1. CREATE PURCHASE REQUSITION: - TCODE (ME51N)
SAPMENU-LOGISTICS-MATERIAL MANAGEMENT-PURCHASING-PURCHASE REQUISITION-ME51N-
EXECUTE-FOLLOW STEPS
S1
HERE CHOOSE YR PR DOCUMENT TYPE, SOURCE DETERMINATION AND IN HEADER U CAN PUT TEXT IN
ITEM OVERVIEW PUT DETAILS LIKE MATERIAL, QUANTITY, PLANT & IN ITEM PUT ALL RELEVANT DATA
IN ALL REQUIRED TAB THEN CLICK ON CHECK AND SAVE AS SHOWN IN S1
S2
HERE CLICK ON OTHER PURCHASE REQUISITION AS SHOWN IN S2
Page | 1
S3
HERE CHOOSE PR AND PUT THE PR NUMBER AND HIT ENTER AS SHOWN IN S3
S4
HERE U CAN CHANGE IN HEADER TEXT, IN ITEM OVERVIEW CHANGE LIKE QUANTITY, DELIVERY DATE,
PURCHASE GROUP AND OTHER DETAIL & IN ITEM CHANGE ALL RELEVANT DATA IN ALL REQUIRED TAB
THEN CLICK ON CHECK AND SAVE AS SHOWN IN S4
S5
THEN SYSTEM WILL GIVE THIS MESSAGE AS SHOWN IN S5 AND PROCESS COMPLETE
Page | 2
S6
HERE CLICK ON OTHER PURCHASE REQUISITION AS SHOWN IN S6
S7
HERE CHOOSE PR AND PUT THE PR NUMBER AND HIT ENTER AS SHOWN IN S7
S8
HERE U CAN DISPLAY HEADER TEXT IN HEADER, IN ITEM OVERVIEW DISPLAY DATA LIKE QUANTITY,
PLANT, DELIVERY DATE, PURCHASE GROUP AND OTHER DETAIL & IN ITEM U CAN SEE ALL DATA IN
REQUIRED TAB THEN CLICK ON BACK AS SHOWN IN S8
Page | 3
S9
HERE SELECT TABLE AND CLICK ON FIELDS AS SHOWN IN S9
S10
HERE SELECT TABLE AND CLICK ON EXECUTE AS SHOWN IN S10
S11
HERE PUT PR NUMBER AND CLICK ON EXECUTE AS SHOWN IN S11
S12
HERE PUT THE NEW VALUE AND CLICK ON CARRY OUT MASS CHANGE AND SAVE AS SHOWN IN S12
Page | 4
S13
THEN SYSTEM WILL GIVE THIS MESSAGE AND CLICK ON BACK AS SHOWN IN S13 AND PROCESS
COMPLETE HERE AS A RESULT DATA WILL BE CHANGE AT A TIME IN NUMBER OF PR
S14
HERE CLICK ON RELEASE STRATEGY TAB AND CLICK ON RELEASE BUTTON AGAINST THE CODE AND
CLICK ON SAVE AS SHOWN IN S14
Page | 5
S15
HERE PUT RELEASE CODE, GROUP, ACTIVE OVERALL OR ITEM WISE RELEASE AND CLICK ON EXECUTE
AS SHOWN IN S15
S16
HERE ACTIVE THE CHECK BOX AGAINST THE REQUIRED DOCUMENT AND CLICK ON SAVE AND BACK
THEN AGAIN PUT THE SECOND CODE AND RELEASE THE DOCUMENT IN SAME PROCESS
S17
HERE PUT MATERIAL, PURCHASE GROUP, PLANT, MATERIAL GROUP AND OTHER DETAILS AND CLICK
ON EXECUTE AS SHOWN IN S17
Page | 6
S18
HERE U CAN FIND THE ALL PR ACCORDING TO THE INPUT MADE IN S17 & CLICK ON BACK AS SHOWN
IN S18
S19
HERE PUT THE COST CENTER AND CLICK ON EXECUTE AS SHOWN IN S19
S20
HERE SYSTEM WILL DISPLAY ALL ACCOUNT ASSIGNED PR & CLICK ON BACK AS SHOWN IN S20
Page | 7
9. DISPLAY LIST OF PR (SERVICE): - TCODE (MSRV2)
SAPMENU-LOGISTICS-MATERIAL MANAGEMENT-PURCHASING-PURCHASE REQUISITION-LIST DISPLAY-
MSRV2-EXECUTE-FOLLOW STEPS
S21
HERE PUT THE SERVICE NUMBER, PURCHASE ORG, MATERIAL GROUP AND ACTIVE THE PR CHECK BOX
AND CLICK ON EXECUTE AS SHOWN IN S21
S22
HERE U CAN FIND THE DETAILS OF SERVICE PR AND CLICK ON BACK AS SHOWN IN S22
S23
HERE PUT TRACKING NUMBER, PURCHASE ORG, PLANT, OTHER DETAIL AND CLICK ON EXECUTE AS
SHOWN IN S23
Page | 8
S24
HERE SYSTEM WILL DISPLAY THE TRANSACTIONS PER TRACKING NUMBER THEN CLICK ON BACK AS
SHOWN IN S24 (BUT U HAVE TO USE TRACKING NUMBER DURING TRANSACTIONS LIKE PR, PO, RFQ,
CONTRACT BEFORE EXECUTING THIS TCODE)
S25
HERE PUT PR NUMBER AND CLICK ON EXECUTE AS SHOWN IN S25
S26
THEN ACTIVE THE CHECK BOX & CLICK EITHER AUTOMATICALLY OR MANUALLY TO ASSIGN A VENDOR
TO THE PR AS SHOWN IN S26
S27
Page | 9
IF U CLICK AUTOMATICALLY IN S26 THEN IT WILL COME FROM SOURCE LIST & IF U CLICK MANUALLY
THEN U HAVE TO GIVE A VENDOR, PURCHASE ORG DETAIL AND HIT ENTER AS SHOWN IN S27
S28
HERE U WILL FIND ANOTHER LINE OF VENDOR AFTER ASSIGN AND CLICK ON SAVE AS SHOWN IN S28
S29
THEN SYSTEM WILL GIVE THIS MESSAGE AS SHOWN IN S29 AND PROCESS COMPLETE HERE
S30
HERE PUT PR NUMBER AND CLICK ON EXECUTE AS SHOWN IN S30
S31
THEN ACTIVE THE CHECK BOX & CLICK EITHER AUTOMATICALLY OR MANUALLY TO ASSIGN A VENDOR
TO THE PR AS SHOWN IN S31
Page | 10
S32
IF U CLICK AUTOMATICALLY IN S31 THEN IT WILL COME FROM SOURCE LIST & IF U CLICK MANUALLY
THEN U HAVE TO GIVE A VENDOR, PURCHASE ORG DETAIL AND HIT ENTER AS SHOWN IN S32
S33
HERE U WILL FIND ANOTHER LINE OF VENDOR AFTER ASSIGN & CLICK ON ASSIGNMENTS AS SHOWN
IN S33
S34
HERE U CAN FIND THE NUMBER OF REQUSITIONS ARE PENDING TO CONVERT INTO PO SO PUT THE
CURSOR POINT ON COMPANY CODE AND CLICK ON PROESS ASSIGNMENT AS SHOWN IN S34
S35
HERE PUT THE DETAILS FOR PO AND HIT ENTER AS SHOWN IN S35
Page | 11
S36
HERE SELECT THE PR & CLICK ON ADOPT THEN ALL DATA WILL COME COPIED FROM THE REQUSITION
TO THE PO SCREEN THEN CHECK ALL DATA IN HEADER AND ITEM THEN CLICK ON CHECK AND SAVE AS
SHOWN IN S36
S37
HERE PUT REQUIRED DETAIL AND CLICK ON EXECUTE AS SHOWN IN S37
S38
HERE U CAN FIND THE NUMBER OF REQUSITIONS ARE PENDING TO CONVERT INTO PO SO PUT THE
CURSOR POINT ON COMPANY CODE AND CLICK ON PROESS ASSIGNMENT AS SHOWN IN S38
Page | 12
S39
HERE PUT PO DETAILS AND HIT ENTER AS SHOWN IN S39
S40
HERE SELECT THE PR & CLICK ON ADOPT THEN ALL DATA WILL COME COPIED FROM THE REQUSITION
TO THE PO SCREEN THEN CHECK ALL DATA IN HEADER AND ITEM THEN CLICK ON CHECK AND SAVE AS
SHOWN IN S40 (U CAN ALSO ADOPT MULTIPLE PR INTO ONE PO BUT VENDOR MUST BE SAME)
S41
Page | 13
HERE PUT REQUIRED DATA AND ACTIVE THE REQUIRED CHECK BOX THEN CLICK ON EXECUTE AS
SHOWN IN S41
S42
HERE SYSTEM WILL GIVE THIS MESSAGE AND AUTOMATICALLY CREATE A PO NUMBER THEN CLICK ON
BACK AS SHOWN IN S42 (BEFORE EXECUTING ME59N U HAVE TO MAINTAIN THE FOLLOWING STEPS)