Sei sulla pagina 1di 8

QUOTATION

SHIN KHAI CONSTRUCTION PTE LTD REFERENCE NO.: 1901-088B


243 KAKI BUKIT AVENUE 1
DATE : 11/01/2019
SHUN LI INDUSTRIAL PARK
SINGAPORE 416056 VALIDITY PERIOD : 7 Days
from date above
Attn.: MR KOH SIOW KHAI / MS SU AI LI CURRENCY : SGD

Tel : 6441 8818 / 9387 4544 Fax : 6441 8819 LOCATION : Pasir Ris St52_500-521

PROPOSED NEW ERECTION OF A 3-STOREY ENVELOPE CONTROL TERRACE HOUSE WITH AN ATTIC
ON LOT 04117T, MK 27 AT 37 KEE SUN AVENUE (BEDOK PLANNING AREA)

Thank you for your inviting us to quote for the above project - Bored Micropile
We are pleased to submit our quotation as follows for your consideration.

DESCRIPTION QTY UM RATE TOTAL


1 Mobilisation and demobilisation of Bored Micropile rig. 1 NO. 18,500.00 18,500.00
* Incl. Internal-mob.

Supply and installation of BORED Micropiles (G35 OPC cement grout)


with diameter 300mm,
2 BH-327, Comb2 819kN ; NSF 70kN. 10 NOS x 32.50 M 325 M. 180.00 58,500.00
3 BH-253, Comb2 747kN ; NSF 56kN. 10 NOS x 32.50 M 325 M. 180.00 58,500.00
with 4H25 non-galvanised & R6-100mm c/c.
* Excl. permanent steel casing & socketing.

4 Supply of capping plate & cutting-off of pile heads to C.O.L after 20 NOS. 100.00 2,000.00
excavation by Main-Con.
* Excl. bending of rebar
* Pile heads to be disposal by others if cutting-off pile heads by others.

5 PDA load test to 2 times working load. 4 NOS. 1,800.00 7,200.00

6 Vibration Monitoring for the entire piling works only. 1 LS. 1,400.00 1,400.00

7 Noise Monitoring for the entire piling works only. 1 LS. 1,300.00 1,300.00

8 Pre-computation boundary survey. (* Excl. TBM) 1 LS. 3,200.00 3,200.00

GST :
PROVISIONAL : SGD
Important Notes :
a) Enclosed :Terms & Conditions , Method statement
b) Paylength Chargeable : Existing Ground-level to toe-of-pile.
c) Minimum Paylength : Not Applicable.
d) Minimum Clearance from any obstruction for operation : Front - 1000 mm & Side - 1300 mm
e) Retention : Strictly Not Applicable

Page : 1/4
QUOTATION

SHIN KHAI CONSTRUCTION PTE LTD REFERENCE NO.: 1901-088B


243 KAKI BUKIT AVENUE 1
DATE : 11/01/2019
SHUN LI INDUSTRIAL PARK
SINGAPORE 416056 VALIDITY PERIOD : 7 Days
from date above
Attn.: MR KOH SIOW KHAI / MS SU AI LI CURRENCY : SGD

Tel : 6441 8818 / 9387 4544 Fax : 6441 8819 LOCATION : Pasir Ris St52_500-521

PROPOSED NEW ERECTION OF A 3-STOREY ENVELOPE CONTROL TERRACE HOUSE WITH AN ATTIC
ON LOT 04117T, MK 27 AT 37 KEE SUN AVENUE (BEDOK PLANNING AREA)

Thank you for your inviting us to quote for the above project - Bored Micropile
We are pleased to submit our quotation as follows for your consideration.

DESCRIPTION QTY UM RATE TOTAL

9 Setting-out / ECC survey. 1 LS. 2,300.00 2,300.00


* SVY 21 Ref. datum to be provided by Main-Con if Pre-com Survey
by other.
* Additional charged for SVY 21 datum @ $1,800.00 LS if not provided
* Up to 2 trips only. Additional trips will be charged at $400.00/trip.

10 As Built Drawing with Registered Surveyor endorsement & 1 LS. 1,200.00 1,200.00
As Built pile information with as built SVY 21 coordinates of individual
pile in excel format.
* Extg Working platform level & Piles Cut-off-level to be provided.
by Main-con (For As Built Pile Information Tabulation)

11 Cable Detection. (* Incl. apply for NCD application.) 1 LOC. 1,800.00 1,800.00

12 NCE application. (*Estimated only) 2 SVCS 500.00 1,000.00


*Additional cost will be charged accordingly depends to services
detected on site
*Trial holes by main-contractor.
*Road closure, TMA and all road closing works by main-con, if required.
*The NCD/NCE application is valid for 6 months only. Resubmit will
charged accordingly.

GST :
PROVISIONAL : SGD
Important Notes :
a) Enclosed :Terms & Conditions , Method statement
b) Paylength Chargeable : Existing Ground-level to toe-of-pile.
c) Minimum Paylength : Not Applicable.
d) Minimum Clearance from any obstruction for operation : Front - 1000 mm & Side - 1300 mm
e) Retention : Strictly Not Applicable

Page : 2/4
QUOTATION

SHIN KHAI CONSTRUCTION PTE LTD REFERENCE NO.: 1901-088B


243 KAKI BUKIT AVENUE 1
DATE : 11/01/2019
SHUN LI INDUSTRIAL PARK
SINGAPORE 416056 VALIDITY PERIOD : 7 Days
from date above
Attn.: MR KOH SIOW KHAI / MS SU AI LI CURRENCY : SGD

Tel : 6441 8818 / 9387 4544 Fax : 6441 8819 LOCATION : Pasir Ris St52_500-521

PROPOSED NEW ERECTION OF A 3-STOREY ENVELOPE CONTROL TERRACE HOUSE WITH AN ATTIC
ON LOT 04117T, MK 27 AT 37 KEE SUN AVENUE (BEDOK PLANNING AREA)

Thank you for your inviting us to quote for the above project - Bored Micropile
We are pleased to submit our quotation as follows for your consideration.

DESCRIPTION QTY UM RATE TOTAL


OPTIONAL:
Extra over item 2 & 3 for socketing thru Hard
stratum / Granite. (SPT>100SPT) with
13 300mm dia. 1 NOS. x 1.00 M. 1 M. 380.00 0.00

Supply & Installation of permanent steel casing


< 4.5mm thks. (Excl. debonding with Bentonite & Bintumen)
14 300mm dia. 1 NOS x 1.00 M 1 M. 90.00 0.00
* Installed to stated or collapsible depth whichever shorter.
* Paylength chargeable: Total installation length of casing.

Tensile Test for :


15 Rebar. 1 TEST 350.00 0.00
16 Spliced Coupler. 1 TEST 450.00 0.00

17 Night (From 7pm - 10pm or part-of) / Sunday / Public holiday works. 1 DAY. 600.00 0.00

Standby of full time :


18 Site Supervisor. 1 MDY. 200.00 0.00
19 Safety Supervisor (* with BCSS cert only). 1 MDY. 200.00 0.00

Important Notes (Cont') : -

GST :
PROVISIONAL : SGD
Important Notes :
a) Enclosed :Terms & Conditions , Method statement
b) Paylength Chargeable : Existing Ground-level to toe-of-pile.
c) Minimum Paylength : Not Applicable.
d) Minimum Clearance from any obstruction for operation : Front - 1000 mm & Side - 1300 mm
e) Retention : Strictly Not Applicable

Page : 3/4
QUOTATION

SHIN KHAI CONSTRUCTION PTE LTD REFERENCE NO.: 1901-088B


243 KAKI BUKIT AVENUE 1
DATE : 11/01/2019
SHUN LI INDUSTRIAL PARK
SINGAPORE 416056 VALIDITY PERIOD : 7 Days
from date above
Attn.: MR KOH SIOW KHAI / MS SU AI LI CURRENCY : SGD

Tel : 6441 8818 / 9387 4544 Fax : 6441 8819 LOCATION : Pasir Ris St52_500-521

PROPOSED NEW ERECTION OF A 3-STOREY ENVELOPE CONTROL TERRACE HOUSE WITH AN ATTIC
ON LOT 04117T, MK 27 AT 37 KEE SUN AVENUE (BEDOK PLANNING AREA)

Thank you for your inviting us to quote for the above project - Bored Micropile
We are pleased to submit our quotation as follows for your consideration.

DESCRIPTION QTY UM RATE TOTAL


f) Site access to be levelled & ECM and perimeter silt fence to be
provided by Main-con.

PAYMENT TEMRS :
1) Save as is expressly provided in this quotation, the provisions of the
Building and Construction Industrial Security of Payment Act ('SOP Act')
shall apply. Sample on Payment Certificate is attached for your reference.
Advance : a) 35% Upon Confirmation.
b) 70% Upon 70% (14nos) piling workdone on site.
c) 90% upon 90% (18 nos) piling workdone on site before
load tests.
(* Subject to adjustment on case by case basis)
Balance : a) Frequency of seving our progress claim :
Every 14th & 28th of the month.
b) Your Payment Responce (Payt Certificate) to us :
Within 7 days from date of our Letter Of Claim.
c) Progress payment due date :
Within 14 days from date of our Letter Of Claim.
Final payment in Exchange for Original Site Documents.
Manyear Support:-
* Project value S$50K - S$100K --> 1MYE
* Project value for next & subsequent every S$100K --> + 1MYE

156,900.00
GST : 10,983.00
PROVISIONAL : SGD 167,883.00
Important Notes :
a) Enclosed :Terms & Conditions , Method statement
b) Paylength Chargeable : Existing Ground-level to toe-of-pile.
c) Minimum Paylength : Not Applicable.
d) Minimum Clearance from any obstruction for operation : Front - 1000 mm & Side - 1300 mm
e) Retention : Strictly Not Applicable

Page : 4/4
Reference No. : 1901-088B Date : 11/01/2019

TERMS & CONDITIONS (T & C)

1) Price quoted is strictly valid for the above mentioned items only. Any additional work done or materials consumed
(not listed / quoted) will be charged accordingly.
2) Any additional method or materials required to drive pile deeper / drive through hard layer shall be charged accordingly.
3) All quantity and penetration stated above are PROVISIONAL only. Actual quantity and paylength will be based on site
re-measurement. All piles will be installed to 2*SWL + 1*NSF (if any) or required set pressure regardless of penetration.
Geotechnical capacity justifications shall not be our responsibility if the pile design is done by others.
4) Piling work is assumed to be carried out continuously until completion without any interruption. Otherwise additional
costs will be charged for ' idling time ' or subsequent mobilisation and demobilisation.
5) The following are NOT INCLUDED / LIABLE in our scope of works & are to be provided / covered by your Company / Client :
5.1) Reasonable access for mobilisation, demobilisation and movement within the site for our piling machine including
sufficient clearances from existing structures and necessary hoisting facilities within site shall be provided.
5.2) Safe and stable working platform, reasonable levelled and flat ground topped with min. 300mm crushed hardcore
that is able to withstand our machineries load is required during piling operation, to avoid soil movement,
sinking of piling equipment etc.
5.3) ALL INSURANCE COVERAGE (INCLUDING EXCESS) during work-in-progress, mobilisation & demobilisation. WE SHALL
NOT BE HELD RESPONSIBLE FOR ANY COMPENSATION OR WHATSOEVER; WHICH MAY BE CLAIMED BY ANY THIRD
PARTY OR LOCAL AUTHORITY CONCERNED. Any repair costs & damage to neighbouring properties eg. soil
movement / weakening / vibration / collapse that result in damage to slabs, columns, retaining structures, boundary
wall etc shall not be borne by us.
5.4) Setting out of pile position accurately (with safe distance away from the underground service, if any) and eccentricity
checks after piling, if undertaken by your Company / Client. Checking of eccentricity (ECC) for all piling point
immediately upon completion of piling work prior to commencement of your excavation work to avoid unnecessary
ECC out of tolerance issue.
5.5) Detection, protection and diversions etc of all existing underground services and damages to such services and
subsequent reinstatement. Application and cost for underground detection services for NCD and NCE (within
the vicinity of high voltage cable, when required) including fees charged by relevant authorities for their services
& attendance notwithstanding that Peck Brothers Construction Pte Ltd ("Peck Brothers") is named as the applicant
in the application to the relevant authorities. To carry out all necessary trial holes(if any) to ensure the piling locations
are cleared of all underground services & structures (MRT, railway tunnels etc). Reports and plan for NCD & NCE
application must be furnished to us. Your Company shall indemnify and cover us against any liabilities, claims and
charges, should our piling works affect, damage any underground services. For piling works carry out on public area,
your site-in-charge personnel to endorse on our indemnity form before commencement of piling works.
5.6) Hacking, removing and reinstatement of concrete surfaces and under/above ground obstructions.
5.7) All temporary works, excavation, marking of pile cut-off-level and pumping of water.
5.8) Obtain all necessary permits / clearance / licences from the relevant authorities before commencing of piling works.
5.9) Pre-construction Survey of surrounding premises. Hoardings, temporary struttings & subsequent reinstatement of site.
5.10) Resident Technical Officer's supervision and overtime claims.
5.11) Provision of supervisor trained in compliance with all Workplace Safety and Health Regulations or any subsequent
amendments thereto.
6) Kindly support us with Manyears Entitlement for our NTS workers' permit, upon awarded project to us.
7) In the event of any circumstance constituting Force Majeure, which is defined as act of God, or due to any cause beyond
Peck Brothers's control, such as market raw material shortages, unforeseen plant breakdown or labour dispute, our
duty to perform its obligations shall be suspended or limited until such circumstance ceases. In any event, Peck Brothers
shall not be liable in any way for loss or damage arising directly through or in consequence of such events or situations.

Notice of commencement: To be discussed (Your early confirmation on our quotation is appreciated for us to schedule your
work).
We look forward to your confirmation and acceptance of our offer.
Thank You !

Yours faithfully, We accept & understood the above QUOTATION incl.


Peck Brothers Construction Pte Ltd TERMS & CONDITIONS, PAYMENT TERMS &
IMPORTANT NOTES

JIA WEN
stamp
for Edmund Peck C H For and on behalf of
Project Manager SHIN KHAI CONSTRUCTION PTE LTD
Name : ______________________________
(Computer generated quote, signature is not required) Designation : _________________________
Date : _______________________________
TERMS & CONDITIONS (T & C) Cont'd

The followings are additional terms & conditions for this contract.
8) No headroom constraint.
9) All instrumentation and monitoring works (other than quoted) shall be done by Main-contractor.
10) Adequate storage space for our equipment and material shall be provided by Main-contractor.
11) In the event pile ECC are out-of tolerance, any enlargement of pilecap, stump, beam and additional beam
etc, claims shall only limit to S$300/m3 of net increase in volume of concrete inclusive of formwork, rebar,
equipment, labour and all associated costs.
12) Vector Control and traffic control incl. traffic diversion and provision of warning & traffic sign by others.
13) Protection & temporary works including retaining structures, planking, strutting, shoring and dewatering
to excavated slopes, basement if applicable, trenches during work-in progress or pile cutting off.
14) Main-contractor shall assist to lift the cut-off-pile section from the pit.
15) Please ensure all sewer inlet and connecting pipes are sealed completely to avoid seepage into the
system. We shall not be held responsible for any seepage into the systems.

The followings facilities and services are to be provided to us at no extra cost.


15) Drilling Slurry (sludge) shall be disposed off site by us and leftover earth on site by Main-contractor at no
cost.
16) Refuse bin shall be provided by Main-contractor to dispose debris and waste at no cost.
17) Washing bay, site toilets, shed, adequate water and power supply (for piling operation). Lighting for night
work when works is required.

18)The following materials shall be supplied by Main-contractor without any administrative charge and
remain fixed for the whole piling contract or duration if shortage of materials in the market:
i) Ordinary Portland Cement OPC 50kg/bag at S$120 per ton.
ii) Non-galvanized steel reinforcement straight bars Grade 500N/mm2 at S$430.00 per ton. Cost will be
deducted from respective progress claim.
Bored Micropile Machine Setback Requirement

b b

b b

a
a

BMP min. setback


BMP min. setback a= 800 mm
a= 800 mm b= 1200 mm
b= 1200 mm

Legend :
Pile Position

Potrebbero piacerti anche