1. There are two industries A and B manufacturing hose couplings.The standard time per
piece is 15 minutes.The output of two small scale industries is 30 and 20 respectively per
shift of 8 hours.Find the productivity of each pers hift of 8 hours.what is the expected
production of each per week consisting of 6 days.
2. Explain the contributions of Taylor for scientific management and how it leads to the
3. Briefly discuss the factors to be considered for the selection of a location for a factory
Construction.
4. State the differences between method study and work measurement with their
objectives.
5. Explain the need and procedure for conducting work sampling study.
batch2
7. There are two industries A and B manufacturing hose couplings.The standard time per
piece is 15 minutes.The output of two small scale industries is 30 and 20 respectively per
shift of 8 hours.Find the productivity of each pers hift of 8 hours.what is the expected
production of each per week consisting of 6 days.
8. What is plant layout? Explain the principles and symptoms of a poor plant layout.
batch 3
11.There are two industries A and B manufacturing hose couplings.The standard time per
piece is 15 minutes.The output of two small scale industries is 30 and 20 respectively per
shift of 8 hours.Find the productivity of each pers hift of 8 hours.what is the expected
production of each per week consisting of 6 days.
12. Explain the tools and techniques of industrial engineering.
15. What do you understand by work measurement and elaborate the important
techniques involved in work measurement?
batch 4
16. Describe the nature and importance of management in modern business organization.
17. There are two industries A and B manufacturing hose couplings.The standard time
per piece is 15 minutes.The output of two small scale industries is 30 and 20 respectively
per shift of 8 hours.Find the productivity of each pers hift of 8 hours.what is the expected
production of each per week consisting of 6 days.
19. Name the various recording techniques used in method study. Give the various
batch 5
26.Explain theory x and theory y and show as a manager how you would apply them to
motivate your staff
27. Explain briefly major factors to be considered in selecting the location of a paper mill.
28. Discuss about breakdown maintenance.
29. What are Therblings? List various Therblings and their use in method study.
30. Stop watch time study of an element is done on an operation, the readings were
observed as follows
0.52 0.51 0.52 0.52 0.51 0.50 0.50 0.52
The average rating factor for the operator is 120%. Find out the Standard time,
assuming allowances 20%.