Item: R-COMMUNICATION

R-COMMUNICATION
R-Communication for NA-I

Road
Cost per Km Appox Cost
Sl. No Description length/span Remarks
(Million Nu.) (Million Nu.)
(km)
A New road for construction
1 Project access roads 12.40 km 16.00 198.40
2 Tokorang to Richanglu farm road 8.50 km 16.00 136.00
3 Bridge-1(Bailey) 98.00 m 0.50 49.00
4 Bridge-2 (Bailey) 60.00 m 0.50 30.00
5 Bridge-3 (Bailey) 52.00 m 0.50 26.00
6 Culverts 38.00 m 0.26 9.88
Subtotal (A) 449.28
B Existing road requiring improvments
Improvement/widening of existing GC/farm road
1 Tashiyangphu to Phegpari-Thungkhar junction 1.50 km 4.00 6.00
2 Phegpari-Thungkhar junction to Pangzam 1.50 km 4.00 6.00
3 Pangzam to adit 1 0.20 km 4.00 0.80
4 Adit 1 to Adit 2 takeoff 0.70 km 4.00 2.80
5 Adit 2 takeoff to Adit 3 takeoff 0.50 km 4.00 2.00
6 Tsangchilu to road junction(Bazor- Yarphu) 0.30 km 4.00 1.20
7 Road junction(Bazor- Yarphu) to Adit 4 (take-off) 0.50 km 4.00 2.00
8 Road junction(Bazor- Yarphu) to surge shaft (take-o 0.20 km 4.00 0.80

Subtotal (B) 21.60


C Black topping of existing farm roads
1 Phegpari junction to Pangzam 4.00 km 2.70 10.80
2 Ramchongma farm road 2.50 km 2.70 6.75
3 Pangzam to Adit A1 1.80 km 2.70 4.86
4 Adit A1 to A2 4.70 km 2.70 12.69
5 Adit A2 to Thungkhar 5.10 km 2.70 13.77
6 Richanglu farm road 5.00 km 2.70 13.50
7 Khoyar farm road 2.50 km 2.70 6.75
Subtotal (C) 69.12
D Insurance @ 0.5% per year for 4.00 Years 10.80
Grand Total (A + B) 550.80

Nyera Amari I II Integrated Hydropower Project Volume-VIII, Chapter-1 Page 1-38


Detailed Project Report Cost Estimate