Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
B.S. 812: 1967 Methods for the Sampling and Testing of Mineral
Aggregates, Sands and Fillers
2 Cement
The Contractor shall submit to the Engineer for approval the name
and address of the supplier and the brand of cement which he
proposes to use in the Works at least two weeks before the
delivery of cement to the site is allowed. Normally the
manufacturer's test certificates will be accepted as proof of the
quality of the cement; but the Engineer may at his discretion
carry out further tests on the cement stored at the site.
C-1
3 Storage of Cement
4 Fine Aggregate
________________________________________________________________
| | | | | | | |
|B.S.Sieve | 5 mm | No. 7 | No. 14 | No. 25 | No. 52 | No. 100|
|__________|_______|_______|________|________|________|________|
| | | | | | | |
|% Passing |95-100 | 70-95 | 45-85 | 25-60 | 5-30 | 0-10 |
|__________|_______|_______|________|________|________|________|
5 Coarse Aggregate
C-2
The grading of coarse aggregate shall be within the following
limits:-
_______________________________________________________
| | | | |
| B.S. Sieve | 20 mm | 10 mm | 5 mm |
|_____________|________|_________|____________________|
| | | | |
| % Passing | 100% | 25 - 55 | Not more than 10 |
|_____________|________|_________|____________________|
7 Storage of Aggregates
C-3
8 Water
Water used for making and curing concrete and for testing the
watertightness of structures shall be fresh, clean and not
contain organic matter, sulphates or other impurities in
sufficient quantities likely to reduce the strength of the
concrete or attack the concrete or the reinforcement. The
Engineer's decision on the suitability or unsuitability of a
source of water for his purpose shall be final.
9 Steel Reinforcement
C-4
Temporary bracing shall be provided to prevent movement of all
steel projecting from the concrete during the course of
construction.
11 Welding of Reinforcement
12 Formwork
(i) Sound softwood tongued and grooved boards not less than 20
mm finished thickness, wrought on one side and two edges,
accurately formed and securely fixed to softwood frames.
The surfaces of the formwork shall be worked to a smooth
finish after fabrication.
C-5
All formwork shall be erected true to line and level and shall be
adequately secured and braced to prevent deflection or movement
during the placing, tamping or vibrating of the concrete, and
shall be sufficiently tight to prevent loss of liquid.
The use of wires passing through the concrete for the purpose of
securing the formwork in position shall not be permitted. Bolts
passing through the concrete may be used, but their number must
be kept to the minimum required to secure the formwork rigidly.
The bolts shall be not less than 13 mm in diameter and of a type
with detachable screw off heads so that the barrels of the bolts
remain cast in the concrete while the detachable heads can be
removed with ease. The barrel of every bolt used in water
retaining, water conveying or water excluding structures shall
have a waterstop in the form of a 100 mm x 100 mm x 3.5 mm steel
washer on at the mid-length of the bolt. The weld shall be
continuous round the barrel and on both sides of the washer.
C-6
formwork shall be face with plywood or equivalent material in
large sheets. The sheets shall be arranged in an approved,
uniform pattern. Wherever possible, joints between sheets shall
be arranged to coincide with architectural features, or changes
in direction of the surface. All joints between panels shall be
vertical and horizontal unless otherwise directed. Suitable
joints shall be provided between sheets to maintain accurate
alignment in the plane of the sheets. Unfaced wrought boarding or
standard steel panels will not be permitted for Class F3 finish.
Type U2. This is a floated finish for surfaces of beds and slabs
to receive mastic pavings or block or tile pavings bedded in
mastic, and for exposed surfaces of pavings where a hard smooth
steel-trowelled surface is not required. Floating shall be done
only after the concrete has hardened sufficiently, and may be by
hand or machine. Care shall be taken that the concrete is worked
no more than necessary to produce a uniform surface free from
screed marks.
Type U3. This is a hard smooth steel trowelled finish for surface
of concrete pavings, tops of walls , copings and other members
exposed to weathering surface of beds and slabs to receive thin
flexible sheet, and tile pavings bedding on adhesive, and
seatings for bearing plates and the like where the metal is in
direct contact with the concrete. Trowelling shall not commence
until the moisture film has disappeared and the concrete hardened
sufficiently to prevent excess laitance from being worked to the
surface. The surfaces shall be trowelled under firm pressure and
left free from trowel marks.
15 Concrete Proportions
C-7
made for the water contained in the aggregate when
calculating the water to be added to the mix.
Designed concrete mixes may be used and shall comply with the
recommendations of BS 8110. However, the grades of concrete to be
used shall be as below which supersede table 3.3 of BS 8110:
Nominal
Mix Minimum Maximum Minimum
Equivalent Crushing aggregate Cement
Resistance in Size Content per cu.
N/mm2 m. of finished
Within 28 Days Concrete
after mixing
C-8
Cement, coarse and fine aggregates and water shall comply with
the foregoing clauses of this specification.
The sampling, making, curing and testing of the works cubes shall
still be carried out by the Superintending Officer or his
representatives, the Contractor affording all facilities. The
Contractor or his representatives may, if they so wish, be
present while the cubes are being made and tested.
The results of the tests shall not exceed the limits stated
in table ‘A’ hereinafter.
C-9
(ii) Slump Test
The results of the tests shall not exceed the limits stated
in table ‘A’ hereinafter.
20 Rejection of Concrete
If any of the test cubes tested at 7 days do not comply with the
compressive strength compliance requirement as mentioned below,
the Engineer shall, at his discretion, order all concreting work
to stop until adequate measures have been taken to produce
concrete which complies with this Specification.
C - 10
When the difference between the two results divided by their mean
exceeds 15%, the test result shall be deemed invalid.
22 Supervision
23 Mixing concrete
The materials for each mix shall be placed in the loading skip in
the following order: coarse aggregate, cement, and fine
aggregate. The water shall be added to the dry materials in the
mixer drum. The quantity of water specified in Table `A' may be
varied up to 5% in order to maintain a constant workability; but
this tolerance shall not be exceeded without prior approval of
the Engineer. Each batch of concrete shall be mixed until there
is a uniform distribution of the materials and the mass is
uniform in colour and consistency. In no case shall the time of
mixing be less than two minutes or more than five minutes after
the water has been added to the batch. Any concrete surplus to
requirements shall be thrown away. In no circumstances may
surplus concrete be remixed for use later.
C - 11
Concrete may be conveyed by chute only with the permission of the
Engineer. Any concrete which has attained its initial set before
being placed shall be discarded. Placing concrete shall be
suspended during rain.
25 Compaction of Concrete
C - 12
In all cases the placing of concrete shall be sufficiently ahead
of the vibrators so that the mass of concrete beyond the
vibrators is sufficient to stand without flowing while vibration
is in progress. On the other hand, the concrete shall be fully
compacted before initial set is attained.
C - 13
28 Construction of Walls of Water Retaining, Water Conveying, or
Water Excluding Structures
The walls are divided into segments by vertical joints which are
continuous with the floor joints and extend the full height of
the walls in unbroken alignment. Each segment between the height
of 50mm above the top of the haunch and the underside of the
wall/ring beam shall be cast in a series of lifts not exceeding
1.35 m high each. Alternate segments in a lift shall be
concreted, and an interval of 7 days shall have elapsed before
the intervening segments in the same lift are concreted. One lift
of the wall all round shall be completed before the next higher
lift is concreted.
Each segment of the wall footing and haunch defined by the floor
and wall joints and a horizontal plane 50 mm above the top of the
haunch shall be concreted in one continuous operation. The
concrete shall be placed and compacted in the manner herein
before specified in this Specification. Great care shall be
exercised to ensure that the concrete in and around the haunch is
thoroughly compacted.
Dome roofs shall be cast on the formwork in one layer. They shall
be cast in segments defined by the joints shown on the Drawings.
Alternate segments shall be cast, and an interval of 7 days shall
have elapsed before the intervening segments are concreted. The
individual segments shall be cast in one continuous operation,
the concrete being placed and compacted in regular strips across
the full width of the segments. Each strip shall be placed
against the previous strip before the concrete in the latter has
attained its initial set. Where reinforcement is continuous
across the joints, the vertical stopping off boards shall be
notched to allow the reinforcement to pass through. The joint
shall each have a U-groove formed on the top to receive sealing
compound.
C - 14
31 Joints
The Contractor shall make the joints in the floors, walls and
roofs strictly in accordance with the Drawings. Particular care
shall be taken to ensure that the waterstops wherever shown on
the Drawings are adequately secured so that they will not be
displaced while concrete is being placed. Under no circumstance
shall waterstops be nailed through. Any water stop which has been
perforated shall be rejected and replaced at the Contractor's
expense.
Any concrete which has been disturbed after it has attained its
initial set shall be rejected and subsequently removed and
replaced by the Contractor at his own expense.
C - 15
33 Sealing Compounds
34 Waterstops
C - 16
hacked roughened fresh surface is obtained. The fresh surfaces
shall then be brushed clean and immediately before concrete is
placed, these surfaces shall be thoroughly wetted and covered
with a layer of 40 mm thickness of 1:1-1/2 cement sand mortar of
the consistency of condensed milk.
36 Curing Concrete
When all the concrete in the floor and the haunch of any water
retaining, water conveying or water excluding structure have been
placed and the concrete attained the final set, the whole of the
floor shall be flooded with water to a depth of not less than 75
mm. This depth of water shall be maintained throughout the rest
of the construction period.
37 Striking Formwork
(unloaded) .. 3 days
After the concrete surface has been inspected by the Engineer the
surface shall be treated as described below.
All areas where the concrete has not been properly consolidated
to a dense uniform surface shall be cut out, and made good to the
C - 17
satisfaction of the Engineer. All bolt holes left by the formwork
bolts shall be plugged as described herein. The sides of the
holes shall be reamed with a hacksaw blade until the cement scum
is removed. The holes shall then be flushed with a strong jet of
water to remove all loose materials. While the holes are still
wet, the sides of the holes shall be dusted with neat cement
using a suitable brush for this purpose. Immediately following
this the holes shall be plugged with a dry pack consisting of one
part of cement and two parts of fine sand. The mixture of cement
and sand shall be made only sufficiently damp with water to allow
it to be rammed solid without exuding any liquid, and after
thorough mixing shall be placed in the holes in thin layers and
solidly compacted over the entire surface with a hardwood stick
and a hammer, and finally struck off to a true surface.
The Contractor shall, at his own expense, conduct the tests for
water tightness of all water retaining, water conveying, and
water excluding structures and shall provide all the water
required for this purpose.
The first test on a structure shall not be carried out until four
weeks have elapsed after the placing of the last batch of
concrete in the structure is completed.
The structure shall be filled with water to the top water level
shown on the Drawings and maintained at that level for three
days. Should any obvious signs of leakage be observed during this
period, or any subsequent test period, the positions of all such
signs of leakage shall be marked and the test shall be stopped;
and the Contractor shall at his own expense carry out such
remedial measures as the Engineer shall direct including the
complete emptying of the structure if necessary. Should the
leakage be general the remedial measures may include the complete
treatment of the inside surfaces of the structure by rendering or
by the application of some other approved waterproof coating.
When all obvious signs of leakage have been stopped and made good
in accordance with the Engineer's instructions, the structure
shall be refilled to top water level, and so maintained for three
days. At the end of the third day, provided no further signs of
leakage are observed the exact water level shall be marked, and
after a further seventy-two hour period, the water level shall
again be marked and the difference recorded. During this seventy-
C - 18
two hour period an evaporation test shall be carried out in the
manner described hereunder. The structure shall be deemed
watertight and shall be so accepted in this respect only by the
Engineer if the recorded difference minus the loss of water by
evaporation gives a figure which does not exceed 1/2000 of the
depth of the water originally in the structure. Should, however,
the above recorded difference minus the loss of water by
evaporation give a figure which exceeds 1/2000 of the depth of
the water originally in the structure, the Contractor shall, at
his own expense, carry out the complete treatment of the inside
of the structure by rendering or such other remedial measures as
the Engineer may direct. On completion of such treatment, the
Contractor shall at his own expense retest the structure and
repeat these remedial measures, if found necessary, until
watertightness is obtained.
C - 19
42 R.C. Lintols and Cills
44 Concrete Pipes
The pipe section shall not be cut off without the approval of the
Engineer. The joints of the pipes shall be ordinary ogee or
rebated joint, sealed with cement mortar.
45 Ready-Mixed Concrete
(ii) The time at which each batch of concrete was mixed and
details of any additives used.
C - 20
The concrete to be agitated continuously by rotation of the mixer
drum during transport to the Site and while awaiting discharge.
C - 21
TABLE `A’
_________________________________________________________________________________________________________________ _____________________
N/mm2 N/mm2
Note: (i) When concrete is compacted by hand (and not vibrated) the compacting factor and the mix
shall be determined by the Engineer when the preliminary test mixes are made.
C - 22
Table B The Characteristic Strength Compliance Requirements
N/mm2 N/mm2
Any consecutive 4 3 3
N/mm2 N/mm2
C7.5 to First 2 0 2
C15
First 3 1 2
Any consecutive 4 2 2
C - 23
Quality Standard for Reinforced Concrete Structures
Item* Standards
1 Formwork
1b Alignment, plumb and level 1) Tolerance for departure of any point from its
position: 10mm
C - 24
Item* Standards
2b Anchorages & lap lengths 1) Required lap length not less than that specified
C - 25
Item* Standards
3b Alignment, plumb and level 1) Tolerance for departure of any point from its
position:
10mm
5) No cracks or damages
C - 26
Item* Standards
4 Precast Specific
Requirements
C - 27
Item* Standards
5 Structure Quality
5a Concrete Cube test 1) For every pour of concrete, test cubes results at
28 days must satisfy the passing criteria as
specification in the contract. The summary of test
report (Form A) must be endorsed by the project’s
structural QP (Qualified Person)
5b Reinforcement (Rebar) 1) To pass the tensile strength test for all the
reinforcement bars used as according to the
contract specifications. The summary of test
reports (Form A) must be endorsed by the project’s
structural QP (Qualified Person)
6 Non-destructive testing
6a Ultra Pulse Velocity test 1) To conduct NDT using ultrasonic pulse velocity
for Concrete Uniformity (UPV) to check the degree of uniformity of
hardened concrete
4) Method as per SS 78
4) Method as per SS 78
C - 28