Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Simanggo-2 HEPP
PROJECT FOR MASTER PLAN STUDY OF HYDROPOWER DEVELOPMENT
IN INDONESIA
Table of Contents
Page
1 INTRODUCTION ...................................................................................................................... 1-1
1.1 General ......................................................................................................................... 1-1
1.2 Purpose and Scope of the Geological Survey ................................................................ 1-1
1.3 Methodology of the Geological Survey ........................................................................ 1-2
1.3.1 Geological mapping ........................................................................................ 1-2
1.3.2 Seismic refraction survey................................................................................ 1-2
1.3.3 Laboratory test for construction materials ..................................................... 1-3
1.4 Quantity of the Geological Survey ................................................................................. 1-3
-i-
4.1 General ........................................................................................................................... 4-1
4.2 Intake Weir Site ............................................................................................................. 4-1
4.2.1 Weir B site....................................................................................................... 4-1
4.2.2 Weir C site ...................................................................................................... 4-3
4.2.3 Weir A site ...................................................................................................... 4-3
4.3 Intermediate Pond Dike Site ......................................................................................... 4-4
4.3.1 Intermediate pond dike B site ......................................................................... 4-4
4.3.2 Intermediate pond dike C site ........................................................................ 4-4
4.4 Connection and Headrace Tunnels (Plan B) ................................................................ 4-5
4.5 Surge Tank and Penstock Area ...................................................................................... 4-6
4.6 Powerhouse Site ............................................................................................................ 4-6
FIGURES
-ii-
Figure 4.2 Geological section of the intermediate pond axis alternative B..................................... 4-9
Figure 4.3 Geological section along the connection and headrace tunnel alignment
alternative B ................................................................................................................. 4-10
TABLES
Table 1.1 Items and Methods of Laboratory Tests Performed for Construction Materials ............. 1-3
Table 1.2 Quantity of Geological Survey for the Simonggo-2 Project ........................................... 1-3
Table 2.1 Regional stratigraphy of the project site .......................................................................... 2-2
Table 2.2 Summary of design seismic coefficients of the similar projects in Sumatra ................... 2-6
Table 2.3 Summary of the estimated peak ground accelerations .................................................... 2-9
Table 2.4 Zone and zone coefficient ............................................................................................. 2-10
Table 2.5 Foundation type and correction factor ........................................................................... 2-10
Table 2.6 Return period and basic earthquake acceleration .......................................................... 2-10
Table 2.7 Design seismic acceleration estimated by ISM ............................................................. 2-10
Table 2.8 Summary of obtained design seismic acceleration ........................................................ 2-11
Table 3.1 Geological classification of seismic units ...................................................................... 3-5
Table 3.2 Location of sand source sampling ................................................................................... 3-6
Table 3.3 Summary of laboratory tests for fine aggregate material ................................................ 3-7
Table 3.4 Location of potential rock quarry Sites ........................................................................... 3-7
Table 3.5 Summary of laboratory tests for coarse aggregate material ............................................ 3-7
Table 4.1 Japanese rock mass classification standard ..................................................................... 4-2
Table 4.2 Estimated rock mass parameters at the weir B site ......................................................... 4-2
Table 4.3 Japanese Rock classification and empirically estimated rock parameters....................... 4-3
Table 4.4 Estimated rock mass parameters at the weir C site ......................................................... 4-3
Table 4.5 Estimated rock mass parameters at the intermediate pond dike B site ............................ 4-4
Table 4.6 Estimated rock mass parameters at the intermediate pond dike C site ............................ 4-5
Table 4.7 Estimated rock mass parameters for the waterway route ................................................ 4-5
Table 4.8 Estimated rock mass parameters for the surge tank and penstock area ........................... 4-6
Table 4.9 Estimated rock mass parameters for the powerhouse site ............................................... 4-7
Table 5.1 Recommended quantity of boring investigation for feasibility study ............................. 5-4
APPENDIX
-iii-
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
CHAPTER 1 INTRODUCTION
1.1 GENERAL
Geological survey was carried out for the Pre-feasibility Study for Simonggo-2 Hydroelectric Power
Project under the Project for the Master Plan Study of the Hydropower Development in Indonesia. The
Simanggo-2 project is a ROR-type scheme and mainly includes intake weir, intermediate pond dike
(regulating pondage), connection tunnel, headrace tunnel, surge tank, penstock, powerhouse, etc.
This supporting report presents the results of the geological and geotechnical investigations and
recommendations for the proposed Simonggo-2 project scheme. The analyses, conclusions and
recommendations provided in this report are based on the understanding of the project scheme and on
the geological and geotechnical consideration and evaluation of the existing project site conditions at
the time of the geological survey as well as on some engineering judgments.
In addition, the geological survey was done by PT. CONUUSA ENERGINDO, a subcontractor of the
Project for the Master Plan Study of Hydropower Development in Indonesia.
a) To evaluation the geological and geotechnical suitability of the project sites for the proposed
ROR-type hydropower projects;
b) To provide geotechnical data and parameters necessary for geotechnical analyses and design of
the proposed projects at the pre-feasibility Study stage; and
c) To foresee and provide solution against geological hazards or problems that may arise due to
subsurface conditions.
a) Review of previous investigation reports and selected published geologic maps and documents
pertinent to the project site;
1-1
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
g) Recommendations on mitigation or solutions for the identified geotechnical problems and impact
in relation to design and construction of the proposed project structures.
In addition to morphological features, distribution of lithological unit and major geological structures,
the surface geological mapping was focused mainly on below:
- Distribution/condition (location, flow amount, temperature, color, smell, etc.) of seepage and
spring.
The seismic refraction survey was carried out by using an OYO McSeis 170f type Seismic Instrument
with 24 seismometers (geophones). Hammer was used to generate seismic source. Geophone intervals
along the survey lines were maintained at 10 meters to produce high resolution data on subsurface
layers. The shot was recorded and reviewed at the site. The recorded data were plotted on
time-distance graphs, and then interpreted into profiles of seismic wave velocity layers. The deduced
seismic wave velocity layers were shown in profiles, using the ground surface profile.
1-2
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
In addition, the seismic wave velocity layers distinguished were geologically and geotechnically
interpreted in correlation with the findings in surface geological mapping.
Table 1.1 Items and Methods of Laboratory Tests Performed for Construction Materials
Test Item Standard or Method Sample No.
1. Sieve analysis of aggregates ASTM C 136 10
2. Specific gravity and water absorption (fine aggregate) ASTM C128 10
3. Specific gravity and water absorption (coarse aggregate) ASTM C127 10
4. Clay lumps and friable particles in aggregate ASTM C 142 10
5. Soundness tests by sodium sulfate (for coarse and fine) ASTM C 88 10
6. Abrasion test of coarse aggregate by Los Angeles machine ASTM C535 10
7. Chemical (alkali) reactivity test ASTM C289 10
The site work of the geological survey started in middle December 2010 and ended in early February
2011. The quantity of the survey is summarized Table 1.2 below while the location of the seismic
refraction survey is shown in Figure 1.1.
1-3
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
1-4
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
2.1 GENERAL
The Simanggo-2 project is situated approximately at 2°16’ to 2°20’ of the north latitude and 98°22’ to
98°26’ of the east longitude on the middle course of the Simanggo river around Rarabintang village,
about 40 km west of Doloksanggul City.
Geologically the project site is located approximately 30 km southwest of the Sumatran Fault Zone
(SFZ), also called Great Sumatra Fault System (GSF), one of the most seismically active zones in
Indonesia, it is thus imperative to evaluate the seismic hazard at the project site and to design the
project facilities to withstand the anticipated ground motions.
This chapter presents the pre-feasibility-level regional geological and seismic hazard assessment and
provides the recommended design seismic coefficient for structural design of the project based on
existing and published information as well as brief project site inspection. Some similar projects
within Sumatra were reviewed to supplementarily determine design seismic parameter.
The regional stratigraphy of the project area is given in Table 2.1 and the regional geological map is
shown in Figure 2.1. The region is underlain by a basement of Early Permian to Late Carboniferous
metamorphic rocks of sedimentary origin. They consist mainly of quartzose sandstones, slates and
phyllites. From Late Trassic up to Late Permian intrusions locally took place, represented by Sibolga
Complex of granite and diorite. These basements are overlain extensively by Toba Tuffs of
Pleistocene age, consisting mainly of partially welded and unwelded ashflow tuffs and occasionally
reworked pyroclastic deposits.
The most important geological structure in the region is the NW-trending SFZ, which runs
approximately 30 km northeast of the project site. In addition to the SFZ, some small faults, definite
and indefinite, are distributed in the vicinity of the project site (Figure 2.1). They are 1) NW-SE fault
system and 2) NNW-SSE fault system. The NW-SE fault system is probably subsidiary to the SFZ.
2-1
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
2-2
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
The SFZ, totally 1,900 km long, traverses the hanging wall block of the Sunda subduction zone,
roughly coincident with the active Sumatra volcanic arc. According to Sieh and Natawidjaja (2000),
the SFZ is highly segmented and is divided into 19 major segments on the basis of its geomorphic and
topographical expressions. These fault segments generally range in length from 35 km to 220 km. The
major segments of the SFZ in the proximity of the project site are a) Renun Segment and b) Toru
Segment.
The Renun segment (2.0oN to 3.55oN), approximately 225 km long, is the longest segment of the SFZ.
The segment traverses the western flanks of the 80-km-long Toba caldera underlain by approximately
73,000-year-old Tobu Tuff. The Runun segment generally strikes 40 degrees northwest and dips
vertically. The segment offsets the Toba Tuff approximately 2 km at its most southeastern end and
therefore reportedly has a 27 mm/yr slip rate for the fault. The Renun segment was the source of some
major historical earthquakes.
The Toru segment (1.2oN to 2.0oN), approximately 95 km long, is well delimited by some bends, and
characterized by contractional bend at southeastern end and by dilatational step at the northwestern
end, respectively. The Toru segment strikes 45 degrees northwest and dips vertically. The segment
accommodates significant components of dip slips and reportedly has a approximately 24 mm/yr slip
rate for the fault. The Pahae Jahe earthquake of Ms 6.4 occurred in 1984 at the northern end of the
Toru segment.
Earthquakes are distributed mostly between the subduction zone and the FSZ and especially
concentrated along the subduction zone and the FSZ. In addition, the earthquakes around the FSZ
generally have deep focal depths – represented by blue and green dots in Figure 2.2, whereas the
earthquakes around the subduction zone shows shallow focal depths – represented by yellow and
brown dots in Figure 2.2.
Historical earthquakes have caused surface ruptures along the SFZ. Figure 2.3 gives historical major
earthquakes along the SFZ and the subduction zone. The smaller ellipsoid shapes in Figure 2.3
indicate some surface rupture on the some segment of the SFZ, while the larger ellipsoid shapes along
the subduction zone in Figure 2.3 indicate recent and historical megathrust events associated with the
subduction zone and the SFZ. The seismic sources are dominated by the subduction zone and the
strike-slip-type SFZ. The subduction zone and the SFZ are both active and capable to generate
earthquakes up to Mw=9.15 (December 26, 2004) and Mw=7.7 (1892), respectively
2-3
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Figure 2.2 Location of earthquake epicenters within ±2 geographical degrees from the
Simonggo-2 weir site in the period since 1973 to 2010 (from USGS seismic database)
- Along the Renun segment of the SFZ, magnitude mb = 6.8, 22 February 1916, strong
shaking at Tarutung valley.
- Along the Renun segment of the SFZ, magnitude mb = 6.8, 24 January 1921, strong shaking
similar to the above 1916 earthquake.
- Along the Renun segment, magnitude Ms = 7.2, 1936, strong shaking at Tarutung valley.
- Along the Toru segment of the SFZ, Pahae Jahe earthquake, magnitude Ms = 6.4, 1984.
- Along the Toru segment of the SFZ, magnitude Ms = 6.6, 25 April 1987, approximately 50
km from the Simonggo-2 project site (weir site).
2-4
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Figure 2.3 Recent and historical major earthquakes along the SFZ and Subduction Zone
(modified from EERI Special Earthquake, May 2007)
a) Maximum Credible Earthquake (MCE): The MCE is defined as the largest reasonably
conceivable earthquake, which is considered likely to occur along a recognized fault or a
2-5
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
seismological area. The MCE is the upper bond of the expected magnitude on a given
seismic source, in general related to 5,000 years to 10,000 years return periods.
b) Operating Basis Earthquake (OBE): The OBE is the level of ground motion that all structures
must be able to withstand and still remain functional. Any damage due to earthquake is
repairable. The OBE ground motions are expected occur during the lifetime of the structure
and generally correspond to 100 years to 500 years return periods.
The selection of seismic design criteria is generally based on the type of structures under consideration
and the safety and environmental consequences of failure. The ROR-type Simonggo-2 project mainly
include some low risk structures (low impact), such as small and low weir dam, low dike pond and so
on. Accordingly, the OBE is considered as design earthquake in the return period of 100 to 200 years.
Table 2.2 Summary of design seismic coefficients of the similar projects in Sumatra
Design Seismic
Project Name Design Facility Remarks
Coefficient
Tes-1 All structures 0.15 ROR. completed in 1991
Besai All structures 0.15 LHD, completed in 2001
Musi Intake dam 0.18 ROR, completed in 2006
Other structures 0.15
Underground structures 0.08
Singkarak Open structures 0.20 LHD, completed in 1998
Underground powerhouse 0.10
Merangin-2 Open structures 0.15 ROR, completed in
Underground powerhouse 0.08
Remun All structures 0.12 ROR, completed in 2005
Asnhan No.2 Tanga arch dam 0.24 ROR, completed in
Other open structures 0.12
Underground powerhouse 0.06
Asahan No. 3 Intake weir 0.15 ROR, under construction
Open structures (more than 20m high) 0.12
Open structures (less than 20m high) 0.15
Underground structure 0.12
Peusangan All structures 0.15 ROR, under construction
2-6
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Peusangan
Lake Toba
Asahan No.2
Asahan No.3
Renun
Simonggo-2
Singkarak
Merangin
Tes-1
Musi Besai
In addition, these seismic events were recorded with different magnitudes, such as body wave
magnitude mb, surface wave magnitude Ms, and moment magnitude Mw. The saturation levels are for
mb=6.5, for ML=7.5 and for Ms=Mw=8.0 according to Kramer (2007).
The formulas used for the seismic hazard assessment are as follows.
Log(N) = a – bM (1)
Where N is the number of earthquakes per given time interval of magnitude greater than or
equal to M. a and b are Gutenberg-Richter coefficients for that seismic events.
2-7
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Where,
Around the project area, the cumulative number of earthquakes for the period of 100 years and of 200
years is shown in Figures 2.5 and 2.6, respectively. Accordingly, the peak horizontal ground
acceleration (a) at the damsite for each earthquake was estimated by the formulas of Cornell and
Estava for comparison. In the course of the preliminary seismic hazard assessment, the seismic sources
within 200-km radius around the weir site were assumed to be a seismic zone. The estimated peak
ground accelerations are summarized in Table 2.3 below.
100
10
1
5 6 7 8 9
Figure 2.5 Cumulative number of the earthquakes versus magnitude for the period of 100
years around the Simonggo2 project site
2-8
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
1000
Accumulated Frequency (Nc)
100
10
1
5 6 7 8 9
Accordingly, the probable peak ground acceleration, which was estimated with widely used Cornell
Formula at the weir site, was in a range of 0.10g to 0.14g for the return period of 100 and 200 years.
a d = Z × a c × v and k h = R × a d / g (4)
2-9
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
R: conversion factor
According to the ISM, the Simonggo-2 project site is located in Zone E, the zone correction
coefficient, Z, was thus taken to be 1.3 (intermediate value) according to Table 2.4. The correction
factor, v was given to be 0.80 for the weir site and 1.10 for the dike pond site (Table 2.5) for the rock
foundation. In addition, the conversion factor, R is generally in the range of 0.40 to 0.60 empirically
and was intermediately set to be 0.50.
The design seismic coefficients (kh) for the return periods of 100 and 200 estimated by the
above-mentioned formula are given in Table 2.7.
2-10
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
In addition, the Simonggo-2 project is located within highly seismically active zone, especially close
to the active fault – the Renun segment of the SFZ with an average slip rate of approximately 27
mm/year.
Accordingly, the design seismic coefficient for the per-feasibility study of the Simonggo-2 project is
recommended conservatively to be 0.15 for design of the weir and intermediate pond dike, and 0.18
for the design of other structures, respectively.
2-11
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
3.1 GENERAL
The geological investigation conducted at the prefeasibility stage for the Simanggo-2 project included
geological mapping, seismic refraction survey, and some laboratory tests for construction materials.
This chapter presents the geological survey results.
The sandstones with some interbedded slates belong to Kluet Formation of the Early Permian to Late
Carboniferous metamorphics and compose the bedrocks of the project area. These rocks are exposed
mainly on the mountain slopes of above elevation 450 meters around the project area. The headrace
tunnel, the surge tank and the penstock would be founded largely on these rocks.
A B Sandstone
Slate
Sandstone
Theses rocks generally strike N45W and dip 25 to 30 degrees to the north. As shown in Figure 3.2, the
3-1
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
sandstone at outcrops is in general grayish white, massive, slightly jointed and weathered. They can
just be broken by many blows of geological hammer at outcrops and therefore was considered to be
sound and to have an estimated uniaxial compressive strength of more than 50 MP. These rocks were
occasionally observed to be moderately to highly fractured or jointed especially associated with local
faulting (Figure 3.3).
A B
Figure 3.3 Highly fractured sandstones due to faulting on road cut slope
The welded tuff is of limited occurrence in the project area and is distributed solely along the
Simanggo River. The proposed weirs and powerhouse would be founded on the welded tuff.
The tuff A, presumably Quaternary age, is generally light gray, massive and slightly jointed mainly
with columnar joints (Figure 3.4). The joints within the tuffs were presumably due chiefly to cooling
and locally to faulting. The rocks are very hard and strong at outcrops and require more than one blow
of geological hammer to fracture it even at outcrops.
Accordingly the rocks were roughly estimated to have uniaxial compressive strength of more than 50
MP at fresh condition and of more than 20 MP at outcrops associated with slightly to moderately
weathering.
A B
Figure 3.4 Outcrops of tuff A, showing massive tuff (A) and columnar joints (B)
3-2
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
The tuff B is extensively distributed on the valleys and lower slopes of the project area. The
intermediate pond dikes, the weir abutments, the intakes and the connection tunnel between the weir
and the immediate pond would rest on the tuffs. These tuffs consist mostly of variably semi-welded to
unwelded pyroclastic-flow and fallout tephra deposits with some reworked materials. These tuffs, in
general gray, appear variable in terms of hardness, are mostly hard and stand vertically at their natural
conditions (Figure 3.5), and locally loose and susceptible to erosion and collapse. These tuffs consist
mainly of gravel and sand with some fine ash deposits, and can be classified as Gravelly SAND (SP)
or Silty SAND (SM) by the visual-manual procedure of ASTM.
A B
C D
Figure 3.5 Outcrops of tuff B along the Kasturi stream (A) and (B), as well as on road cut
slope (C) and (D)
In addition, surficial deposits locally overlie the tuffs, especially on the lower slopes of the project area.
These surficial deposits consist mainly of valley-fill alluvium, hillslope colluvium and reworked
pyroclastic materials. They are loose and approximately 1 to 5 m thick.
Three local faults were found along the valleys through topographical interpretation and geological
mapping. They are hereinafter called Simanggo fault sub-parallel to the Simanggo River, Kasturi fault
along the Kasturi river, and Sitapung fault along the Sitapung river, respectively.
3-3
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
The Kasturi fault shows a vertically shear zone within the Early Permian to Late Carboniferous
sandstone (Figure 3.6A) and a series of waterfalls within the Quaternary tuff A (Figure 3.6B). This
may indicate the fault is a strike slip faulting.
A B
Figure 3.6 Shear zone within sandstones (A) and a series of waterfalls within the tuff A (B)
In addition, the Kasturi river covered by Quaternary Tuff B is characterized by straight course and
deep V-shaped valley, this may indicates that the river valley is formed by faulting movement after
Quaternary. The river morphology and the surface trace of the Kasturi fault present in Quaternary Tuff
A within the Simanggo River indicate that the fault may be “potentially active” in geological terms, i.e.
movement since Quaternary.
For the fault to be considered a significant earthquake hazard that would influence the design of the
dam, it is necessary to determine whether movement has occurred on the fault within the last 10,000 to
20,000 years. At the site reconnaissance, no evidences of faulting during Holocene (the last 10,000
years) time or the surface traces within recent deposits were found with respect to these local faults.
Accordingly these faults seemed to inconclusively be active.
Moreover, although no large-scale soil collapse or landslide was identified either through
topographical interpretation or site reconnaissance; because of unfavorable geological features, stable
conditions of the tuff slopes are likely to be changed by slope alterations due to cut or fill, saturation of
slope materials from impounded water.
Accordingly some slope instability will be expected in the development of the project, such as
foundation excavation and pond impoundment.
3-4
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
A B
Figure 3.7 View of soil collapse and soil erosion in the project site
The locations of the seismic survey lines are shown in Figure 1.1. The interpreted seismic profiles are
given in Appendix B while the inferred geological classification is summarized in Table 3.1 below.
3-5
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
The interpreted seismic data indicate four velocity layers underlie the project site. The first layer with
velocity of less than 800 m/sec is consistent with surficial loose deposits such as talus, colluvial, and
riverbed material. The secondary layer with velocity varying from 1,000 m/sec to 1,800 m/sec is the
interpreted tuff B. The third layer has a fairly narrow range of low seismic velocity (1,800 to 2,000
m/sec). The velocity values correlate to slightly weathered, jointed tuff A (welded tuff) observed at
outcrops along the Simanggo river. Similarly the fourth layer is consistent with slightly weathered and
jointed sandstone/slate observed at rock outcrops along the proposed penstock route.
3.4.1 SAND
Some sand was needed for the fine aggregates of concrete, grout and mortar. Riverbed deposits on the
Simanggo River, around the powerhouse site (AS-1 through AS-5) and about 4 km upstream from the
Parlilitan village (AS-8), consisted mainly of fine to coars-grained sand (well graded SAND) and was
small in quantity.
On the other hand, riverbed deposits around the Beringin village, about 12 km far from the Parlilitan
village (AS-6) and along the Riman River around Sihombu Village, about 10 km far from the
powerhouse area (AS-7), were composed mainly of medium to coarse sands and were large in quantity.
Table 3.3 summarizes laboratory test results of the samples. Accordingly, the riverbed sand tested are
recommendable as fine concrete aggregates.
3-6
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
A B
3-7
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
As stated in Table 3.5 above, several sandstone quarry sites within and around the project site were
available in quality and quantity and therefore were recommended to be used.
3-8
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Figure 3.1 Geological map with location of sampling for construction material
3-9
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
4.1 GENERAL
At the prefeasibility study stage, three alternative layouts, Plan A, Plan B and Plan C were proposed
for comparison assessment purposes. Plan A, the Simanggo-2 project Site (1-1901-41) originally
proposed in HPPS2 in 1989, consisted of an intake weir, headrace tunnel, surge tank, penstock and a
surface power station. In order to effectively use the potential for hydropower generation and to
provide more peak load hydropower generation, Plan B and Plan C were proposed in the present study.
The general layouts of Plan B and Plan C were almost the same and both included an intake weir,
intermediate pond, connection and headrace tunnels, surge tank, penstock and a surface power station.
The following presents the preliminary geological conditions for the various project facilities
including weir, intermediate pond dike, connection tunnel, headrace tunnel, surge tank, penstock and
surface powerhouse.
Figure 4.1 shows geological conditions of the weir site B. The right and left abutment slopes are
underlain by partially welded tuff (Tuff B) which is covered by overburden of about 1 to 5 m thick.
The Simanngo valley is covered by welded tuff (Tuff A).
The tuff A at outcrops is generally massive, slightly jointed and weathered, and locally moderately
fractured by local faults or shear zones. The tuffs at outcrops can be classified as CM to CH class rock
mass based on Japanese Rock Classification Standard (Table 4.1). On the other hand, the tuff B at the
right and left abutment slopes is soft rocks and can be classified as D to CL class rock mass according
to Japanese Rock Classification Standard.
On the basis of the above preliminary geological assessment, the proposed weir site was considered to
4-1
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
be geologically suitable for the construction of the proposed concrete weir. The overburden overlying
the tuff B on the right/left abutment slopes generally ranges in thickness from 1.0 to 5.0 meters and
have low strength and high permeability. These deposits should be removed from the weir foundation.
Accordingly, the excavation depth of the weir foundation will be 1.0 to 5.0 meters in depth from the
ground surface at both abutments and zone meters from the riverbed at the river valley up to the top
surface of D - CL class rock mass within the tuff B and to the top surface of CM – CH class rock mass
within the tuff A, respectively. Locally highly fractured tuff A should also be removed.
Note: Japanese Standard by Central Research Institute of Electric Power Industry (CRIEPI).
In addition, because no in-situ and laboratory test results are available, the rock mass parameters, as
shown in Table 4.2 for design were roughly determined from the conventionally adopted empirical
table of design parameters (Table 4.3).
4-2
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Table 4.3 Japanese rock classification and empirically estimated rock parameters
Rock qu Es Ed c φ V
class (kgf/cm2) (kgf/cm2) (kgf/cm2) (kgf/cm2) (degree) (km/sec)
A-B Over 800 Over 80,000 Over 50,000 Over 40 55 – 65 Over 3.7
CH 800 - 400 80,000 - 40,000 50,000 - 20,000 40 - 20 40 – 55 3.0 – 3.7
CM 400 - 200 40,000 - 15,000 20,000 - 5,000 20 - 10 30 – 40 1.5 – 3.0
D-CL Below 200 Below 15,000 Below 5,000 Below 10 15 - 30 Below 1.7
Source: Rock classification and its application, K. Yoshinaka, et al., Japanese Society of Civil
Engineering, 1989.
Note: qu = Unconfined compressive strength, Es = Modulus of elasticity, Ed = Modulus of
deformation, c = Cohesion, φ= Internal friction angle, V= Velocity of elastic wave, 1 kgf/cm2
= 100 kPa = 0.1 MPa.
On the other hand, the geological condition of the weir site C is basically the same as that at the weir
site B. Similarly, the rock mass parameters of the weir site C were empirically determined and given
in Table 4.4.
4-3
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
The geology of the pond dike site, as shown in Figure 4.2, consists mainly of tuff B which is covered
by overburden deposits of 1 to 3 m in thickness. Generally the tuff B is partially welded or
semi-consolidated pyroclastic deposits. As indicated above, the tuff B can classified as D to CL class
rock. For the foundation of the pond dike embankment it is desirable to found on the tuff B of
relatively homogeneous quality in order to avoid irregular settlement of the dike embankment.
According to the conventionally adopted empirical table of design parameters, as shown in Table 4.3
above, the rock mass parameters for the design of the proposed pond dike embankment were roughly
determined and summarized in Table 4.5 below.
Table 4.5 Estimated rock mass parameters at the intermediate pond dike site B
Item River valley and left/right abutment Remarks
Geological unit Partially welded tuff (Tuff B)
Rock classification (Japanese standard) D – CL class rocks
3
Unit weight (ton/m ) 1.8
Unconfined compressive strength (MPa) 10
Internal friction anger (degree) 25°
Cohesion (kPa) 500
Deformation Modulus (MPa) 500
In addition, although no major faults are observed to be located within the intermediate pond dike site,
as mentioned above, the Kasturi fault – a local, old and inactive small fault is expected to traverse the
pond dike site. The fault and associated shear zone would largely contribute to potential for
liquefaction of foundation soil – partially welded tuff B. Accordingly the expected geological risk with
the tuff B foundation in the intermediate pond dike site is plastic deformation, differential settlement,
low strength value and bearing strength.
The geological condition of the pond dike site C is the same as that at the pond dike site B. The pond
4-4
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
dike embankment is expected to rest on the tuff B and the rock mass parameters of the pond dike site
C were empirically determined and given in Table 4.6.
Table 4.6 Estimated rock mass parameters at the intermediate pond dike site C
Item River valley and left/right abutment Remarks
Geological unit Partially welded tuff (Tuff B)
Rock classification (Japanese standard) D – CL class rocks
Unit weight (ton/m3) 1.8
Unconfined compressive strength (MPa) 10
Internal friction anger (degree) 25°
Cohesion (kPa) 500
Deformation Modulus (MPa) 500
No detailed geological survey was done for the tunnel route. On the basis of the geological mapping
and limited seismic refraction survey, the geology of the tunnel route is composed mainly of quartzose
sandstone with some interbedded slate between the proposed surge tank and intermediate pond, and
the tuff B between the proposed intermediate pond and weir, as shown in Figure 4.3.
The rock mass quality along the tunnel is expected to be classified in Japanese Standard as follows:
According to the conventionally adopted empirical table of design parameters, as shown in Table 4.3
above, the rock mass parameters for the design of the proposed tunnels were roughly determined and
summarized in Table 4.7 below.
Table 4.7 Estimated rock mass parameters for the waterway route
Item Headrace tunnel Connection tunnel
Geological unit Sandstone interbedded with slate Tuff B
Rock classification (Japanese standard) CM to B D to CL D to CL
Unit weight (ton/m3) 2.2 2.0 1.8
Unconfined compressive strength (MPa) 40 10 10
Internal friction anger (degree) 45° 25° 25°
Cohesion (kPa) 3,000 500 500
Deformation Modulus (MPa) 5,000 500 500
4-5
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
The D to CL class sandstone with some interbedded slate would be encountered mainly over some
meters at the inlet area associated highly weathered and jointed zone. The D to CL class zones
including tuff B will require more support and however are not expected to cause any major geological
problems during the tunnel excavation.
The surge tank is located in about 500 m away from the right bank slope of the Simanggo River. The
steep slope of the ridge trending east-west in direction will be excavated for surge tank construction
work. The surge tank will be excavated at an elevation of 540 m and is expected to be founded on
massive, slightly weathered and less jointed quartzose sandstone. The foundation rocks of the surge
tank are expected to be classified as CM to B class rock mass in Japanese Rock Classification
Standard.
Similarly, the penstock foundation will be located on the predominant sandstone bedrocks which can
be classified as CM to B class rock mass in Japanese Rock Classification Standard.
According to the conventionally adopted empirical table of design parameters, as shown in Table 4.3
above, the rock mass parameters for the design of the proposed tunnels were roughly determined and
summarized in Table 4.8 below.
Table 4.8 Estimated rock mass parameters for the surge tank and penstock area
Item Surge tank/Penstock Remarks
Geological unit Sandstone
Rock classification (Japanese standard) CM to B
3
Unit weight (ton/m ) 2.2
Unconfined compressive strength (MPa) 40
Internal friction anger (degree) 45°
Cohesion (kPa) 3,000
Deformation Modulus (MPa) 5,000
The exposed tuff A, as observed around the intake weir sites, is generally massive, slightly jointed and
weathered, and can be classified as CM to CH class rock mass based on Japanese Rock Classification
4-6
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Standard. Furthermore, the overburden is thin. Accordingly, no foundation problems are expected for
the construction of the proposed surface powerhouse at the planned powerhouse site.
Similarly, the rock mass quality and design parameters of the powerhouse were empirically
determined and given in Table 4.9.
Table 4.9 Estimated rock mass parameters for the powerhouse site
Item Powerhouse site Remarks
Geological unit Tuff A
Rock classification (Japanese standard) CM – CH class rocks
Unit weight (ton/m3) 2.0
Unconfined compressive strength (MPa) 20
Internal friction anger (degree) 35°
Cohesion (kPa) 3,000
Deformation Modulus (MPa) 2,000
4-7
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Figure 4.1 Geological Section of the Weir Axis Alternative B
4-8
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Figure 4.2 Geological Section of the Intermediate Pond Axis Alternative B
4-9
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
Figure 4.3 Geological Section along the Connection and Headrace Tunnel Alignment Alternative B
4-10
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
- The geology of the project site consists mainly of Early Permian to Late Carboniferous
metamorphic sandstone/slate and Quaternary tuff B (partially welded tuff) with a limited
occurrence of Quaternary tuff A (welded tuff). Except for several local and inactive faults, no
major faults were observed within the project site.
- The proposed weirs were expected to be founded on the tuff A for the river valley and tuff B for
abutments, the intermediate pond dikes on the tuff B, the connection tunnel on the tuff B, the
headrace tunnel on the sandstone, the surge tank and penstock on the sandstone, and the
powerhouse on the tuff A. These foundation rocks were not expected to cause any major
geological problems associated with the construction of the proposed project structures.
- The geological conditions at alternative Plan B and Plan C are similar considering rock mass
quality and geological profiles.
- Slope instability associated with the development of the project would occur especially within
the tuff B but will be manageable technically and economically because of their small size.
- Some sandstone quarry sites within the project site are appropriate potential construction
material sources in quality and quantity, and no noticeable problems were found out by
laboratory test. On the other hand, alluvial sands alone the Simanggo River and Riman River in
the proximity of the project site are available in quality but small in quantity.
- The project site is located within a region of high seismic activity and the project structures
should thus be designed to withstand the expected level of earthquake-induced ground shaking.
The design seismic coefficient for the per-feasibility study of the Simonggo-2 project is
recommended conservatively to be 0.15 for the design of the weir and intermediate pond dike,
and 0.18 for the design of other structures, respectively.
5-1
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
- Reservoir rim slope stability behind the intermediate pond - Earthquake-induced landslides of
reservoir slopes.
The intermediate pond dike is planned to rest on the tuff B - partially welded tuff. The tuff B is
expected to have a low strength and small bearing capacity. In addition, the Kasturi fault will traverse
the intermediate pond dike foundation. The fault and associated shear zone would largely contribute to
potential for liquefaction of the foundation tuff B and lead to decreased strength and bearing capacity
of the foundation tuff B.
Accordingly the expected geological hazard with the foundation tuff B in the intermediate pond dike
site is plastic deformation, differential settlement, low strength value and bearing strength. Additional
boring investigations will be required to explore and evaluate foundation rock mass conditions.
The reservoir rim slopes behind the intermediate pond are extensively covered by the tuff B. The tuff
B, semi-consolidated to non-consolidated pyroclastic deposits, consists mainly of coarse-grained sand
and fine-grained volcanical ash. These volcanical deposits are generally hard and stable at their natural
condition but seem to be susceptible to erosion by action of running water; deep gulley erosion and
associated collapse are common in the volcanical deposits.
These have a low potential for liquefaction during strong earthquake shaking, especially after
impoundment. Once liquefied, large-scale landslides due to liquefaction would occur along the rim
slopes of the intermediate pond. These landslides would lead to great reduction of the intermediate
pond storage capacity by sediment accumulation and even cause dike embankment collapse at worst
case.
As previously mentioned, the Kasturi fault traverses the planned intermediate pond site. Further,
topographical interpretation and brief site reconnaissance indicate a probability of Quaternary fault.
Having moved within the last 10,000 years (since Holocene), the fault would be most susceptible to
5-2
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
renewed activity. If so, the fault would pose a surface-rupture hazard to the planned intermediate pond
dike. Accordingly the seismic hazard of the fault has to be explored and evaluated in detail in terms of
surface rupturing and activity.
Because no laboratory and in-situ test data for foundation rocks are obtained, it is thus difficult to
evaluate the rock mass conditions and mechanical properties of the foundation rocks. For the purpose
of preliminary design of the project structures, it is recommended to use the roughly estimated rock
mass parameters according to the conventionally adopted empirical table of design parameters, as
given in Chapter 4, Geological and Geotechnical Conditions of the Project Site.
The main cut slopes in the project site will be excavated at the following locations:
These cut areas or slopes will be associated with the following geological units:
- Sandstone interbedded with slate – Slightly jointed and weathered, massive, hard rock
Because no geotechnical data are available for determining the strength properties of these rocks to
give a reasonable factor of safety for the design of the cut slopes, empirical geometric standards for cut
slopes are referred to determine the stable cut slopes.
The slope inclinations adopted for the various geological units are as follows:
5-3
Project for Master Plans Study of Hydropower Development Volume IV, Geology
In Indonesia Geological Survey for Simanggo-2 HPP
In addition, for design of cut slopes, especially within the tuff B, measures are taken in order to drain
the slopes and take care of the surface water. Diverting water away from the slope by introducing
ditches is often recommendable.
1) To explore and evaluate subsurface conditions of the project sites for the development of the
ROR-type hydropower projects.
2) To provide geotechnical data and parameters necessary for geotechnical analyses and design of the
proposed projects in the Feasibility Study.
3) To confirm and provide solution against geological hazards or problems that may arise due to
subsurface conditions.
The geological and geotechnical investigation works is suggested to consist main of 1) Detailed
geological mapping around the main project structure sites, 2) Boring investigation and related in-situ
tests, and 3) Laboratory test for foundation rocks. Table 5.1 gives the recommended boring
investigations and relevant in-situ tests.
5-4
Appendix A
Line-1.2
Line-1.3
Line-2
Line-3.1
Line-3.2
Line-4.1
Line-4.2
Line-4.3
Line-4.4
Line-4.5
Line-5.1
Line-5.2
Line-5.3
Line-6
Line-7.1
Line-7.2
Line-8.1
Line-8.2
Line-9.1
Line-9.2
Line-9.3
Line-10.1
Line-10.2
Line-11.1
Line-11.2
Line-11.3
Line-12
Line-13.1
Line-13.2
Line-14
Vp-1 <800m/sec