and Approval of Method Statement 15 22-Oct-19 05-Nov-19 Submission and Approval of Method Statement
336 22-Oct-19 31-Aug-20 31-Aug-20, PROCUREMENT FOR BOTH OPEN SHED AND FE
PROCUREMENT FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
PRO-101 Identification of materials required for both the facilities 40 22-Oct-19 28-Nov-19 Identification of materials required for both the facilities
PRO-111 Submission of Material submittal as per the approved Design 50 28-Nov-19 14-Jan-20 Submission of Material submittal as per the approved Design
PRO-121 Approval of Material submittal 65 14-Jan-20 15-Mar-20 Approval of Material submittal
PRO-131 Placing the order 35 15-Mar-20 16-Apr-20 Placing the order
PRO-141 Delivery of Materials at the Port 120 16-Apr-20 06-Aug-20 Delivery of Materials at the Port
PRO-151 Custom Clearance by the Government 15 06-Aug-20 20-Aug-20 Custom Clearance by the Government
PRO-161 Delivery of Materials at the site 5 20-Aug-20 25-Aug-20 Delivery of Materials at the site
PRO-171 Inspection by the QP Engineers 6 25-Aug-20 31-Aug-20 Inspection by the QP Engineers
481 05-Nov-19 27-Jan-21 27-Jan-21, CONSTRUCTION
CONSTRUCTION
PRE-CONSTRUCTION 50 05-Nov-19 22-Dec-19 22-Dec-19, PRE-CONSTRUCTION
PRECON-101 Demolition of existing asphalt pavement 25 05-Nov-19 28-Nov-19 Demolition of existing asphalt pavement
PRECON-111 Demolition of existing 1.5mtr high fencing for installation of new fencing & gates 25 28-Nov-19 22-Dec-19 Demolition of existing 1.5mtr high fencing for installation of new fencing & gates
PROVISION OF OPEN SHED IN HSE YARD 441 28-Nov-19 13-Jan-21 13-Jan-21, PROVISION OF OPEN SHED IN HSE Y
OSCON-101 Excavation 35 28-Nov-19 31-Dec-19 Excavation
OSCON-111 Blinding Concrete 15 31-Dec-19 14-Jan-20 Blinding Concrete
OSCON-121 Structural Concrete and Water Proofing 30 15-Mar-20 12-Apr-20 Structural Concrete and Water Proofing
OSCON-131 Structural Steel Erection 25 31-Aug-20 23-Sep-20 Structural Steel Erection
OSCON-141 RC Vehicle Ramp construction 25 12-Apr-20 05-May-20 RC Vehicle Ramp construction
OSCON-151 RC Slab & Drain Works 25 23-Sep-20 17-Oct-20 RC Slab & Drain Works
OSCON-161 Roofing and Cladding for Open Shed 20 17-Oct-20 04-Nov-20 Roofing and Cladding for Open Shed
OSCON-171 Wall Cladding for RC Slab 50 04-Nov-20 21-Dec-20 Wall Cladding for RC Slab
OSCON-181 Lightening Protection System 25 21-Dec-20 13-Jan-21 Lightening Protection System
PROVISION OF FENCING & GATES FOR HSE SOLID WASTE STORAGE AREA 160 31-Aug-20 27-Jan-21 27-Jan-21, PROVISION OF FENCING & GATES F

Page 1 of 2 Prepared by M.S. Sathyajeth   


Remaining Level of Effort Primary Baseline Remaining Work
Critical Path Actual Work Critical Remaining ... MTC(c) Primavera Systems, Inc.
Provision of Open Shed in HSE yard and Fencing for Waste storage- Dukhan Fields Provision of Open Shed in HSE Yard and Fencing for Waste Storage- Dukhan Fields 27-Apr-19 18:25

Activity ID Activity Name Original Duration Start Finish 2019 2020 2021

FGCON-101 Excavation & RC foundation works for Fencing, steel post erection 55 31-Aug-20 21-Oct-20 Excavation & RC foundation works for Fencing, steel post er
FGCON-111 Chain Link Fencing 40 21-Oct-20 28-Nov-20 Chain Link Fencing
FGCON-121 Installation of Single emergency gates 25 28-Nov-20 21-Dec-20 Installation of Single emergency gates
FGCON-131 Double chain link gates 40 21-Dec-20 27-Jan-21 Double chain link gates
185 27-Jan-21 19-Jul-21 19-Jul-21, PROJECT COMMISS
PROJECT COMMISSIONING FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
PC-101 Completion of Construction Snags 40 27-Jan-21 06-Mar-21 Completion of Construction Snags
PC-111 Submission of Project Dossier 140 27-Jan-21 07-Jun-21 Submission of Project Dossier
PC-121 Approval of Project Dossier 45 07-Jun-21 19-Jul-21 Approval of Project Dossier
146 06-Mar-21 20-Jul-21 20-Jul-21, COMPLETION AND D
COMPLETION AND DELIVERABLES FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
A1000 As-Built Drawings 90 06-Mar-21 29-May-21 As-Built Drawings
A1010 Asset Captilization Schedule 65 06-Mar-21 05-May-21 Asset Captilization Schedule
A1020 Obtaining Completion Certificate from QP 1 19-Jul-21 20-Jul-21 Obtaining Completion Certificate

Page 2 of 2 Prepared by M.S. Sathyajeth   


Remaining Level of Effort Primary Baseline Remaining Work
Critical Path Actual Work Critical Remaining ... MTC(c) Primavera Systems, Inc.