Provision of Open Shed in HSE Yard and Fencing for Waste Storage- Dukhan Fields 27-Apr-19 18:25
Activity ID Activity Name Original Duration Start Finish 2019 2020 2021
Activity ID Activity Name Original Duration Start Finish 2019 2020 2021
FGCON-101 Excavation & RC foundation works for Fencing, steel post erection 55 31-Aug-20 21-Oct-20 Excavation & RC foundation works for Fencing, steel post er
FGCON-111 Chain Link Fencing 40 21-Oct-20 28-Nov-20 Chain Link Fencing
FGCON-121 Installation of Single emergency gates 25 28-Nov-20 21-Dec-20 Installation of Single emergency gates
FGCON-131 Double chain link gates 40 21-Dec-20 27-Jan-21 Double chain link gates
185 27-Jan-21 19-Jul-21 19-Jul-21, PROJECT COMMISS
PROJECT COMMISSIONING FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
PC-101 Completion of Construction Snags 40 27-Jan-21 06-Mar-21 Completion of Construction Snags
PC-111 Submission of Project Dossier 140 27-Jan-21 07-Jun-21 Submission of Project Dossier
PC-121 Approval of Project Dossier 45 07-Jun-21 19-Jul-21 Approval of Project Dossier
146 06-Mar-21 20-Jul-21 20-Jul-21, COMPLETION AND D
COMPLETION AND DELIVERABLES FOR BOTH OPEN SHED AND FENCING FOR WASTE STORAGE AREA
A1000 As-Built Drawings 90 06-Mar-21 29-May-21 As-Built Drawings
A1010 Asset Captilization Schedule 65 06-Mar-21 05-May-21 Asset Captilization Schedule
A1020 Obtaining Completion Certificate from QP 1 19-Jul-21 20-Jul-21 Obtaining Completion Certificate