Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. NLC will deduct the rent of Batching Plant Per Cum or Per Month as
decided by NLC.
2. Minor repair maintainance of the Plant is our responsibility.
LANT TORKHAM
Transportation and
Pouring
of Concrete
(TMs+Concrete
775 5270
Pump)
775 5144
775 4632
775 4543
775 4600
775 5985
sponsibility.
RATE ANALYSIS
(A) MANPOWER
Ser Desciption Qty Hr. Rate/Day
1 Batching Plt Op 1 1 1,538.46
2 Plant Op Helper 1 1 692.31
3 Plant Electrition 1 1 961.54
4 Labour 3 1 692.31
Total
Total/Unit
(B) EQUIPMENT
1 Batching Plt Op 1 1 9,615.38
2 Front Loader 1 1 9,615.38
3 Batching Plt Generator 1 1 6,923.08
4 Water Bowzer 1 1 2,500.00
Total
Total/Unit
(C) EQUIPMENT FUEL
1 Front Loader 1 1 20.00
2 Batching Plt Generator 1 1 32.00
3 Water Bowzer 1 1 5.00
Total
Total/Unit
(D) MATERIAL
1 Crush All Tupe CM 8.4
2 Cement Bas 41
3 Sand CM 4.16
Total
Total/Unit
(E) SUMMARY
E.1 Basic Cost (A+B+C+D)
E.2 Cost per CM
Add Maintance Charges / Cum
Total Cost Per CM
E.3 Add @ 25% for Contractor Profit+Tax+Overhead
Total Cost Per CM
RATE ANALYSIS
(A) MANPOWER
Ser Desciption Qty Hr. Rate/Day
1 Batching Plt Op 1 1 1,538.46
2 Plant Op Helper 1 1 692.31
3 Plant Electrition 1 1 961.54
4 Labour 3 1 692.31
Total
Total/Unit
(B) EQUIPMENT
1 Batching Plt Op 1 1 9,615.38
2 Front Loader 1 1 9,615.38
3 Batching Plt Generator 1 1 6,923.08
4 Water Bowzer 1 1 2,500.00
Total
Total/Unit
(C) EQUIPMENT FUEL
1 Front Loader 1 1 20.00
2 Batching Plt Generator 1 1 32.00
3 Water Bowzer 1 1 5.00
Total
Total/Unit
(D) MATERIAL
1 Crush All Tupe CM 7.96
2 Cement Bas 54
3 Sand CM 3.98
Total
Total/Unit
(E) SUMMARY
E.1 Basic Cost (A+B+C+D)
E.2 Cost per CM
Add Maintance Charges / Cum
Total Cost Per CM
E.3 Add @ 25% for Contractor Profit+Tax+Overhead
Total Cost Per CM
RATE ANALYSIS
(A) MANPOWER
Ser Desciption Qty Hr. Rate/Day
1 Batching Plt Op 1 8 1,538.46
2 Plant Op Helper 1 8 692.31
3 Plant Electrition 1 8 961.54
4 Labour 4 8 692.31
Total
Total/Unit
(B) EQUIPMENT
1 Batching Plt 1 4 9,615.38
2 Front Loader 1 4 9,615.38
3 Batching Plt Generator 1 4 6,923.08
4 Water Bowzer 1 4 2,500.00
Total
Total/Unit
(C) EQUIPMENT FUEL
1 Front Loader 1 4 20.00
2 Batching Plt Generator 1 4 32.00
3 Water Bowzer 1 4 5.00
Total
Total/Unit
(D) MATERIAL
1 Crush All Tupe CM 52.41
2 Cement Bags 597.4
3 Sand CM 32.76
4 Admixture Lit 382.32
Total
Total/Unit
(E) SUMMARY
E.1 Basic Cost (A+B+C+D)
E.2 Cost per CM
Add Maintance Charges / Cum
Total Cost Per CM
E.3 Add @ 25% for Contractor Profit+Tax+Overhead
Total Cost Per CM
RATE ANALYSIS
(A) MANPOWER
Ser Desciption Qty Hr. Rate/Day
1 Batching Plt Op 1 8 1,538.46
2 Plant Op Helper 1 8 692.31
3 Plant Electrition 1 8 961.54
4 Labour 4 8 692.31
Total
Total/Unit
(B) EQUIPMENT
1 Batching Plt 1 4 9,615.38
2 Front Loader 1 4 9,615.38
3 Batching Plt Generator 1 4 6,923.08
4 Water Bowzer 1 4 2,500.00
Total
Total/Unit
(C) EQUIPMENT FUEL
1 Front Loader 1 4 20.00
2 Batching Plt Generator 1 4 32.00
3 Water Bowzer 1 4 5.00
Total
Total/Unit
(D) MATERIAL
1 Crush All Tupe CM 50.68
2 Cement Bags 630.38
3 Sand CM 31.68
4 Admixture Lit 377.28
Total
Total/Unit
(E) SUMMARY
E.1 Basic Cost (A+B+C+D)
E.2 Cost per CM
Add Maintance Charges / Cum
Total Cost Per CM
E.3 Add @ 25% for Contractor Profit+Tax+Overhead
Total Cost Per CM
RATE ANALYSIS
(A) MANPOWER
Ser Desciption Qty Hr. Rate/Day
1 Batching Plt Op 1 8 1,538.46
2 Plant Op Helper 1 8 692.31
3 Plant Electrition 1 8 961.54
4 Labour 4 8 692.31
Total
Total/Unit
(B) EQUIPMENT
1 Batching Plt 1 4 9,615.38
2 Front Loader 1 4 9,615.38
3 Batching Plt Generator 1 4 6,923.08
4 Water Bowzer 1 4 2,500.00
Total
Total/Unit
(C) EQUIPMENT FUEL
1 Front Loader 1 4 20.00
2 Batching Plt Generator 1 4 32.00
3 Water Bowzer 1 4 5.00
Total
Total/Unit
(D) MATERIAL
1 Crush All Tupe CM 59.78
2 Cement Bags 638.6
3 Sand CM 27.51
4 Admixture Lit 381.6
Total
Total/Unit
(E) SUMMARY
E.1 Basic Cost (A+B+C+D)
E.2 Cost per CM
Add Maintance Charges / Cum
Total Cost Per CM
E.3 Add @ 25% for Contractor Profit+Tax+Overhead
Total Cost Per CM
RATE ANALYSIS
(A) MANPOWER
Ser Desciption Qty Hr. Rate/Day
1 Batching Plt Op 1 1 1,538.46
2 Plant Op Helper 1 1 692.31
3 Plant Electrition 1 1 961.54
4 Labour 4 1 692.31
Total
Total/Unit
(B) EQUIPMENT
1 Batching Plt 1 1 9,615.38
2 Front Loader 1 1 9,615.38
3 Batching Plt Generator 1 1 6,923.08
4 Water Bowzer 1 1 2,500.00
Total
Total/Unit
(C) EQUIPMENT FUEL
1 Front Loader 1 1 20.00
2 Batching Plt Generator 1 1 32.00
3 Water Bowzer 1 1 5.00
Total
Total/Unit
(D) MATERIAL
1 Crush All Tupe CM 3620
2 Cement Bags 74.16
3 Sand CM 2.85
4 Admixture Lit 27.12
Total
Total/Unit
(E) SUMMARY
E.1 Basic Cost (A+B+C+D)
E.2 Cost per CM
Add Maintance Charges / Cum
Total Cost Per CM
E.3 Add @ 25% for Contractor Profit+Tax+Overhead
Total Cost Per CM
Rate/Hr Amount (Rs)
192.31 192.31
86.54 86.54
120.19 120.19
86.54 259.62
658.65
73.18
1,201.92 1,201.92
1,201.92 1,201.92
865.38 865.38
312.50 312.50
3,581.73
397.97
130.00 2,600.00
130.00 4,160.00
130.00 650.00
7,410.00
823.33
1,342.16 11,274.14
- -
2,225.16 9,256.67
20,530.81
2,281.20
32,181.19
3,575.89
20.00
3,595.69
898.92
4,494.61
Rate/Hr Amount (Rs)
192.31 192.31
86.54 86.54
120.19 120.19
86.54 346.15
745.19
82.80
1,201.92 1,201.92
1,201.92 1,201.92
865.38 865.38
312.50 312.50
3,581.73
397.97
130.00 2,600.00
130.00 4,160.00
130.00 650.00
7,410.00
823.33
1,342.16 10,683.59
- -
2,225.16 8,856.14
19,539.73
2,171.08
31,276.65
3,475.18
20.00
3,495.18
873.80
4,368.98
Rate/Hr Amount (Rs)
192.31 1,538.46
86.54 692.31
120.19 961.54
86.54 2,769.23
5,961.54
82.80
1,201.92 4,807.69
1,201.92 4,807.69
865.38 3,461.54
312.50 1,250.00
14,326.92
198.89
130.00 10,400.00
130.00 16,640.00
130.00 2,600.00
29,640.00
411.67
1,342.16 70,342.61
- -
2,225.16 72,896.24
72.00 27,527.04
170,765.89
2,371.75
220,694.35
3,065.20
20.00
3,085.20
771.30
3,856.50
Rate/Hr Amount (Rs)
192.31 1,538.46
86.54 692.31
120.19 961.54
86.54 2,769.23
5,961.54
82.80
1,201.92 4,807.69
1,201.92 4,807.69
865.38 3,461.54
312.50 1,250.00
14,326.92
198.99
130.00 10,400.00
130.00 16,640.00
130.00 2,600.00
29,640.00
411.67
1,342.16 68,020.67
- -
2,225.16 70,493.07
72.00 27,164.16
165,677.90
2,301.08
215,606.36
2,994.53
20.00
3,014.53
753.63
3,768.17
Rate/Hr Amount (Rs)
192.31 1,538.46
86.54 692.31
120.19 961.54
86.54 2,769.23
5,961.54
82.80
1,201.92 4,807.69
1,201.92 4,807.69
865.38 3,461.54
312.50 1,250.00
14,326.92
198.99
130.00 10,400.00
130.00 16,640.00
130.00 2,600.00
29,640.00
411.67
1,342.16 80,234.32
- -
2,225.16 61,214.15
72.00 27,475.20
168,923.68
2,346.16
218,852.14
3,039.61
20.00
3,059.61
764.90
3,824.52
Rate/Hr Amount (Rs)
192.31 192.31
86.54 86.54
120.19 120.19
86.54 346.15
745.19
124.20
1,201.92 1,201.92
1,201.92 1,201.92
865.38 865.38
312.50 312.50
3,581.73
596.96
130.00 2,600.00
130.00 4,160.00
130.00 650.00
7,410.00
1,235.00
1,342.16 4,858.62
- -
2,225.16 6,341.71
72.00 1,952.64
13,152.97
2,192.16
24,889.89
4,148.31
20.00
4,168.31
1,042.08
5,210.39
NAVEED BROTHERS
Concrete Design Cement Sand Crush Chemical
Bags CuM CuM Lit
Lean 41 4.16 8.4
Class B 54 3.98 7.96
Class A1 597.4 32.76 52.41 382.32
Class A2 630.38 31.68 50.68 377.28
Class A3 638.6 27.51 59.78 381.6
Class D1 74.16 2.85 3.62 27.12