Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract— PV development and its integration to the power 23% fuel mix portion for new and renewable energy (NRE) in
grid were growing rapidly, these rapid developments due to 2025 [1]. This NRE target consists of several type of power
sustainability and environmental issue. In order to support the plant, and PV development was among the biggest growth to
development, all researchers and engineers worldwide were develop (other than hydro and geothermal which already highly
conducted studies related to the PV development. Currently, most developed in Indonesia’s system).
of PV development studies only consider an aspect. Developers
consider irradiation, land acquisition, road access, and proximity PV development in Indonesia mainly because Indonesia as a
with the load. Government consider the PV’s potential and tropical country located in 60° North Latitude – 110° South
existing power system readiness. Utility considers the technical Latitude and 95° East Longitude – 141° East Longitude, i.e.
effect of PV integration based on Grid Code limitation. In order to around the equator. Based on the National Energy Plan,
have a complete view of PV development, this study considers 3 Indonesia has the potential of solar radiation reaching 4.8
aspects, such as mapping the potential of PV, the readiness of the kWh/m2/day [2].
system by statistical methods, and determining the capacity &
location of PV plants that meet Grid Code. The results of the PV The other reason is the land availability to put utility size PV
development study which considered several aspects would in Indonesia, but the problem was occurred because of the
provide benefits to PV development. This study will be applied to number of islands in Indonesia. Different system readiness
the island of Bali as a case study. would be the case, some of them like Jawa-Bali and Sumatera is
ready to have high penetration of intermittent power plant, some
Keywords—PV, Integration, Bali, Mapping, Intermittent, of them could not absorb the large size PV power plant even
Location though it has high irradiance potency.
I. INTRODUCTION Based on the above facts, it would be interesting to calculate
PV development is a current and major discussion among the PV Development in an island that have high irradiance, good
utility, developer even government. The unlimited sources, price system readiness and high availability of land use, which is Bali
trend, and low carbon emission are the main reasons which push Island.
PV development in power grid worldwide. Several The calculation process is:
considerations to develop PV such as the irradiation potency, a. Mapping analysis of PV development availability which
power system readiness, the need to reduce carbon emission, and consider irradiance, land-use, contour, etc.
decreasing PV cost already studied worldwide. Such b. System readiness by calculating the accepted
consideration usually studied by different agent, which give production drop of Bali’s system, that determined by
advantage for each agent. Developer consider irradiation statistical data of contributed inertia from power plant
potency and workability of PV’s project in order to maintain the availability.
benefit of PV Development. Government consider bigger c. Grid impact from several combinations of PV capacities
picture of PV development such as reducing carbon emission or and locations.
maintain energy sustainability, therefore such output like PV
capacity came from government target. Utility consider system II. BASIC THEORY
readiness and the grid impact of PV development. This PV
A. Geographic Information Systems
development consideration also occur on Indonesia. PV
development in Indonesia will be encouraged by several facts ESRI, a geographic information system company, defines
which is government target, high irradiance potency in some GIS as an organized collection of computer hardware, software,
islands, and system readiness. geographic data and efficiently designed to obtain, store, update,
manipulate, analyze and display all forms of information that are
Referring to Government of Indonesia’s target which stated geographic in reference [3]. GIS is designed to collect, store and
in Presidential Decree No 22, 2017, one of the targets is reaching analyze objects and phenomena where geographical location is
= (1)
Figure III.1. GIS Potency Results
Which is:
Δf : Frequency drop (Hz) The results of PV potency are around:
f : Frequency rated (Hz) 1. Kubu 150 kV Substation
H : Total system inertia (a) 2. Pemaron 150 kV Substation
ΔP : Production drop (MW) 3. Negara 150 kV Substation
Pr : Rated capacity (system peak load) 4. Amlapura 150 kV Substation
5. Gianyar 150 kV Substation
C. Grid Impact Study
With “unlimited” resources for each substation, therefore the
Every interconnection should have its own grid impact next step of calculating should give the PV penetration value
study, the importance of the power infrastructure gives different which could be accepted by the grid.
necessity of these Grid Impact Study. Several analysis and
simulation that make the whole Grid Impact Study are Load IV. BALI’S SYSTEM READINESS
Flow Analysis, Short Circuit Analysis and Dynamic Analysis.
Common knowledge to calculate system readiness of PV
Load flow analysis is an iteration simulation with main integration by comparing PV’s production drop with system
purpose to see system condition in steady state, both in normal stiffness. In order to maintain system’s condition, the PV’s
production drop should be limited to normal frequency band,
Jawa Bali system limits frequency ± 0.2 Hz. Based on swing
equation the frequency drop affected by the system inertia.
Power system configuration will not remain the same, especially
when the dispatches should maintain production cost. Different
power plant configuration would give different system inertia
[7]. Therefore, if system needs to maintain certain frequency
drop and the system inertia changes because different power
plant configuration from time to time, the PV’s production drop
will have different value from time to time. Different value of
PV’s production drop could shape into frequency density graph.
Second aspect in this study to develop PV is statistical method,
which shown on frequency density graph.
A. Swing Equation Application
The formula was changed for the purposes of this study to: Fig. IV.2. Solar Power Plant Quota
Based on the statistical aspect of system readiness, the
= (2) accepted PV capacity is 40-50 MW. Several condition that
would change this value are constant factor for production drop
Some assumption is, different production drop (ΔP) could be and PV capacity, additional inertia sources or optimal allocation
calculated with several inertia form several system inertia (H) of intermittent buffer such as battery [8].
and total load (Pr) conditions. Frequency (f) would be 50 Hz and
frequency drop (Δf) would be 0.2 Hz. Therefore, the next step of calculation should be conducted
on a case that does not have any significant additional inertia
B. Statistical Data sources in Bali’s System.
This study will consider 3 existing inertia sources which is
V. PV DEVELOPMENT LOCATION & CAPACITY
Celukan Bawang CFPP, Pesanggaran Diesel Gas Power Plant,
and power import from Java System through 150 kV 4 circuits Determining PV location and capacity will be based on load
submarine cable. In order to get value ranges of inertia sources, flow and short circuit with several combination of location and
historical data of whole 2018 was used. The power plant loading capacity. Load Flow study output is losses, loading and voltage
was calculated only between 07.00 – 17.30, which assumed the drop both for normal and N-1 condition. Short Circuit calculated
production time of PV. Therefore, the power drop came from 11 to show SCR level for each combinations of PV’s capacities &
data per day (07.00 – 17:30 by half hour) and 365 days. locations.
C. PV Quota Results A. Assumption
Based on the calculation of several value of power plant In order to have similar condition with PV quota calculation,
configuration and loading, the frequency graph of the production the base year that was chose to conduct the simulation is 2023.
drop is shown on Fig. IV.I There will be high additional inertia sources after 2023 which is
Jawa-Bali Connection project, a 500-kV interconnection from
big power plant in Jawa to load center in Bali.
The simulation conducted on 2023 case referring to every
development of power plant, transmission, substation and
demand that stated in RUPTL 2019-2028 [9]. Because this
simulation was conducted to assess the PV development, the
load and power plant configuration were adjusted to noon peak
load condition.
The PV location and capacity combination referring to the
location based on the PV potency before and total accepted
(quota) for VRE in an island. The combination shows on Table
V.1.
Fig. IV.1. Frequency Density of Production Drop
The main problems after the calculation has results, would TABLE V.1. SIMULATION COMBINATION
be PV capacity that would not give any negative impact the Substation Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb.