Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
What
Marcus Tower and David Bacarini (Department of Construction
Management, Curtin University of Technology, Perth, Western Australia
Commercial construction 30 91
Demographics
Civil Construction 3 9
Demographic details for the interviewees and
online respondents are set out in Tables 1-4, 33 100
which show:
• Job title – three job types dominated the Table 3 - Respondents - Expertise
sample: Managing Director, Estimator and Project values Nr %
Company Director
• Work experience in preparing tenders – Under $5m 11 34
the majority have over 15 years
experience $5m - $20m 7 21
• Types of project - nearly all work in
commercial construction over $20m 15 45
• Project values - respondents work on
33 100
wide range of project values
Table 4 - Respondents – Project value
Job Title Nr % Pricing for risk
Managing Director 14 43
The ten interviewees were asked: When
preparing tenders is pricing, for risk a separate
Estimator 7 22 process to preparing the base estimate?
(Online respondents were not asked this
Company Director 5 15 question). This study identified three
discernable approaches to determining how
Project Manager 2 5 risk is priced in r tenders – See Table 5. The
responses suggest there is no universally
Business Development Manager 1 3 accepted standard or default protocol in the
tendering process for pricing risk.
Estimating Manager 1 3
Risk Pricing Process Nr
Contracts Manager 1 3
Separate to preparing base estimate 4
Construction Director 1 3
Integral part of preparing base estimate 3
Chairman of Directors 1 3
during & after base estimate preparation 3
33 100
10
Table 1 - Respondents - Job Title
Table 5 – Risk Pricing Process
Four respondents indicated that pricing of risk
is an entirely separate process to preparing
the base estimate. Two respondents stated
that risk is not considered until the base
estimate has been prepared. In the other two
Years of experience Nr % organisations, risk is priced over the same
period of time in which the base estimate is
0-5 years 1 3 prepared, however it is usually conducted by
separate parties and both processes are
mutually exclusive. One respondent described The value of the project tends to have has a
this process: “Once we receive the project relationship with the number of people
documents two separate processes begin. involved in pricing for risk. Construction
The first process is that the estimator will work organisations tendering for projects less than
through the documents and drawings and $5 million may have as few as two people
price the quantifiable aspects of the project involved in the pricing of risk, the primary
using standard engineering principles. At the persons being the estimator and executive
same time other parties will identify and price manager. If necessary, other members of the
any commercial, technical, environmental or organisation such as additional executive
OS&H risk associated with the project. So managers, contract managers or site
although these activities happen in parallel managers may also be involved. As observed
they are separate processes”. by Akintoye & Fitzgerald (2000), it is unusual
for small firms to have a separate cost
In three organisations, pricing of risk occurs as
estimating department, which means that
an integral part of preparing the base estimate.
proprietors of the firm are usually more closely
The parties responsible for preparing the base
involved in the preparation of tenders and the
estimate price for risk as the estimate is
pricing of risk. In organisations bidding for
prepared and document any decisions or
projects between $5 million and $20 million,
assumptions, for review by management
respondents indicated there are generally
before the tender is submitted. As one
approximately four people involved in pricing
respondent explained: “The risk is priced into
risk - estimator, contract manager, site
the individual components of where we see the
manager and executive manager.
risk. When we add this contingency to each
sub trade it appears as a separate figure All organisations primarily tendering for
underneath the relevant sub trade within our projects in excess of $20 million described a
estimate… these amounts are then reviewed multi-stage process, consisting of a series of
by management before the tender is submitted meetings or brainstorming sessions attended
by members of the estimating team and
Three respondents indicated that the process
executive management throughout the tender
in their organisation is to price risk for all trade
preparation period. In the two largest firms
elements of the project as the base estimate is
surveyed, tenders exceeding a certain value
prepared, which is a common method of
go through an iterative process and the tender
pricing for risk (Ahmad & Minkarah 1988).
is reviewed several times by people with
Then risk associated with non-trade elements
increasingly higher levels of responsibility to
of the project, such as preliminaries and
ensure all risks have been adequately
contractual risk, is generally priced once the
accounted for. The process followed by one
base cost of the project has been established.
large commercial construction contractor is:
In summary, the responses indicate that there
1. The tender is prepared in a standard format
is no dominant process for pricing risk in
and the estimating team documents where
tenders; rather the process is contingent upon
and why they have included a contingency
organisational preference. These findings
for each trade.
contrast with the literature, which tends to
2. The base estimate and all documentation
emphasise that pricing for risks is a separate
are reviewed by State management.
process that follows on from preparing the
3. The tender is reviewed by an Internal
base estimate.
Credit Committee made up of the
Involvement in Pricing Risk Managing Directors of each state to ensure
due diligence has been followed and
Interviewees were asked: Who is involved in regional market conditions have been
the process of pricing for risk? (Online
accounted for.
respondents were not asked this question). All
respondents indicated that executive The responses suggest that the number and
management was ultimately responsible for type of organisational personnel involved in
determining the price of risk, which usually the pricing of risks in tenders tends to vary with
occurs during a tender review or adjudication project size. Generally, as project size
meeting. As Smith (1995) contends, tender increases so the number and level of
adjudication meetings are usually attended by personnel increases with more senior
those who have played a significant part in management involvement. This might be
preparing the estimate and representatives expected because greater project value
from senior management. Akintoye & demands more financial investment, which one
Fitzgerald (2000) also found that approval of could reasonably expect to stimulate more
tender sums for both small and large projects intensive consideration on the risk pricing
is undertaken by senior management. process in tenders.
Calculation of risk Three respondents prepare the base estimate
then an amount is added to cover risk in all
Interviewees were asked: “How do you
trade areas. One respondent highlighted this
calculate the amount to include for risk in your
process: “I always instruct my estimators to
tenders” (Online respondents were not asked
price the job in accordance with the trade
this question). Interestingly, with a small
prices we receive and their best guess for
sample of ten interviewees, five methods of
preliminaries and supervision. Then we will
pricing risk were identified (see Table 6), which
have a discussion with the Managing Director
indicates a wide range of possible approaches
to assess the project and identify and price
to calculating risks in tenders.
any extraneous factors when we are finalising
the tender…It may mean we add a lump sum
to cover all the risk items we have identified or
Methods of calculating risk Nr
we may just make a consideration in the
Micro 3 amount of margin we apply”. Another
respondent indicated they usually apply a
Macro 3 macro approach: “Generally we will look at a
past project and say that the contingency
Micro + Macro 2 percentage we used on that project was pretty
spot on so if we do the same for the new
Construction period 2 project we should be OK … of course we will
examine the documentation to identify any
Monte Carlo simulation 1 major differences between the projects and
make adjustments accordingly”. According to
11* Clark et al (1997), amounts to include for risk
are often applied as an across-the-board
*Note: 11 responses from 10 respondents. One mark-up typically derived from past experience
organisation uses two methods: Monte Carlo and historical data. By looking at the
simulation for projects over a certain value; micro
contingency percentage for past projects, risk
method for projects below this value
is priced from this benchmark.
Table 6 – Methods of calculating risk
Micro + Macro
Micro
Two respondents price some risk on a trade by
Three respondents price risk on a trade by trade or elemental basis as the base estimate
trade or elemental basis and a contingency is prepared and some risk is priced by making
amount is included in each trade area or a lump sum or percentage addition to the base
element as the base estimate is prepared. One estimate. One respondent explained the
respondent explained this process: “We price process: “For each cost centre we will look at
risk on a trade by trade basis as we receive past projects and consider any problems we
subcontractor and supplier prices … We have had with that area of work and include a
assess the suitability of the prices we receive lump sum for that trade area if we feel it is
and determine how much it should cost to do necessary for this job …as well as that, we
the work … We need to look at each area of may apply a percentage or lump sum amount
the work in isolation to assess our risk and for entire job if the project is particularly
make adjustments accordingly…the same also complex”.
applies for amounts we include for
preliminaries and supervision”. Several Construction Period
authors (e.g. Smith & Bohn 1999; Karlsen & Two respondents include for risk calculated on
Lereim 2005) suggest the calculation of a the duration of the construction period. From
different contingency amount for each major one respondent: “We loosely calculate the
cost element is a common approach to pricing amount to include based on the nominated
risk in tenders. Each major segment of the construction period. We look at several factors
estimate is classified in terms of its degree of to determine a rate per week which is then
uncertainty and attracts its own inclusion for multiplied by the number of weeks to calculate
risk (Bent & Humphreys 1996). This method of our contingency amount”. This approach
pricing risk is considered more reliable than support’s research by Skitmore & Wilcock
the simple application of one overall (1994) that found some contractors examine
percentage or lump sum addition to the base the construction period stated in the tender
estimate because it encourages close documents to assess the feasibility of that
examination of each cost area (Moselhi 1997). period and if necessary they make an
Macro allowance for extra time by multiplying the
weekly liquidated damages by the difference
between the number of weeks stated in the
tender documents and the period they that the amount included for risk is usually
consider reasonable and practical. based on subjective judgement.
Monte Carlo Simulation
Most significant risks
Monte Carlo simulation is a probabilistic
estimating technique that allows determination From the literature, 23 risks relevant to
of an overall contingency amount. One construction contractors were identified. All 33
respondent from a large organisation respondents were asked to indicate the 5 risks
explained the use Monte Carlo simulation to they felt were most significant when pricing for
assist in pricing risk: “We have tender risk in their tender - see table 7
standards which dictate that we use Monte
Carlo analysis for all projects valued over $100 Examining the five risks which contractors rate
million. However in the West Australian branch as the most significant, two discernable areas
we probably use it more along the lines of any of risk can be identified:
project worth over $10 million”. For projects
valued at less than $10 million, the respondent Risks Nr %
indicated they use the micro method because 1 Design or documentation errors 20 61
the systems they employ for Monte Carlo
Availability of labour, materials or
simulation are quite sophisticated and require 2
equipment
19 58
an external facilitator which is not warranted
on smaller projects. Previous studies have 3 Buildability issues 19 58
found it is uncommon for contracting 4 Subcontractor/supplier ability 16 48
organisations to employ statistical or
5 Incomplete design 14 42
mathematical methods to price risk in tenders
(e.g. Dulaimi & Shan 2002) and this is the 6 Possible estimation error 11 33
case in this research 7 Site access issues 8 24
Experience and intuition 8 Complexity of project team 8 24
Risks considered