WORK PROGRAM FOR CONSTRUCTION OF GNPC TAKORADI HEAD OFFICE COMPLEX AT WESTERN REGION.

ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 Novembe
28 02 07 12 17 22 27 01 06 11 16 21 26 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07
1 CONSTRUCTION OF GNPC TAKORADI HEAD OFFICE 540 days Wed 01-01-20 Tue 02-11-21
COMPLEX
2 Preliminary works 12 days Wed 01-01-20 Wed 15-01-20
3 Earthworks 5 days Wed 01-01-20 Tue 07-01-20
4 Setting out 7 days Tue 07-01-20 Wed 15-01-20
5 Civil & MEP works 473.5 days Thu 16-01-20 Thu 26-08-21
6 Basement 102.25 days Thu 16-01-20 Thu 21-05-20
7 Earthworks & Excavation of foundation trenches 5 days Thu 16-01-20 Wed 22-01-20
8 Formwork for column bases 10 days Wed 22-01-20 Tue 04-02-20
9 Construction of foundation 11 days Tue 04-02-20 Mon 17-02-20
10 Formwork for sleeper columns 8 days Mon 17-02-20 Thu 27-02-20
11 Laying of sleeper walls 10 days Thu 27-02-20 Tue 10-03-20
12 Hardcore filling and compaction 9 days Wed 11-03-20 Sat 21-03-20
13 Formwork for oversite concrete 9 days Sat 21-03-20 Thu 02-04-20
14 Construction of ground beams and oversite concrete 12 days Thu 02-04-20 Thu 16-04-20
15 Formwork for column 8 days Thu 16-04-20 Mon 27-04-20
16 Construction of columns 11 days Mon 27-04-20 Mon 11-05-20
17 First Fix works 8 days Tue 12-05-20 Thu 21-05-20
18 First floor 60.25 days Mon 11-05-20 Thu 23-07-20
19 Formwork for suspended beams and slabs 8 days Mon 11-05-20 Wed 20-05-20
20 Construction of suspended beams and slabs 11 days Wed 20-05-20 Wed 03-06-20
21 Formwork for columns 9 days Wed 03-06-20 Mon 15-06-20
22 Construction of columns 13 days Mon 15-06-20 Tue 30-06-20
23 Lift Concrete works 10 days Wed 01-07-20 Mon 13-07-20
24 First Fix works 8 days Tue 14-07-20 Thu 23-07-20
25 Second floor 60.25 days Tue 14-07-20 Fri 25-09-20
26 Formwork for suspended beams and slabs 8 days Tue 14-07-20 Thu 23-07-20
27 Construction of suspended beams and slabs 11 days Fri 24-07-20 Thu 06-08-20
28 Formwork for columns 9 days Thu 06-08-20 Tue 18-08-20
29 Construction of columns 13 days Tue 18-08-20 Thu 03-09-20
30 Lift Concrete works 10 days Thu 03-09-20 Tue 15-09-20
31 First fix works 8 days Wed 16-09-20 Fri 25-09-20
32 Third Floor 59.88 days Wed 16-09-20 Sat 28-11-20
33 Formwork for suspended beams and slabs 8 days Wed 16-09-20 Fri 25-09-20
34 Construction of suspended beams and slabs 11 days Fri 25-09-20 Thu 08-10-20
35 Formwork for columns 9 days Fri 09-10-20 Tue 20-10-20
36 Construction of columns 13 days Wed 21-10-20 Thu 05-11-20
37 Lift Concrete works 10 days Thu 05-11-20 Wed 18-11-20
38 First fix works 8 days Thu 19-11-20 Sat 28-11-20
39 Fourth Floor 60.88 days Wed 18-11-20 Mon 01-02-21
40 Formwork for suspended beams and slabs 8 days Wed 18-11-20 Fri 27-11-20
41 Construction of suspended beams and slabs 11 days Sat 28-11-20 Fri 11-12-20
42 Formwork for columns 9 days Sat 12-12-20 Wed 23-12-20
43 Construction of columns 13 days Thu 24-12-20 Fri 08-01-21
44 Lift Concrete works 10 days Sat 09-01-21 Thu 21-01-21
45 First fix works 8 days Fri 22-01-21 Mon 01-02-21
46 Fifth Floor 80.75 days Thu 21-01-21 Fri 30-04-21
47 Formwork for suspended beams and slabs 8 days Thu 21-01-21 Mon 01-02-21
48 Construction of suspended beams and slabs 11 days Tue 02-02-21 Mon 15-02-21
49 Formwork for columns 9 days Tue 16-02-21 Fri 26-02-21
50 Construction of columns 13 days Sat 27-02-21 Tue 16-03-21
51 Formwork for roof beams 10 days Tue 16-03-21 Sat 27-03-21
52 Construction of roof beams 8 days Sat 27-03-21 Wed 07-04-21
53 Lift Concrete works 10 days Wed 07-04-21 Mon 19-04-21
54 First fix works 8 days Wed 21-04-21 Fri 30-04-21
55 Block works 62.88 days Mon 11-05-20 Mon 27-07-20
56 Laying of Basement blocks 18 days Mon 11-05-20 Tue 02-06-20
57 Laying of first floor blocks 8 days Tue 02-06-20 Thu 11-06-20
58 Laying of second floor blocks 9 days Thu 11-06-20 Tue 23-06-20
59 Laying of third floor blocks 9 days Tue 23-06-20 Fri 03-07-20
60 Laying of fourth floor blocks 9 days Sat 04-07-20 Wed 15-07-20
61 Laying of fifth floor blocks 9 days Wed 15-07-20 Mon 27-07-20
62 Roofing works 34.75 days Wed 07-04-21 Wed 19-05-21
63 Concrete roofing works 15 days Wed 07-04-21 Mon 26-04-21
64 Roof carcassing 9 days Mon 26-04-21 Thu 06-05-21
65 Roof covering materials works 10 days Thu 06-05-21 Wed 19-05-21
66 Surface finish works 234.63 days Mon 27-07-20 Thu 13-05-21
67 Internal & External plastering at basement 12 days Mon 27-07-20 Tue 11-08-20
68 Installation of doors & windows 11 days Tue 11-08-20 Mon 24-08-20
69 Internal & External plastering at first floor 20 days Tue 25-08-20 Fri 18-09-20
70 Installation of doors & windows 11 days Fri 18-09-20 Thu 01-10-20
71 Internal & External plastering at second floor 21 days Thu 01-10-20 Wed 28-10-20
72 Installation of doors & windows 11 days Wed 28-10-20 Wed 11-11-20
73 Internal & External plastering at third floor 21 days Wed 11-11-20 Mon 07-12-20
74 Installation of doors & windows 11 days Mon 07-12-20 Mon 21-12-20
75 Internal & External plastering at fourth floor 21 days Mon 21-12-20 Fri 15-01-21
76 Installation of doors & windows 11 days Fri 15-01-21 Fri 29-01-21
77 Internal & External plastering at fifth floor 19 days Fri 29-01-21 Mon 22-02-21
78 Installation of doors & windows 11 days Mon 22-02-21 Mon 08-03-21
79 Painting on basement 9 days Mon 08-03-21 Thu 18-03-21
80 Painting on first floor 9 days Thu 18-03-21 Tue 30-03-21
81 Painting on second floor 9 days Tue 30-03-21 Fri 09-04-21
82 Painting on third floor 9 days Sat 10-04-21 Wed 21-04-21
83 Painting on fourth floor 9 days Wed 21-04-21 Mon 03-05-21
84 Painting on fifth floor 9 days Mon 03-05-21 Thu 13-05-21
85 MEP works 84 days Thu 13-05-21 Thu 26-08-21
86 Second fix works on Basement 14 days Thu 13-05-21 Mon 31-05-21
87 Second fix works on first floor 14 days Tue 01-06-21 Thu 17-06-21
88 Second fix works on second floor 14 days Thu 17-06-21 Mon 05-07-21
89 Second fix works on Third floor 14 days Mon 05-07-21 Thu 22-07-21
90 Second fix works on Fourth floor 14 days Thu 22-07-21 Mon 09-08-21
91 Second fix works on Fifth floor 14 days Mon 09-08-21 Thu 26-08-21
92 External works 75.13 days Thu 17-06-21 Fri 17-09-21
93 Driving & Parking areas 58.88 days Thu 17-06-21 Sat 28-08-21
94 Ground leveling and compaction 8 days Thu 17-06-21 Sat 26-06-21
95 Kerb works 19 days Sat 26-06-21 Tue 20-07-21
96 Pavement blocks laying works 25 days Tue 20-07-21 Fri 20-08-21
97 Planting and turfing works 11 days Fri 20-08-21 Fri 03-09-21
98 Painting & decoration works 11 days Sat 04-09-21 Fri 17-09-21
99 Drainage works 30.75 days Sat 18-09-21 Tue 26-10-21
100 Construction of U-Drain 16 days Sat 18-09-21 Fri 08-10-21
101 Septic tank works 14 days Fri 08-10-21 Tue 26-10-21
102 Preparation for handing over 6 days Tue 26-10-21 Tue 02-11-21
103 Test and commissioning of electrical, AC,plumbing and ICT works 3 days Tue 26-10-21 Fri 29-10-21
104 Internal and External cleaning 2 days Fri 29-10-21 Mon 01-11-21
105 handing over 1 day Mon 01-11-21 Tue 02-11-21