Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
TR-106857-V9
WO4109
Prepared by
Applied Resource Management
313 Nobles Lane
Corrales, New Mexico
Principal Investigators
David Worledge, Applied Resource Management
Glenn Hinchcliffe, EPRI NDE Center
Prepared for
Electric Power Research Institute
3412 Hillview Avenue
Palo Alto, California 94304
(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH RESPECT
TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS
REPORT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH
USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S
INTELLECTUAL PROPERTY, OR (III) THAT THIS REPORT IS SUITABLE TO ANY PARTICULAR USER'S
CIRCUMSTANCE; OR
(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY
CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE HAS BEEN ADVISED OF THE
POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS REPORT OR ANY
INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS REPORT.
Key Words: Preventive maintenance, Maintenance optimization, Component reliability, Power plant
reliability
ORDERING INFORMATION
Requests for copies of this report should be directed to the EPRI Distribution Center, 207
Coggins Drive, P.O. Box 23205, Pleasant Hill, CA 94523, (510) 934-4212.
Electric Power Research Institute and EPRI are registered service marks of Electric Power Research
Institute, Inc.
Copyright © 1997 Electric Power Research Institute, Inc. All rights reserved.
ii
REPORT SUMMARY
________________________________________________________________________
U.S. nuclear plants are implementing preventive maintenance (PM) tasks with
little documented basis beyond fundamental vendor information to support the
tasks or their intervals. The Preventive Maintenance Basis project provides
utilities with the technical basis for PM tasks and task intervals associated with
40 specific components such as valves, electric motors, pumps, and HVAC
equipment. This report provides an overview of the PM Basis project and
describes use of the PM Basis database.
Background
A large fraction of U.S. nuclear plants are reducing PM costs and improving
equipment performance by more closely matching PM tasks with the functional
importance of equipment. For this to succeed, utilities require information on the
most appropriate tasks and task intervals for the major equipment types,
accounting for the influences of duty cycle and service conditions. Previously,
this data did not exist in an accessible form, often resulting in arbitrary and
unsuitable tasks and intervals which increased maintenance costs and
diminished reliability. The PM Basis project was developed in response to
requests by the EPRI nuclear membership to provide a technical basis beyond
vendor information and recommendations for assigning PM tasks to plant
components.
Objective
To provide an essential reference on PM task selection and intervals for 40
common major nuclear power plant components.
Approach
Expert panels composed of knowledgeable individuals from EPRI, EPRI member
utilities, and manufacturers formulated the bases and range of PM task options
for selected equipment. Most of the expert panels addressed a small number of
closely associated component types, such as three types of pressure relief valves.
A utility oversight committee, the PM Basis steering committee, directed this
process. While the inclusion of any equipment-specific recommendations was
made by the individual expert panels, the steering committee maintained
purview over the project structure and process, selected and prioritized
component types, assisted with expert panel member recruiting, and approved
the consensus method employed for establishing the PM tasks, task intervals,
and rationales. The PM Basis Project Steering Committee was also accountable to
the EPRI Operations and Maintenance Cost Control Target Steering Committee
for ensuring all utility needs were considered and met.
iii
Results
The PM Basis will serve the nuclear utility maintenance community as an
essential reference for PM task selection for 40 common major components,
including major mechanical, electrical, and heat transfer classes. Each PM Basis
report explains 1) the approach used to develop the PM basis and the strategic
considerations that influenced the working group, 2) the recommended PM
program in a concise format, including task interval recommendations, and 3) a
tabular summary of degradation and failure mechanism information obtained
by direct interviews.
Each report describes the technical basis behind PM tasks and the relationship
between failure locations, failure mechanisms, influences on equipment
degradation, and timing of failures. Tasks are divided according to three
categories: condition monitoring to measure the progression toward failure so
that corrective action can be planned or initiated, time-directed to prevent failure
by performing scheduled maintenance, and failure finding to identify a failed
condition so that corrective maintenance can be initiated. These three task types
comprise the basic set of PM strategies employed by the majority of nuclear
utilities.
This report contains an overview of the objectives, project organization, and the
process used in developing the 40 individual component PM programs and
supporting technical bases. The report also describes the information in each of
the component reports and how this information is to be interpreted. Finally,
this overview considers how the component reports and technical bases can be
used in utility projects such as PM optimization, PM audits, program
development, and training. Each component report is individually presented as
a separate volume of this series, scheduled for completion by the end of 1998.
EPRI Perspective
The 40-volume PM Basis will be an essential reference for utilities seeking to
validate their current PM program, and those wishing to perform PM tasks less
frequently as part of a living maintenance program. It will also prove invaluable
for utilities performing PM audits or working to establish a balance between
reliability and availability under the NRC maintenance rule, 10CFR50.65.
Finally, the PM Basis will help promote consistency in utility PM programs,
enhance maintenance personnel training, and contribute to greater equipment
reliability. EPRI’s Preventive Maintenance Basis Project Brochure listing specific
components is available through the EPRI project manager.
Interest Categories: Assessment and optimization, Motors and pumps, Turbines
and generators, Valves
iv
TABLE OF CONTENTS
________________________________________________________________________
1. INTRODUCTION.................................................................................................. 1-1
1.1 Purpose............................................................................................................... 1-1
1.2 Contents ............................................................................................................. 1-1
1.3 Approach ............................................................................................................ 1-2
1.4 Use of Vendor Manuals ....................................................................................... 1-4
1.5 Determination of Time-Directed Task Intervals ................................................... 1-4
1.6 Design Changes That May Increase Task Intervals .............................................. 1-5
1.7 Component Boundary Description ....................................................................... 1-6
1.8 General References ............................................................................................. 1-6
1.9 Industry References: ANSI, IEEE, INPO, NRC .................................................. 1-7
2. PREVENTIVE MAINTENANCE TEMPLATE...................................................2-1
2.1 Medium Voltage Motors PM TEMPLATE ......................................................... 2-1
2.2 Template Notes and Definitions: .......................................................................... 2-2
2.3 PM Application Notes: ........................................................................................ 2-4
2.3.1 Thermography............................................................................................. 2-4
2.3.2 Vibration Monitoring .................................................................................. 2-5
2.3.3 Oil Analysis ................................................................................................. 2-5
2.3.4 Electrical Tests - On-Line............................................................................ 2-6
2.3.5 Mechanical Tests - On-Line......................................................................... 2-7
2.3.6 Electrical Tests - Off-Line ........................................................................... 2-8
2.3.7 Mechanical Tests - Off-Line ...................................................................... 2-10
2.3.8 External Visual Inspection ......................................................................... 2-11
2.3.9 Partial Disassembly and Inspection ............................................................ 2-12
2.3.10 Partial Refurbishment .............................................................................. 2-14
2.3.11 Refurbishment ......................................................................................... 2-14
2.3.12 Functional Tests ...................................................................................... 2-16
2.4 Examples of Components Satisfying Template Conditions ................................. 2-17
2.5 Definitions of Template Application Conditions: ................................................ 2-18
2.5.1 Critical ...................................................................................................... 2-18
2.5.2 Duty Cycle Definitions .............................................................................. 2-18
2.5.3 Service Condition ...................................................................................... 2-18
3. PM STRATEGY TO ADDRESS DEGRADATION MECHANISMS.................3-1
3.1 Building A PM Strategy ...................................................................................... 3-1
3.2 Failure Locations, Degradation Mechanisms, and PM Strategies .......................... 3-3
3.3 PM Tasks and their Degradation Mechanisms .................................................... 3-31
v
LIST OF TABLES
________________________________________________________________________
vi
1
INTRODUCTION
________________________________________________________________________
1.1 Purpose
This document provides a program of preventive maintenance (PM) tasks suitable for
application to medium voltage (between 1kV and 5kV) electric motors in nuclear power
plants. The PM tasks that are recommended provide a cost-effective way to intercept the
causes and mechanisms that lead to degradation and failure. They can be used, in
conjunction with material form other sources, to develop a complete PM program or to
improve an existing program. Users of this information will be utility managers,
supervisors, craft technicians, and training instructors responsible for developing,
optimizing, or fine-tuning PM programs.
Reactor Coolant Pumps motors ( RCPs) are not excluded from this report in so far as
good PM practices for motors of the appropriate class are concerned. However, the
special auxiliary equipment normally associated with RCPs has not been included.
Consequently, this report does not provide a complete PM program for RCPs. Industry
and vendor programs for RCPs should be consulted for complete definition of RCP
motor PM programs.
1.2 Contents
Section 1 explains the approach used to develop the PM basis and the strategic
considerations that influenced the expert working group. The PM basis is described in
terms of a component boundary that includes the motor, motor mount, electrical cabling,
detectors, lubrication, and cooling connections.
1-1
Section 3 contains a tabular summary of degradation and failure mechanism information
for medium voltage (between 1kV and 5kV) electric motors obtained by direct interviews
with the expert panel members. The data contained represents the panels opinions of the
factors that influence failure: 1) where failures are most likely to occur, 2) how these
failures exhibit themselves, 3) the degradation mechanisms, 4) the factors that influence
the degradation, 5) how the degradation progresses over time, 6) the opportunities to
recognize the on-set or status of the degradation, and 7) the PM actions and strategies that
can be employed to discover or prevent the failure from occurring.
1.3 Approach
A utility steering committee and chairman provide overall direction to this project. The
broad objective is to develop a PM Basis for a large number of component types using
information supplied by the industry. The steering committee provided assistance with
identifying expert panel members and with soliciting the support of their organizations.
An analysis of causes of failures of medium voltage motors was taken from previous
NMAC analysis (1) of NPRDS data, and from a Brookhaven National Laboratory report
(2) on aging of large electric motors. Other inputs to the expert group consisted of PM
templates for large motors previously prepared by ComEd and by PECO Energy.
The PM Basis Database project utilized a process through which the expert group reaches
agreement on the details of the template and its supporting basis information. Major
process steps are:
1) review of maintenance and failure cause data obtained from relevant EPRI
NMAC guides to categorize failure types and to gauge the relative effectiveness of
current maintenance practices,
2) determine if the component type needs to be sub-divided into logical groups by
design characteristics. It was determined that AC motors should be divided into
high voltage motors, i.e. those designed for greater than 5kV; a medium
1-2
voltage group for motors between 1kV and 5 kV, the subject of this report; and
low voltage motors for those 600V and below. In addition, DC motors form a
fourth group.
3) define the motor boundary and the components, and subcomponents that are to
be included when considering PM tasks,
4) establish the service conditions and duty cycles that impact PM strategies and
what their influences are,
5) establish a preliminary PM task list to assist in defining how failure causes can
be discovered,
6) divide the component into major maintainable subgroups (e.g. mechanical
components, and electrical components),
7) establish subcomponent failure locations (e.g. open rotor bars),
8) assign degradation processes, the factors that influence the degradation, and the
time characteristics of the progression to failure,
9) describe the discovery opportunities for each of the subcomponent failure
locations, and
10) list the PM strategies and tasks considered by the expert panel to be effective
in discovering degradation and prevention and preventing the onset of the failure
mechanism, or in returning the component to an as new condition through
accepted preventive maintenance techniques.
The remainder of the process for developing effective PM strategies and their
supportive bases is:
11) develop the final PM task list including the task content,
12) list the dominant causes of component failure in order to provide additional
focus to the PM program,
13) develop a maintenance template providing PM tasks and task intervals which
summarize and capture the information developed in the previous items,
14) provide a list of component examples for the eight combinations of criticality,
duty cycle, and service condition (e.g. Essential Raw Cooling Water motors would
be one example of a motor that was considered to be critical, to have a high duty
cycle, and to experience severe service conditions),
15) perform a sanity check on the cost-effectiveness of the not critical but
important template columns to verify that the proper intervals and tasks were
selected when compared to those in the critical columns,
16) revisit the PM basis matrix to determine that the quantitative limits on failure-
free periods, and the randomness of failure times, are properly reflected in the
template intervals (every degradation process should be covered effectively by
some PM task and with adequate timing to prevent or discover the failure),
17) list the key component degradation processes that control the task intervals on
the template for use in interval extension,
18) describe design improvements that are either available or are needed to
improve reliability or to decrease the cost of preventive maintenance, and
1-3
19) develop a list of recent NRC and INPO reports.
The basis for departures from vendor recommendations need to be carefully considered
and documented. The information in this report should enable decisions involving
departures from vendor recommendations to be made with a greater awareness of the
specific failure causes that are involved, and the indications of degradation that can show
whether or not the decision was appropriate as time passes. It is recognized that a specific
PM task may address many failure causes that are also addressed by other tasks. This may
provide for over lapping between tasks that can make such decisions less critical by the
adoption of compensating actions.
Intervals are to be determined and adjusted by each utility based on individual plant
experience and OEM information notices. Intervals provided in the template are
suggested starting points for this process, although in general, where these tasks are
already being performed, the existing intervals could be used as the starting point
providing a basis exists. Such a basis could be constructed from diagnostic data, past
inspection data and failure history, and from information in this document. A key point is
that it is prudent to change overhaul intervals in the search for intervals that are short
enough to protect against unacceptable equipment deterioration, but not so short as to
waste maintenance resources or to introduce unnecessary sources of maintenance error.
1-4
When selecting time intervals for overhauls and for internal inspections, it is not
necessarily conservative to select shorter rather than longer time intervals in a possible
range. Shorter intervals expose the equipment to more opportunities for maintenance
error and to the potential for non-optimal setup. Furthermore, reliability data for other
complex plant component types suggests that components receiving a higher proportion of
intrusive preventive maintenance tasks may experience many more failures than those
which receive predominantly non-intrusive maintenance. While similar data was not
available for medium voltage electric motors, the expert group had the opinion that
intrusive maintenance for motors does not carry a significant risk of introducing additional
failures, at least not in relation to the risk of not doing the maintenance. An additional
factor is that approximately two thirds of motor failures are caused by the driven
equipment (2). The expert group thought that at many utilities medium voltage electric
motors suffer from too little preventive maintenance, not from too much. Nevertheless,
good practice suggests that performing the right maintenance only at the right time is a
major step in improving or maintaining good performance. This statement applies
particularly to refurbishment; reliability is likely to be improved by performing motor
refurbishment very carefully and only at the correct time intervals.
The process of selecting time intervals for condition monitoring tasks should include
consideration for providing an adequate amount of data for use in extending time-directed
task intervals. Condition monitoring intervals should be shorter than time-directed
intervals.
Users are cautioned that an appropriate level of design review is required before
eliminating or changing the design of any component. Some suggested changes or
improvements noted by the expert panel were:
• Use of removable brush holder assemblies
• Use of more durable brushes
• Installation of permanently mounted external vibration monitoring.
• Installation of run time measurement to assist in determining proper
maintenance intervals.
• Use of premium lubricants such as polyurea gel greases, and synthetic or semi-
synthetic oils
1-5
• Use of Class H premium winding insulation materials in concert with a VPI
(vacuum pressure impregnation) insulation process
• Use of quick electrical disconnects with removable / reusable connection
insulation systems
The boundary of a medium voltage electric motor for the purpose of this database is
defined to include the following:
• Electric motor and motor shaft excluding the coupling
• All power, sensing, and control cables up to but not including the switchgear
breaker
• Motor mounting and base
• Surge capacitors, if present
• Bearing and stator cooling water connections excluding all valves and piping
external to the motors shell or frame
• Air filters, if present
• Internal motor heaters
• Detectors such as, temperature, vibration, and alarms
Note this program assumes that the motors are in nominally good condition to begin with.
Motors that have not been serviced for a long time may need to have an overhaul or a
detailed inspection performed before this program is applied.
1. Electric Motor Predictive and Preventive Maintenance Guide, EPRI (NMAC) NP-
7502, July 1992.
2. Aging Assessment of Large Electric Motors in Nuclear Power Plants, NRC
NUREG/CR-6336 (BNL-NUREG-52460), March 1996.
3. Manual of Bearing Failures and Repair in Power Plant Rotating Equipment, EPRI
GS-7352, July 1991.
4. Temporary Operation of Motors with Cut-Out Coils, EPRI EL-4059, June 1985.
1-6
5. Electrical References Series: Vol. 17 - Guide for Rewinding and Reconditioning
Medium Voltage Electric Motors, EPRI EL-5036- V-17, June 1996.
6. The Detection of Broken Bars in Motors, EPRI GS-6589-L, January 1990.
7. Guidelines for the Selection, Procurement, and Acceptance of Nuclear Safety Related
Mild Environment Motor Insulation for Rewinds, EPRI TR-103585.
8. Guidelines for the Selection, Procurement, and Acceptance of Nuclear Safety Related
Harsh Environment Motor Insulation for Rewinds, EPRI TR-104872.
9. Guidelines for the Repair of Nuclear Power Plant Safety-Related Motors (NCIG-12),
EPRI NP-6407, March 1990.
Owing to the large number of industry references relating to specific regulatory notices,
and testing requirements, and instructions for each of the major manufacturers, the reader
is referred to the listing of these sources which can be found in the EPRI NMAC report
listed in section 1.8. The following are references that have appeared since January 1,
1994.
1-7
1-8
2
PREVENTIVE MAINTENANCE TEMPLATE
_____________________________________________________________________________________________________________
2-1
2.2 Template Notes and Definitions:
General Notes:
NOTE 1: The Expert Panel felt there was sufficient cause to perform tasks with intervals
stated in years as close as possible to the intervals indicated in the template
unless specific means are employed to add confidence that a more extended
interval can be used (e.g. visual inspection, the use of condition monitoring,
maintenance history, and as-found conditions).
NOTE 2: If the component operates in severe service conditions, the plant specific
conditions must be considered in order to select appropriate intervals.
NOTE 3: If there are plant specific conditions (i.e. one or more columns) for which no
PM task is appropriate, this is considered to be Run-To-Failure (RTF). RTF is
only a maintenance option for those non-critical components that meet all the
following conditions:
• The component is not required for vital system redundancy,
• The components failure does not promote failure of other components,
• There is no increased personnel radiation exposure if the component is run
to failure,
• It is more cost-effective to repair or replace the component than to do
preventive maintenance,
• There is no simple cost-effective task to maintain the component.
NOTE 4: After completion of any action that could affect component function, it is
prudent to verify that the component operates in an acceptable manner, whether
or not this is required by applicable regulations.
2-2
NOTE 5: Existing Technical Specifications and other regulatory requirements, e.g. ASME
Section XI and other licensing commitments, should always be followed.
Moreover, there are parts of ASME Section XI which can be employed for
trending condition monitoring data such as vibration levels and bearing
temperatures. If the above recommendations differ from these regulations the
more conservative approach should be followed. Appropriate task interval
determination could lead to recommendations for intervals which differ from the
existing regulations. In such cases, there may be a basis for seeking changes to
the regulations.
NOTE 6: Although the off-line tests require the investment of significant maintenance
resources, the intervals for both the on-line and the off-line tests have been
stated to be the same on the Template for non-critical motors as they are for the
critical motors, on the basis that these are very large and expensive motors.
Non-critical motors could be the subject of interval extension studies, especially
for the mechanical off-line task where the borescope examination takes some
time to complete, and many of the degradation processes addressed are also
covered by vibration monitoring, on-line testing, and external inspection.
NOTE 7: If a problem appears on the driven element it is prudent to examine the relevant
aspects of the motor for associated degradation.
NOTE 8: The use of grease is unusual in this class of motors but some motors may have
some greased bearings, see the vendor manual on greasing or follow the
greasing program outlined in EPRI NMAC NP-7502.
NOTE 9: Air filter changes should follow plant a specific filter replacement program or
vendor recommendations appropriate to the environment and duty cycle.
2-3
2.3 PM Application Notes:
2.3.1 Thermography
In some instances, e.g. the impairment of the oil pumping action caused by excessive oil in
vertical configuration bearings, the degradation could be sufficiently rapid that
thermography at a 6 month interval would not be an effective method of detection.
In any case, both direct bearing temperature indication and motor current are likely to be
monitored continuously, i.e. observed every shift, and vibration and acoustic monitoring
provide independent indications of bearing wear. Consequently, thermography is not a
critical technology for detection of bearing wear in this class of motors.
2-4
Thermography should include:
• Inspection for unusual and unbalanced heating of the connections at the main
motor and motor heater leads and their respective power cable interfaces
• Unusual differences in exit air temperatures when compared to historical values
• Inspection for unusual heating in motor bearing and windings that cannot be
attributed to normal thermal patterns and temperatures
2-5
can lead to degradation. Typical anti-friction bearing temperatures usually will not exceed
45° C above ambient; 2-pole motors usually will not exceed 50 ° C above ambient.
In the case of standby motors, the electrical on-line tests should be performed after the
motor has been running at rated speed for four hours in order to be at a stable operating
temperature. The partial discharge tests for corona damage requires the installation of
appropriate couplers to take on-line data.
2-6
Electrical Tests - On-Line should include some or all of the following; these tests should
be trended and compared to historical data to derive their maximum benefit:
• Motor current and power signature analysis
• Power factor testing
• Applied voltage and running current testing
• Flux monitoring
• Partial discharge
Measurement of cooling water flow and pressure is an additional means to detect failed
cooling coils, and is a part of the mechanical on-line measurements.
2-7
filters, screens, and air passages which can degrade significantly over a period of a few
months. High winding temperatures above rated values from high temperature
environments provide early indication of the likelihood of premature winding failure.
Although the effect of elevated temperature on winding life is said to be well understood,
predictable, and severe, winding failures from this source are expected only on a time scale
of several years.
The mechanical on-line tests include visual observation of arcing at brushes and slip rings
although more detailed inspection of brushes is included in the mechanical off-line task, or
may even constitute a more frequent separate task if there is a history of brush problems.
In the case of standby motors, the mechanical on-line tests should be performed after the
motor has been running at rated speed for four hours in order to be at a stable operating
temperature.
2-8
Electrical insulation is subject to continuous degradation. The main causes of insulation
degradation are excessive heat above the rated limit, excessive starts within a short period,
winding movement and vibration, age, and contamination (which may be e.g. oil, moisture,
salt).
Although the initiation of these influences may be random, the degradation progresses
relatively slowly and is expected to give a trouble free period of at least several years
(exception could be high temperatures from excessive starts within a short period, which
should be controlled by operational procedures). Insulation on stator laminations also
degrades continuously and is expected to provide a failure free period that may approach
40 years.
Problems with feeder cables, motor leads, connections, lugs, switches and electrical
devices such as surge capacitors are likely to occur randomly on various time scales,
shorter than those above. Measurement of winding resistance can detect shorts between
turns, and ductor tests can be performed to evaluate the resistance of connections.
Electrical off-line tests can only be conducted meaningfully when all parts of the motor are
within 10° F of ambient temperature. The tests should include some or all of the
following; these tests should be trended and compared to historical data to derive their
maximum benefit:
• Winding resistance
• Insulation resistance
• Polarization indexing
• Motor circuit evaluation
• AC High Pot.
• DC Step voltage
• Surge testing
• Power factor tip-up testing
2-9
2.3.7 Mechanical Tests - Off-Line
Additional inspection can be carried out by borescope. The objective then is to examine
otherwise hidden areas of the rotor and stator for loose, damaged, or contaminated
laminations, failed rotor bars or shorting rings, corona damage to insulation or fretting of
insulation, broken surge rings or failed surge ring support brackets, broken ties or loose
wedges, as well as loose windings, pole pieces or banding on wound rotors.
An additional test uses eddy current detection to examine the mechanical integrity of the
cooling coil. This requires entry into the cooling coil and need not be performed at every
mechanical off-line test.
Corrosion, erosion and fouling may act continuously or randomly and may result in
cooling coil failures at random times. Eddy current testing provides the only effective
means to detect such degradation before failure, since partial disassembly would otherwise
be required in order to view the coil, and it is not a regularly scheduled task.
2-10
• Inspect motor mountings for indications of soft-foot
• Inspect the slip ring and brushes for abnormal wear and proper alignment
• Hand rotate to determine presence of any shaft run-out, binding or rubbing
noise
Bearing temperature, motor current, and winding temperature are all likely to be either
continuously recorded or observed every shift during operator rounds. These frequent
observations are included in the external visual inspection task, both here and in Tables 3.1
and 3.2, although plants will have a separate procedure, possibly a part of operator
rounds, for how they are observed, recorded or trended. Bearing temperature is a key
indication for all causes of bearing wear, failures in the oil distribution system, and other
failures that can affect the wear of bearings. Motor current can also detect some bearing
failures but usually at a later stage of development than bearing temperature. Winding
temperature is a useful indicator for clogged air filters, air passages, and winding
insulation failure.
Certain degradation processes in electrical circuits can also be observed, such as degraded
insulation on feeder cables, and failed space heaters.
The inspection also includes general observation for loose, missing, or damaged parts, and
listening for unusual noises or vibrations.
2-11
noises) are also assumed to be included as a formal part of operator rounds, so that
operator rounds does not appear as a separate PM Strategy on the Template or in Tables
3.1, or 3.2.
The degree to which internal areas of the motor can be accessed will depend greatly upon
the motor type, design, and construction. This will therefore impact the amount of
disassembly and inspection required for this task.
2-12
Partial Disassembly should include:
• All tasks found in the External Visual Inspection, plus
• Removal of motor end covers and inspection plates and covers to allow access
to motor bearings and windings without floating the rotor (i.e. rotor
positioning and alignment are not to be affected by this inspection)
• Check for any damaged, loose, or missing parts
• Inspect bearings for abnormal wear, loss of babbitt, pitting, and indications of
lubrication problems such as discoloration and scorching
• Inspect the internal bearing insulation for integrity, damage, flash over,
tracking, and proper insulation levels as recommended by the OEM
• Inspect and test the bearing RTDs for damage and proper temperature
indication
• Perform a bearing journal and thrust runner inspection looking for indications
of abnormal wear, proper RMS surface finish, proper alignment and
positioning, and damage
• Inspect bearing seals for wear, alignment, and damage
• Inspect the oil cooler, reservoir, and oil piping for leaking, mechanical
integrity, fouling, cleanliness, pitting, corrosion, erosion, and damage
• For horizontal motors remove and inspect the upper end turn air baffles for
damage, electrical tracking, and cleanliness. With the air baffles removed
inspect winding end turns for dusting, looseness, electrical tracking, mechanical
integrity of the ties and blocking, and any damage to the windings.
• For vertical motors inspect for indication of loose coil wedges
• Inspect internal coating for integrity and damage
• Inspect internal motor leads for degradation of or damage to the lead wire
insulation
• Motor rotor fans should be inspected for damaged, cracked, or missing blades,
or loose hardware
• Inspect the pawls and ratchet plates of any anti-rotation devices for damage
and abnormal wear. If possible perform an uncoupled break-away test on
vertical motors employing an anti-rotation device.
• Remove covers and inspect all junction and termination boxes and contents for
damage, grounded wiring indications of electrical arcing or tracking, and the
condition and tightness of connections and insulation systems
• If present at the motor, inspect current transformers and or surge capacitors
for leakage, damage and the proper tightness of the connections
2-13
2.3.10 Partial Refurbishment
2.3.11 Refurbishment
Frame and mounting degradations are also covered by vibration monitoring and by visual
inspection. All the rotor degradations are also covered by vibration monitoring. Stator
2-14
laminations, and winding degradation might also be revealed by a borescope examination
but can be more fully examined during refurbishment. Refurbishment should include
inspection of corona damage to stator winding insulation because a few instances of
damage from corona discharge have been noted in the industry. There do not appear to be
any other degradation mechanisms that absolutely require a refurbishment to reveal the
condition of the equipment, i.e. that are not also covered by one or more of the other
tasks.
Some utilities currently have the confidence in their condition monitoring programs and
inspections to eliminate refurbishment as a regularly scheduled PM task. The foregoing
analysis shows that all the failure causes should indeed be covered by condition monitoring
and inspection.
2-15
• Inspect shaft bearing journals for wear, pitting, and damage; resurface, as
required, to restore journals to proper micron finish
• Balance the rotor
• Clean and inspect the stator winding and core for: contamination, damaged or
loose windings, end turns, blocking, wedging, ties, and stator iron; detached or
loose surge ring; evidence of corona discharge damage, test winding and
insulation resistance
• Verify proper operation of winding RTDs
• Clean air passages
• Tighten end windings and retreat stator to restore proper insulation and
mechanical rigidity
• Inspect and test all supply cables, motor heaters, and alarms
• Inspect and refurbish the anti-rotation device, as required
The functional test is a start / run test conducted as a post maintenance test on the motor
to verify operability, proper rotation, and readiness for return to service and also
frequently as a post maintenance test on the driven equipment. Other forms of functional
testing are IST tests that verify the operability of stand-by equipments.
2-16
2.4 Examples of Components Satisfying Template Conditions
1.
Critical Essential Raw Cooling Water Pump Motor
High Duty Cycle Circulating Water Pump Motor
Severe Service Condition Condensate Pump Motor
2.
Critical Essential Raw Cooling Water Pump Motor
Low Duty Cycle Cooling Tower Lift Pump Motor
Severe Service Condition High Pressure Fire Pump Motor
3.
Critical Steam Generator Feed Pump Motor
High Duty Cycle Recirculation M-G Set Motor
Mild Service Condition Condensate Pump Motor
4.
Critical Residual Heat Removal Pump Motor
Low Duty Cycle Safety Injection Pump Motor
Mild Service Condition Auxiliary Feedwater Pump Motor
5.
Non Critical HVAC Chiller Compressor Motor
High Duty Cycle Circulating Water Pump Motor
Severe Service Condition
6.
Non Critical Cooling Tower Lift Pump Motor
Low Duty Cycle
Severe Service Condition
7.
Non Critical Heater Drain Pump Motor
High Duty Cycle
Mild Service Condition
8.
Non Critical No example given
Low Duty Cycle
Mild Service Condition
Note: Range of service conditions (i.e. inside or outside) influences the above
assignments.
2-17
2.5 Definitions of Template Application Conditions:
2.5.1 Critical
2-18
2-19
2-20
3
PM STRATEGY TO ADDRESS DEGRADATION
MECHANISMS
________________________________________________________________________
The expert group identified the most common, i.e. dominant, failure locations and
mechanisms for medium voltage electric motors, guided in part by the failure causes
reported in NPRDS and in the BNL Aging Study (2). These were failures of:
The expert group then identified the leading degradation mechanisms, the main physical
influences on the degradation, and the time progression of the degradation for each failure
location. For each case, the expert group considered when the degradation would actually
become a failure (i.e. the time scale on which the failure would occur), and what discovery
opportunities or tests could identify the condition prior to the failure. This information is
presented in Table 3.1. The final column in the table is a cost effective way of packaging
the individual tasks into a small number of PM tasks.
The process was necessarily fairly repetitive to ensure that each set of circumstances (i.e.
component failure location and degradation mechanism) was given proper consideration.
A different version of Table 3.1 is presented in Table 3.2. Table 3.2 recompiles the data in
Table 3.1, removing repetitive information, and leaving out most of the timing
information. It focuses on the PM tasks themselves, showing very quickly which failure
causes are addressed by each task, whether or not a task covers a broad group of potential
failure locations, and which tasks are backed up by other tasks.
A text reconstruction of the information in these tables has been presented as the PM task
rationale in the PM Application Notes of Section 2.3. The tables of detailed information
3-1
are presented here to support utilities requiring to modify the suggested tasks or task
intervals to account for plant specific conditions. Section 2 also contains an outline of
suggested task content, e.g. which tests go with each level of inspection.
3-2
3.2 Failure Locations, Degradation Mechanisms, and PM Strategies
3-3
Table 3.1 continued
3-4
Table 3.1 continued
3-5
Table 3.1 continued
3-6
Table 3.1 continued
3-7
Table 3.1 continued
3-8
Table 3.1 continued
3-9
Table 3.1 continued
3-10
Table 3.1 continued
3-11
Table 3.1 continued
3-12
Table 3.1 continued
3-13
Table 3.1 continued
3-14
Table 3.1 continued
3-15
Table 3.1 continued
3-16
Table 3.1 continued
3-17
Table 3.1 continued
3-18
Table 3.1 continued
3-19
Table 3.1 continued
3-20
Table 3.1 continued
3-21
Table 3.1 continued
3-22
Table 3.1 continued
3-23
Table 3.1 continued
3-24
Table 3.1 continued
3-25
Table 3.1 continued
3-26
Table 3.1 continued
3-27
Table 3.1 continued
3-28
Table 3.1 continued
3-29
Table 3.1 continued
3-30
3.3 PM Tasks and their Degradation Mechanisms
Anti-friction Bearings:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Task Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - 24 Wear- X X X X X X
months Degraded
lubricant
Random Wear- Incorrect X X X X X X
lubricant
Random Wear- X X X X X X
Insufficient
lubricant
Random - Wear- X X X X X
>months Excessive
grease
Random - Wear- X X X X X
>months Excessive oil
Random - Wear- X X X X
months Misalignment
>Several years Wear- Electric X X X X
currents
3-31
Table 3.2 continued
3-32
Table 3.2 continued
Sleeve Bearings:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - >24 Wear- X X X X X X
months Degraded
lubricant
Random Wear- Incorrect X X X X X X
lubricant
Random Wear- X X X X X X
Insufficient
lubricant
May not fail Wear- X X X X X X
Random Excessive oil in
certain vertical
design
configurations.
Random - a few Wear - X X X X X X
months Misalignment
Random Wear- Electric X X X X X
currents
Random - Rapid Wear - X X X X X
based on loading Excessive
mechanical
loading
3-33
Table 3.2 continued
3-34
Table 3.2 continued
Kingsbury Bearings:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
3-35
Table 3.2 continued
3-36
Table 3.2 continued
Bearing Seals:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - Wear, all X X X
months or sources
<bearing life.
<15y for non-
metallics
Shaft:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random Integrity/cracks X X X X
Failure free for Wear X X X X X
several years
Random Bowing / X X X
sagging
3-37
Table 3.2 continued
Oil Distribution:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random Blocked X
breather caps,
or sight glass
vents
Random Blocked X
metering orifice
Random Weld failure X X
Random - Failed gaskets X X
months to years
Random Pipes / X X
connections
Random Machine fits X X
Failure free for Failed slinger X
years rings
Random Failed cooling X X X X
coil
3-38
Table 3.2 continued
Air Filters:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Months Clogged X
Air Baffles:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random Loose X X
3-39
Table 3.2 continued
3-40
Table 3.2 continued
Rotor:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - or 10- Lamination, all X X
40 years sources
Random Loose X X X
laminations
Random Failed rotor X X X
bars or shorting
rings
Random - Rapid Rotor / Stator X X X X
mechanical
interference
Random Loose retaining X X
rings
Random Loose rotor X X X X
cage
3-41
Table 3.2 continued
Wound Rotor:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - years Loose Windings X X X
Random Insulation X X X
degradation
Random Loose pole X X X
pieces and
Banding
Random Degraded X X X
connections
Random Worn slip ring X X
Random - weeks Worn brushes X X
Random - weeks Wrong length X X
brushes
3-42
Table 3.2 continued
Stator:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Failure free for < Insulation X X
40 years breakdown of
laminations
Random Laminations, X X
most sources
Random Contaminated X X X
laminations
Random - many Winding X X X
years insulation
degradation
Many trouble free Winding X X X
years insulation
degradation
from corona
Random - many Loose blocking X X
years & bracing
Random - years Other stator X X
winding failures
3-43
Table 3.2 continued
Feeder Cables:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - years Degraded X
insulation
Motor Leads:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - years Degraded X X
insulation
3-44
Table 3.2 continued
Electrical Connections:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random High resistance X X X
Random Degraded X X
insulation
Surge Capacitors:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random Insulation X
degradation
Random Bushing X
damage
Random Leakage X
3-45
Table 3.2 continued
Bearing Insulation:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random Broken X
Random Degraded X
insulation or
personnel error
3-46
Table 3.2 continued
Space Heaters:
Electrical Electrical Mechanical Mechanical External Full Thermography Vibration Oil Partial Partial
PM Task Off-Line On-Line Off-Line On-Line Visual Refurbish Analysis Dis- Refurbish
Inspection assembly
Interval 2-3Y 3-4Y 2-4Y 1-2Y 1Y 10-20Y 0.5Y 0.5Y 1Y AR AR
Time of Failure Location /
Degradation
Random - many Failed space X X
years heaters
3-47
3-48