Sei sulla pagina 1di 97

Inspection and Test Plan for- DRANGE WORKS

Date of Issue: 11-12-2014 ITP Reference Number / Serial No.: 006

Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.


Project Name: ALDARB General Agreement No: REV:0 Engineer / Engineer Representative: Inspection Points:H=Hold Point,
Hospital ( 200 Bed ) W=Witness Point, R=Review Point,
S=Surveillance, A=Approval
Project No.: C0517 Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorporated

Project Loc. : ALDARB

Inspection Points
Frequency of Test or Acceptance Criteria / Tolerance Specification
Item No. Activity Description Inspection & Test Activity Inspection Parameters Reference Verifying Document / Report
SUB-CON CONTRACTOR ITL ENGINEER

1 Method Statement
1.1 Approval of Method Statement Submit to the Enigeer Before Work Approval from Engineer Representative Specification Section A A Approved Submittals
2 Prior Activities
2.1 Approved Shop Drawing Verify the approval Approval from Engineer Representative Specification Section A S Approved Submittals

Every existing service has to be correctly


2.2 Identification, location and protection Verify location and protection Prior to Start Work located and protected W A Exisiting Service as found drawing

2.3 Survey + Execution Set out of the excavation area According to the Drawings A A Survey Report

3 Main Activities

THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED CONSULTANT OFFICE AND


3.1 MINISTRY OF HEALTH
SPECIFICATION &CODES A/W A/W
MIR(material inspection
request check delivery) Inspection Reports and each
DRAINAGE WORKS VISUAL INSPECTION
and safe &adequate delivery
protection
3.2 INSPECTION REQUEST OF MATERIALS (PIPEING AND FITTING AND ACCESSORIES) AS SPECIFIED W W

1. Open an approved shop drawings. This shop drawings consist of


approved
sanitary fixtures details and mechanical pipe sleeves location and
sanitary fixtures ventilation.in the shaft walls)
2. Waiting pipes, stub pipes and fittings from risers and underground
pipes should be present before starting inside the sanitary fixtures.
Hollow vertical shaft or duct located nearby the sanitary fixtures will not
be cover to work easily inside the building especially connection to the
risers.
3. Assign the location of pipes in the wall or floor that is exactly as
mention on the approved sanitary fixtures details shop drawing. Mark
with the line corresponds to the sanitary fixtures area to bury the pipe in
the wall or floor (for lavatory and A/C drain).
4. Use block cutter or simply portable grinder to cut a side of block
continuously along the line that had been marked. Absolute care should
be done not to cut or damaged the pre-installed pipe sleeves of sanitary
fixtures vents.
5. By using sharp- pointed steel rod and other proper chipping tools, chip
the block side to the thickness required to fixed the sanitary pipes.
6. Standard fittings and materials must be used and all pipes and fittings
must be joined using the approved glue. Sanitary tee fittings for vent be
3.3 fixed inclined slope from center line of pipe it serve.
7. Level of the slab should be identified by surveyor before proceeding
installation. Also locate points as alternative reference point for pipe and
pipe fittings installation.
8. Install / layout the pipes at designated height, location and slopes (1%
slope for sanitary fixtures and 0.5% slope for A/C drain). Sanitary fixtures
outlet location should also be installed and identified.
9. Connection of drainage pipes other than water closet drain (i.e. A/C
drain, lavatory drain, bidet drain, bathtub drain and shower tray drain)
should be slope toward gully trap floor drain based on the approved toilet
details shop drawings.
10. Pipes and pipe fittings connection should be on the compacted fine
project specification
DRAINAGE WORK INSTALLATION sand and partly small of cement mortar as its support. Height distance DURING WORK Approval specifications section A W A/R Inspection Reports
between gully trap bottom and slab should be two (2) centimeter for all
toilets.
11. Absolute care should be imposed not to damage the water proofing
upon installation.
12. Install sleeves for pipes passing through the concrete or masonry
walls. Put sealant in between the pipes and sleeves.
13. Check the pipes securely fixed, joint and capped before leak testing.
14. Leak test for the installed pipes is to be carried-out with presence of
inspector

for underground sewer pipe installation. 1.


Excavate trenches to provide a clearance 200mm on each of the pipe.
2. Bedding to be compacted in layers not exceeding 150mm to give
uniform bed.
3. Lay the pipe directly on the bedding.
4. The pipes must be installed as indicated on the approved shop drawing
with the required invert level and proper slope using the approved
materials and fittings.
5. Trench is not to be open too far in advance of pipe laying and then
backfilled as soon as possible .
6. Use fine sand and compact fill firmly between the side of the pipe and
the trench.
7. Brick or hard materials under the pipe are not allowed to be used.
8. Provide a warning tape along the pipe and below the upper layer of the
sand.
9. Until the crown of the pipe is covered by at least two feet of a tamped
sand, considerable care shall be exercised in the back filling of trenches.
10. The underground pipe must comply with the manufacturer
recommendations for laying the underground pipes.

FINAL INSPECTION FOR ALL WORK APPROVAL FOR ALL LEVEL AFTER FINSH AND AFTER COMPLEET project specification
3.4 FINAL APPROVAL BEFOR INSTALING SEELING WORK TO THE SHOP DRAWING section A W A/W FINAL SITE INSPECTION

ITP SIGN OFF-POST COMPLETION OF WORKS

REV. COMMENTS SUB-CONTRACTOR-if available CONTRACTOR ITL, If applicable ENGINEER


0
SIGNED: SIGNED: SIGNED: SINGED:

NAME: NAME: NAME: NAME:

DATE: DATE: DATE: DATE:


er supply WORKS

Inspection Points:H=Hold Point,


W=Witness Point, R=Review Point,
S=Surveillance, A=Approval
an, CI=Comments Incorporated

Inspection Points
Verifying Document / Report
ENGINEE
SUB-CON CONTRACTOR ITL
R

A A Approved Submittals

A S Approved Submittals

Exisiting Service as found


W A drawing

A A Survey Report

A/W A/W

Inspection Reports and each


delivery
Inspection Reports and each
delivery
W W

A W A/R Inspection Reports


A W A /R FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SIGNED: SINGED:

NAME: NAME:

DATE: DATE:
Inspection and Test Plan for- water supply WORKS

REV:0 Engineer / Engineer Representative:

aboratory, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorpora

Frequency of Acceptance Criteria / Specification


Test or Tolerance Parameters Reference
Inspection

Approval from Engineer Specification


Before Work Representative Section

Approval from Engineer Specification


Representative Section

Prior to Start Every existing service has to


Work be correctly located and
protected

According to the
Drawings

SPECIFICATION &CODES
MIR(material
inspection
VISUAL request check
INSPECTION delivery) and safe
&adequate
protection
MIR(material
inspection
VISUAL request check
INSPECTION delivery) and safe
&adequate
AS SPECIFIED protection

project
DURING WORK Approval specifications specification
section
AFTER project
COMPLEET TO THE SHOP DRAWING specification
WORK section

ITP SIGN OFF-POST COMPLETION OF WORKS

RACTOR-if available CONTRACTOR

SIGNED:

NAME:

DATE:
Inspection a

ITP Reference Number / Serial No.: 006

. Co. Ltd.

Agreement No:

Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-Contractor, ITP

Inspection & Test Activity

Submit to the Enigeer

Verify the approval

Verify location and protection

Set out of the excavation area

THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED CONSULTANT OFFICE AND


MINISTRY OF HEALTH
INSPECTION REQUEST OF MATERIALS (PIPEING AND FITTING AND ACCESSORIES)

1.Open an approved drawing detail for sanitary fixtures . This drawing should be accompanied with
the approved location of mechanical pipe sleeves sanitary fixtures ventilation.
2.Installation of pipes should be done after the block work inside the toilet.
3.Locate the pipe locations in the wall and mark with the line corresponds to the total area to bury
the pipe in the wall.
4.Use block cutter or simply portable grinder to cut a side of block continuously along the line that
had been marked. Absolute care should be done not to cut or damaged the pre-installed pipe
sleeves of fixture pipes.
5.By using sharp- pointed steel rod and other proper chipping tools, chip the block side to the
thickness required to fix the water pipes.
6.Use approved pipes, pipe fittings, and joining compound.
pipes or fittings. Do not over tight the joints.
8.For pipes passing through the wall, install sleeves of size larger than the pipes serving it. Seal
annular space between sleeve and pipe using silicon sealant.
9. Install the pipes at designated height and location on the wall and on the floor.
10.Align the pipes horizontally and vertically without strain. Avoid pipe bending or sagging.
11- Pipes shall be installed by one of the following installation methods
A - For pipes that prove glue, the welding locations are cleaned well, then the welding is made and
the welding process is well
B - For pipes that prove that heat is achieved, the welding locations are thoroughly cleaned and the
welding machine is tested. The welding process is started.
13 - The valves are installed
14.Check the pipes securely and firmly fix on its location before leak testing.
15.Leak test the pipes and proved tight under a water pressure not less than 1½ its working
pressure under which it is to be used. Leak test the pipes for four (4) hours. Do not test the pipes
without the presence of inspection Engineer.
16.After the approval of inspection Engineer, cover
17- The network should be tested partly as well as after the completion of the total extensions of
the building being tested for the entire network
18 - Installation of all accessories as well as sanitary appliances and taps after the completion of the
finishing work for the area where there are sanitary devices
19. The feeding station shall be installed from tarmac, taps, pressure gauges as well as desalination
plant, and the necessary tests shall be carried out to ensure the operation efficiency of the plant
and to provide the required amount for operation of the project with appropriate pressure.
20 - The entire network is washed thoroughly to start operation
FINAL INSPECTION FOR ALL WORK APPROVAL FOR ALL LEVEL AFTER FINSH AND BEFOR
INSTALING SEELING

ITP SIGN OFF-POST COMPLETION OF W

SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 7-5-2017
Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General
Hospital ( 200 Bed )

Project No.: C0517

Project Loc. : ALDARB

Item No. Activity Description

1 Method Statement

1.1 Approval of Method Statement

2 Prior Activities

2.1 Approved Shop Drawing

2.2 Identification, location and protection

2.3 Survey + Execution

3 Main Activities

3.1

water supply WORKS


water supply WORKS

3.2

3.3 DRAINAGE WORK INSTALLATION


3.4 FINAL APPROVAL

REV. COMMENTS
0
R PipesWORKS

Inspection Points:H=Hold Point, W=Witness


Point, R=Review Point, S=Surveillance,
A=Approval
Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report
A/W A/W

Inspection Reports and each delivery

W W

A W A/R Inspection Reports


A W A FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for- HOOT WATER PipesWORKS

REV:0 Engineer / Engineer Representative:

, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorporated

Insp
Frequency of Test Acceptance Criteria / Tolerance Specification
or Inspection Parameters Reference
SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer Specification Section


Representative

Prior to Start Every existing service has to be


Work correctly located and protected

According to the Drawings


Approved Shop
Drawing&MATERIAL
MIR(material
inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK section

Delivery of all work steps


to the consultant according
to specifications and
approved drawings
project
AFTER COMPLEET
WORK specification
section

ITP SIGN OFF-POST COMPLETION OF WORKS

able CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ITP Reference Number / Serial No.: 009

Partners Contg. Co. Ltd.

Agreement No:

Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-C

Inspection & Test Activity

Submit to the Enigeer

Verify the approval

Verify location and protection

Set out of the excavation area


THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY OF HEALTH

INSPECTION REQUEST OF MATERIALS (PIPEING AND


FITTING AND ACCESSORIES)

1-Bremer Pipe Paint

2.-installation the draainageChilled water pipes


accordance with the approved and audited it and
then submit a request to receive a business
consultant to receive extensions and dimensions of
the scheme test

3-Pipe welding, pressure testing, pipe coating, primer,


piping insulation, delivery to consultants, and starting
of accessories

4-Installation of accessories and insulation of pipes

5- ‫ا‬Installation of control zone valves

6- Installation of sprinklers
7-Connecting to the fire pumps room

ITP SIGN O

SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 25-4-2017
Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General
Hospital ( 200 Bed )

Project No.: C0517

Project Loc. : ALDARB

Item No. Activity Description

1 Method Statement

1.1 Approval of Method Statement

2 Prior Activities

2.1 Approved Shop Drawing

2.2
Identification, location and
protection

2.3 Survey + Execution

3 Main Activities
Pipe welding and pressure
3.1 testing of pipes After welding
and pressure testing, the
welding locations are painted
and delivered to the
3.2 consultant to start processing
the installation of accessories
WORKS

3.3

HOOT WATER PipesWORKS


3.4 FINAL APPROVAL

REV. COMMENTS
0
WORKS

Inspection Points:H=Hold Point, W=Witness


Point, R=Review Point, S=Surveillance,
A=Approval
Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report
A/W A/W

Inspection Reports and each delivery

W W

A W A/R Inspection Reports


A W A FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for- duct WORKS

REV:0 Engineer / Engineer Representative:

, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorporated

Insp
Frequency of Test Acceptance Criteria / Tolerance Specification
or Inspection Parameters Reference
SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer


Representative Specification Section

Prior to Start Every existing service has to be


Work correctly located and protected

According to the Drawings


Approved Shop
Drawing&MATERIAL
MIR(material
inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK section

Delivery of all work steps


to the consultant according
to specifications and
approved drawings
project
AFTER COMPLEET
WORK specification
section

ITP SIGN OFF-POST COMPLETION OF WORKS

able CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ITP Reference Number / Serial No.: 005

Partners Contg. Co. Ltd.

Agreement No:

Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-C

Inspection & Test Activity

Submit to the Enigeer

Verify the approval

Verify location and protection

Set out of the excavation area


THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY OF HEALTH

INSPECTION REQUEST OF MATERIALS (PIPEING AND


FITTING AND ACCESSORIES)

1.-installation the draainage duct accordance with


the approved and audited it and then submit a
request to receive a business consultant to receive
extensions and dimensions of the scheme

2-after approved the request received a business


extensions and dimensions are to start lines and
Althbyt on concrete pillars and then test the duct
lines to make sure no leaks and the success of the test

3-Request to receive a acts are testing the waters and


the tendencies of the Consultant work

4-After completion of the work of the air ducts and


delivery to the consultant, the equipment is ready to
start the silicon
5- After the completion of the silicon air delivered to
the consultant, the processing is done to start the
smoke test

6-After the completion of the smoke test and delivery


to the consultant, the work of insulation of the air
ducts and the installation of airway exits is started

7-FINAL INSPECTION FOR ALL WORK APPROVAL The


units are connected

ITP SIGN O

SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 25-4-2017
Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General
Hospital ( 200 Bed )

Project No.: C0517

Project Loc. : ALDARB

Item No. Activity Description

1 Method Statement

1.1 Approval of Method Statement


2 Prior Activities

2.1 Approved Shop Drawing

2.2
Identification, location and
protection

2.3 Survey + Execution

3 Main Activities
3.1

duct WORKS
3.2

3.3 duct WORK INSTALLATION


3.4 FINAL APPROVAL

REV. COMMENTS
0
es WORKS

Inspection Points:H=Hold Point, W=Witness


Point, R=Review Point, S=Surveillance,
A=Approval
Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report
A/W A/W

Inspection Reports and each delivery

W W

A W A/R Inspection Reports


A W A FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for- Fire pipes WORKS

REV:0 Engineer / Engineer Representative:

, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorporated

Insp
Frequency of Test Acceptance Criteria / Tolerance Specification
or Inspection Parameters Reference
SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer Specification Section


Representative

Prior to Start Every existing service has to be


Work correctly located and protected

According to the Drawings


Approved Shop
Drawing&MATERIAL
MIR(material
inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK section

Delivery of all work steps


to the consultant according
to specifications and
approved drawings
project
AFTER COMPLEET
WORK specification
section

ITP SIGN OFF-POST COMPLETION OF WORKS

able CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ITP Reference Number / Serial No.: 007

Partners Contg. Co. Ltd.

Agreement No:

Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-C

Inspection & Test Activity

Submit to the Enigeer

Verify the approval

Verify location and protection

Set out of the excavation area


THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY OF HEALTH

INSPECTION REQUEST OF MATERIALS (PIPEING AND


FITTING AND ACCESSORIES)

1-Bremer Pipe Paint

2.-installation the draainageChilled water pipes


accordance with the approved and audited it and
then submit a request to receive a business
consultant to receive extensions and dimensions of
the scheme test

3-Pipe welding, pressure testing, pipe coating, primer,


piping insulation, delivery to consultants, and starting
of accessories

4-Installation of accessories and insulation of pipes

5- ‫ا‬Installation of control zone valves

6- Installation of sprinklers
7-Connecting to the fire pumps room

ITP SIGN O

SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 25-4-2017
Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General
Hospital ( 200 Bed )

Project No.: C0517

Project Loc. : ALDARB

Item No. Activity Description

1 Method Statement

1.1 Approval of Method Statement

2 Prior Activities

2.1 Approved Shop Drawing

2.2
Identification, location and
protection

2.3 Survey + Execution

3 Main Activities
Pipe welding and pressure
3.1 testing of pipes After welding
and pressure testing, the
welding locations are painted
and delivered to the
3.2 consultant to start processing
the installation of accessories
WORKS

3.3 Fire pipes


3.4 FINAL APPROVAL

REV. COMMENTS
0
pipes WORKS

Inspection Points:H=Hold Point, W=Witness


Point, R=Review Point, S=Surveillance,
A=Approval
Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report
A/W A/W

Inspection Reports and each delivery

W W

A W A/R Inspection Reports

A W A FINAL SITE INSPECTION

ITL, If applicable ENGINEER


SINGED:

NAME:

DATE:
Inspection and Test Plan for- Chilled water pipes WORKS

REV:0 Engineer / Engineer Representative:

, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorporated

Insp
Frequency of Test Acceptance Criteria / Tolerance Specification
or Inspection Parameters Reference
SUB-CON

Approval from Engineer


Before Work Representative Specification Section

Approval from Engineer Specification Section


Representative

Prior to Start Every existing service has to be


Work correctly located and protected

According to the Drawings


Approved Shop
Drawing&MATERIAL
MIR(material
inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK section
Delivery of all work steps
to the consultant according
to specifications and
approved drawings

project
AFTER COMPLEET
WORK specification
section

ITP SIGN OFF-POST COMPLETION OF WORKS

able CONTRACTOR ITL, If applicabl


SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ITP Reference Number / Serial No.: 006

Partners Contg. Co. Ltd.

Agreement No:

Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-C

Inspection & Test Activity

Submit to the Enigeer

Verify the approval

Verify location and protection

Set out of the excavation area


THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY OF HEALTH

INSPECTION REQUEST OF MATERIALS (PIPEING AND


FITTING AND ACCESSORIES)

1-Bremer Pipe Paint

2.-installation the draainageChilled water pipes


accordance with the approved and audited it and
then submit a request to receive a business
consultant to receive extensions and dimensions of
the scheme test

3-Pipe welding and pressure testing of pipes After


welding and pressure testing, the welding locations
are painted and delivered to the consultant to start
processing the installation of accessories

4-Installation of accessories and insulation of pipes

5-FINAL INSPECTION FOR ALL WORK APPROVAL The


units are connected

ITP SIGN O

SUB-CONTRACTOR-if available
SIGNED:

NAME:

DATE:
Date of Issue: 25-4-2017
Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General
Hospital ( 200 Bed )

Project No.: C0517

Project Loc. : ALDARB

Item No. Activity Description

1 Method Statement

1.1 Approval of Method Statement

2 Prior Activities

2.1 Approved Shop Drawing

2.2
Identification, location and
protection

2.3 Survey + Execution

3 Main Activities
Pipe welding and pressure
3.1 testing of pipes After welding
and pressure testing, the
welding locations are painted
and delivered to the
3.2 consultant to start processing
the installation of accessories
WORKS

3.3 Chilled water pipes

3.4 FINAL APPROVAL

REV. COMMENTS
0
pesWORKS

Inspection Points:H=Hold Point, W=Witness


Point, R=Review Point, S=Surveillance,
A=Approval
Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report
A/W A/W

Inspection Reports and each delivery

W W

A W A/R Inspection Reports


A W A FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for- Steam PipesWORKS

REV:0 Engineer / Engineer Representative:

, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Comments Incorporated

Insp
Frequency of Test Acceptance Criteria / Tolerance Specification
or Inspection Parameters Reference
SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer Specification Section


Representative

Prior to Start Every existing service has to be


Work correctly located and protected

According to the Drawings


Approved Shop
Drawing&MATERIAL
MIR(material
inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK section

Delivery of all work steps


to the consultant according
to specifications and
approved drawings
project
AFTER COMPLEET
WORK specification
section

ITP SIGN OFF-POST COMPLETION OF WORKS

able CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ITP Reference Number / Serial No.: 008

Partners Contg. Co. Ltd.

Agreement No:

Legends: ITL=Independent Testing Laboratory, SUB-CON=Sub-C

Inspection & Test Activity

Submit to the Enigeer

Verify the approval

Verify location and protection

Set out of the excavation area


THE SUPPLY OF MATERIALS ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY OF HEALTH

INSPECTION REQUEST OF MATERIALS (PIPEING AND


FITTING AND ACCESSORIES)

1-Bremer Pipe Paint

2.-installation the draainageChilled water pipes


accordance with the approved and audited it and
then submit a request to receive a business
consultant to receive extensions and dimensions of
the scheme test

3-Pipe welding and pressure testing of pipes After


welding and pressure testing, the welding locations
are painted and delivered to the consultant to start
processing the installation of accessories

4-Installation of accessories and insulation of pipes

5- ‫ا‬Installation of control zone valves

6- Installation of sprinklers
7-Connecting to the fire pumps room

ITP SIGN O

SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 25-4-2017
Contractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General
Hospital ( 200 Bed )

Project No.: C0517

Project Loc. : ALDARB

Item No. Activity Description

1 Method Statement

1.1 Approval of Method Statement

2 Prior Activities

2.1 Approved Shop Drawing

2.2
Identification, location and
protection

2.3 Survey + Execution

3 Main Activities
Pipe welding and pressure
3.1 testing of pipes After welding
and pressure testing, the
welding locations are painted
and delivered to the
3.2 consultant to start processing
the installation of accessories
WORKS

3.3

Steam Pipes
3.4 FINAL APPROVAL

REV. COMMENTS
0
- MIDECAL GAS WORKS

Inspection Points:H=Hold Point,


W=Witness Point, R=Review Point,
S=Surveillance, A=Approval
nd Test Plan, CI=Comments Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report

A/W A/W
Inspection Reports and each
delivery
W W

A W A/R Inspection Reports


A W A/R Inspection Reports

A W A /R FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for- MIDECAL GAS WOR
Serial No.: 006

REV:0 Engineer / Engineer Representative:

dent Testing Laboratory, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Commen

Frequency of Test or Acceptance Criteria / Tolerance Specification Insp


Inspection Parameters Reference SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer Specification Section


Representative

Prior to Start Work Every existing service has to be


correctly located and protected

According to the Drawings

SPECIFICATION &CODES MIR(material


inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK Approval specifications section
project specification
DURING WORK Approval specifications section

AFTER COMPLEET project specification


TO THE SHOP DRAWING
WORK section

ITP SIGN OFF-POST COMPLETION OF WORKS


ACTOR-if available CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ate of Issue: 11-12-2014 ITP Reference Number / Serial No.: 006
ntractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General Agreement No:
Hospital ( 200 Bed )
Project No.: C0517 Legends: ITL=Independent Testing Lab
Project Loc. : ALDARB
Activity Description Inspection & Test Activity

Method Statement

Approval of Method Statement Submit to the Enigeer

Prior Activities

Approved Shop Drawing Verify the approval

Identification, location and protection Verify location and protection

Survey + Execution Set out of the excavation area


Main Activities
THE SUPPLY OF MATERIALS
ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY
MIDECAL GAS WORKS OF HEALTH

INSPECTION REQUEST OF MATERIALS


(PIPEING AND FITTING AND
ACCESSORIES)

1.-installation the MIDECAL GAS pipe


accordance with the approved and
audited it and then submit a request to
receive a business consultant to
receive extensions and dimensions of
the drowing

MIDECAL GAS INSTALLATION


2-after approved the request
received a business extensions and
MIDECAL GAS INSTALLATION dimensions are to start work for
testing lines by aire and nitrogen
24 hour to make sure no leaks and
the success of the test(TEST
PRESSURE =1.5 OF NET WORK
PESSURE )

3-Request to receive a acts are testing


the aire and nitrogen of the
Consultant work

FINAL INSPECTION FOR ALL WORK


FINAL APPROVAL APPROVAL FOR ALL LEVEL AFTER FINSH
AND BEFOR INSTALING SEELING

COMMENTS SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 11-12-2014
Contractor: A.S. Al-Sayed & Pa

Item No.

1.1

2.1

2.2

2.3
3

3.1

3.2

3.3
3.3

3.4

REV.
0
quid petroleum gas WORKS

Inspection Points:H=Hold Point,


W=Witness Point, R=Review Point,
S=Surveillance, A=Approval
nd Test Plan, CI=Comments Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report

A/W A/W
Inspection Reports and each
delivery
W W

A W A/R Inspection Reports


A W A/R Inspection Reports

A W A /R FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for- Liquid petroleum gas W
Serial No.: 006

REV:0 Engineer / Engineer Representative:

dent Testing Laboratory, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Commen

Frequency of Test or Acceptance Criteria / Tolerance Specification Insp


Inspection Parameters Reference SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer Specification Section


Representative

Prior to Start Work Every existing service has to be


correctly located and protected

According to the Drawings

SPECIFICATION &CODES MIR(material


inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK Approval specifications section
project specification
DURING WORK Approval specifications section

AFTER COMPLEET project specification


TO THE SHOP DRAWING
WORK section

ITP SIGN OFF-POST COMPLETION OF WORKS


ACTOR-if available CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ate of Issue: 11-12-2014 ITP Reference Number / Serial No.: 006
ntractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General Agreement No:
Hospital ( 200 Bed )
Project No.: C0517 Legends: ITL=Independent Testing Lab
Project Loc. : ALDARB
Activity Description Inspection & Test Activity

Method Statement

Approval of Method Statement Submit to the Enigeer

Prior Activities

Approved Shop Drawing Verify the approval

Identification, location and protection Verify location and protection

Survey + Execution Set out of the excavation area


Main Activities
THE SUPPLY OF MATERIALS
ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY
OF HEALTH
Liquid petroleum gas work
INSPECTION REQUEST OF MATERIALS
(PIPEING AND FITTING AND
ACCESSORIES)

1.-installation the LPG pipe


accordance with the approved and
audited it and then submit a request to
receive a business consultant to
receive extensions and dimensions of
the drowing

Liquid petroleum gas INSTALLATION


2-after approved the request
received a business extensions and
Liquid petroleum gas INSTALLATION
dimensions are to start work for
testing lines by WATER 24 hour
to make sure no leaks and the
success of the test(TEST PRESSURE
=1.5 OF NET WORK PESSURE )

3-Request to receive a acts are testing


the aireWATER of the Consultant work

FINAL INSPECTION FOR ALL WORK


FINAL APPROVAL APPROVAL FOR ALL LEVEL AFTER FINSH
AND BEFOR INSTALING SEELING

COMMENTS SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 11-12-2014
Contractor: A.S. Al-Sayed & Pa

Item No.

1.1

2.1

2.2

2.3
3

3.1

3.2

3.3
3.3

3.4

REV.
0
an for fuel WORKS

Inspection Points:H=Hold Point,


W=Witness Point, R=Review Point,
S=Surveillance, A=Approval
nd Test Plan, CI=Comments Incorporated

Inspection Points
Verifying Document / Report
CONTRACTOR ITL ENGINEER

A A Approved Submittals

A S Approved Submittals

W A Exisiting Service as found drawing

A A Survey Report

A/W A/W
Inspection Reports and each
delivery
W W

A W A/R Inspection Reports


A W A/R Inspection Reports

A W A /R FINAL SITE INSPECTION

ITL, If applicable ENGINEER

SINGED:

NAME:

DATE:
Inspection and Test Plan for fuel WORKS
Serial No.: 006

REV:0 Engineer / Engineer Representative:

dent Testing Laboratory, SUB-CON=Sub-Contractor, ITP= Inspection and Test Plan, CI=Commen

Frequency of Test or Acceptance Criteria / Tolerance Specification Insp


Inspection Parameters Reference SUB-CON

Approval from Engineer


Before Work Specification Section
Representative

Approval from Engineer Specification Section


Representative

Prior to Start Work Every existing service has to be


correctly located and protected

According to the Drawings

SPECIFICATION &CODES MIR(material


inspection request
VISUAL INSPECTION check delivery) and
safe &adequate
AS SPECIFIED protection

project specification
DURING WORK Approval specifications section
project specification
DURING WORK Approval specifications section

AFTER COMPLEET project specification


TO THE SHOP DRAWING
WORK section

ITP SIGN OFF-POST COMPLETION OF WORKS


ACTOR-if available CONTRACTOR ITL, If applicabl

SIGNED: SIGNED:

NAME: NAME:

DATE: DATE:
ate of Issue: 11-12-2014 ITP Reference Number / Serial No.: 006
ntractor: A.S. Al-Sayed & Partners Contg. Co. Ltd.
Project Name: ALDARB General Agreement No:
Hospital ( 200 Bed )
Project No.: C0517 Legends: ITL=Independent Testing Lab
Project Loc. : ALDARB
Activity Description Inspection & Test Activity

Method Statement

Approval of Method Statement Submit to the Enigeer

Prior Activities

Approved Shop Drawing Verify the approval

Identification, location and protection Verify location and protection

Survey + Execution Set out of the excavation area


Main Activities
THE SUPPLY OF MATERIALS
ACCORDING TO THE CERFIED
CONSULTANT OFFICE AND MINISTRY
fuel work OF HEALTH

INSPECTION REQUEST OF MATERIALS


(PIPEING AND FITTING AND
ACCESSORIES)

1.-installation the fuel pipe


accordance with the approved and
audited it and then submit a request to
receive a business consultant to
receive extensions and dimensions of
the drowing

fuel INSTALLATION
2-after approved the request
received a business extensions and
fuel INSTALLATION
dimensions are to start work for
testing lines by WATER 24 hour
to make sure no leaks and the
success of the test(TEST PRESSURE
=1.5 OF NET WORK PESSURE )

3-Request to receive a acts are testing


the aireWATER of the Consultant work

FINAL INSPECTION FOR ALL WORK


FINAL APPROVAL APPROVAL FOR ALL LEVEL AFTER FINSH
AND BEFOR INSTALING SEELING

COMMENTS SUB-CONTRACTOR-if available

SIGNED:

NAME:

DATE:
Date of Issue: 11-12-2014
Contractor: A.S. Al-Sayed & Pa

Item No.

1.1

2.1

2.2

2.3
3

3.1

3.2

3.3
3.3

3.4

REV.
0

Potrebbero piacerti anche