Sei sulla pagina 1di 5

2019 International Conference on High Voltage Engineering and Power System

October 1-4, 2019, Bali, Indonesia

Study of PV Development in Bali Island


with 3 Aspects Consideration
Musa Partahi Marbun Fajar Ari K. Anindita Satria Surya
System Planning Division Load Dispatch Centre
PT PLN (Persero) Head Office PT PLN (Persero) PT PLN (Persero)
Indonesia Indonesia Indonesia
musa@pln.co.id fajar.ari.k@gmail.com anindita.satria@pln.co.id

Abstract— PV development and its integration to the power 23% fuel mix portion for new and renewable energy (NRE) in
grid were growing rapidly, these rapid developments due to 2025 [1]. This NRE target consists of several type of power
sustainability and environmental issue. In order to support the plant, and PV development was among the biggest growth to
development, all researchers and engineers worldwide were develop (other than hydro and geothermal which already highly
conducted studies related to the PV development. Currently, most developed in Indonesia’s system).
of PV development studies only consider an aspect. Developers
consider irradiation, land acquisition, road access, and proximity PV development in Indonesia mainly because Indonesia as a
with the load. Government consider the PV’s potential and tropical country located in 60° North Latitude – 110° South
existing power system readiness. Utility considers the technical Latitude and 95° East Longitude – 141° East Longitude, i.e.
effect of PV integration based on Grid Code limitation. In order to around the equator. Based on the National Energy Plan,
have a complete view of PV development, this study considers 3 Indonesia has the potential of solar radiation reaching 4.8
aspects, such as mapping the potential of PV, the readiness of the kWh/m2/day [2].
system by statistical methods, and determining the capacity &
location of PV plants that meet Grid Code. The results of the PV The other reason is the land availability to put utility size PV
development study which considered several aspects would in Indonesia, but the problem was occurred because of the
provide benefits to PV development. This study will be applied to number of islands in Indonesia. Different system readiness
the island of Bali as a case study. would be the case, some of them like Jawa-Bali and Sumatera is
ready to have high penetration of intermittent power plant, some
Keywords—PV, Integration, Bali, Mapping, Intermittent, of them could not absorb the large size PV power plant even
Location though it has high irradiance potency.
I. INTRODUCTION Based on the above facts, it would be interesting to calculate
PV development is a current and major discussion among the PV Development in an island that have high irradiance, good
utility, developer even government. The unlimited sources, price system readiness and high availability of land use, which is Bali
trend, and low carbon emission are the main reasons which push Island.
PV development in power grid worldwide. Several The calculation process is:
considerations to develop PV such as the irradiation potency, a. Mapping analysis of PV development availability which
power system readiness, the need to reduce carbon emission, and consider irradiance, land-use, contour, etc.
decreasing PV cost already studied worldwide. Such b. System readiness by calculating the accepted
consideration usually studied by different agent, which give production drop of Bali’s system, that determined by
advantage for each agent. Developer consider irradiation statistical data of contributed inertia from power plant
potency and workability of PV’s project in order to maintain the availability.
benefit of PV Development. Government consider bigger c. Grid impact from several combinations of PV capacities
picture of PV development such as reducing carbon emission or and locations.
maintain energy sustainability, therefore such output like PV
capacity came from government target. Utility consider system II. BASIC THEORY
readiness and the grid impact of PV development. This PV
A. Geographic Information Systems
development consideration also occur on Indonesia. PV
development in Indonesia will be encouraged by several facts ESRI, a geographic information system company, defines
which is government target, high irradiance potency in some GIS as an organized collection of computer hardware, software,
islands, and system readiness. geographic data and efficiently designed to obtain, store, update,
manipulate, analyze and display all forms of information that are
Referring to Government of Indonesia’s target which stated geographic in reference [3]. GIS is designed to collect, store and
in Presidential Decree No 22, 2017, one of the targets is reaching analyze objects and phenomena where geographical location is

978-1-7281-2669-2/19/$31.00 ©2019 IEEE


an important and critical characteristic to analyze. Thus, GIS is state or N-1 state (or more contingency criteria). The important
a computer system that has four subsystems in handling output of this analysis is the loading of any power installations,
geographic reference data [4]. voltage drop of bus and system losses.
a. Data input Short circuit analysis uses symmetrical components to
b. Output data calculate the impedance. This calculation will be used to
c. Data Management calculate the short circuit current. Several assumptions and
d. Data Manipulation and Analysis standard were applied to calculate the short circuit current. The
other use of this simulation to determine the Short Circuit Ratio
Most of the data that will be handled in GIS is spatial data (SCR) of any substation, the low number of SCR could mean
that has geographical orientation. This data has a specific weak system or weak substation and vice versa.
coordinate system as its reference base and has two important
parts which are explained as follows [5] : III. PV POTENCY USING GIS
a. Location/position/coordinates information Current method to determine PV potency by implementing
(geographically referenced). several layers of irradiance, land use, and substation map, etc.
b. Descriptive information or non-spatial information
(non-geographically referenced). A. Layering
Several layer that used to determine the PV potency is:
In GIS, spatial data can be represented in two formats:
1. Slope
a. Vector Data
2. Roads
b. Raster data
3. River & Lake
One of the requirements for GIS is spatial data. This spatial 4. Forestry
data can be obtained from several sources including: 5. GHI (Global Horizontal Irradiance)
a. Data sources from analog maps B. Results
b. Data source from remote sensing systems Referring to the results, the PV potency in Bali island as
c. Source of data from measurement results in the field shown on Fig. III.1.
B. Stability
VRE characteristics is intermittent and non-dispatchable,
one of the aspects that should be considered was system
readiness. Different system condition would give different
results of penetration level for VRE. Main parameter to be
consider determining PV penetration level is system stiffness.
Power System always maintain the system frequency, the
concept is rapid production drop of PV should not disturb power
system.
Referring to [6] there is a formula that show the relationship
between system’s inertia and frequency drop which is swing
equation. By assume and some variable below are the
application of swing equation:

= (1)
Figure III.1. GIS Potency Results
Which is:
Δf : Frequency drop (Hz) The results of PV potency are around:
f : Frequency rated (Hz) 1. Kubu 150 kV Substation
H : Total system inertia (a) 2. Pemaron 150 kV Substation
ΔP : Production drop (MW) 3. Negara 150 kV Substation
Pr : Rated capacity (system peak load) 4. Amlapura 150 kV Substation
5. Gianyar 150 kV Substation
C. Grid Impact Study
With “unlimited” resources for each substation, therefore the
Every interconnection should have its own grid impact next step of calculating should give the PV penetration value
study, the importance of the power infrastructure gives different which could be accepted by the grid.
necessity of these Grid Impact Study. Several analysis and
simulation that make the whole Grid Impact Study are Load IV. BALI’S SYSTEM READINESS
Flow Analysis, Short Circuit Analysis and Dynamic Analysis.
Common knowledge to calculate system readiness of PV
Load flow analysis is an iteration simulation with main integration by comparing PV’s production drop with system
purpose to see system condition in steady state, both in normal stiffness. In order to maintain system’s condition, the PV’s
production drop should be limited to normal frequency band,
Jawa Bali system limits frequency ± 0.2 Hz. Based on swing
equation the frequency drop affected by the system inertia.
Power system configuration will not remain the same, especially
when the dispatches should maintain production cost. Different
power plant configuration would give different system inertia
[7]. Therefore, if system needs to maintain certain frequency
drop and the system inertia changes because different power
plant configuration from time to time, the PV’s production drop
will have different value from time to time. Different value of
PV’s production drop could shape into frequency density graph.
Second aspect in this study to develop PV is statistical method,
which shown on frequency density graph.
A. Swing Equation Application
The formula was changed for the purposes of this study to: Fig. IV.2. Solar Power Plant Quota


Based on the statistical aspect of system readiness, the
= (2) accepted PV capacity is 40-50 MW. Several condition that
would change this value are constant factor for production drop
Some assumption is, different production drop (ΔP) could be and PV capacity, additional inertia sources or optimal allocation
calculated with several inertia form several system inertia (H) of intermittent buffer such as battery [8].
and total load (Pr) conditions. Frequency (f) would be 50 Hz and
frequency drop (Δf) would be 0.2 Hz. Therefore, the next step of calculation should be conducted
on a case that does not have any significant additional inertia
B. Statistical Data sources in Bali’s System.
This study will consider 3 existing inertia sources which is
V. PV DEVELOPMENT LOCATION & CAPACITY
Celukan Bawang CFPP, Pesanggaran Diesel Gas Power Plant,
and power import from Java System through 150 kV 4 circuits Determining PV location and capacity will be based on load
submarine cable. In order to get value ranges of inertia sources, flow and short circuit with several combination of location and
historical data of whole 2018 was used. The power plant loading capacity. Load Flow study output is losses, loading and voltage
was calculated only between 07.00 – 17.30, which assumed the drop both for normal and N-1 condition. Short Circuit calculated
production time of PV. Therefore, the power drop came from 11 to show SCR level for each combinations of PV’s capacities &
data per day (07.00 – 17:30 by half hour) and 365 days. locations.
C. PV Quota Results A. Assumption
Based on the calculation of several value of power plant In order to have similar condition with PV quota calculation,
configuration and loading, the frequency graph of the production the base year that was chose to conduct the simulation is 2023.
drop is shown on Fig. IV.I There will be high additional inertia sources after 2023 which is
Jawa-Bali Connection project, a 500-kV interconnection from
big power plant in Jawa to load center in Bali.
The simulation conducted on 2023 case referring to every
development of power plant, transmission, substation and
demand that stated in RUPTL 2019-2028 [9]. Because this
simulation was conducted to assess the PV development, the
load and power plant configuration were adjusted to noon peak
load condition.
The PV location and capacity combination referring to the
location based on the PV potency before and total accepted
(quota) for VRE in an island. The combination shows on Table
V.1.
Fig. IV.1. Frequency Density of Production Drop
The main problems after the calculation has results, would TABLE V.1. SIMULATION COMBINATION
be PV capacity that would not give any negative impact the Substation Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb. Comb.

system. This study assumes the constant factor between


Name 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
Kubu 25 25 25 25 50

production drop and PV maximum capacity, or quota is 1:10 it Pemaron


Negara
25
25
25
25
25 25
25 25
50
50
means it is safe to assume for every 10 MW of PV installed there Amlapura 25 25 25 25 50

would be around 1 MW production drop. The results shown on Gianyar


Total 0 50 50 50
25
50 50 50
25
50 50
25
50
25
50 50 50 50 50
50
50
Fig. IV.2
B. Load Flow Result There are several cases that have same condition with base
Based on the load flow simulation, below is the Table V.2 as case, this is not negative results, but it would give better
the results. condition if the PV development could give better impact for the
system. But again, it was not safe to assume the better results
TABLE V.2. NORMAL CONDITIONS LOAD FLOW RESULTS was the better location.

Load Flow (Normal)


C. Short Circuit Result
Scenario Based on the short circuit calculation the minimum short
Losses Loading > 60% Voltage < 0.9 pu
circuit current and minimum short circuit power of 5 designated
Base (No PV) 15.3 MW (1.49%) 0 Segment(s) 0 Bus(es) substations are:
Kubu Pemaron 14.2 MW (1.38%) 0 Segment(s) 0 Bus(es) 1. Kubu 9.68 kA 2515 MVASC
Kubu Negara 14.4 MW (1.4%) 0 Segment(s) 0 Bus(es) 2. Pemaron 11.17 kA 2902 MVASC
3. Negara 16.99 kA 4414 MVASC
Kubu Amlapura 13.8 MW (1.34%) 0 Segment(s) 0 Bus(es)
4. Amlapura 8.97 kA 2330 MVASC
Kubu Gianyar 13.4 MW (1.3%) 0 Segment(s) 0 Bus(es) 5. Gianyar 12.26 kA 3185 MVASC
Pemaron Negara 14.5 MW (1.41%) 0 Segment(s) 0 Bus(es)
Therefore, the short circuit ratio (SCR) of each PV location
Pemaron Amlapura 13.9 MW (1.35%) 0 Segment(s) 0 Bus(es) and capacity combination are:
Pemaron Gianyar 13.5 MW (1.31%) 0 Segment(s) 0 Bus(es) 1. 25 MW PV in Kubu SCR: 101
Negara Amlapura 14.2 MW (1.38%) 0 Segment(s) 0 Bus(es)
2. 25 MW PV in Pemaron SCR: 116
3. 25 MW PV in Negara SCR: 177
Negara Gianyar 13.8 MW (1.34%) 0 Segment(s) 0 Bus(es) 4. 25 MW PV in Amlapura SCR: 93
Amlapura Gianyar 13.2 MW (1.28%) 0 Segment(s) 0 Bus(es) 5. 25 MW PV in Gianyar SCR: 127
Kubu 13.8 MW (1.34%) 0 Segment(s) 0 Bus(es) 6. 50 MW PV in Kubu SCR: 50
7. 50 MW PV in Pemaron SCR: 58
Pemaron 14 MW (1.36%) 0 Segment(s) 0 Bus(es)
8. 50 MW PV in Negara SCR: 88
Negara 14.7 MW (1.43%) 0 Segment(s) 0 Bus(es) 9. 50 MW PV in Amlapura SCR: 47
Amlapura 13.5 MW (1.31%) 0 Segment(s) 0 Bus(es) 10. 50 MW PV in Gianyar SCR: 64
Gianyar 12.9 MW (1.25%) 0 Segment(s) 0 Bus(es) Even though there are high value of SCR, but if the SCR >3
it would consider strong system interconnections. In order to get
There are no transmission overloading or high voltage drop better understanding of the impact, below is the results of
with each of combination. There are several results of technical weighted short circuit ratio (WSCR).
losses and for every combination the losses were drop. Even 1. 25 MW PV each in Kubu & Pemaron 54
though there are lowest number of technical losses, it was not 2. 25 MW PV each in Kubu & Negara 69
safe to assume the lowest value was the better location. The N- 3. 25 MW PV each in Kubu & Amlapura 48
1 condition of load flow simulation show on Table V.3. 4. 25 MW PV each in Kubu & Gianyar 57
5. 25 MW PV each in Pemaron & Negara 73
TABLE V.3. NORMAL CONDITIONS LOAD FLOW RESULTS 6. 25 MW PV each in Pemaron & Amlapura 52
Load Flow (N-1)
7. 25 MW PV each in Pemaron & Gianyar 61
Scenario 8. 25 MW PV each in Negara & Amlapura 67
Loading > 60% Voltage < 0.9 pu
9. 25 MW PV each in Negara & Gianyar 76
Base (No PV) 1 Case(s) & 3 Segment(s) 1 Case(s) & 6 Bus(es) 10. 25 MW PV each in Amlapura & Gianyar 55
Kubu Pemaron 1 Case(s) & 3 Segment(s) 0 Case(s) & 0 Bus(es) 11. 50 MW PV in Kubu 50
Kubu Negara 1 Case(s) & 3 Segment(s) 1 Case(s) & 1 Bus(es)
12. 50 MW PV in Pemaron 58
13. 50 MW PV in Negara 88
Kubu Amlapura 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es) 14. 50 MW PV in Amlapura 47
Kubu Gianyar 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es) 15. 50 MW PV in Gianyar 64
Pemaron Negara 1 Case(s) & 3 Segment(s) 1 Case(s) & 1 Bus(es)
Pemaron Amlapura 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es)
Based on above results there are some high value of WSCR,
because the minimum number is 3, therefore the assumption of
Pemaron Gianyar 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es)
every combination still fulfills the WSCR’s criteria even though
Negara Amlapura 1 Case(s) & 3 Segment(s) 1 Case(s) & 1 Bus(es) there are several combinations that has better WSCR value.
Negara Gianyar 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es)
D. Analysis
Amlapura Gianyar 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es)
Based on the results, this kind of results occur because there
Kubu 1 Case(s) & 3 Segment(s) 1 Case(s) & 1 Bus(es) are no cases that exceeded the existing condition and not to
Pemaron 1 Case(s) & 3 Segment(s) 1 Case(s) & 1 Bus(es) mention exceeded the Grid Code’s criteria. Some of the
Negara 1 Case(s) & 3 Segment(s) 1 Case(s) & 6 Bus(es) combination are better than the other but with a single case (2023
case of 14.00 peak load) should not justify other condition.
Amlapura 1 Case(s) & 2 Segment(s) 1 Case(s) & 1 Bus(es)
Therefore, the system impact aspect in this study case only give
Gianyar 1 Case(s) & 2 Segment(s) 0 Case(s) & 0 Bus(es) reassurance of PV Development based on the other aspects.
VI. CONCLUSION [3] M. Law and A. Collins, Getting to Know ArcGIS Desktop, Fifth.
California: Esri Press, 2018.
PV development in Bali Island should referring to the results [4] D. Peuquet and D. Marble, Introductory Readings In Geographic
of the study, which the results consist of the PV location and its Information Systems/edited by Donna J. Peuquet, Duane F. Marble.
capacity. 2013.
[5] J. M. Sánchez-Lozano, J. Teruel-Solano, P. L. Soto-Elvira, and M.
The alternative location could be near Kubu, Pemaron, Socorro García-Cascales, “Geographical Information Systems (GIS)
Negara, Amlapura, and Gianyar. Specific land survey should be and Multi-Criteria Decision Making (MCDM) methods for the
conducted to get real condition of these substations, especially evaluation of solar farms locations: Case study in south-eastern
space for the land. Spain,” Renew. Sustain. Energy Rev., vol. 24, pp. 544–556, 2013.
[6] P. Kundur, Power System Stability and Control, Third Edition. Mc
The PV capacity in Bali, before Bali’s system has additional Graw Hill, Inc, 1994.
inertia sources, is no more than 50 MW. Based on grid impact [7] M. P. Marbun, A. Y. Salile, and A. S. Surya, “Grid Impact Study of
study even though there are no problem for 50 MW in one Variable Renewable Energy Integration to Java-Bali System,” 2018
substation, but it would be better to have 25 MW in 2 different 8th Int. Conf. Power Energy Syst. ICPES 2018, pp. 182–189, 2019.
substations. [8] A. S. Surya, P. Awater, M. P. Marbun, and N. Hariyanto, “Optimal
Allocation of Photovoltaic in the Hybrid Power System using
REFERENCES Knapsack Dynamic Programming,” IEEE PES Innov. Smart Grid
Technol. Conf. Asia, 2019.
[9] PT PLN (Persero), Rencana Usaha Penyediaan Tenaga Listrik PT
[1] R. I. Kementrian ESDM, “Peraturan Presiden Republik Indonesia PLN (Persero) 2019-2028, vol. 1. Jakarta, Indonesia, 2019.
Nomor 22 Tahun 2017.pdf.” Jakarta, Indonesia, 2017.
[2] IRENA, Power Generation Costs in 2017, vol. Abu Dhabi. 2018.

Potrebbero piacerti anche