Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
BENGALURU
1. Introduction
The 43rd meeting of Protection Coordination Sub-Committee (PCSC) was held on 29th April,
2015 in the Conference Hall of Southern Regional Power Committee, Bangalore. The list of
participants is enclosed at Annexure-I.
Shri S.R.Bhat, Member Secretary (MS), SRPC welcomed the Members and Participants to the
meeting and briefed them on the following points:
Multiple trippings at Raichur during March-April, 2015 caused a wide spread impact on
the NEWS grid and made the grid vulnerable. In order to study the cause of the
trippings, a Protection System Analysis Group (PSAG-13) Meeting was conducted at
Raichur and had given necessary recommendations. PCSC forum appreciated the
cooperation extended by the PSAG members in sorting out of the Protection issues in
that corridor.
With reference to the Item No.7 (ii) of the Minutes of the meeting held on 02.03.2015 in
CEA, New Delhi for implementation of 24x7 power supply in the state of Goa, a team of
Officials from CEA, New Delhi and SRPC forum visited 5 substations on 9.4.2015 and
10.4.2015 in Karnataka and Goa in the context of improving the reliability of supply to
Goa. The Minutes of the Meeting are enclosed at Annexure-II.
Non-furnishing of remedial measures/ action taken for the tripping incidents, the number
has increased above 100. He requested the Constituents to provide the measures/ action
taken to SRPC at the earliest.
On 22nd April 2015, there was a Grid disturbance in Kerala, which resulted in black out
in northern and Central Kerala. The reason for the power interruption in Kerala is to be
analysed and need to avoid the re-occurrence of such situation.
Some of the Special protection Scheme (SPS) would be discussed in the meeting:
o SPS for Raichur TPS for the generation evacuation.
An SPS is being proposed to relieve the stress on evacuation lines of RTPS
complex during cascade line trippings.
o Modification of Kudankulam SPS signal with the commissioning of two units.
As Unit-II was likely to be synchronized shortly, Constituents were
requested to identify the additional loads for Trip-Signal-2.
Minutes of the 43rd PCSC Meeting held on 29-04-2015 Page 1
o Modification of SEPL/MEPL SPS signal.
MEPL presented their concern regarding the tripping of their unit during the
month of April, 2015 on the receipt of Special Protection Scheme (SPS) signal
from PGCIL Nellore Pooling Station (NPS). On analysis, it was found that unit
trip happened due to some malfunctioning of PLCC at PGCIL-NPS end.
Considering the requirement of SPS, MEPL requested to review the existing
SPS.
22. Confirmation of the Minutes of the 42nd PCSC meeting held on 26-03-2015
SE (Protection), SRPC stated that the Minutes of the 42nd meeting of the PCSC had been
circulated vide SRPC letter No. SRPC/SE-III/ PCSC·42/ 2015/ 2559 – 590 dated 17.04.2015.
However, as it was noticed that an error had occurred in the deliberations relating to the grid
incidence on Tripping of Unit-3 & 5 at Jindal Power Station given at Sl. No. II (16) of the
Annexure-II to the Minutes, the deliberations given by JSWEL
“The two 400/ 220 kV ICT tripped on back-up protection with a time delay of 900 msec.”
“The two 400/ 220 kV ICT did not trip on back-up protection.”
With this, the Minutes of the 42nd meeting of the PCSC were confirmed.
3. Details of Grid Disturbances (GD’s), Grid Incidents (GI’s), Line Trippings due to PLCC
mal- operation, Auto-Reclose non-operation
The trippings due to GD’s, GI’s, PLCC mal-operation and Auto–Reclosure failure/non-
operation that had occurred during the period March - April, 2015 were discussed in the
Meeting. The deliberations and recommendations of the PCSC-forum are enclosed at
Annexure–III.
5. Remedial measures/ Action taken for the tripping incidents of the transmission elements
under forced outage
The tripping incidents of the transmission elements under forced outage for which the remedial
measures/ actions taken still awaited were discussed in the Meeting. The Constituents have
been requested to kindly furnish the remedial measures/ action taken in time so as to forward
the same to Central Electricity Authority. The updated list of the same as on 18.05.2015 is
enclosed at Annexure-V.
Minutes of the 43rd PCSC Meeting held on 29-04-2015 Page 2
6. Certificate for Healthiness of Batteries
As per the MoP/ CEA direction given in pursuant to recommendations of the Enquiry
Committee (NEW grid disturbance on 30th & 31st July, 2012), RPC’s are required to obtain
from their respective Constituents the monthly certificate for healthiness of batteries, installed
at 220 KV and above voltage level Substations (for power supply to Relays, RTUs and PLCC
equipment) and furnish the same to CEA/ MoP.
With reference to above, the Constituents have been requested to submit the certificate on
healthiness of batteries on monthly basis (i.e. status for a month may be sent by the 7th day
of the succeeding month) to SRPC.
The Constituents have been requested to furnish station-wise status as per the format given
below:
Sl. Station Application Battery Battery Charger Remarks
No.
Station Code Type Protection/ Details Status Details Status
Name (Healthy/ (Healthy/
(PS/ SS) Communication Unhealthy) Unhealthy)
1 Station-A Protection (Bank-1)
Protection (Bank-2)
Communication
(Bank-1)
Communication
(Bank-2)
2 Station-B …
PSAG-13 was held on 22nd and 23rd April, 2015 at Raichur to analyze the cause of multiple
trippings that occurred at Raichur (PG) and RTPS on 09-03-2015 and 11-04-2015. Minutes
of the PSAG-13 meeting are enclosed at Annexure-VI.
All Constituents are directed to implement the revised settings of Over-voltage Grading of the
existing and newly commissioned 400kV and 765kV lines in Southern Region. The details of
the settings had been uploaded on SRPC website under “All Uploads Protection Voltage
grading” menu icon.
9.1 Kudankulam SPS (load relief by the constituents) with 2 Units in Operation
A meeting was held with NPCIL/ KKNPP on 07.04.2015 at SRPC, Bengaluru to discuss the
operational and accounting issues in respect of KKNPP Units. In the meeting, the following
issues with respect to Kudankulam SPS were noted:
It was noted that the SPS for two units in operation needed to be configured at KKNPP.
Constituents were to identify additional loads of 848 MW for Trip Signal-2. As per
NLDC new feeders are to be identified by the SR-Constituents for the above quantum of
load shedding.
On analysis, MEPL found that there was no tripping of either NPS-Almathy or NPS-
Sriperumbudur 400 kV lines during the instant case, but SPS signal was received from
NPS (confirmed by Rx counter increment of PLCC at MEPL’s end) tripping their
Unit#2, which points to some malfunctioning of PLCC at PGCIL-NPS end.
Deliberations:
It could be disabled but wiring and other equipment are not to be removed as it has to
be put in use in case of requirement.
Recommendations:
PCSC forum recommended MEPL/SEPL to select the switch to OFF condition and
disable SPS so that the spurious tripping of element can be avoided.
Deliberations:
KPTCL:
The issue would be discussed with SCADA division, and would revert with further
On 22nd April 2015, 400kV Udumalpet-Palakkad D/C lines tripped which led to the Central
and North Kerala blackout condition. Hence, an SPS has been proposed to prevent partial
blackouts in Kerala. The designed SPS logic is as follows:
Recommendations:
PCSC forum requested KSEB to identify the loads to be shed for this SPS logic.
All SLDCs have been requested to direct the embedded IPPs connected at 220 kV and above
voltage level to submit completed dynamic study format to SRPC, Secretariat. Constituents
have been requested to submit the Dynamic study data at the earliest.
As per the information furnished by SR-Constituents to the OCC forum in their 106th
Meeting held on 10.04.2015 (Minutes circulated on 27.04.2015) and the data from Monthly
Progress Report, it is observed that some network configuration changes (additions/
deletions/ modifications of transmission elements) took place in southern grid during the
month of March, 2015.
63MVAR Line reactors of Vijayawada-Nellore lines were commissioned on
14.03.2015 by PGCIL at Vijayawada SS.
12.1 Petition No. 146/MP/2013 with I.A. 36/2013: Order dated 20.02.2014
Compliance of Regulations 5.2 (r) of the Grid Code: Issue regarding non-
furnishing of FIR / Trip Analysis Report, EL, DR, etc. was also
highlighted. It is pointed out that the above reports are to be submitted /
uploaded on SRLDC web application within 24 hours as mandated under
IEGC / CEA Regulations.
Implementation of Phase-I and Phase-II of Protection Audit
Recommendations: All the constituents are requested to submit the updated
status of the compliance (those who have not completed recommendations
mentioned in the Phase I and Phase II) to SRPC Secretariat at the earliest.
Compliance of Regulations 5.2 (e) & 5.2 (l) of the Grid Code and Regulation
3(1)(e) of CEA Grid Standards: The constituents are requested to strictly
comply with these provisions by ensuring standard protections systems having
the reliability, selectivity, speed and sensitivity to isolate the faulty equipment
and protect all components from any type of faults, within the specified fault
clearance time and providing protection coordination
Ensuring proper maintenance of transmission lines and adopting best O&M
practices: The constituents are requested to conduct line patrolling regularly
as per the SRPC transmission line patrolling guidelines (available under the
menu item "All Uploads Operation Miscellaneous Transmission Line
Patrolling Protocol / Guidelines for Southern Region" on SRPC website).
(http://www.srpc.kar.nic.in/website/2014/operation/patrolling.pdf).
12.2 Petition No. 167/Suo- Motu/2012: Order dated 22.02.2014
The Constituents are requested to follow approved protection philosophy
ISTS licensees are requested to submit details of updated distance protection relay
setting of all inter-regional lines to POSOCO & RPCs.
All SLDCs are requested to install/activate sound recording system in their control
rooms within three months from the date of issue of this order.
The Constituents are requested to submit the progress of implementation to
SRPC and SRLDC as specified in the Hon'ble CERC Order.
12.3 Petition No. 263/MP/2012: Order dated 19.12.2013
Constituents are requested to implement the quantum of relief by AUFR and df/dt
relays by identifying additional feeders and keep them functional within one month
of issuing this order.
SLDCs are also requested to map these relays on their respective SCADA
system within three months of issuance of this order.
The Constituents are requested to submit the progress of implementation to
SRPC and SRLDC as specified in the Hon'ble CERC Order.
12.4 Petition No. 374/MP/2014: Date of hearing 15.01.2015
1
ANNEXURE-I
2
ANNEXURE-I
3
ANNEXURE-I
4
ANNEXURE-I
5
ANNEXURE-II
~Hftzr~~
--
t:t\'tr ~
29 t<t ~ ~ <'t5"
lil ff: "'( Q, ~Ql/lnd ..
t ",", SHE D POST
--
eo sect .2006
- vaboo.«>m " ' - (l:OIO. 1: 261M6
T.
I. CblcfEnglllCu (SP&.P."'). ('EA. Ddhi 'ello
~. Executive Di=tor. SRLOC. POSOCO. Bcngaluru
3. b«;uu\ c Director. PGCIL (SRTS-III. Bellgaluru •
4. ClucfEnginceqRT). KPTC L. Bengaluru
S. E.\!XIIII" EnginttT (EII\'). Pam j, &: OSD (0 Hon'ble ~linisl~'T of Power
!'out>: Report 0 11 Ib e fie ld , hits IInd e n .....n to ........rtain Ih .. problem. io rbe tr a o>lni..ion
lin ... f...-diol: Goa from I..:arna 'akaln ~"u lhcrn R<'J:ion - T<1l.
Ih f : I. .\ , i nult. of t be m~l inll hdd on 112.0 .1.20 15 in C LA. .....,. Del hi for in'pltm rnr. ' ion
of 2.h 7 po,. .., .uppJ ~ in Ibe ~l • •f uf GQa. Enclosed at Annexure-VII.
2. SRPC Icltcr '0. SRPC/Me·lllt S P.\l i201512129- 21.'4 d at ed 1Ib.U4.2015
Sir.
[0 pursuanl (0 Item :-':0, 7 (il) of the mmutes cited und~'J R"fl'TCOCc- l, ... ('omm ;""",
rompri.i~ the Officials from (' EA. SRPC, SRl lX', I'GCll (SRTS-III, KPT(' l and !'1<'Cmeil)'
[)qwtmml of Goa (GEDJ ,-iSlled three stallOns in Kamataka (Ambc\o.adl 220 110 and Arumod
110, II k\' ""bstalions, Supa ~encnlin, stallonl and [\100 substations in Goa \Xeldcm S Sand .
Ponda S 51 dunng 1M pocriod 9_10 Apnl, 20lS 10 a."'~rtaln 1M problelll.lO lfl 1M UllllWtllssion lines
feedin, Goa from Kamataka In Soulbem Rew;ion and ro ~"plo ... 1M possibilll)' of handing o'er
l~ hncs ro PGClL for 0 &\ 1 ptUpOSC The findIng' of 1M ('OlJllIlll"'" arc enclosed for f\Ir1her
needfullktlOfl_
,L
During the course of field visits to various stations (Ambewadi S/S, Supa HPS, Anamod S/s,
Xeldem S/S, and Ponda S/s), the Committee held meetings and interacted thoroughly with the
personnel of the respective stations. The list of participants is given at Annexure-I. The findings
of the Committee are detailed in the subsequent paragraphs.
I. Status and observations of the transmission lines and substations
Goa is connected to Karnataka through Ambewadi - Ponda 220 kV D/C line and Supa – Ponda
110 kV D/C line. The present status of these lines and substations are as follows:
a) Transmission Lines
220 kV lines:
(i) Ambewadi – Ponda line -1 designated as AP-1 has been LILOed at Xeldem 220/110
kV substation in Goa. i.e., Ambewadi – Ponda line-1 has been reconfigured as Ambewadi-
Xeldem 220 kV S/C line (AP-1) and Xeldem – Ponda 220 kV S/C line ( PXR line). At
present, 100 MW share of Goa in Ramagundam STPS is wheeled through this Ambewadi-
Xeldem 220 kV S/C line only (AP-1).
(ii) Ambewadi – Ponda line - 2 designated as AP-2 is kept idle-charged from Ambwadi
end and kept opened at Ponda end.
110 kV lines:
The installed capacity of Supa HEP is 100 MW (2X50 MW) and this plant is
operated as base load plant. The lines emanating from Supa HEP generation
switchyard are Supa- Ambewadi 110 kV D/C line and Supa-Ponda 110 kV D/C line.
Almost entire power generated from Supa HEP is evacuated through Supa-
Ambewadi 110 kV D/C line. The status of Supa-Ponda 110 kV D/C line is as given
below:
The route length of Supa-Ponda 110 kV D/C is about 76 km out of which 40 km
stretch of the line from Supa end is maintained by KPTCL and about 36 km stretch of
the line from Ponda end is maintained by Goa Electricity Department.
Goa Karnataka
Ponda Ambewadi
AP-2 220 kV
AP-1
Xeldem
110 kV 1
Ponda Supa
b) Substations
(i) Ambewadi Substation:
SLD & Protection aspects as per the protection audit format (SR) filled up by KPTCL
are enclosed at Annexure –II.
KPTCL informed that the following R&M works are in progress and will be
completed in one year:
Replacement of 2x55 by 2x100 MVA, 220/110 kV; One transformer has already
been replaced, and the other would be replaced within 3 months.
Strengthening of outdoor structures (tubular towers to be replaced by lattice
structures and all isolators (40 nos.: 5 nos./bay, 8 bays)
All existing CTs (220 kV & 110 kV) of lines & transformer bays and bus coupler
would be replaced.
Strengthening of earthing system by addition of 181 new CI pipes, earth flats and
raisers.
All existing C&R panels would be replaced by new C&R with Main-1, Main-2,
bus bar, LBB protections.
PLCC system would be made functional.
Split bus operation would be in place by 3 months.
Observations:
o R&M work was going on.
o AP-1 line: Wave Trap (WT) available.
o AP-2 line: WT available.
o A/R feature is not available.
o Switching Scheme: Double bus with bus coupler; but bus coupler is not in
service; at a time one bus is being used
a) KPTCL:
The lines availability maintained at present is as per the prevailing applicable standards;
O&M work of the line would be continued by KPTCL itself.
AP-1 & AP-2 (KPTCL portion):
For further improving the availability of the lines, KPTCL has already invited tenders
for procurement of D-Shackles, clamps, insulators, hardware, etc. and the order would
be placed within 60 days. Work would be completed in 70 LC days.
b) GED:
The lines are being maintained in healthy condition departmentally.
However, they have no objection in handing over the entire stretch of Ambewadi-Ponda
lines to PGCIL for O&M purpose.
AP-1 & AP-2 (Goa portion):
All the porcelain insulators have been replaced by polymer insulators; old hardware
was replaced by new hardware; re-jumpering work has already been completed by
GED.
c) PGCIL:
In case O&M work is to be taken up by POWERGRID, the following conditions have to
be fulfilled:
Tower schedule with number of locations data to be furnished.
Lines should be in healthy condition before taking up O&M by POWERGRID.
Fault location feature at both ends to be made functional.
Joint inspection of the lines is required for ascertaining the condition of the lines.
Approval of POWERGRID management is required before taking over O&M of the
lines.
Joint line inspection by KPTCL and GED has to be conducted to ascertain the quantum
of works to be undertaken for healthiness of the line.
Presently south Goa load is fed through Ambewadi-Xeldem 220 kV S/C line (AP-1) only. The
other line, namely, AP-2, is in charged condition from Karnataka but kept OPEN at Ponda
end. Therefore, in case of fault on AP-1 line, supply to south Goa from SR is lost and
restoration of the power supply is possible only after the fault on this is rectified.
a) Short term solution for improving the reliability of feed from SR to South Goa
To reduce the outage time in case of fault on AP-1 line, the committee proposes the
following solutions :
(ii) GED to take into service the Ambewadi-Ponda line-2 ( AP-2), which is idle
charged from Ambewadi end up to the Gantry point of Bus-II at Ponda;
Normally both Ponda 220 bus1 & 2 are operated with WR grid with MP-1, KP-1,
2x100 MVA & 1x50 MVA transformers on bus-1 and MP-2, TP-2, PXR, 1x100 MVA
transformer on bus-2. The existing set-up/ arrangement is enclosed at Annexure –VI.
220 kV Ponda bus-2 to be operated with AP-2 line, one 100 MVA transformer,
50 MVA transformer with SR grid (Karntaka supply).
220 kV Ponda bus-1 to be operated with MP-1, MP-2, KP-1, TP-2, two nos. of
100 MVA transformers and Ponda-Xeldem line with WR grid.
For effecting the above change, GED needs to put the 220 kV bus coupler bay into
service by providing the necessary bus isolators, CTs, control & relay panels, and one
number of bus isolator each to AP-2, Xeldom line bays. The inter-state metering
arrangement for AP-2 line also needs to be kept in healthy condition.
This arrangement is only a temporary measure and will be in place till the fault on
AP-1 line is cleared. After that, the normal existing set-up/ arrangement needs to be
restored.
For implementing the above temporary arrangement, GED needs to finalise the
switching sequence and bring it to the notice of / get it ratified by WRPC Operation
Coordination/ Protection Coordination Committee.
LILO of AP-2 line at Xeldem needs to be established by GED and this would require
construction of 220kV D/C line for a distance of about 18 km length from the LILO point
to Xeldem S/S. With this, Ambewadi-Ponda 220 kV D/C line would be reconfigured as:
Ambewadi- Xeldem 220 kV D/C line and Xeldem- Ponda 220 kV D/C line.
Joint line inspection by KPTCL and GED needs to be carried out, to ascertain the
quantum of works required to be undertaken in their respective jurisdiction, for
operationalization of the line.
At Ponda 110 kV switchyard, the dead end towers of Ponda –Supa 110 kV D/C line and
Ponda – Xeldem 110 kV D/C line (one direct ckt. and other ckt LILOed at Verna) are
adjacent to each other. Ponda – Xeldem 110 kV line is idle charged from Xeldem end.
With restoration of Supa- Ponda 110 kV line-1, it could be connected with Ponda –
Xeldem 110 kV line to form Supa- Xeldem 110 kV S/C line thus providing an additional
feed from Karnataka.
x-------------------x-----------------------x-----------------x
Annexure-I
List of Participants
CEA
1. Sh. Awdhesh Kumar Yadav, Director, SP&PA Division
SRPC
1. Sh. A. Balan, SE (Protection)
2. Sh. N.R.L.K. Prasad, EE (Protection)
SRLDC
1. Sh. K. Suresh Kumar, Sr. Engineer
PGCIL (SRTS-II)
1. Sh. B. Sridhar, Chief Manager
2. Sh. P. Nagaraju, Sr. Engineer
KPTCL
1. Sh. M.T. Manjunath, CE (SLDC)
2. Sh. Sadashiva, CE (RT and R&D)
3. Sh. K. Siddaraju, CE (Transmission zone, Bhagalkot)
4. Sh. J.S. Shivashankara Bhatta, SE (E) RT
5. Sh. Vinayak K. Hawaldar, SEE (I/c), W&M Circle, Hubli
6. Sh. B.V. Girish, EE (RT), Bengaluru
7. Sh. J. Ramakantha, EEE (SLDC)
8. Sh. S.S. Mithare, EE (E) RT Division, Hubli
GED
1. Sh. Ravi Ashrit, EE (EHV)
2. Sh. Manoj V. Mor, Engineer
Ambewadi S/s, KPTCL
1. Sh. Harish K. Nayak, EE (Elec.), Ta & SS Division
2. Sh. Md. Iqbal Kamagal, AEE (Elec)
3. Sh. Rajanikant L Hemani, AEE (Elec.)
4. Sh. S.H. Chandrashekhar, AEE (Elec.)
Supa S/S, KPCL
1. Sh. K .Santosh Kumar, SE (Elec.)
2. Sh. Alam Nawaaz Sheikh, AEE (Elec.)
3. Sh. Tirumala V. Naik, AE (Elec.)
Ponda S/S, GED
1. Sh. Sunil Kumar A. Kamalapurkar, AEE
Annexure-II (Ambewadi)
S F-6 BREAKER
ISOLATOR
CURRENT
TRANSFORMER
LIGHTNING
ARRESTER
EARTH ISOLATOR
220kV Bus-1
220kV Bus-2
100MVA 100MVA
220/110 220/110
kV Tfr.-1 kV Tfr.-2
F-10 F-9 F-8 F-7 F-6 F-5 F-4 F-3 F-2 F-1
Annexure-II (Ambewadi)
A. General Information:
220KV : 01.03.1992
1 Name of Sub-Station: 220/110KV R/s Ambewadi 2 Date of Commissioning:
110KV : 31.01.1988
1) Instrument Transformer
A Current transformer (C T)
Feeder Name: 220KV Narendra 1
a Date of Testing 3.03.2011
b CT ratio Test (R-Ph)
Core I Core II Core III Core IV Core V
i Ratio Adopted 800/1 800/1 800/1
i Ratio Adopted
ii Ratio measured
iii error calculated
Feeder Name: 220KV Xeldem
1 Location of PT Not available
a Date of Testing
b PT Ratio Test
i Ratio Adopted
ii Ratio measured
iii error calculated
Annexure-II (Ambewadi)
Time
Availability Availability Synchronizing Settings of
Synchronizing Date of Event Logger Synchro Check Relay
System (in service or (in service or Facility synchrocheck
system (GPS) Testing (Make & Model) (Make & Model)
not) not) available or not relay
(Make & Model)
% lockout
ii) 220 KV Feeders Not available No ---- Not available No Available EE, Type: SKD
v1-v2 87.5V
Annexure-II (Ambewadi)
Relay failed on :
3 220KV Narendra-1 Areva, P437 Not inservice
17.01.13
Relay failed on :
11 220KV Narendra-1 ABB, NSD50 In service 90-500kHz Available in Available in
17.01.13
No
Dist relay Dist relay
Relay failed on :
12 220KV Narendra-2 ABB, NSD50 In service 90-500kHz
17.01.13
E Transformer Protection
Rtd Vg:
198kV, Rtd Vg: 96
i 55 MVA - 1 EE, DTH32 EE, CAG EE, CDG Not available Working In service No 22.01.15 Dis.ct: 10KA, kV, Dis.ct:
Pr relief.ct: 10KA
40KA rms
Rtd Vg:
198kV, Rtd
Shifaqng ERL
ii 100 MVA - 2 ERL MIT161 ERL MBT191 Working In service No 22.01.15 Dis.ct: 10KA, Vg:96kV,
CSC-326 2TJM12
Pr relief.ct: Dis.ct: 10KA
40KA rms
F Reactor Protection
Annexure-II (Ambewadi)
Differential Back-up
REF Protection OTI/WTI
Name of the Protection Impedance Buchholz/ Any other Date of LA Rating HV
(Make & Indication
Reactor (Make & protection (Make PRD protection testing side
Model) working or not
Model) & Model)
i
Annexure-II (Ambewadi)
Rom
Xom
4 DC SUPPLY
Status of
No. of No. of
Breaker PIR(available Date of last Remarks (if
Feeder Bay Make & Model CB Rating Trip Close Healthiness
Available or or not) timing taken any)
coil Coil
not
Not taken
4 220KV Nagazari - 2 CGL,200-SFM-40A 245KV Available 2 1 Healthy No
Make
Available (Yes/No)
Not available
Verification
A. General Information:
1. Name of Sub-station: SUPA Power 2. Date of commissioning: 11.11.1985
House
3. Type of Bus Switching Scheme: Bus- Coupler 4. Whether SLD collected or Not:
1) Instrument Transformer
A Current transformer (C T)
a Date of Testing
b CT ratio Test
Core I Core II Core III Core IV Core V
i Ratio Adopted
ii Ratio measured
iii error calculated
iv Knee Point Voltage (KPV)
B Capacitive voltage transformer (C V T)
1 Location of CVT ODY
a Date of Testing 09.05.2013
b CVT ratio Test 110KV/110V
Page 1 of 8
Annexure-III (Supa)
AUDIT CHECK LIST
Core I Core II Core III
i Ratio Adopted
ii Ratio measured
iii error calculated
2 Location of CVT
a Date of Testing
b CVT ratio Test
Core I Core II Core III
i Ratio Adopted
ii Ratio measured
iii error calculated
i) Make and Model of Bus Bar relay AREVA and Micom P743/Micom P741
ii) Whether stability checks done or not Checks have been carried out
Page 2 of 8
Annexure-III (Supa)
AUDIT CHECK LIST
C) Sub-station protection and monitoring Equipments
Synchro
Time
Event Check
synchronizing Availability Availability Synchronizing Setting of
Date of Logger Relay
System system(GPS) (in service (in service Facility Available Synhrocheck
testing (Make & (Make
(Make & or not) or not) or not Relay
Model) and
Model)
Model)
i) All Voltage levels SERTEL In Service 17.09.2011 Computer In Service Auto Synchronizer ALSTOM
II) T-GPS-300 MX3EG1A
Transmission Line
D)
Protection-I
Availabi
Main-I Main-II Availabilit LBB lity
Availability
Protection Date of Protection y Date of Protection (in Date of
Name of Line (in service
(Make and testing (Make and (in service testing (Make and service testing
or not)
Model) Model) or not) Model) or not)
i) All Transmission lines AREVA In Service 12-08-2011 AREVA InService 12-08-2011 AREVA In 07-03-2012
Micom P442 Micom P442 Micom P743 Service
Page 3 of 8
Annexure-III (Supa)
AUDIT CHECK LIST
E) Transformer Protection
Back-up
Differential REF Over Over Flux OTI/WTI Any LA
LA
Protection Protection
Current Protection Indication Other Date of Rating
Name of ICT Buchholz/PRD Rating
(Make & (Make &
Protection (Make & working protectio testing HV
IV Side
Model) Model)
(Make & Model) or not n Side
Model)
i) All Transformers AREVA AREVA AREVA AREVA Working Working 28/08/2011
Micom P633 Micom P633 Micom P633 Micom P633
F) Reactor Protection
Name of Reactor Back-up
Differential REF OTI/WTI
Impedance
Protection Protection Indication Any Other LA Rating
Protection Buchholz/PRD Date of testing
(Make & (Make & working or protection HV Side
(Make &
Model) Model) not
Model)
i) All Reactors NA NA NA NA NA NA NA NA
3) Line Parameters
Line 1 Line 2 Line 3 Line 4 Line 5 Line 6
i) Name of Line Ambewadi -1 Ambewadi -2 Goa-1 Goa-2
ii) Line Length 15KM 15KM 35KM 35KM
Line Parameters
iii) ( In Ohms/Per KM/Per 1.914 1.916 4.554 4.554
Phase Primary value)
R1
X1
Ro
Xo
RoM
XoM
Page 4 of 8
Annexure-III (Supa)
AUDIT CHECK LIST
4) DC supply
220 /110 V DC-I 220 /110 V DC-II 48 V DC-I 48 V DC-II
Measured voltage (to be
a measured at furtherest 233 234
Panel
i) Positive to Earth 117 118 NA NA
ii) Negative to Earth 116 116
b No. of Cells Per Bank 110 108
Availability of Battery
c Yes Yes
Charger Yes/No Yes/No
Capacity Test result & date
d
of curative discharge test
5) Circuit Breaker
Status of No. of PIR
Date of Last Remarks (If
Make and Model CB Rating Breaker trip/close coil (Available
Timing taken any)
Available or Not & healthiness or Not)
The details of all the 110KV circuit breakers are attached as Annexure
i).
All 400 kV bays
ii) All 220 kV bays
ii) DG Set
Make Kirloskar
Rating & Year of manufacture 320 KVA & 11.09.2007
Whether Dg set on Auto or Auto and Manual
manual
Whether DG set is in service or
In Service
out of service
Page 6 of 8
Annexure-III (Supa)
AUDIT CHECK LIST
12)
Any Other Observation/ Comments
Signature
(Member 1) (Member 2) (Member 3) (Member 4)
(Name:
(Mobile No:
(Email ID:
(Fax No :
(Organization:
Page 7 of 8
Annexure-III (Supa)
AUDIT CHECK LIST
(Division
Page 8 of 8
Annexure-IV (Xeldem)
Annexure-IV (Xeldem)
AUDIT CHECK LIST
A. General Information:
1. Name of Sub-station: Xeldem 2. Date of commissioning: 17/03/1991
3. Type of Bus Switching Scheme: Isolators & 4. Whether SLD collected or Not: --
Breakers
1) Instrument Transformer
A Current transformer (C T)
220KV AP-I & 220KV AP-II
a Date of Testing
b CT ratio Test
Core I Core II Core III Core IV Core V
i Ratio Adopted 400/1A 400/1A 800/1A -- --
ii Ratio measured
iii error calculated
iv Knee Point Voltage (KPV)
B Capacitive voltage transformer (C V T) Not Connected
1 Location of CVT
a Date of Testing
b CVT ratio Test 220KV/110V
Core I Core II Core III
Page 1 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
i Ratio Adopted
ii Ratio measured
iii error calculated
2 Location of CVT
a Date of Testing
b CVT ratio Test
Core I Core II Core III
i Ratio Adopted
ii Ratio measured
iii error calculated
Page 2 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
C) Sub-station protection and monitoring Equipments
Time
Availability Event Logger Availability Synchronizing Synchro Check Setting of
synchronizing
System (in service or Date of testing (Make & (in service or Facility Available Relay (Make Synhrocheck
system(GPS)
not) Model) not) or not and Model) Relay
(Make & Model)
i) All Voltage levels N.A. No N.A. N.A. N.A. N.A. N.A. N.A.
II)
Page 3 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
Transmission Line Protection-II
Availability
Disturbance (in service or
PLCC/Protection Availability Wave Trap Details of
Date of Recorder(DR) not) Date of
Name of Line coupler (Make (in service or Frequency O/V
testing (Make and testing
and Model) not) Setting (Range) Protection
Model)
220KV AP - I NO NO NO NO NO -- NO --
220KV AP -II NO NO NO NO NO -- NO --
Page 4 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
E) Transformer Protection
OTI/WTI Any Date LA LA
Back-up Over Current Buchh
Differential Protection REF Protection Over Flux Protection Indication Other of Rating Ratin
Name of ICT Protection olz/PR
(Make & Model) (Make & Model) (Make & Model) working or protecti testin HV g IV
(Make & Model) D
not on g Side Side
WTI/M 10KA
OG/OTI/ 96KV
I)
ALSTOM ALSTOM Faulty overflux relay Surge 10KA
100MVA -I Ashida Numerical ADR – 133A CAG1AAF12A CDD41CF203ZYCH removed Working Yes arrestor 198KV
SIEMENS SIEMENS 7SR12062HA 10KA 10KA
II)
100MVA -II SIEMENS 7SR24222D-AGCAD 7SR12062HA 122 CAO 122 CAO ALSTOM CAG14AF12A Working Yes -do- 198KV 96KV
ALSTOM ALSTOM ALSTOM 10KA 10KA
III)
50MVA -I AREVA CAG1AAF12A CDD31PF021SYCH GTM22AF8003A64 Working Yes -do- 198KV 30KV
English Electric English Electric CDD English Electric GTT21AF 10KA 10KA
IV)
40MVA -I Ashida Numerical ADR – 133A CAG14F12 31PF90562Y (M) 8001A (M) Working Yes -do- 96KV 30KV
English Electric English Electric CDD English Electric GTT21AF 10KA 10KA
V)
40MVA -II English Electric 90015788012 CAG14F12A 31PF90562Y (M) 8001A (M) Working Yes -do- 96KV 30KV
F) Reactor Protection NO
Name of Reactor Back-up
REF
Differential Impedance OTI/WTI
Protection Any Other LA Rating HV
Protection Protection Indication working Buchholz/PRD Date of testing
(Make & protection Side
(Make & Model) (Make & or not
Model)
Model)
i) All Reactors
Page 5 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
3) Line Parameters
Line 1 Line 2 Line 3 Line 4 Line 5 Line 6
i) Name of Line 220KV AP-I 220KV AP-II
ii) Line Length 20.04KM 20.04KM
Line Parameters
iii) ( In Ohms/Per KM/Per
Phase Primary value) 0.0717Ohm/km 0.0717Ohm/km
R1
X1
Ro
Xo
RoM
XoM
4) DC supply
220 /110 V DC-I 220 /110 V DC-II 48 V DC-I 48 V DC-II
Measured voltage (to be
a measured at furtherest
Panel
i) Positive to Earth 220V DC NA NA
ii) Negative to Earth 0
b No. of Cells Per Bank 110Nos
Availability of Battery
c
Charger Yes Yes/No Yes/No Yes/No
Capacity Test result & date
d
of curative discharge test
Page 6 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
5) Circuit Breaker
Status of No. of PIR
Date of Last Remarks (If
Make and Model CB Rating Breaker trip/close coil (Available
Timing taken any)
220KV Available or Not & healthiness or Not)
Crompton 1250A
i).
Bay - I HS - 1093 Yes 2, 1 -- -- --
Crompton 1250A 2, 1
Bay – II HS - 1093 Yes -- -- --
Crompton 1250A 2, 1
Bay – III HS - 1093 Yes -- -- --
Crompton 1250A 2, 1
Bay – IV HS - 2793 Yes -- -- --
Crompton 1250A 2, 1
Bay – V HS - 1093 Yes -- -- --
Crompton 1250A 2, 1
Bay – VI P0 40151 Yes -- -- --
Crompton 1250A 2, 1
Bay - VII HS - 2742 Yes -- -- --
Crompton 1250A 2, 1
Bay - VIII HS - 2742 Yes -- -- --
ii) DG Set
Make Cummins India Ltd
Rating & Year of manufacture 250KVA
Page 7 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
12)
Any Other Observation/ Comments
Page 8 of 9
Annexure-IV (Xeldem)
AUDIT CHECK LIST
Signature
(Member 1) (Member 2) (Member 3) (Member 4)
(Name:
(Mobile No:
(Email ID:
(Fax No :
(Organization:
(Division
Page 9 of 9
Annexure-V (Ponda)
Annexure-V (Ponda)
Annexure-V (Ponda)
Annexure-V (Ponda)
Annexure-V (Ponda)
Annexure-V (Ponda)
Annexure-V (Ponda)
Annexure-VI
ANNEXURE-VII
1
ANNEXURE-VII
2
ANNEXURE-VII
3
ANNEXURE-VII
4
ANNEXURE-VII
5
ANNEXURE-III
GRID OCCURRENCES
Mylatti (Kasargode)
Taliparambu
Kanhirode (Kannur)
220 kV
110 kV
Kadakola (KAR)
Vadakara
(Orkattery)
M1: Z1 (R-Y-B)
Kaniyampetta
M2: Z1 (B-n)
1
M1: Z1 (B-C)
M2: Z1 (B-n)
2
Nallalam
220 kV
Areakode (Kozhikode)
DEF (67N)
110 kV
M1: Z1 (A-n)
M2: Z2 (B-C), PD
220 kV
Trichur (Madakathara)
Deliberations:
KSEB:
From the trip analysis, the following were noted:
o Areacode – Kanhirode 220 kV feeder tripped at Areacode end with a
fault indication of Zone 1, BC phase on Main – I (Distance,
Quadramho) relay and Zone-1, BG on Main – 2 (Distance, SEL
311C)relay.
SRLDC:
Event logger submitted for the corresponding incident was not clear and
unable to find out the root cause of the incident.
When 220 kV lines are not available, lines could be tripped on 110kV side so
as to avoid overloading. SPS could be designed by KSEB and intimated to
SRPC forum.
Installation of lightning arrestors on towers in fault prone area of the line
may be explored by KSEB. The experiment was done in North Eastern
region by PGCIL and it was reported that after the installation of LAs on
towers, the number of trippings have come down drastically.
At Kanhirode end, the non-tripping of 220 kV CB of Areakode-Kanhirode
line shall be checked and found out the reason.
SRPC: .
It was noted that Kanhirode end of the Areacode – Kanhirode 220 kV feeder
did not trip despite the possibility of 110kV supply at Kanhirode.
Recommendations:
KSEB has to carry out the detailed analysis of the fault and submit a detailed
report to the PCSC forum.
PCSC forum requested KSEB to propose a Special Protection Scheme (SPS)
for Nallalam station.
SLD:
100 MVA 2
2 Kundara - Kayamkulam
1 Sabarigiri
Pothencode
Deliberations:
KSEB:
During the tripping event, heavy lightening was present. B-pole breaker of
220kV Edamon-Tirunelveli line-1 blasted at Edamon end.
Closing spring mechanism of the B- pole breaker got damaged.
The tripping spring was not charged fully prior to the event and hence could not
open the 'B' pole fully as the required energy/strength was not present in the
spring.
Blasting of the CB is due to the delayed arc quenching due to the damage in the
operating mechanism of the breaker.
Bus isolator of 220kV Edamon-Tirunelveli-2 got damaged due to CB failure in
Line-1.
Accordingly LBB acted (after Z1 time + 200ms), but LBB output is taken to the
input of Bus bar relay which could not operate correctly as there was some
delay.
220kV bus bar protection got operated at Edamon end and isolated the upper
bus. But its operation got delayed and hence all feeders connected to the lower
bus also tripped at the remote station.
This resulted in tripping of all 220kV lines and 100 MVA transformers
PGCIL:
DT was received after 200 ms from remote end (Tirunelveli).
As there was persisting arc for 600 ms, Z3 might have sensed.
Zone-4 is used as a forward zone for fault sensing/detecting only and not for
tripping.
SRLDC:
As per the DR submitted the appearance of full voltage at both the ends after
the fault clearance (2.5 seconds later). The reason for the above has to be
analyzed.
KSEB to check the possibility of providing annunciation of spring coil charging
of the Breaker (mechanical indication) to the control room.
Mylatti (Kasargode)
Legend:
Substation : blackout
Taliparamb 220 kV HT: hand trip
u DT: direct transfer trip
Kanhirode UFR: under frequency relay
(Kannur) Kadakola (KAR) O/C: over current
: closed CB
Vadakara : open CB
Kaniyampetta
(Orkattery)
Areakode (Kozhikode)
Nallalam
Shoranur
Malaparamba Trichur (Madakathara)
220 kV
Udumalaipettai
(TN)
400 kV Palakkad 1
DT HT UF 1 DT
R
Kochi
6 5 4 2
3
2
DT HT UF DT HT
Kalamasery R
Udumalaipettai
(TN)
Brahmapuram O/C PS
O/C Idukki
Ambalamughal
UF
R Z1 (ABC)
Pallom Lower Periyar
1 2 3 5 4 6
PS
New Pallom UF RSD Lockout RSD Non-Lockout
Sabarigiri trip trip
O/C O/C R
PGCIL:
KSEB:
400kV Udumalpet - Palakkad line-1 tripped during NTAMC testing works at Palakkad
SS.
400kV Udumalpet - Palakkad line-2 was hand tripped on emergency due to smoke
observed in R-phase wave trap at Udumalpet end.
Simultaneously, 400 kV Palakkad - Trichur line-1 & 2 got tripped due to under
frequency protection.
400 kV Trichur - Kochi line-1 & 2 tripped on loss of voltage at Trichur.
All units in service (1, 4, and 6) were tripped at Idukki hydro plant (generation loss of
275 MW) on non-lockout trip except the Unit #1.
220kV Punnapra- New Pallom feeder tripped at Punnapra end with 3 phase over load &
then convert to B phase to earth fault and it was Autoreclosed at Punnapra end but
tripped at New Pallom end with O/C.
220 kV Kayamkulam-New Pallom tripped at Kayamkulam end on Channel-2 protection
of Power Swing operation (PS).
220kV Idukki-New pallom and 220kV Ambalamugal- Sabarigiri tripped at New Pallom
and Ambalamugal respectively by the acting of under frequency relay (UF) installed as
a part of islanding scheme.
Blackout occurred at Mylatty, Taliparambu, Kanhirode, Areakkode, Vadakara,
Nallalam partial, Shornur, Malaparamba, Madakkathara, Palakkad, Kalamassery,
Brahmapuram, Ambalamugal, Pallam, New Pallom, Punnapra partial and all its
connected feeding stations.
220 kV Idukki-Udumalpet line tripped and restored at 11:05 Hrs.
Steps have been taken to investigate the lockout trip of Unit #1 at Idukki.
220kV Ambalamugal-Sabarigiri feeder was under Permit to work during the tripping
time.
With the above breaker operation, the south zone was islanded with the support of
The twin-moose conductor can carry around 1480 A for 1.5 hours to 2 hours, based on
the short term thermal loading of the conductors. Here the current was not above 1400
A, and nothing would have happened to conductors as the short term thermal
overloading was not exceeded.
SPS for 400 kV Udumalpet-Pallakad D/C may be planned to shed load if flow on any
one line is above 650 MW after the tripping of other line.
The designed SPS logic is as follows:
Recommendations:
KSEB has to carry out the detailed analysis of the fault and submit a detailed report to
the PCSC forum.
KSEB shall finalize the proposed SPS for Udumalpet-Pallakad and submit the details of
implementation with the loads to be shed to the PCSC forum.
SLD:
400 kV
3 1 2
Z1 (A, C)
Mambakkam
(SIPCOT)
Deliberations:
TANTRANSCO:
Setup:
o Each bus of double bus has its own bus bar protection system. Main and check
zone protection both got operated. Different cores are used for main and check
zone measurement of bus bar protection.
o Existing bus bar protection is of high impedance type, and it would be replaced
by low impedance type.
Pre-fault condition:
o During the tripping event, all the 230kV feeders were connected to a single bus
instead of two bus system operation.
o After the last O&M work on one bus, double bus system operations was not
restored.
Fault:
o Bus bar protection was operated for a through fault condition.
Remedial Measure:
o Planned to change the CT ratio to 1600/1 A from existing 1200/1A.
o Reorganization of feeders between two bus would also be done.
SRLDC:
Short circuit level (fault) is increasing at that area as more generations are coming up.
An action plan should be initiated for upgrading the system elements to meet the fault
level.
Recommendations:
TANTRANSCO has to submit the detailed report and remedial measures taken.
Deliberations:
PGCIL:
Non-Return Valve (NRV) relay located between tank and conservator inadvertently
got operated due to jerk/vibration felt when the AC supply to oil pump failed.
Remedial Measure:
The faulty NRV relay for B-phase has been replaced.
The reason for the mal-operation of the relay is taken up with the manufacturer and
would submit a detailed report on it.
PGCIL:
There was no occurrence of fault in the system.
230kV Bus-2 at Hosur (PG) got tripped as spurious initiation got extended to LBB
relay of 230kV Hosur- Hosur(PG) line at Hosur(PG) end due to shorting of 6&7
contacts in lockout relay.
Accidentally steel washer was fallen on 6&7 terminals of 85LO relay of 230kV
Hosur line and it initiated LBB Protection of 230KV Hosur line.
400/230kV ICT-2, ICT-3, 230kV Hosur-Vinnamangalam, 230kV Hosur(PG)-
Hosur which were connected to Bus-2 got tripped along with bus coupler breaker.
LBB is a conventional trip operation and without any re-trip option. Relay would
pick up if there is current above 0.2A through the CB.
Remedial Measure:
All the relay and control panels of all the feeders are checked for any loose items
and found in order.
SRLDC/SRPC:
It is better to have LBB relay with re-trip feature and re-trip implementation shall
be explored.
Recommendations:
PGCIL (SR-II) to check the possibility of providing re-trip feature in LBB relay.
Deliberations:
KPTCL:
220kV Guttur-Haveri lines cross 400kV Kaiga-Guttur line corridor at a distance of
8-9km from Guttur.
Suspected that momentary over voltage (spike) in Kaiga-1 &2 lines might have got
induced during fault in 220kV Guttur-Haveri-1 circuit.
The fault was due to de-capping of the insulator near the substation.
The fault location was at after one span crossing of 220 kV Haveri and 400 kV
line.
O/V is being experienced by the bottom conductor of 400 kV lines which is
crossing over on top of 220 kV Haveri line with earth/shield wire.
O/V stage-2 operated on both the 400 kV KGS lines. On other 400 kV lines only
O/V initiation was present.
Remedial Measure:
It is informed that, ground wire continuity in Guttur-Haveri lines have been
checked up and found to be normal.
Measurement of tower footing resistance is being taken up.
Recommendations:
KPTCL shall submit the DR of all the lines at that particular instant to the PCSC
forum for further analysis.
TSTRANSCO:
REF relay got operated due to suspected loose contact of the R-phase CT.
The pickup current for REF relay is 0.1A.
The signals REF IL1, IL2, and IL3 shown on DR, are sum of respective phases of
HV and LV side CTs.
Remedial Measure:
Tightened the loose contacts in REF relay.
Deliberations:
TANTRANSCO:
400kV Alamathy-SVChatram line-1&2 are in the same tower.
Line fault occurred on 400kV Alamathy-SVChatram line-1 due to jumper cut in B
phase.
400/110kV, 3×66.67MVA, ICT-3 tripped on V/f trip (Overflux) due to sudden rise
in voltage (around Va=321 & Vc=333KV) and actuation of V/f Trip of ICT-3
occurs few milliseconds after the fault tripping of 400KV Alamathy-1 Feeder and
400KV Alamathy-2 feeder.
SRLDC:
Both the relay sensed fault in different phases.
At each end of the line, Main-1 and Main-2 relays are of same make and type (i.e
P442 and D60).
PGCIL:
V/f relay is configured with both alarm and trip functions.
Recommendations:
TANTRANSCO to furnish the detailed report of the incident within a week‟s time
(i.e by May 5th 2015).
TANTRANSCO was requested to swap the relays between two stations, so that
Main-1 and Main-2 will be of different make at each station.
TSTRANSCO:
Tripped at both ends on R phase to ground fault.
On patrolling, it was found that a net from nearby crop fallen on conductor due to
heavy gale.
It was a case of high resistance fault.
Remedial Measure:
Net was removed and charged the feeder.
SRLDC:
It was noted that despite the fault on „R‟ phase, there was not much voltage drop in
that phase.
In-feed from Malkaram might have caused the under reach of the relay.
PGCIL:
Pole 1 generated ESOF at Kolar end on operation of O/C+ E/F relay of the
Converter Transformer.
Before tripping there was Tap Changer out of step alarm in R-phase Converter
Transformer of Pole-1.
Pole 2 metallic return mode was successful and the final DC power in Pole 2
settled at 1005MW (Talcher side).
Tap changer out of step alarm was reported in the SER.
It was observed that the R phase tap position was at “2” and Y & B phase tap
positions were at “3”.
Before the tap position in R-phase transformer could be moved / corrected to “3”
manually in local, the alarm got cleared. Due to this, control system has given tap
raise command to Y&B phases.
Since again there was a difference in tap positions, out of step alarm was reported.
But this alarm got cleared within few “msec” and tap raise command was given to
Y&B phases again.
This sequence continued further and the tap changer of Y&B phases reached to
“13” while R phase remained at “2”. Due to unequal tap positions and unbalanced
AC current between phases, neutral current increased to the threshold level of E/F
current setting (400A, 400msec) on the valve side of Converter Transformers and
the E/F relay operated and tripped the Converter Transformer on Transformer
protection.
Consequently Pole 1 tripped.
The unbalance AC current is evident with the repeated bypass of the blocking
device in Pole 1 Converter Transformer during the event.
It was found that the K31 got faulty in the OLTC control cubicle and the drive
protector also tripped. Due to this the OLTC could not operate from the remote.
Since there was a difference in the OLTC positions, the tap changer could not
move to start position after the tripping of Pole.
Tap changers of all the 3 transformers were brought to start position manually.
Remedial Measure:
The ON delay timer K31 timer was replaced with the spare and the Converter
Transformer was charged.
Tap changer operation was checked and found to be normal.
Deliberations:
KPCL:
Remedial Measure:
The setting has been revised and would be set at 4.75A instead of 4 A with
instantaneous trigger.
Deliberations:
TSTRANSCO/ APTRANSCO:
At Kurnool end, stub protection operated and I>4 protection operated at Srisailam
end.
Problem with the auxiliary contact switch of the line isolator initiated the stub
protection to trip.
The switching scheme is one and half breaker with 4 CTs. The stub protection pick
up current setting is 1.5 A.
Remedial Measure:
Deliberations:
KPTCL:
The existing relay is of electromechanical type and the e/f relay is non-directional.
Similar fault happened on Sedam-Shapur line on 06.4.2015.
On 11-04-2015, this line got tripped, during the occurrence of multiple tripping
events at Raichur TPS incident.
Even though it is a through fault condition, the line trips occasionally.
Remedial Measure:
The relay would be made directional and the pickup setting would be increased so
as to avoid tripping.
Deliberations:
PGCIL:
With respect to Tripping Analysis Report, the following were noted:
Remedial Measure:
The limit switch of PRD-2 was replaced with spare switch from the stock. The
switch was fixed and its operation was checked and found to be in good condition.
Deliberations:
Protection System Analysis Group (PSAG-13) was held on 22nd and 23rd April, 2015 at
Raichur to analyze the cause of multiple trippings that occurred at Raichur (PG) and
RTPS on 09-03-2015 and 11-04-2015(Annexure-VI).
Recommendations:
KPCL, KPTCL and PGCIL (SR-I) to furnish the action taken report on the
recommendations given by PSAG members held at Raichur on 22-04-2015 and
23-04-2015.
UPCL:
A high resistive fault occurred when a bamboo tree got burned down due to the
contact with the lines.
Auto Recloser was successful at UPCL end.
But, due to the persisting fault in the line; TOR protection operated & Line breaker
(4-652) got tripped.
There were many trippings on the line due to transient fault.
As Corrective Action: The settings of DMT would be changed to IDMT type for
both the lines.
SRLDC:
GPS Time synchronization should be done.
Recommendations:
KPTCL was suggested to carry out Line patrolling (tree cutting) on this line.
Deliberations:
KPCL:
It is seen from the ICT location that 400kV side 89L „R‟ phase isolator operating rod bolt
got broken and due to heavy wind and rain, isolator got partially opened.
Due to the problem in R-phase contactor, O/C and e/f protection got operated.
SRLDC:
RTPS-BTPS line is made LILO at Yermarus. KPCL shall consider the implementation of
line differential protection between RTPS and Yermarus stations as the line is very short
(7-8 km) and would be in use for more than 4 or 5 years.
Line differential protection is under operation on the line connecting Vallur-NCTPS
power plants.
Recommendations:
SRLDC/ SRPC:
As it is an inter-state
line, A/R has to be
provided.
SRLDC:
Information regarding
A/R disconnection is not
informed to SRLDC.
Single phase auto
reclose has to be
implemented on the
lines.
SRLDC:
The reason for the
failure of the carrier
transmission needs to be
analyzed.
Recommendations:
Relays have to be
checked and made
functional by 30-05-
2015.
Remedial Measure:
By May, 2015 auxiliary relay
will be replaced.
TANTRANSCO:
On Theni-Mozhiyar (Sabarigiri)
A/R is not functioning on
20.3.2015.
Andhra Pradesh
39/III/1 Tripping of 10, 11, 13, Tripped on over PCSC forum recommended APTRANSCO to APGENC APTRANSCO informed vide their e- Pending
400kv 14,15 Dec voltage. check up the O mail dated 27.02.15 that the issue
VTPS- 2014 The drop off to pick drop off to pick up ratio of the Overvoltage pertains to APGENCO.
Satenapalli line- up ratio and grading in relay and correct
1 &2 over voltage protection it (if needed).
needs to be verified.
40/IV/2 400 kV 07-01-2015 Line tripped on Rphase APTRANSCO was requested to check up the APTRANS Yet to be informed Pending
HYDERABA at 6:17 hrs to earth fault. A/R lock A/R feature at both the ends and submit the CO
D- out remedial measures to the PCSC
KURNOOL observed in E.L of forum.
line Hyderabad end
42/I/5 Complete 22-03-2015 at B-phase CT failure on Reasons for non-tripping of ICT-3 along APTRANS Yet to be informed Pending
(GD) outage of 220 19:31 hrs LV side of 220/132kV with remedial measures taken shall be CO
kV Tadikonda ICT-1 at Tadikonda led furnished by APTRANSCO to PCSC forum.
substation of to complete outage of
APTRANSCO Tadikonda station.
1
ANNEXURE-IV
42/II/3 Outage at 21-02-2015 at Y-Ph Metering PT APTRANSCO to furnish the remedial APTRANS Yet to be informed Pending
Regulapadu 00:49 hrs failed at 220KV measures taken in consequent to the tripping CO
station of Ragulapadu Substation. incident along with the status of bus bar
APTRANSCO Fault got cleared protection and bus coupler at Regulapadu S/s.
by tripping of lines A/R feature to be enabled on Regulapadu
from remote ends. – Alipuira 220 kV inter-state line.
Telangana
41/II/2 Tripping of 23-01-2015 at Bus-2 at Srisailam TSGENCO to furnish the reasons for TSGENC Yet to be informed Pending
400kV 16:10 hrs became dead while BBP operation at Srisailam LLB and the O
Srisailam- converting Srisailam remedial action taken to PCSC forum.
Mamidapalli-2 generator to condenser
line and 400kV mode. Direct trip was
Srisailam- received at Mamidapalli
Satenapalli-1 and Satenapalli end.
line
42/I/4 Complete 20-03-2015 at Fault in GIS bus at TSGENCO to provide bus bar protection at TSGENC Yet to be informed Pending
(GD) outage of 11:22 hrs Srisailam. 400kV Srisailam left bank HES, and furnish the O
Srisailam left Mamidapalli-1&2, time frame for implementation of the same by
bank hydro Satenapalli-1&2 and 20.04.2015.
power station Kurnool lines tripped
on operation of residual
over current protection
at Srisailam.
Karnataka
2
ANNEXURE-IV
30/I/A RTPS Mar-14 Spl meeting held at The PCSC forum recommended for KPCL 1. e- Tender folated for the retrofit of Pending
Tripping RTPS on 13th and 14th replacement of existing electromechanical existing static relays with Numerical
incidents and March 2014 relays with Numerical relays. version for lines M.nagar,M.bad,ICT-1
the Spl meeting & 2 -Technical Bid opened & price bid
held at RTPS yet to be opened.
on 13th and
14th March 2. Retrofit of existing bus bar (CAG-34)
2014 with numerical version -Budgetetory
offers obtained and is under process.
33/II/3 400kV 22-05-14 & B phase to ground fault The PCSC forum requested KPCL to enable KPCL 1. A/R for 220kV lines enabled already. Pending
Hiriyur-BTPS 23/05/2014 had occurred in line and the A/R feature at RTPS end before next 2. Shtu down of lines availed to
line-2 line auto reclosed at PCSC meeting (i.e. 31st July, 2014. commission the auto reclosing schme fro
Hiriyur end but failed to 400 kV line at BTPS.
reclose at BTPS end. 3. A/R shall be enabled in next
shutdown
34/III/1 400kV 26-06-2014 Transient fault in R- A/R at BTPS end to be made operational KPCL 1. A/R for 220kV lines enabled already. Pending
Raichur-BTPS phase. within one month 2. Shtu down of lines availed to
line Line did not auto commission the auto reclosing schme fro
reclose 400 kV line at BTPS.
3. A/R shall be enabled in next
shutdown
3
ANNEXURE-IV
38/GD/3 GD-1 at Kadra 13-11-2014 at A fault had occurred in 1. The PCSC forum requested KPCL to speed KPCL All the recommendations of PSAG - 10 Pending
.5 and Kodasalli 19:31hrs 220 kV Kadra and up the installation of Numerical Distance are completed except the following
hydro power Kodasalli. As A result, Protection relay in Kadra –Kaiga and pending issue:
station de-energization of Kodasalli –Kaiga.
220kV bus occurred at i)e-NIT floated on 28.07.2014 for
Kadra and 2. The PCSC forum requested KPCL to procurement of Numerical distance
Kodasalli. submit the implementation status of PSAG-10 relays & GPS. Bid evaluation is under
recommendations within a week’s time. progress. The work will be completed by
December - 2015. Hower, as per the
recommendations of PSAG, Relays
were temporarily rearranged, replaced
and wired up. testing & commissioning
shall be completed with the assistance of
KPTCL by March 1st week , 2015.
34/I/6 400/220 kV 16-07-2014 As reported directional 1. Bus bar protection shall be provided by KPTCL Management approval is obtained for Pending
ICT-1 & 2 at over current relay of asset owner ( i.e KPTCL) . taking up the work of providing bus bar
MUNIRABA ICT’s operated due to protection to 220kV buses at
D snapping of line 2. Settings for main distance protection & Guddadahally (Munirabad) Sub Station
jumper in 220kV Overcurrent protection shall be examined along with replacement of 3 core/age old
Lingapur line. and reviewed. CTs of 220kV bays belong to KPTCL.
38/GD/3 GD-1 at 25-10-2014 Fault had occurred in 1. PCSC forum recommended KPTCL to KPTCL Mail received on 25-03-2015 Pending
.1 Mahalingapura 220kV replace the old static distance protection (KPTCL):
Substation of Mahalingapura- relays with numerical relays. 1.Existing Back up relays will be
KPTCL Narendra line-2. Due to replaced by numerical type distance
the 2. PCSC forum also requested KPTCL to relays.Procurement is in tendering stage.
failure of relay provide a broken conductor alarm indication 2. Alarm for Broken conductor is in
operation at in Control Room. service.
Mahalingapura, 3. Clear instructions have been given to
breakers at remote end 3. Standing instruction needed to be given to station staff.
tripped which the all substation personnel for not changing
resulted in bus dead the relay settings without approval of
condition. RT/MRT wing.
4
ANNEXURE-IV
38/GD/3 GD-1 at Guttur 05-11-2014 at Circuit breaker of KPTCL was requested to expedite the early KPTCL Mail received on 25-03-2015 Pending
.2 Substation of 11:42 hrs 400kV Guttur-Hiriyur implementation of pending recommendations (KPTCL):
KPTCL line-1 failed at Guttur of: Replacement of failed breaker of Hiriyur-
end while availing 1 line, 400kV BC and TBC is taken up at
shutdown for 1. Protection Audit (Phase-I & Phase-II) Guttur. Work is entrusted to M/s
replacement of CVT. Alstom.Complaince will be furnished to
The 2. PSAG-4, PSAG-5, and PSAG-8 SRPC upon completion of these works.
failure of breaker Mail received on 28-04-2015: At
caused bus fault at Guttur, Alstom make new breaker
Guttur. commissioned for 400kV Bus Coupler
on6.04.2015 and split bus operation is
put back to service since 13.04.2015
through Bus Coupler breaker.
Replacement of failed breaker of Hiriyur-
1 line is taken up at present. Work is
entrusted to M/s Alstom.
39/I/5 Tripping of 01-12-2014 Suspected mal- 1. PCSC forum recommended KPTCL to KPTCL Mail received on 25-03-2015 Pending
400/220kV operation of 220kV replace the relay with a different make. (KPTCL): C&R panels of
ICT-2 at side Rphase 500MVA ICT 1&2 will be replaced
Hoody over current relay 2. KPTCL was also requested to train the under scheduled R&M works. O&M
substation of O&M personnel adequately before personnel are instructed to take
KPTCL performing any maintenance works to avoid sufficient care in order to avoid
such unwanted trippings. unwarrented trippings.
5
ANNEXURE-IV
40/I/1 GD-1 at 220kV 22-12-2014 at Triggering incident was 1. Till the completion of R&M works for bus KPTCL Mail received on 28-04-2015: 1. Pending
Ambewadi 21:22 hrs B-phase to earth fault in bar and LBB protection, KPTCL shall In view of operating 220kV Ambewadi
Station of 220kV Ambewadi- explore the possibility of having split bus SS in split bus mode, action is being
KPTCL Nagzari line-1. B-pole operation at Ambewadi and submit the taken up by KPTCL. Problem in the
of breaker did not open details of the same to PCSC forum. 220kV bus coupler breaker is attended
at Ambewadi end. LBB and isolator overhauling work is under
protection not available 2. KPTCL shall check up the ICTs progress. Spilt bus operation at
at Ambewadi end. All protection system for finding the cause of Ambewadi will be made possible at the
elements tripped on not tripping for the line fault (through fault) earliest. 2.
Zone-2 from remote and submit the remedial measures. ICT protection system at Ambewadi and
ends. trippings occured at Supa GS during the
3. KPTCL shall provide the details of the instance is checked up and remedial
tripping of Supa hydro station connected measures already furnished in this
downstream from 110 kV bus. regard.
40/IV/1 220kV Sedam- 20-12-2014 Line tripped on Yphase KPTCL was requested to explore the KPTCL Yet to be informed Pending
Tandur line at 22:20 hrs to earth fault from both possibility of providing A/R feature to this
the ends line and submit the remedial measures to the
PCSC forum.
41/I/1 GD-1 at 220kV 16-02-2015 at Triggering incident was 1. KPCL to make functional the Main2 KPCL Yet to be informed Pending
Kadra power 12:56 hrs B-phase to earth fault (EPAC) relay with the help of KPTCL at the
Station of had occurred in 220kV earliest.
KPCL Kadra-Kodasalli line. 2. KPCL to investigate the reason for DC
Line tripped from fuse fail during transient fault in 220kV
Kodasalli end only. Kadra-Kodasalli line including the testing/
220kV Kaiga-Kadra checking of DC supply cables, breaker control
tripped in Zone-3 from cables, and trip coils.
Kaiga end. Tripping of 3. KPCL to ensure supply for Main-1&
evacuating lines caused Main-2 protections, Trip Coils (TC1, TC2)
bus shut down at Kadra from separate battery banks.
hydro station.
6
ANNEXURE-IV
41/I/3 Complete 22-02-2015 at During de- 1. KPCL to investigate the cause of Y-pole KPCL Yet to be informed Pending
outage of 11:09 hrs synchronization of Unit- breaker lock-out of Unit-3, and take suitable
Nagjheri 3, the Y-pole of the CB remedial measures within a week’s time
Hydro power did not open (was 2. KPCL to furnish what caused LBB
station of locked-out). This initiation and furnish LBB Scheme details
KPCL (GD-1) caused LBB protection to PCSC forum
to operate resulting in 3. KPCL to furnish detailed tripping report
tripping of the Bus and (with DR & EL) of the incident
all connected 220kV
lines and running units
at Nagjheri power
station.
41/I/4 Complete 27-01-2015 at R-Phase to ground fault 1. KPTCL to provide Bus bar and LBB KPTCL Mail received on 28-04-2015: 1. Pending
outage at 8.00 hrs occurred on 220kV protections for 220 kV bus at Sedam S/s. Procurement of Bus bar and LBB
220kV Sedam Sedam-Shahpur line. 2. KPTCL to implement A/R feature on protection is in the final tendering stage.
Substation of Fault not cleared from 220 kV Sedam-Tandur inter-state line. 2. Action is being taken to restore the
KPTCL (GD- Sedam end due to stuck- carrier protection for 220kV Sedam-
1) breaker condition. Tandoor line. AR will be enabled.
While the Sedam-
Sahapur line tripped
from Shahapur end in
Zone-1, the other 220
kv lines from Sedam
tripped at remote ends
in Zone-2. This caused
complete outage of
220kV Sedam
substation.
41/II/11 Tripping of 13-02-2015 at Line tripped at BTPS KPCL to furnish remedial measures KPCL Yet to be informed Pending
400kV BTPS - 17:07hrs end only. taken to prevent recurrence of PLCC mal-
Hiriyur line-2 operation at BTPS.
7
ANNEXURE-IV
42/I/1 Complete 15-02-2015 at Fault occurred in 1. KPTCL to provide Bus Bar protection and KPTCL Yet to be informed Pending
(GD) outage of 14:24 hrs 220kV Sedam-Shahpur LBB protection at Sedam S/s and furnish
220kV Sedam line the status of their implementation to PCSC
substation of forum.
KPTCL 2. KPTCL to implement A/R feature on 220
kV Sedam-Tandur inter-state line.
42/I/2 Complete 12-03-2015 at Fault in 220kV 1. KPTCL shall provide A/R feature on KPTCL Yet to be informed Pending
(GD) outage of 7:51 hrs Ambewadi-Nagjheri Ambewadi – Ponda 220 kV D/C inter-state
220kV line-2 line.
Ambewadi 2. Till the completion of R&M works for bus
substation of bar and LBB protection, KPTCL shall explore
KPTCL the possibility of having split bus operation at
Ambewadi and submit the details of the
same to PCSC forum.
42/II/2 Tripping of 20-02-2015 at Lines tripped during 1. KPTCL to provide A/R feature on the 220 KPTCL Yet to be informed Pending
220kV 06:40 hrs test charging 220kV kV Chikkodi – Talandage, and 220 kV
Chikodi- Chikodi-Belgaum line-2 Chikkodi –Mudashinge inter-state lines.
Talandage and from Chikodi 2. KPTCL to carry out E/F relay coordination
220kV Chikodi- end. for Chikkodi - Talandage and Chikkodi –
Mudshingi line Mudashinge lines in coordination with
Maharashtra.
Tamil Nadu
8
ANNEXURE-IV
36/II/9 400kV Arasur- 29-09-2014 Mettur S/s to Enable A/R Scheme. TANTRA 1. During the 38th PCSC meeting, Pending
Mettur Line I NSCO TANTRANSCO informed that the Auto
Reclosing facility would be enabled
within 15 days.
37/II/3 400kV Mettur- 29-09-2014 Line tripped due to Y- A/R scheme to be enabled. TANTRA 1. During the 38th PCSC meeting, Pending
Arasur line-1 Phase to earth fault. NSCO TANTRANSCO informed that the Auto
Line did not auto Reclosing facility would be enabled
reclose as Auto reclose within 15 days.
scheme is kept in non-
auto mode. 2. A/R scheme will be implemented after
the commissioning of 400 kV
Thiruvalam Line-I & II.
38/II/3 Tripping of 22-10-2014 Line tripped on Rphase A/R feature to be enabled. TANTRA 1. During the 38th PCSC meeting, Pending
400kV to earth fault. NSCO TANTRANSCO informed that the Auto
Mettur-Arasur Auto reclose kept in Reclosing facility would be enabled
line-2 non-auto mode. within 15 days.
Kerala
PGCIL
9
ANNEXURE-IV
34/I/3 Tripping of 09-07-2014 As reported, pole-1&2 1. The PCSC forum recommended PGCIL, PGCIL 1. Implementation of Tertiary Winding Pending
HVDC tripped due to auxiliary SRTS-I take up the issue with WRTS to submit of ICT for the auxilliary power supply is
Bhadravati supply failure. the report as per IEGC guidelines. going to come up which resolves this
Pole-1 & 2 issue.
2. SRLDC is also requested to write a letter to
WRLDC to submit the reports to SR also. 2. PGCIL informed that all issues would
be discussed during PSAG-11 visit.
3. Based on the SRTS/SRLDC
correspondences, SRPC would take it up with
WR and PGCIL if the issue is not getting
resolved.
34/I/7 HVDC 18-07-2014 As reported pole-2 1. Complete analysis of the faults and PGCIL Yet to be informed Pending
BHADRAVA tripped due on 5th rectification/remedial action taken to avert
THI POLE 2 harmonic alarm. similar occurrence in the HVDC Back to Back
station shall be submitted.
39/I/1 Tripping of 22-11-2014 Line tripped due to Retrofitting of the relay or installation of PGCIL Yet to be informed Pending
400kV suspected PLCC Optical Fiber cable is recommended by PCSC
Gooty- Mal-operation at Gooty forum to PGCIL.
Somanahalli end.
10
ANNEXURE-IV
40/II/1 Tripping of 18-12-2014 at Line tripped due to PGCIL shall review the TEED protection at PGCIL Yet to be informed Pending
400kV 18:33 hrs operation of TEED Gajuwaka end and submit the details to
Vijayawada- protection at Gajuwaka PCSC forum.
Gajuwaka end due to opening of
line jumper of Y phase CT.
41/II/1 Tripping of 22-01-2015 at line tripped on PGCIL shallreview the TEED protection PGCIL Yet to be informed Pending
400kV 11:39 hrs operation of TEED at Vijayawada end with their OEM group
Vijayawada- protection at and submit action taken report to PCSC
Nellore line 1 Vijayawada end and forum.
direct trip was received
at Nellore end
41/II/6 Tripping of 07-02-2015 at B-phase to earth fault PGCILto carry out hot-line washing PGCIL Yet to be informed Pending
400kV Coastal 01:07 hrs and had occurred in Line regularly as NTPL is in highly polluted
Energen at 00:08hrs on during both instants. As location.
(CEPL)--- 08-02-2015 seen from D.R of
NTPL line Coastal Energen
distance relay sensed
fault in zone-2 and
earth fault protection
had operated which
resulted in tripping of
line.
41/II/8 Tripping of 10-02-2015 at Pole-2 tripped due to PGCIL to test the pumps at Talcher PGCIL Yet to be informed Pending
HVDC Talcher- 7:37 hrs ESOF from Talcher end HVDC during pole shut-down and submit
Kolar pole-2 the report to PCSC forum.
41/II/16 Tripping of 15-02-2015 at Line tripped at pugalur PGCIL to check the protection coupler PGCIL Yet to be informed Pending
400 kV 18:38 hrs end due to direct trip of PLCC system at Pugalur end.
NEYVELI TS receive
2 - PUGALUR
41/III/1 Tripping of 20-01-2014 at line tripped at Gooty • PGCIL to furnish remedial measures PGCIL Yet to be informed Pending
400kV Gooty- 11:44 hrs end only and was taken.
Somanahalli holding from • PGCIL to properly tune PLCC panels.
line Somanahalli end line
11
ANNEXURE-IV
41/III/2 Tripping of 09-02-2015 at PLCC of Udumalpet- • PGCIL to furnish remedial measures PGCIL Yet to be informed Pending
400kV 9:50hrs Arasur-2 mal-operated taken.
Udumalpet- • PGCIL to properly tune PLCC panels.
Palakad line-
1& 400
Udumalpet-
Arasur line-2
42/II/7 Tripping of 23-02-2015 at HVDC pole-1 got PGCIL (SR-II) to submit the report of M/s PGCIL Yet to be informed Pending
400kV 13:34 hrs tripped due to failure ABB’s on preventing supply card failures.
Jeypore- of 4 no. power supply
Gazuwaka line- card. HVDC
1&2 and pole-2 tripped on DC
tripping of low voltage trip.
HVDC back to 400kV Jeypore-
back pole- Gazuwaka line-1&2
1&2 at tripped due to operation
Gazuwaka of Over voltage
protection at Gazuwaka
end.
42/II/8 Tripping of 23-02-2015 at Pole 1 of Talcher-Kolar PGCIL (SR-II) to submit a report on the PGCIL Yet to be informed Pending
HVDC 15:37 HVDC reasons for operation of filter protection at
Talcher-Kolar hrs Transmission system Talcher, and subsequent receipt of ESOF at
pole-1 tripped on receipt Kolar.
of ESOF (Emergency
Switch-off) from
42/II/9 Tripping of 25-02-2015 at Talcher
ICT-1 at Raichur PGCIL (SR-II) to disable the top oil PGCIL Yet to be informed Pending
765/400kV 18:32 hrs tripped due to temperature protection in the concerned relay
ICT-1 at maloperation at
Raichur of contact Raichur-PG and Tiruvalam-PG also
multiplication relay
42/II/13 Tripping of 02-03-2015 at Line tripped on PGCIL (SR-II) to check OVR operation at PGCIL Yet to be informed Pending
400kV 23:30 operation of over Nelamangala.
Neelamangala- hrs voltage protection at
Mysore Neelamangala end.
Line-1
12
ANNEXURE-IV
42/II/17 Tripping of 08-03-2015 ICT -I got tripped on PGCIL (SR-II) to furnish the reasons for mal- PGCIL Yet to be informed Pending
ICT-1 at 19:41hrs operation of operation of distance relay & non-operation
Munirabad 220KV E/F of
220 kV DEF for ICT-2 at Munirabad-PG,
along with the remedial measures taken to
PCSC
forum.
42/II/22 Tripping of 14-03-2015 at HVDC Pole-1 at PGCIL (SR-I) to furnish the reasons for PGCIL Yet to be informed Pending
HVDC pole- 17:12 hrs Gazuwaka tripped due Converter Transformer differential protection
1&2 to operation for Pole-2 along with the remedial
at Gazuwaka tripping of filter banks measures taken.
and and Pole-2 tripped
400kV 400kV due to operation of
Jeypore differential protection.
Gajuwaka 400kV Jeypore-
line -1 Gazuwaka line-1
tripped
on over-voltage from
Gazuwaka end.
42/II/23 Tripping of 18-03-2015 at Pole tripped due to PGCIL (SR-I) to submit the compliance PGCIL Yet to be informed Pending
HVDC 13:55 hrs failure of auxiliary report on PSAG-11 recommendations to
Bhadravathi supply PCSC
Pole-1 forum.
Others
13
ANNEXURE-IV
37/I/9 Tripping of 04-10-2014 ICT-1&2 tripped during To avoid tripping of ICTs for line fault, UPCL It has been reported by UPCL that, the Pending
400/220kV transient fault in R- UPCL is requested to review the settings of work of review of relay coordination
ICT-1&2 at phase in 400kV Hassan- ICT’s SEF relay and consider IDMT and setings for the entire plant is given
UPCL UPCL line-1 setting instead of existing Definite Time to M//s Alstom for entire plant. UPCL
setting. has furnished the settings given by M/s
Alstom for verification. Revised settings
will be issued this week for
implementation
Mail recieved on 28-04-2015:
Revised settings issued to UPCL on 27-
04-2015 for implementation.
40/II/8 Tripping of 14-01-2014 at Y-phase Differential 1. NPCIL, Kudankulam was recommended to NPCIL, Yet to be informed Pending
Unit-1 at 19:20 hrs protection of submit all the relevant reports of the above Kudankula
Kudankulam Generating transformer incident. m
of Unit-1 got operated
which resulted in 2. PCSC forum also requested NPCIL,
tripping of Unit-1. Kudankulam to upload all the reports
(DR/EL/ FIR) of any incident in the SRLDC
web portal within 24 hrs of its occurrence.
41/II/10 Tripping of 12-02-2015 at Line tripped due to high UPCL to revise their DEF relay settings. UPCL Mail recieved on 28-04-2015: Pending
Hassan-UPCL 15:57 hrs resistance fault in B- Revised settings issued to UPCL on 27-
line-2 phase. DEF picked up 04-2015 for implementation.
at hassan end and DT
was sent to UPCL. DEF
protection did not pick
up at UPCL
14
ANNEXURE-IV
41/II/12 Tripping of 13-02-2015 at Line tripped B-phase to CEPL to check A/R scheme at their end. CEPL Yet to be informed Pending
400KV Coastal- 22:54 hrs earth fault and later
NTPL line tripped on R-Y phase
fault. From Coastal end
D.R, Y & B poles of
breaker opened first and
R-pole appears to be
opened on Pole
discrepancy.
41/IV/2 400kV 09-02-2015 at Y-phase to earth fault NTPL to check A/R scheme at their end. NTPL Yet to be informed Pending
Tuticorin PS- 03:17 hrs had occurred in line.
NTPL line Line auto reclosed at
Tuticorin PS end and
failed to reclose at
NTPL end.
42/II/16 Tripping of 08-03-2015 Units tripped due to JSWEL to enable DEF feature in the JSWEL Yet to be informed Pending
UNIT- 3 19:41hrs tripping of SUT. numerical relay for the 220 kV Jindal –
& 5 at Jindal Lingapur lines
power at Jindal end.
station
42/II/19 Tripping of 11-03-2015 at B-phase CT failed in KGS to furnish the reasons for CT failure to KGS Yet to be informed Pending
220kV 21:59 hrs 220kV Kaiga- PCSC forum.
Kaiga- Kodasalli line. Bus bar
Kodassalli protection of
line, Unit-1, 220kV Bus-2 got
2&3 at operated
Kaiga
PowerStation
Miscellaneous
15
ANNEXURE-IV
36/II/8 400kV 07-09-2014 B-phase to earth fault KPTCL: PGCIL / Yet to be informed Pending
Raichur- had occurred in line. PD (pole discrepancy) time delay would be KPTCL
Munirabad line Line auto reclosed at changed.
Munirabad end and
failed to reclose at
Raichur end.
37/I/6 Tripping of 25-09-2014 High resistance fault as 1. At UPCL end, unused zones of distance UPCL / It has been reported by UPCL that, the Pending
400KV the fault ampere was protection (probably zone 5 to 8) shall be KPTCL work of review of relay coordination
Hassan-UPCL very less i.e., 0.6kA at disabled. and setings for the entire plant is given
line-2 Hassan end and nearly to M//s Alstom for entire plant. UPCL
0.9kA at UPCL end. 2. At UPCL end, time synchronization has furnished the settings given by M/s
between main-1 and main-2 relays shall be Alstom for verification. Revised settings
Back up earth fault ensured. will be issued this week for
protection had operated implementation.
at Hassan. 3. UPCL shall ensure time synchronization Mail recieved on 28-04-2015:
with Hassan substation. Revised settings issued to UPCL on 27-
At UPCL end the high 04-2015 for implementation.
resistance fault got 4. Reasons for non operation of back up
converted into a R ph-B- protection at UPCL for high resistance
ph fault which resulted fault is to be submitted.
in operation of distance
protection Zone-1. 5. Reasons for not sending DT to UPCL by
Hassan end is to be submitted.
The reason for non-
38/II/2 Tripping of 11-10-2014 Line tripped on Yphase APTRANSCO and TSTRANSCO were PGCIL/ Yet to be informed. Pending
400kV to earth fault. requested to clear the corridor jointly at the APTRANS
Khammam- Line did not auto earliest. CO/
Kalpakka line reclose at Khammam TSTRANS
end. CO
38/II/5 400kV 27-10-2014 Line tripped on Planned to replace the PLCC system within a NTPC/ Yet to be informed. Pending
Ramagundam- Bphase week's time at both the ends during the PGCIL
Hyderabad line- to earth fault. shutdown.
4 Line did not auto
reclose at Hyderabad
end due to
PLCCmal-operation.
16
ANNEXURE-IV
39/I/2 Tripping of 22-12-14 Due to PLCC Mal- PGCIL is requested check up with the PGCIL/ Yet to be informed. Pending
400Kv at 10:52 hrs, operation at HYD S/S manufacturer to resolve the issue and TSTRANS
Ghanapur- 24-12-14 at end, DT received at submit remedial measures to PCSC forum. CO
Mamidipally 11:32 MMPLY end and line
line hrs, got tripped.
24-12-14 at
16:16 hrs
40/II/3 Tripping of 01-01-2015 at On account of R-phase 1. PGCIL and KPTCL to ascertain the PGCIL/ Mail recieved on 28-04-2015: Pending
400 13:38 hrs to earth fault, line reason for the phase discrepancy in the KPTCL End to end testing of PLCC has been
kV tripped at Hassan end relay operation and take suitable remedial done and problem in the PLCC is
TALAGUPPA due to operation of measures. atttended.
– HASSAN distance Zone-2 and
line non-receipt of 2. KPTCL to check the PLCC operation at
carrier. From D.R of Talaguppa end and submit the report to the
Talaguppa end it is PCSC forum.
observed that fault had
occurred in Yphase.
41/I/2 Complete 15-02-2015 at Bus fault occurred in 1. PED to investigate the cause of non- PED/PGCI Yet to be informed Pending
outage at 11:20 hrs 110kV bus at operation of ICT’s protection system L
220kV Bahoor 230/110kV Bahoor (differential protection, back-up
Substation of substation due to failure protection) and review the relay settings
Pondicherry of Y-phase main bus suitably.
(GD-1) strain insulator. 220kV 2. PGCIL to check the settings of distance
lines connected to relay and back-up relays for correctness of
Bahoor (viz., Bahoor- operation.
NLC TPS II and
Bahoor – Pondy)
tripped from remote
end on operation of
back up protection.
17
ANNEXURE-IV
41/II/3 Tripping of 24-01-2015 on 400kV NLC-1 EXP- IL&FS, NLC -1 Exp & PGCIL (SR-II) to IL&FS / Mail received on 07-05-2015: Pending
400kV NLC-1 13:15 hrs IL&FS line tripped on a furnish action taken report on the PGCIL ILFS: All recommendations are
EXP- IL&FS R-phase to earth fault. recommendations given by SRPC (SR-II)/ implemented.(Detailed compliance
line and 400kV Line did not auto- Committee in their meeting held at IL&FS on NLC-1 report for Applicable points to ILFS are
IL&FS - reclose. 400kV IL&FS - 19-02-2015 to SRPC. Exp provided)
Trichy line Trichy line tripped at
Trichy due to Direct
trip receive from
IF&FS.
41/II/5 Tripping od 05-02-2015 at Line tripped due to IL&FS, NLC -1 Exp & PGCIL (SR-II) to IL&FS / Mail received on 07-05-2015: Pending
400 kV NLC 06:05 hrs direct trip receipt from furnish action taken report on the PGCIL ILFS: All recommendations are
EXP- ILFS line IL&FS recommendations given by SRPC (SR-II)/ implemented.(Detailed compliance
Committee in their meeting held at IL&FS on NLC-1 report for Applicable points to ILFS are
19-02-2015 to SRPC. Exp provided)
41/II/13, Tripping of 13-02-2015 at Line tripped on R-phase PGCIL to carry out hot-line washing PGCIL/NT Yet to be informed Pending
41/II/14, 400kV NTPL- 23:12 hrs to earth fault at 22:53 regularly as NTPL is in highly polluted PL
41/II/15 Tuticorin hrs. Line auto reclosed location.
pooling station at Tuticorin pooling end NTPL to review A/R scheme at their end.
and holding. At 23:12
line tripped on B-phase
to earth fault in zone-2
time.
18
ANNEXURE-IV
42/II/1 Tripping of 19-02-2015 at Line tripped at Coastal PLCC end-to-end testing shall be carried out CEPL/ Yet to be informed Pending
400kV Coastal- 16:37 hrs end only by CEPL and Tuticorin PS (PGCIL-SR II) by PGCIL(SR-
Tuticorin PS due to suspected PLCC 06.04.2015. II)
line maloperation
and was holding from
Tuticorin PS end.
Running Unit at
Coastal energen also
got tripped
during the event.
42/II/18 Multiple 09-03-2015 at 400kV Raichur TPS- 1. KPCL to review REF setting (DMT or KPCL/TST Yet to be informed Pending
tripping at 06:36 hrs Raichur(PG) line- IDMTL) for unit-7 by first week of April, RANSCO/
Raichur 1&2, 400kV Raichur- 2015 and PGCIL
thermal Mahboobnagar, inform the same to PCSC forum. (SR-I)
power station Unit#7 and ICT-2 at 2. TSTRANSCO to furnish Mehaboobnagar’s
of RTPS tripped DR and EL and the reasons for distance relay
KPCL during the incident. B operation at their end within a week’s time.
phase to earth 3. PGCIL (SR-I) to rectify the issues relating
fault had occurred in to A/R operation, relay reach (Z2), reverse
400kV Raichur reach
TPS-Raichur line-1 (Z4) and SOTF auxiliary contacts within a
week’s time, and submit the actions taken to
PCSC forum.
19
ANNEXURE- V
2 TSTRANSCO:
PGCIL (SR-I):The feeder
Auto reclosed and tripped
400 kV
PGCIL (SR-I)/ on B-N persistent fault in
KHAMMAM - 22-03-2015/12:01:00 22-03-2015/20:21:00 B - N FAULT
APTRANSCO line.
MAMIDIPALLY 1
3 TSTRANSCO:
PGCIL (SR-I):The feeder
Auto reclosed and tripped
400 kV
PGCIL (SR-I)/ on B-N persistent fault in
KHAMMAM - 25-03-2015/18:32:00 25-03-2015/19:15:00 B-N FAULT
APTRANSCO line.
MAMIDIPALLY 1
4 TSTRANSCO:
TRIPPED
400 Kv RAICHUR DURING RELAY
28-03-2015/19:34:00 28-03-2015/19:52:00 PGCIL (SR-I) To-be-discussed
PG - GOOTY 1 TESTING AT
RAICHUR
5
1
ANNEXURE- V
765 KV RAICHUR
10-04-2015/18:45:00 10-04-2015/21:16:00 Y-B FAULT PGCIL (SR-I) To-be-discussed
- KURNOOL
6
TANTRANSCO:
220 kV IDUKKI - Temporary fault. AR
12-04-2015/15:12:00 12-04-2015/16:26:00 B-N FAULT KSEB/ TNEB
UDUMALPET operated at
7 Udumalpet end.
TANTRANSCO:
B PHASE
220 kV IDUKKI - Temporary fault. AR
12-04-2015/01:43:00 12-04-2015/02:18:00 DISTANCE KSEB/ TNEB
UDUMALPET operated at
PROTECTION
8 Udumalpet end.
400 kV TRIPPED AT
PGCIL(SR-I)/
GHANAPUR - 14-04-2015/03:42:00 MDPL END To-be-discussed
TSTRANSCO
9 MAMIDIPALLY ONLY
400 kV
KHAMMAM - 16-04-2015/13:58:00 16-04-2015/14:25:00 Y-N FAULT PGCIL (SR-I) To-be-discussed
10 N'SAGAR
400 kV
RAMAGUNDAM - 17-04-2015/10:18:00 17-04-2015/10:30:00 DT RECEIVED NTPC/ PGCIL (SR-I) To-be-discussed
11 N'SAGAR 2
PGCIL (SR-II):'400/230KV
ICTs owned and
400/230 Kv ICT 1
maintained by M/s TNEB.
AT 17-04-2015/20:15:00 TRIPPED PGCIL (SR-II)
TANTRANSCO: Differential
THIRUVALLAM
protection operated. ICT
tested OK and charged.
12
400 kV
DT RECEIVED
RAMAGUNDAM - 18-04-2015/11:43:00 18-04-2015/11:49:00 NTPC/ PGCIL (SR-I) To-be-discussed
AT SGR
13 N'SAGAR 2
TRIPPED AT
400 Kv COASTAL
20-04-2015/12:35:00 20-04-2015/13:14:00 COSTAL END KSEB To-be-discussed
- TTRNPS
14 ONLY
2
ANNEXURE- V
3
ANNEXURE- V
CONFIG
400 Kv BROKEN
TNEB/ NTECL TANTRANSCO: LC
ALAMATHI - 23-04-2015/11:04:00 23-04-2015/18:57:00 CONDUCTOR
availed.
NCTPS ST2 -2 PROTECTION IN
ALARAM MODE
24
400 kV DISTANCE
TSGENCO/
SRISAILAM- 23-04-2015/19:05:00 23-04-2015/19:26:00 PROTECTION To-be-discussed
TSTRANSCO
MAMIDIPALLI 2 OPERATED
25
400 kV
TRIPPED DUE
VIJAYAWADA - 24-04-2015/04:56:00 PGCIL (SR-I) To-be-discussed
TO Y-N FAULT
26 NELLORE 2
CONFG.
400 Kv NCTPS - BROKEN COND. TANTRANSCO: LC
24-04-2015/10:21:00 TNEB/NTECL
SVCTM-I PROT. IN availed.
ALRAM MODE
27
400 kV
DT RECEIVED PGCIL (SR-I) /
KHAMMAM - 25-04-2015/12:14:00 25-04-2015/12:30:00 To-be-discussed
AT MDPL TSTRANSCO
MAMIDIPALLY 1
29
400 kV
LA BLAST AT PGCIL (SR-I)/
VIJAYAWADA - 25-04-2015/10:04:00 To-be-discussed
VEM END APTRANSCO
30 VEMAGIRI 1
4
ANNEXURE- V
SUSPECTED DC
765 KV
E/F PERSISTING
KURNOOL - NPS 25-04-2015/18:10:00 PGCIL (SR-I) To-be-discussed
DURING THE
1
TRIPPING.
31
TRIPPED ON
400/220 kV ICT-2
25-04-2015/10:04:00 25-04-2015/10:34:00 GROUP A/B APTRANSCO To-be-discussed
AT VEMAGIRI
32 PROTECTION
400 kV
VEMAGIRI - TRIPPED ON
25-04-2015/10:04:00 25-04-2015/10:50:00 APTRANSCO To-be-discussed
GOUTHAMI MAIN 1 PROTN
33 CCCP 2
PGCIL(SR-II): Tripped on
SUSPECTED DC
765 KV receipt of DT at THVLM
E/F PERSISTING PGCIL (SR-I)/
KURNOOL - 25-04-2015/18:10:00 25-04-2015/19:41:00 end. It is understood that
DURING THE PGCIL(SR-II)
THIRUVALLM 1 there was DC earthfault at
TRIPPING.
Kurnool end.
34
400 kV TRIPPED ON BN
PGCIL (SR-I)/
VIJAYAWADA - 25-04-2015/10:04:00 25-04-2015/10:22:00 FAULT AT VJA To-be-discussed
APTRANSCO
35 VEMAGIRI 3 END
400 kV
TRIPPED AT
VEMAGIRI - 25-04-2015/10:04:00 25-04-2015/13:34:00 APTRANSCO To-be-discussed
KSM END
36 KONASEEMA 2
5
ANNEXURE- V
6
ANNEXURE- V
220 kV EDAMON -
30-04-2015/15:34:00 30-04-2015/16:13:00 Y - N FAULT KSEB/ PGCIL(SR-II) To-be-discussed
TIRUNELVELI 2
48
400 kV HIRIYUR -
NELAMANGALA 02-05-2015/17:53:00 02-05-2015/18:12:00 Y-N FAULT PGCIL (SR-II)/ KPTCL To-be-discussed
2
54
400 kV
TIRUVALLUM - TRIPPED ON R-N
03-05-2015/04:13:00 To-be-discussed
KALAIVANTHAP FAULT
55 ATTU 2
400 kV KAIGA - TRIPPED ON R-
05-05-2015/19:15:00 05-05-2015/19:34:00 KAPS/ PGCIL (SR-I) To-be-discussed
56 NARENDRA 1 PH FAULT
7
ANNEXURE- V
220 Kv
TRIPPED ON B-
CHIKKODI - 05-05-2015/18:41:00 05-05-2015/20:00:00 KPTCL To-be-discussed
PH FAULT
57 TALANDGE
400 kV KAIGA - DT RECEIVED
06-05-2015/03:05:00 KAPS/ KPTCL To-be-discussed
58 GUTTUR 2 AT KGA
400 kV KAIGA -
06-05-2015/01:02:00 Y-B FAULT KAPS/ PGCIL (SR-I) To-be-discussed
59 NARENDRA 1
400 Kv HASSAN - TRIPPED ON Y-
06-05-2015/15:37:00 06-05-2015/16:34:00 PGCIL (SR-II)/ KPTCL To-be-discussed
UPCL 2 PH FAULT
60
400 kV REASON
RAMAGUNDAM - 07-05-2015/18:46:00 08-05-2015/22:25:00 AWAITED FROM NTPC/ PGCIL (WR-I) To-be-discussed
CHANDRAPUR 2 RGDM
65
BUS -1 TRIPPED
400/132 kV ICT-2
07-05-2015/18:46:00 07-05-2015/19:16:00 DUE TO LBB NTPC To-be-discussed
AT RSTPS
OPERATION
66
8
ANNEXURE- V
LV SIDE
PROBLEM ,
400/220 kV ICT-1
07-05-2015/15:31:00 07-05-2015/17:31:00 MASTER TRIP KPTCL To-be-discussed
AT GUTTUR
RELAY
67 OPERATED
400 kV GUTTUR -
08-05-2015/17:11:00 Y - N FAULT KPTCL/ PGCIL(SR-II) To-be-discussed
NARENDRA 2
68
TRIPPED ON
765/400 Kv ICT-1
09-05-2015/16:37:00 09-05-2015/23:52:00 BUCHHOLZ PGCIL(SR-II) To-be-discussed
AT THVLM
69 RELAY
220 Kv TRIPPED AT
CHIKKODI - 09-05-2015/22:45:00 10-05-2015/01:27:00 CHIKKODI END KPTCL To-be-discussed
70 TALANDGE ONLY
400 kV
R PHASE EARTH PGCIL(SR-I)/
KHAMMAM - 09-05-2015/17:47:00 09-05-2015/18:32:00 To-be-discussed
FAULT APTRANSCO
71 KTPS 1
220 kV
AMBEWADI - 10-05-2015/10:53:00 10-05-2015/11:13:00 R -N FAULT KPTCL/ GOA To-be-discussed
72 PONDA 1
400 kV
RAMAGUNDAM - 12-05-2015/00:27:00 R - N FAULT NTPC/ PGCIL (WR-I) To-be-discussed
CHANDRAPUR
73
400 Kv NCTPS - DIFF. PROT.
12-05-2015/06:31:00 12-05-2015/10:24:00 TNEB/NTECL To-be-discussed
74 VALLUR 1 OPERATED
400 Kv NCTPS -
13-05-2015/00:40:00 R-Y FAULT TNEB/NTECL To-be-discussed
75 VALLUR 1
TRIPPED AT
400 kV KAIGA - GTR DUE TO
13-05-2015/07:44:00 13-05-2015/08:28:00 KAPS/KPTCL To-be-discussed
GUTTUR 2 BREAKR
PRESSURE LOW
76
9
ANNEXURE- V
400 Kv NCTPS -
13-05-2015/03:31:00 Y -N FAULT TNEB/NTECL To-be-discussed
77 VALLUR 2
400 kV
TRIPPED ON R- PGCIL (SR-I) /
KHAMMAM - 13-05-2015/13:56:00 13-05-2015/14:45:00 To-be-discussed
PH FAULT APTRANSCO
78 KALPAKKA 2
220 kV SEDAM - TRANSIENT
15-05-2015/14:20:00 15-05-2015/15:59:00 KPTCL/ TSTRANSCO To-be-discussed
79 TANDUR FAULT
RELAY
400 kV KAIGA -
15-05-2015/18:18:00 15-05-2015/19:42:00 MALOPERATIO KAPS/KPTCL To-be-discussed
GUTTUR 1
80 N
400 kV NLC EXP- TRIPPED ON B-N
16-05-2015/11:11:00 16-05-2015/12:04:00 NLC/ IL&FS To-be-discussed
81 ILFS FAULT
OLTC
400/220 kV ICT-1 BUCHHOLZ
16-05-2015/19:43:00 16-05-2015/21:35:00 PGCIL (SR-I) To-be-discussed
AT GOOTY RELAY
82 OPERATED
220 kV
YERANDAHALL 16-05-2015/14:51:00 16-05-2015/15:15:00 B - N FAULT KPTCL/TNEB To-be-discussed
83 Y - HOSUR
400 kV
APTRANSCO/ PGCIL
CHITTOOR - 17-05-2015/14:21:00 17-05-2015/14:36:00 R-N FAULT To-be-discussed
(SR-II)
84 SPDR
220 kV
GUMMUDIPUND 17-05-2015/13:20:00 B - N FAULT TNEB/ APTRANSCO To-be-discussed
I - SULLURPET
85
400 Kv NCTPS -
17-05-2015/04:41:00 H/T DUE TO FOG TNEB/NTECL To-be-discussed
86 VALLUR 1
10
ANNEXURE-VI
1
ANNEXURE-VI
A team of Officials from SRPC, SRLDC, PGCIL (SR-I), KPCL, KPTCL visited Raichur (PG) and RTPS during
22-23 April, 2015 to analyze the cause of multiple trippings that occurred there on 09.03.2015 &
11.04.2015. The list of participants is given at Annexure-I. The single line diagrams of Raichur (PG)
and RTPS are given at Annexure-II.
REF of GT distance
protection
(Bn)
GT G7
During this event, 400kV Raichur TPS-Raichur(PG) line-1&2, 400kV Raichur-Mahboobnagar, Unit#7 at
RTPS tripped during the incident.
As informed by Powergrid representative, B-phase(of RYB) to earth fault had occurred at 6:36:18 hrs
in 400kV Raichur TPS-Raichur line-1 and fault was near to RTPS end. Distance protection at Raichur
(PG) sensed the fault in zone-2 and line auto reclosed from Raichur(PG) end on carrier aided
protection. Breaker at RTPS end did not auto-reclose and all three poles of breaker got tripped.
A second fault i.e a Y-B phase fault occurred at 06:36:31 hrs in 400kV Raichur-RTPS line-1. Breaker of
line-1 was in tripped condition at RTPS end and breaker was in closed position at Raichur(PG) after
1st fault. Distance protection at Raichur(PG) sensed fault in zone-2 and tripped in zone-2 time as
RTPS end did not sense the fault due to breaker open condition at RTPS i.e. fault could not be
cleared immediately with carrier aided protection. 400kV Raichur TPS-Raichur line-2 tripped at
Raichur TPS end on zone-2 start/ SOTF indication on distance relay (Ir-0.69 kA, Iy-6.32kA, Ib-2.2kA,
Va 203kV, Vb 132kV, Vb – 299kV). 400 kV Raichur-Mahboobnagar line tripped from Mahboobnagar
end due to suspected mal-operation of distance protection (Main-2 distance relay).
2
ANNEXURE-VI
Unit-7 at RTPS tripped on operation of restricted earth fault protection (REF) protection. It was
informed by KPCL representatives that REF protection for GT of Unit-7 maloperated during 1st fault
in 400kV Raichur-RTPS line-1.
2. 400kV Raichur PG-2 line tripped from RTPS end on Zone-2 start with SOTF during occurrence
of 2nd fault in 400kV Raichur PG-1 line. It was observed by committee that the relay was
reading 127% for the fault at nearly 190% of Line length as fault was near 2nd tower from
gantry of Line-1 at RTPS. Present implemented zone settings at RTPS for Raichur PG -1&2
lines are Zone-1 : 2.48ohm, Zone-2 : 4.65 ohm with 500ms, Zone-3 : 20.95 ohm with 1.5sec,
Zone-rev : 0.62 ohm with 1.6 Sec, CT ratio 2000/1A. Committee had recommended referring
the event to OEM as relay at RTPS over-reached in zone-2 and sensed the fault near to RTPS
end. POWERGRID had asked 1 month time to rectify the same.
4. POWERGRID had informed that at Mehaboobnagar end, the Main-2 distance relay (ABB-REL
316) of RTPS-Mehaboobnagar line will be replaced within 2 to 3 days’ time. It was also
informed that the PLCC panels of the line would be replaced at both ends.
5. Committee checked the REF scheme for GT of Unit-7. REF scheme is provided for HV side of
GT. KPCL informed that 250MVA GT of Unit-7 was replaced by 315MVA during November-
2013. The implemented current setting for REF is 0.1 Ampere as suggested by OEM. KPCL
had informed that REF scheme will be checked during next shut down. D.R is not available to
validate the pickup current of REF relay.
3
ANNEXURE-VI
Swing of
conductors O/V St.2 trip 4
765 kV 400 kV
RTPS
GT Class B trip
GT
5
1 17:52
18:07 6
Z1 (R) Z1 (B)
U5 Mehabubnagar BTPS
POWERGRID, KPCL and KPTCL representatives briefed the committee about the above tripping:
1. 400kV Raichur-BTPS line tripped at 17:52 hrs due to B-phase fault. Line did not auto reclose
and tripped from both ends. It was informed by KPCL that Auto-reclose is implemented at
RTPS end and not commissioned at BTPS. It was informed that line did not auto reclose due
to auto reclose block command in distance relay which was due to fuse fail start/on
condition.
2. 765kV Raichur-Kurnool tripped due Y-B fault in line at 18:04:05 hrs. Same was validated with
DR of line.
3. As per FIR from POWERGRID, at 18:04:17 hrs, R-phase lightening arrestor of 400kV
RaichurGooty line-2 failed at Gooty end. Line tripped at both ends due to operation of
distance protection. From Gooty end D.R and PMU plots, it was observed that line tried to
auto reclose and as it was permanent fault due to LA failure, there was a 3 phase trip.
4
ANNEXURE-VI
needs further investigation. Both line-1&2 were holding from RTPS end. The reason for
nontransmission of direct trip to other end needs further investigation.
5. 400 kV Raichur-Mahboobnagar line tripped from Mahboobnagar end due to suspected mal-
operation of distance protection. Main-2 distance protection had sensed fault in R-phase,
Zone-1.
6. Unit#5 at RTPS tripped at 18:05 hrs due to operation of Class-B master trip relay. It was
informed that no class-B trip relay had initiated trip to the Master relay.
7. 220kV Sedam-Tandur and 220kV Regulapadu-Alipur lines had tripped at 18:12 hrs and 18:13
hrs due to transient fault in line. Auto reclose provision is not available for these lines.
2. 400kV Raichur-Gooty line-2 tripped due to failure of R-phase L.A at Raichur(PG). It was
informed that L.A broke down due to turbulent wind. The line protection tried auto reclose
once and gave a 3 phase trip due to permanent fault. Powergrid was asked to submit the
equipment failure report to CEA.
Committee had asked to monitor/check the transient behaviour of CVT and refer same to
OEM of CVT. 400kV RTPS-Raichur PG-1&2, 400kV Raichur-Gooty-1&2 are having same make
CVT’s. POWERGRID was asked to investigate reason for such high over voltage (phase to
earth) on healthy phases during R-phase fault in 400kV Raichur-Gooty line-2.
It was observed that Direct trip was not sent to remote end when over-voltage protection
had operated at Raichur(PG) end. It was informed by POWEGRID and KPCL that Channel-1&2
of both 400kV RTPS-Raichur PG-1&2 were having receive(Rx) fail alarm at RTPS end. It was
informed by KPCL that receive(Rx) fail alarm was persistent in PLCC Channel-1&2 of line-2
from couple of days before occurrence of fault. PLCC Channel-1&2 fail alarm for line-1
5
ANNEXURE-VI
appeared before tripping of 400kV RTPS-Raichur PG-1&2 lines. POWERGRID had informed
that frequency drift was being frequently observed in PLCC panels of RTPS-Raichur PG-1&2
lines, inspite of repeated tuning. Committee had recommended to replace the PLCC panels
at both ends at the earliest.
At Gooty end, Time synchronization of Gooty-1 feeder D.R was found to be out of sync with
GPS. Same was asked to be rectified.
4. For non-auto-reclosing of RTPS-BTPS line, it was informed that line did not auto reclose due
to auto reclose block command in distance relay at RTPS end which was due to fuse fail
start/on condition. Committee had asked to take up with OEM and check the configuration
for auto reclose in relay as block for auto reclose should not initiate with fuse fail On/ start.
KPCL had informed that the same will be checked and feedback regarding remedial action
will be given at the earliest. Committee had asked to implement auto reclose scheme at
BTPS end at the earliest. KPCL informed that they are taking up with OEM for the same. Also
Committee had asked that KPCL may ensure that auto-reclose is implemented when 400kV
RTPS-BTPS line is LILO’d at Yeramarus TPS. Committee had proposed for differential
protection for 400kV RTPS-Yeramarus-BTPS section. KPCL had informed that the LILO at
Yeramarus TPS is temporary and hence distance protection will be implemented with auto-
reclose.
5. For tripping of Unit-5 on operation of class-B protection it was observed that no class-B
initiation relay had operated as seen from sequence of events. The protection DC was
checked for earth fault. The DC source-1&2 were found to be in-order. Committee asked to
simulate the sequence of event for relays which trigger Class-B master relay and also check
up the pick-up voltage of Class-B Master trip relay. KPCL had informed that such tripping of
master trip relay without initiation from Class B relays was observed for the 1st time.
6. 220kV Sedam-Tandur line tripped at sedam end only on operation of backup protection. It
was informed that the back up relay had mal-operated. Committee had asked to check the
relay and if required replace the same.
7. 220kV Alipur-Regulapadu line tripped at Alipur end only on operation of distance protection.
It was informed that the line is radial from Alipur end. Committee had asked to submit the
D.R for the event to validate the tripping.
x------------------------------x------------------------------x-----------------------------x
6
ANNEXURE-VI
Annexure-I
7
ANNEXURE-VI
Annexure-I
8
ANNEXURE-VI
Annexure-II
9
10
SHAHPUR-2
SHAHPUR-1
ANNEXURE-VI