SHUTDOWN PLAN

KOMATSU 530M
PLAN COMPONENT REPLACEMENT
ID Work Order Task Name Duration % Start Finish 2011 March 2011 April 2011
Complete 7 Feb '11 14 Feb '11 21 Feb '11 28 Feb '11 7 Mar '11 14 Mar '11 21 Mar '11 28 Mar '11 4 Apr '11 11 Apr '11 18 Ap
S T T F SS T T F SS T T FSS T T FSS T T F SS T T F SS T T F SS T T FSS T T FSS T T F SS T T
1 Shutdown Schedule Komatsu 530M 1112 hrs 11% 8/02/11 26/03/11
2
3 RD7735 216 hrs 100% 8/02/11 17/02/11
4 Preparation 0 hrs 100% 8/02/11 8/02/11 8/02
5 Send unit to Gatotkaca shutdown Pad 0 hrs 100% 8/02/11 8/02/11 8/02
6
7 Backlog Job 216 hrs 100% 8/02/11 17/02/11
8 1131204 C/O Turbo Primary LEFT - Schedule (UT-NEW) ==> C/O Engine Eks RD7732 [Due 88%] 12 hrs 100% 8/02/11 8/02/11 C/O Turbo Primary LEFT - Schedule (UT-NEW) ==> C/O Engine Eks RD7732 [Due 88%]
9 1131206 C/O Fuel Injector - Schedule (UT-NEW) ==> C/O Engine eks RD7732 [Due 88%] 12 hrs 100% 9/02/11 9/02/11 C/O Fuel Injector - Schedule (UT-NEW) ==> C/O Engine eks RD7732 [Due 88%]
10 1362235 Replace Fuel Pump - Schedule (UT-NEW) ==> C/O Engine eks RD7732 [Due 88%] 12 hrs 100% 9/02/11 9/02/11 Replace Fuel Pump - Schedule (UT-NEW) ==> C/O Engine eks RD7732 [Due 88%]
11 1471219 C/O Hyd Cyl Hoist LEFT - Schedule (UT-PEX) (Part has been installed) 12 hrs 100% 10/02/11 10/02/11 C/O Hyd Cyl Hoist LEFT - Schedule (UT-PEX) (Part has been installed)
12 103574 C/O Hyd Cyl Hoist RIGHT - Schedule (UT-PEX) (Part has been installed) 12 hrs 100% 10/02/11 10/02/11 C/O Hyd Cyl Hoist RIGHT - Schedule (UT-PEX) (Part has been installed)
13 1362237 C/O Ride Strut POS 3 ( Swap from RD7733 - POS 4 ) [ Due 59% ] 12 hrs 100% 11/02/11 11/02/11 C/O Ride Strut POS 3 ( Swap from RD7733 - POS 4 ) [ Due 59% ]
14 49830 C/O Final Drive POS 1 ( Swap from RD7732 - POS 1 ) [ Due 71% ] 24 hrs 100% 14/02/11 15/02/11 C/O Final Drive POS 1 ( Swap from RD7732 - POS 1 ) [ Due 71% ]
15 1535426 3 Month Seat Belt Inspection 1 hr 100% 15/02/11 15/02/11 3 Month Seat Belt Inspection
16 Repair Chassis and Frame Due to Crack 24 hrs 100% 16/02/11 17/02/11 Repair Chassis and Frame Due to Crack
17
18 Finishing & Final Check 12 hrs 100% 16/02/11 16/02/11
19 Test Performance 12 hrs 100% 16/02/11 16/02/11 Test Performance
20
21 RD7731 112 hrs 0% 28/02/11 4/03/11
22 Preparation 0 hrs 0% 28/02/11 28/02/11 28/02
23 Send unit to Gatotkaca shutdown Pad 0 hrs 0% 28/02/11 28/02/11 28/02
24
25 Backlog Job 108 hrs 0% 28/02/11 4/03/11
26 658836 Recondition Radiator eks RD7733 for Repair & Return 12 hrs 0% 28/02/11 28/02/11 Recondition Radiator eks RD7733 for Repair & Return
27 1176827 C/O Engine Assy (UT-PEX), ETA 27 Feb 2011 56 hrs 0% 28/02/11 2/03/11 C/O Engine Assy (UT-PEX), ETA 27 Feb 2011
28 834403 C/O Final Drive POS 2 (UT-PEX) 24 hrs 0% 2/03/11 3/03/11 C/O Final Drive POS 2 (UT-PEX)
29 811208 C/O Uni's Drive Line FRONT ( Swap from RD7732 ) [ Due 81% ] 3 hrs 0% 3/03/11 3/03/11 C/O Uni's Drive Line FRONT ( Swap from RD7732 ) [ Due 81% ]
30 1544797 Reseal Ride Strut POS 2 12 hrs 0% 3/03/11 4/03/11 Reseal Ride Strut POS 2
31 1534250 3 Month Seat Belt Inspection 1 hr 0% 4/03/11 4/03/11 3 Month Seat Belt Inspection
32 1534927 C/O bolt mounting hydraulic tank due to broken 12 hrs 0% 2/03/11 3/03/11 C/O bolt mounting hydraulic tank due to broken
33 1535743 Repair Chassis and Frame Due to Crack (UT job) 60 hrs 0% 28/02/11 2/03/11 Repair Chassis and Frame Due to Crack (UT job)
34
35 Finishing & Final Check 4 hrs 0% 4/03/11 4/03/11
36 Test Performance 4 hrs 0% 4/03/11 4/03/11 Test Performance
37
38 RD7767 76 hrs 0% 4/03/11 7/03/11
39 Preparation 0 hrs 0% 4/03/11 4/03/11 4/03
40 Send unit to Gatotkaca shutdown Pad 0 hrs 0% 4/03/11 4/03/11 4/03
41
42 Backlog Job 72 hrs 0% 4/03/11 7/03/11
43 1543926 C/O Transmission ( c/w Torqueconverter ) - Schedule (UT-PEX) 48 hrs 0% 4/03/11 6/03/11 C/O Transmission ( c/w Torqueconverter ) - Schedule (UT-PEX)
44 1557079 C/O Transmission Pump ( Swap from RD7732 ) [ Due 1%] 11 hrs 0% 6/03/11 7/03/11 C/O Transmission Pump ( Swap from RD7732 ) [ Due 1%]
45 1544432 C/O Pump Hoist - Schedule (Supplied by UT) 6 hrs 0% 7/03/11 7/03/11 C/O Pump Hoist - Schedule (Supplied by UT)
46 1544433 C/O Pump Steering - Schedule ( Swap from RD7732 ) [ Due 1%] 6 hrs 0% 7/03/11 7/03/11 C/O Pump Steering - Schedule ( Swap from RD7732 ) [ Due 1%]
47 99105 C/O Uni's Drive Line REAR ( Swap from RD7732 ) [ Due 55% ] 1 hr 0% 7/03/11 7/03/11 C/O Uni's Drive Line REAR ( Swap from RD7732 ) [ Due 55% ]
48 1415568 Repair crack on RH upper hoist cyl mounting (UT Job) 48 hrs 0% 4/03/11 6/03/11 Repair crack on RH upper hoist cyl mounting (UT Job)
49
50 Finishing & Final Check 4 hrs 0% 7/03/11 7/03/11
51 Test Performance 4 hrs 0% 7/03/11 7/03/11 Test Performance
52
53 RD7993 76 hrs 0% 7/03/11 11/03/11
54 Preparation 0 hrs 0% 7/03/11 7/03/11 7/03

Project: SHUTDOWN PLAN Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Date: 25/02/11
Progress Summary Rolled Up Milestone Split Project Summary

Prepaired by: Zhan Fadillah Page : 1 of 3 ZF

Our Objective is ZERO Incidents and Accidents


SHUTDOWN PLAN
KOMATSU 530M
PLAN COMPONENT REPLACEMENT
ID Work Order Task Name Duration % Start Finish 2011 March 2011 April 2011
Complete 7 Feb '11 14 Feb '11 21 Feb '11 28 Feb '11 7 Mar '11 14 Mar '11 21 Mar '11 28 Mar '11 4 Apr '11 11 Apr '11 18 Ap
S T T F SS T T F SS T T FSS T T FSS T T F SS T T F SS T T F SS T T FSS T T FSS T T F SS T T
55 Send unit to Gatotkaca shutdown Pad 0 hrs 0% 7/03/11 7/03/11 7/03
56
57 Backlog Job 72 hrs 0% 7/03/11 10/03/11
58 1295172 C/O Bevel Gear ( Swap from RD7736 / 7733 ) [70%] 24 hrs 0% 7/03/11 8/03/11 C/O Bevel Gear ( Swap from RD7736 / 7733 ) [70%]
59 63312 C/O Final Drive POS 1 - Schedule (UT-PEX) 24 hrs 0% 8/03/11 9/03/11 C/O Final Drive POS 1 - Schedule (UT-PEX)
60 57612 C/O Final Drive POS 2 - Schedule (UT-PEX) 24 hrs 0% 9/03/11 10/03/11 C/O Final Drive POS 2 - Schedule (UT-PEX)
61 400704 C/O Pump Steering - ( Cannibal from RD7733 ) [ Due 60% ] 4 hrs 0% 8/03/11 9/03/11 C/O Pump Steering - ( Cannibal from RD7733 ) [ Due 60% ]
62 Repair Chassis and Frame Due to Crack (UT job) 60 hrs 0% 7/03/11 10/03/11 Repair Chassis and Frame Due to Crack (UT job)
63
64 Finishing & Final Check 4 hrs 0% 10/03/11 11/03/11
65 Test Performance 4 hrs 0% 10/03/11 11/03/11 Test Performance
66
67 RD7734 76 hrs 0% 11/03/11 14/03/11
68 Preparation 0 hrs 0% 11/03/11 11/03/11 11/03
69 Send unit to Gatotkaca shutdown Pad 0 hrs 0% 11/03/11 11/03/11 11/03
70
71 Backlog Job 72 hrs 0% 11/03/11 14/03/11
72 200331 C/O Uni's drive Line FRONT 6 hrs 0% 11/03/11 11/03/11 C/O Uni's drive Line FRONT
73 164051 C/O Uni's Drive Line REAR ( Swap RD7733 ) [ Due 73% ] 6 hrs 0% 11/03/11 11/03/11 C/O Uni's Drive Line REAR ( Swap RD7733 ) [ Due 73% ]
74 49810 C/O Bevel Gear - Schedule (UT-PEX) 36 hrs 0% 11/03/11 13/03/11 C/O Bevel Gear - Schedule (UT-PEX)
75 1203967 C/O Final Drive POS 2 - Schedule (UT-PEX) 12 hrs 0% 13/03/11 13/03/11 C/O Final Drive POS 2 - Schedule (UT-PEX)
76 Repair Chassis and Frame Due to Crack (UT job) 72 hrs 0% 11/03/11 14/03/11 Repair Chassis and Frame Due to Crack (UT job)
77
78 Finishing & Final Check 4 hrs 0% 14/03/11 14/03/11
79 Test Performance 4 hrs 0% 14/03/11 14/03/11 Test Performance
80
81 RD7768 96 hrs 0% 14/03/11 18/03/11
82 Preparation 6 hrs 0% 14/03/11 14/03/11
83 Send unit to Gatotkaca shutdown Pad 6 hrs 0% 14/03/11 14/03/11 Send unit to Gatotkaca shutdown Pad
84
85 Backlog Job 84 hrs 0% 14/03/11 17/03/11
86 807600 C/O Tranmission ( c/w Torqueconverter ) - Schedule (UT-PEX) 49 hrs 0% 14/03/11 16/03/11 C/O Tranmission ( c/w Torqueconverter ) - Schedule (UT
87 316055 C/O Transmission Pump - Schedule (UT-NEW) 12 hrs 0% 16/03/11 16/03/11 C/O Transmission Pump - Schedule (UT-NEW)
88 50043 C/O Pump Hoist - Schedule (UT-NEW) 12 hrs 0% 16/03/11 17/03/11 C/O Pump Hoist - Schedule (UT-NEW)
89 1362244 C/O Pump Steering ( Swap from RD7733 ) [ Due 60% ] 10 hrs 0% 17/03/11 17/03/11 C/O Pump Steering ( Swap from RD7733 ) [ Due 60% ]
90 1535428 3 Month Seat Belt Inspection 1 hr 0% 17/03/11 17/03/11 3 Month Seat Belt Inspection
91 Repair Chassis and Frame Due to Crack 48 hrs 0% 14/03/11 16/03/11 Repair Chassis and Frame Due to Crack
92
93 Finishing & Final Check 12 hrs 0% 17/03/11 18/03/11
94 Test Performance 12 hrs 0% 17/03/11 18/03/11 Test Performance
95
96 RD7803 102 hrs 0% 18/03/11 22/03/11
97 Preparation 6 hrs 0% 18/03/11 18/03/11
98 Send unit to Gatotkaca shutdown Pad 6 hrs 0% 18/03/11 18/03/11 Send unit to Gatotkaca shutdown Pad
99
100 Backlog Job 90 hrs 0% 18/03/11 21/03/11
101 65548 C/O Hyd Cyl Hoist LEFT - Schedule (UT-PEX) 12 hrs 0% 18/03/11 18/03/11 C/O Hyd Cyl Hoist LEFT - Schedule (UT-PEX)
102 66511 C/O Hyd Cyl Hoist RIGHT ( Swap from RD7732 - LEFT ) [ 21% ] 12 hrs 0% 18/03/11 19/03/11 C/O Hyd Cyl Hoist RIGHT ( Swap from RD7732 - LEF
103 50015 C/O Bevel Gear - Schedule (UT-PEX) 24 hrs 0% 19/03/11 20/03/11 C/O Bevel Gear - Schedule (UT-PEX)
104 492043 C/O Final Drive POS 1 ( Swap from RD7732 - POS 2 ) [ Due 71% ] 24 hrs 0% 20/03/11 21/03/11 C/O Final Drive POS 1 ( Swap from RD7732 - PO
105 1544766 C/O Hyd Cyl Steer POS 1 ( Swap from RD7733 - POS 1 ) [ Due 1% ] 6 hrs 0% 21/03/11 21/03/11 C/O Hyd Cyl Steer POS 1 ( Swap from RD7733 -
106 3 Month Seat Belt Inspection 12 hrs 0% 21/03/11 21/03/11 3 Month Seat Belt Inspection
107 Repair Chassis and Frame Due to Crack 24 hrs 0% 18/03/11 19/03/11 Repair Chassis and Frame Due to Crack
108

Project: SHUTDOWN PLAN Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Date: 25/02/11
Progress Summary Rolled Up Milestone Split Project Summary

Prepaired by: Zhan Fadillah Page : 2 of 3 ZF

Our Objective is ZERO Incidents and Accidents


SHUTDOWN PLAN
KOMATSU 530M
PLAN COMPONENT REPLACEMENT
ID Work Order Task Name Duration % Start Finish 2011 March 2011 April 2011
Complete 7 Feb '11 14 Feb '11 21 Feb '11 28 Feb '11 7 Mar '11 14 Mar '11 21 Mar '11 28 Mar '11 4 Apr '11 11 Apr '11 18 Ap
S T T F SS T T F SS T T FSS T T FSS T T F SS T T F SS T T F SS T T FSS T T FSS T T F SS T T
109 Finishing & Final Check 12 hrs 0% 21/03/11 22/03/11
110 Test Performance 12 hrs 0% 21/03/11 22/03/11 Test Performance
111
112 RD7736 94 hrs 0% 22/03/11 26/03/11
113 Preparation 6 hrs 0% 22/03/11 22/03/11
114 Send unit to Gatotkaca shutdown Pad 6 hrs 0% 22/03/11 22/03/11 Send unit to Gatotkaca shutdown Pad
115
116 Backlog Job 82 hrs 0% 22/03/11 25/03/11
117 1544763 C/O Bevel Gear - Schedule (UT-PEX) 24 hrs 0% 22/03/11 23/03/11 C/O Bevel Gear - Schedule (UT-PEX)
118 1544764 C/O Final Drive POS 1 - Schedule 24 hrs 0% 23/03/11 24/03/11 C/O Final Drive POS 1 - Schedule
119 1544765 C/O Final Drive POS 2 - Schedule 24 hrs 0% 24/03/11 25/03/11 C/O Final Drive POS 2 - Schedule
120 200334 C/O Hyd Cyl Hoist RIGHT ( Swap from RD7732 - RIGHT ) [ Due 86% ] 10 hrs 0% 25/03/11 25/03/11 C/O Hyd Cyl Hoist RIGHT ( Swap from RD
121 Repair Chassis and Frame Due to Crack 60 hrs 0% 22/03/11 24/03/11 Repair Chassis and Frame Due to Crack
122
123 Finishing & Final Check 12 hrs 0% 25/03/11 26/03/11
124 Test Performance 12 hrs 0% 25/03/11 26/03/11 Test Performance

Project: SHUTDOWN PLAN Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Date: 25/02/11
Progress Summary Rolled Up Milestone Split Project Summary

Prepaired by: Zhan Fadillah Page : 3 of 3 ZF

Our Objective is ZERO Incidents and Accidents