PROJECT: 23 Chin Bee Avenue

RE: Site Setup & Preliminary Work + Demolition Work + Tree Cutting Work
Date: 06/09/2019

S/No Task Activity Unit Rate Amount Remark


1 Install Heavy Duty Netting
1.1 Elevation 1 @ GL: 1-10/F* 116.765m $ 11,000.00
1.1.1 6m GI-Pipe secure with all existing fence pole Quote Optional
1.1.2 Install 2layer Heavy Duty Netting (Top Portion only) Quote Optional
1.2 Elevation 2 @ GL: 10/A*-F* 65.070m $ 5,000.00
1.2.1 Install 1layer Heavy Duty Netting (Cover extg fencing)
1.3 Elevation 3 @ GL: 1-10*/A* 96.11m
1.3.1 Install 1layer Heavy Duty Netting (Cover extg fencing)
1.4 Elevation 4 @ GL: 1*/A*-F* 59.726m
1.4.1 Install 1layer Heavy Duty Netting (Cover extg fencing)
1.5 3.6mH Hoarding @ Elevation 1 (install used metal sheets) 116.765m $ 8,000.00
1.6 1.8mH Hoarding @ Elevation 2,3 & 4 (install used metal sheets) 220.906m $ 8,000.00

Water Pit will share


2 Setup Vehicle Washing Bay
with ECM Holding Tank
2.1 The Steel Vehicle Bay size: 2m (W) X 5m (L) X 260mm (H) = 2unit By Figtree
2.1.1 The vehicle washing bay clear sump pit = 3.5m (W) X 4m (L) X 1.5m (Depth) 1 lot $ 10,000.00 Select Option A
2.1.2 Sump Pit size: 1.5m X 1.5m X 1.2 and enclose with G.I Pipe barricade 1 lot $ 1,000.00

3 Setup ECM incl Filtration Tank, Holding Pond, Chemicals & CCTV (4months)
Using Old Container 2.4m (W) X 6m (L) X 2.4m (H), act as Holding Tank & create
separate wall, include weld 6nos for hooking + top portion add SHS/ or I beam
3.1 1 lot $ 12,000.00
support allow for ECM Filtration Tank sitting + The opening must close up secure with
Walking Platform + G.I Pipe Barricade & using short G.I pipe act as Door Access
Brick wall setup sump pit size: 1m (W) X 4.5m (L) X 1.2m (H), with 3 compactment for
3.2 1 lot $ 3,000.00
final discharge point. (Built at platform surface)
3.3 Excavace pit & surface laid concrete 3m (W) X 10m (L) 1 lot $ 3,000.00

Lightning tape/ earth


4 100mm thk pour concrete + Leveling + Roof Covering 1 lot $ 10,000.00
pit by others
4.1 Scurity Guard House (2.5m X 6m) Container by other
4.2 Site Office (2.5m X 6m) Container by other
4.3 RE + RTO Office (2.5m X 6m) Container by other
4.4 Meeting Room (2.5m X 6m) Container by other
4.5 Container by other
Staff (M/F) Container Toilet include timber staircase with railing around 1m (H)
Worker Container Toilet (2.5m X 6m) include timber staircase with railing around 1m Container by other and
4.6
(H) select option A
4.7 Generator Room (2.5m X 4m)
4.8 Concrete Cube Room (2.5m X 3m)
4.9 Worker Rest Area (2.5m X 20m)
4.10 2m (W) X 31m (L) Corridor access

250mm thk pour concrete + leveling near to Gate 1 Entrance


4A 1 lot $ 15,000.00
(Yellow Highlighted)

Neighbour
Hen-Tick M&E water
5 Dismantle the boundary wall (going to collapse) @ Elevation 1 @ GL: 10*/F*
main in-coming & Fire
Hydrant Pipe
5.1 install metal hoarding with removable pole 2.4m (H) X 15m (L) 1 lot $ 1,500.00

6 The extg entrance gate to make Good & Cover Existing Metal Cladding Sheet 1 lot $ 1,000.00
6.1 Extg Entrance Gate 1 size: 5970mm (L) X 2.4m (H)
6.2 Extg Entrance Gate 2 size: 7600mm (L) X 2.4m (H) Extg gate will omit
Extg gate will be omit/
6.3 Extg Entrance Gate 3 size: 5860mm (L) X 2.4m (H)
relocate

7 Construction temporary drainage


Elevation 1 & 4 - Construct concrete lining drain with silt fence and sump connect to
7.1 LS $ 5,000.00
ECM holding pond
Elevation 2 & 3 - Construct C7 drain with silt fence and sump connect to ECM holding
7.2 LS $ 10,000.00
pond (including pipe along driveway)

8 Create Hardcore for Construction Access LS $ 2,000.00

9 Demolition Work
9.1 Phtysical Demolition works including foundation LS $ 47,000.00
9.2 RTO services LS $ 3,000.00

10 Tree Cutting include removing of tree roots (32nos) LS $ 4,800.00

Total $ 160,300.00