BILL NO.

2 - ARCHITECTURAL WORKS
Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.1 INTERNAL WALLS AND PARTITIONS

CINEMA 1, 2, 3, 4, 5

Gypsum Partitions, constructing of metal studs,


channel section framing system with floor track
plugged and screwed to concrete slabs and ceiling ,
including any necessary stiffeners above the ceiling,
covered with wall lining with scrimmed and flush
joints, all as described

A 100mm thick gypsum partitions, constructed of 1,478 m2 13.136 65 8.538 100 13.136
metal stud 45x22x0.45mm; covered one side with
2 layers of 12mm thick gypsumboard lining; infill
with rockwool 50mm thick 60 Kg/m3 density +
chicken wiremesh; fixed to Hebel/Celcon walls;
(Type W1, W2, W5) (Dwg.No.4101, 4201, 4202)

B 100mm thick gypsum partitions, constructed of 585 m2 5.199 65 3.379 100 5.199
metal stud 45x22x0.45mm; covered one side with
2 layers of 12mm thick gypsumboard lining; infill
with rockwool 50mm thick 60 Kg/m3 density +
chicken wiremesh; fixed to Hebel/Celcon walls;
(Type W3A & W3B) (Dwg.No.4101, 4201, 4202)

OFFICE, LOCKER ROOM & SUPPORT ROOM

Gypsum Partitions, constructing of metal studs,


channel section framing system with floor track
plugged and screwed to concrete slabs and ceiling ,
including any necessary stiffeners above the ceiling,
covered with wall lining with scrimmed and flush
joints, all as described

C 100mm thick gypsum partitions, constructed of 66 m2 0.401 20 0.080 100 0.401


metal stud 76x25x4mm; covered both sides with
9mm thick gypsumboard lining (Dwg.No.6201)

HANDRAIL AT ENTRY GATE OF CINEMA

D Hand railing in black duco finish, fixed to gypsum 61 m 0.774 60 0.465 85 0.658
walls; constructed of 40mm diameter solid wood
handrail with pipe support; installed complete
including additional steel frames, steel ring, bolts,
base plate, anchors as described

2.1.1. INTERNAL WALLS AND PARTITIONS 19.51 12.46 19.39


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.2 TOILET CUBICLES

TOILET & JANITOR

Toilet cubicle; constructed of 18mm thick multiplex,


covered both sides with Taco HPL Natural Ordin TH
1250 FA; install complete including doors,
ironmongery, perimeter aluminium frames,
aluminium post and all necessary fixing accessories
as described (Dwg.No.6903, Section Elevation)

FEMALE TOILET

A Toilet partitions with doors; size 900x1850mm 7 No. 0.378 - -


high, above 150mm high aluminium post

B Toilet partitions; size 1800x2000mm high; ditto 6 No. 0.554 - -

MALE TOILET

C Toilet partitions with 2No. doors; size 3500x1850mm 1 No. 0.210 - -


high, above 150mm high aluminium post

D Toilet partitions with 2No. doors; size 1800x2000mm 1 No. 0.117 - -


high; ditto

E Toilet partitions; size 1200x2000mm high; ditto 2 No. 0.123 - -

F Toilet partitions; size 1800x2000mm high; ditto 1 No. 0.062 - -

G Wall hang urinoir partitions; size 400x1100mm high 7 No. 0.147 - -

2.1.2. TOILET CUBICLES 1.591 - -


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.3 INTERNAL DOORS

Supply, assemble, set and install Internal Doors;


install complete including ironmongery and all
necessary fixing accessories, grouting the frames in
cement mortar, easing openable parts, protecting
frames and cleaning on completion; as described

CINEMA 1, 2, 3, 4, 5

A Timber door and frames; door size 1000x2050x55mm 5 No. 0.771 65 0.501 85 0.655
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 2x12mm thick plywood; one side finish
with timber profil in duco finish and one side covered
with 3mm thick carpet; infill with 25mm thick,
45kg/m3 fiberglass wool insulation; all in duco paint
finish; including acrylic lighted push plate (Type DA-1)

B Supply & Install Ironmongery for Door Type DA-1 5 Set 0.581 65 0.378 85 0.494
- Pull handle "Dumont" - P 08.12 (AB) - 420mm
- Heavy duty hinges
- Door closer
- Acoustic sealant Raven RP 8Si, Rp.16Si, Rp.10si

C 2 hours fire rated steel door and frames; door size 5 No. 0.764 65 0.497 85 0.650
1000x2050x55mm thick; steel door frames size
50x150mm; door constructed of solid timber frames
covered both sides with 2x2mm thick steel plate and
2x12mm thick plywood; ditto (Type DE-1B)

D Supply & Install Ironmongery for Door Type DE-1B 5 Set 0.999 65 0.650 75 0.750
- Panic bar
- Heavy duty hinges
- Acoustic sealant Raven RP 8Si, Rp.16Si, Rp.10

OFFICE, LOCKER ROOM & SUPPORT ROOM

E Doble timber door and frames; door size 1 No. 0.181 70 0.127 85 0.154
1200x2050x40mm thick; 12mm thick multiplex
door frames size 50x84mm in oil paint finish; door
constructed of solid timber frames covered both
sides with 9mm thick multiplex; finish with Taco HPL
TH 003D, black doff; including viewing window from
5mm thick clear glass (Type WD-1A)

F Supply & Install Ironmongery for Door Type WD-1A 1 Set 0.070 70 0.049 85 0.059
- Pull handle and push plate
- Cylinder
- Lockcase
- Hinges
- Door closer
- Magnetic door stopper

Sub-Total Page No. 4/3 3.366 2.201 2.762


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.3 INTERNAL DOORS

Supply, assemble, set and install Internal Doors;


install complete including ironmongery and all
necessary fixing accessories, grouting the frames in
cement mortar, easing openable parts, protecting
frames and cleaning on completion; as described

OFFICE, LOCKER ROOM & SUPPORT ROOM

A Timber door and frames; door size 900x2050x40mm 4 No. 0.579 70 0.405 80 0.463
thick; 12mm thick multiplex door frames size
50x84mm in oil paint finish; door constructed of solid
timber frames covered both sides with 9mm thick
multiplex; finish with Taco HPL TH 003D, black doff;
including viewing window from 5mm thick clear glass
(Type WD-2B)

B Supply & Install Ironmongery for Door Type WD-2B 4 Set 0.210 70 0.147 80 0.168
- Pull handle and push plate
- Cylinder
- Lockcase
- Hinges
- Door closer
- Magnetic door stopper

C Timber door and frames; door size 800x2050x40mm 1 No. 0.139 70 0.098 80 0.112
thick; 12mm thick multiplex door frames size
50x84mm in oil paint finish; door constructed of solid
timber frames covered both sides with 9mm thick
multiplex; finish with Taco HPL TH 003D, black doff;
including timber louver window in paint finish (Type
WD-3A)

D Supply & Install Ironmongery for Door Type WD-3A 1 Set 0.030 70 0.021 80 0.024
- Lever handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

E Timber door and frames; door size 800x2050x40mm 3 No. 0.418 70 0.293 80 0.335
thick; 12mm thick multiplex door frames size
50x84mm in oil paint finish; door constructed of solid
timber frames covered both sides with 9mm thick
multiplex; finish with Taco HPL TH 003D, black doff;
including timber louver window in paint finish (Type
WD-3B)

F Supply & Install Ironmongery for Door Type WD-3B 3 Set 0.090 70 0.063 80 0.072
- Lever handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

Sub-Total Page No. 4/4 1.466 1.026 1.173


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.3 INTERNAL DOORS

Supply, assemble, set and install Internal Doors;


install complete including ironmongery and all
necessary fixing accessories, grouting the frames in
cement mortar, easing openable parts, protecting
frames and cleaning on completion; as described

OFFICE, LOCKER ROOM & SUPPORT ROOM

A Timber door and frames; door size 900x2050x55mm 3 No. 0.434 70 0.304 80 0.347
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 9mm thick multiplex; one side finish with
timber profil in duco finish and one side covered with
white HPL + push plate (Type D-5A)

B Supply & Install Ironmongery for Door Type D-5A 3 Set 0.090 70 0.063 80 0.072
- Handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

C Double timber door and frames; door size 2 No. 0.362 70 0.253 80 0.290
1600x2050x55mm thick; solid timber door frames
size 50x150mm; door constructed of solid timber
frames covered both sides with 9mm thick multiplex;
one side finish with timber profil in duco finish and
one side covered with white HPL + push plate (Type
D-5B)

D Supply & Install Ironmongery for Door Type D-5B 2 Set 0.100 70 0.070 80 0.080
- Handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

C Double timber door and frames; door size 1 No. 0.276 70 0.193 80 0.220
1600x2050x55mm thick; solid timber door frames
size 50x150mm; door constructed of solid timber
frames covered both sides with 9mm thick multiplex;
one side finish with timber profil in duco finish and
one side covered with white HPL + push plate (Type
D-5C)

D Supply & Install Ironmongery for Door Type D-5C 1 Set 0.050 70 0.035 80 0.040
- Handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

Sub-Total Page No. 4/5 1.312 0.918 1.049


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.3 INTERNAL DOORS

Supply, assemble, set and install Internal Doors;


install complete including ironmongery and all
necessary fixing accessories, grouting the frames in
cement mortar, easing openable parts, protecting
frames and cleaning on completion; as described

OFFICE, LOCKER ROOM & SUPPORT ROOM

A Timber door and frames; door size 900x2050x55mm 5 No. 0.104 70 0.073 80 0.083
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames; one side covered
with 9mm thick black carpet and one side finish with
timber profil in duco finish (Type D-5D)

Supply & Install Ironmongery for Door Type D-5D


B - Handle 5 Set inclde A
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

C Timber door and frames; door size 900x2050x55mm 2 No. 0.289 70 0.203 80 0.232
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 9mm thick multiplex; one side finish with
timber profil in duco finish and one side covered with
white HPL; including timber louver window in paint
finish and stainless steel kick plate (Type D-6A)

D Supply & Install Ironmongery for Door Type D-6A 2 Set 0.065 70 0.046 80 0.052
- Lever handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

E Timber door and frames; door size 900x2050x55mm 2 No. 0.265 70 0.185 80 0.212
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 9mm thick multiplex; one side finish with
timber profil in duco finish and one side covered with
white HPL; including timber louver window in paint
finish and stainless steel kick plate (Type D-6B)

F Supply & Install Ironmongery for Door Type D-6B 2 Set 0.060 70 0.042 80 0.048
- Handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

Sub-Total Page No. 4/6 0.783 0.55 0.63


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.2 INTERNAL DOORS

A Timber door and frames; door size 1000x2050x55mm 4 No. 0.617 70 0.432 80 0.493
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 2x12mm thick plywood; one side finish
with timber profil in dark brown melamik finish and
one side covered with 3mm thick carpet; infill with
25mm thick, 45kg/m3 fiberglass wool insulation;
all in duco paint finish; including acrylic lighted push
plate (Type DA-1A)

B Supply & Install Ironmongery for Door Type DA-1A 4 Set 0.465 70 0.325 80 0.372
- Pull handle "Dumont" - P 08.12 (AB) - 420mm
- Heavy duty hinges
- Door closer
- Acoustic sealant Raven RP 8Si, Rp.16Si, Rp.10

C Timber door and frames; door size 900x2050x55mm 1 No. 0.145 70 0.101 80 0.116
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 9mm thick multiplex; one side finish with
timber profil in melamik dark brown and one side
covered with black HPL; including timber louver window
in paintfinish and stainless steel kick plate (Type D-7B)

D Supply & Install Ironmongery for Door Type D-7B 1 Set 0.033 70 0.023 80 0.026
- Handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

E Timber door and frames; door size 800x2050x55mm 2 No. 0.279 70 0.195 80 0.223
thick; solid timber door frames size 50x150mm; door
constructed of solid timber frames covered both
sides with 9mm thick multiplex; both side finish with
melamik dark brown (Type D-8C)

F Supply & Install Ironmongery for Door Type D-8C 2 Set 0.060 70 0.042 80 0.048
- Handle
- Cylinder
- Lockcase
- Hinges
- Magnetic door stopper

Sub-Total Page No. 4/7 1.597 1.118 1.28


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

COLLECTION

Page No. 4/3 3.366 2.201 2.762

Page No. 4/4 1.466 1.026 1.173

Page No. 4/5 1.312 0.918 1.049

Page No. 4/6 0.783 0.548 0.627

Page No. 4/7 1.597 1.118 1.278

2.1.3. INTERNAL DOORS 8.525 5.812 6.889


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

2.1. INTERNAL DIVISIONS

2.1.3 INTERNAL WINDOWS

Supply, assemble, set and install Internal Windows;


install complete including all necessary fixing
accessories, grouting the frames in cement mortar,
easing openable parts, protecting frames and
cleaning on completion; as described

A Timber window and frames (Locket); window size 1 No. 0.046 65 0.030 80 0.037
600x1100x50mm thick; 12mm thick multiplex window
frames size 50x84mm in oil paint finish; with 5mm
thick clear glass; hanging table constructed of
12mm thick multiplex finish with Taco HPL TH 003D,
black doff (Type W-1)

B Instal Port Hole on every cinema; size 600mm wide 5 no 0.061 65 0.040 80 0.049

2.1.4. INTERNAL WINDOWS 0.107 0.069 0.085


Item BILL NO. 2 2.1. INTERNAL Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS DIVISIONS 18/10/2019 28/10/2019

COLLECTION

2.1.1. INTERNAL WALLS AND PARTITIONS 19.510 12.463 19.394

2.1.2. TOILET CUBICLES 1.591 - -

2.1.3. INTERNAL DOORS 8.525 5.812 6.889

2.1.4. INTERNAL WINDOWS 0.107 0.069 0.085

2.1. INTERNAL DIVISIONS 29.734 18.344 26.368


Item BILL NO. 2 2.2. FITTINGS Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS AND SUNDRIES 18/10/2019 28/10/2019

2.2. FITTINGS AND SUNDRIES

VANITY COUNTER

A Vanity counter, size 600mm wide, 4000mm long, 1 No. 0.405 - -


250mm thick; constructed from hollow structural
frames covered with 2x12mm thick multiplex, finish
with Corian solid surface, Rifinay Rf-009 (SF-02;
including extra over to form hole for 3No. wash
basin; install complete with expansion bolts and all
necessary fixing accessories, as described
(Female Toilet)

B Vanity counter, size 600mm wide, 4300mm long, 1 No. 0.438 - -


250mm thick; ditto (Male Toilet)

C Vanity counter, size 600mm wide, 900mm long, 2 No. 0.203 - -


250mm thick; ditto (Male & Female Toilet)

MIRROR

D Horizontal mirror; size 3300x900x50mm thick; 1 No. 0.089 - -


constructed of 5mm thick mirror on 12mm thick
plywood backing; perimeter timber frames size
30x50mm in duco black matt finish; install complete
including bracket and all necessary fixing
accessories as describe (Female)

E Horizontal mirror; size 3700x900x50mm thick; 1 No. 0.099 - -


ditto (Male Toilet)

2.2. FITTINGS AND SUNDRIES 1.234 - -


Item BILL NO. 2 2.2. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.1 FLOOR FINISHES

CINEMA 1, 2, 3, 4, 5

Screed cement and sand (1:3) mortar

A Screed, 40mm thick, 150mm wide to received 16 m 0.006 95 0.006 100 0.006
homogenous tiles treshold

B 5mm thick, to cover concrete step treads and risers 106 m2 0.099 95 0.094 100 0.099
surfaces

C Supply and Install 12mm thick plywood to receive 71 m2 0.230 95 0.219 100 0.230
underlayer and carpet at step stair

Supply and Install floor tiles bedded on screed (m.s),


jointed in cement and sand (1:3) and pointed in
coloured grouting

D Homogenous tiles treshold, size 150x600mm (HT-03) 16 m 0.076 95 0.072 100 0.076

Supply and Install Carpet, bonded with approved


adhesive; complete including all necessary fixing
accessories as described

E CP-07 Carpet Zebra abu-abu + underlayer 753 m2 (by other)

F CP-07 Carpet Zebra abu-abu 86 m2 (by other)

Supply and Install Vinyl floor tiles, bonded with


approved adhesive; complete including all necessary
fixing accessories as described; polished and
cleaned upon completion

G Vinyl tiles ; ex Maxwell/Amstrong; black (VN-01) 637 m2 3.958 95 3.760 100 3.958

H Vinyl tiles ; ex Maxwell/Amstrong; grey (VN-02) 177 m2 1.100 95 1.045 100 1.100

I PVC Step nosing 388 m 1.331 95 1.265 100 1.331

Prepare and apply acrylic emulsion paint finish as


described

J Black doff paint finish to step riser 250 m2 0.331 95 0.314 100 0.331

K Raise floor (various level thickness) with 68 m2 0.478 95 0.454 100 0.478
hebel/celcon in cement and sand mortar (1:4);
including bonding ties, as described
( step stair for single step & double step)

Sub-Total Page No. 2/12 7.609 7.228 7.609


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.1 FLOOR FINISHES

LOBBY AND CORRIDOR

Screed cement and sand (1:3) mortar

A Screed, 40mm thick, to receive, homogenous 657 m2 1.328 95 1.261 100 1.328
tiles and border

Supply and Install floor tiles bedded on screed (m.s),


jointed in cement and sand (1:3) and pointed in
coloured grouting

B Homogenous tiles, size 600x600mm (HT-05) 657 m2 7.010 95 6.660 100 7.010

OFFICE, LOCKER ROOM & SUPPORT ROOM

Screed cement and sand (1:3) mortar

C Screed, 44mm thick, to receive ceramic tiles 8 m2 0.016 95 0.015 100 0.016

D Screed, 40mm thick, 150mm wide to received 6 m 0.002 95 0.002 100 0.002
homogenous tiles treshold

Supply and Install floor tiles bedded on screed (m.s),


jointed in cement and sand (1:3) and pointed in
coloured grouting

F Ceramic tiles, size 300x300mm (TL-04) 230 m2 1.224 95 1.163 100 1.224

G Homogenous tiles treshold, size 150x600mm (HT-03) 6 m 0.028 95 0.027 100 0.028

Approved waterproofing coating system, applied


strictly in accordance with the manufacturer's
instruction; measured nett to : -

H Floor (Storage & Preproom) 10 m2 0.062 95 0.059 100 0.062

Sub-Total Page No. 4/13 9.670 9.187 9.670


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.1 FLOOR FINISHES

TOILET AND JANITOR

Approved waterproofing coating system, applied


strictly in accordance with the manufacturer's
instruction; measured nett to : -

A Floor (Toilet & Janitor) 117 m2 0.721 100 0.721 100 0.721

Screed cement and sand (1:3) mortar

B Screed, 40mm thick, to receive homogenous tiles 109 m2 0.220 100 0.220 100 0.220

C Screed, 44mm thick, to receive ceramic tiles 8 m2 0.016 100 0.016 100 0.016

Supply and Install floor tiles bedded on screed (m.s),


jointed in cement and sand (1:3) and pointed in
coloured grouting

D Floor tiles (toilet) 109 m2 1.069 - -

E Ceramic tiles, size 300x300mm (Janitor; TL-01) 8 m2 0.043 - -

Sub-Total Page No. 4/14 2.068 0.957 0.957

COLLECTION

Page No. 4/12 7.609 7.23 7.61

Page No. 4/13 9.670 9.19 9.67

Page No. 4/14 2.068 0.96 0.96

2.3.1. FLOOR FINISHES 19.35 17.37 18.24


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.2 WALL FINISHES

CINEMA 1, 2, 3, 4, 5

Acoustic Padded Walls; constructed of 15mm thick


plywood with PVC fastrack, covered with local
fabrics ex Ateja, infill with rockwool insulation 50mm
thick, 40Kg/m3 density+spindle pin; install complete
including all necessary fixing accessories as
described (Dwg.MCP-4201 and MCP-4202)

A 50mm thick, Padded Walls (Type WF-1) 895 m2 9.840 65 6.396 80 7.872

Acoustic Padded Walls; constructed of 15mm thick


plywood with PVC fastrack, covered with black
fabrics ex Ateja, infill with rockwool insulation 50mm
thick, 80Kg/m3 density+spindle pin; install complete
including all necessary fixing accessories as
described (Dwg.MCP-4201 and MCP-4202)

B 50mm thick, Padded Walls (Type WF-2) 458 m2 5.530 65 3.595 80 4.424

Supply and Install Carpet, bonded with approved


adhesive; complete including all necessary fixing
accessories as described

C Carpet fixed to walls, 2-3mm thick; colour solid 1,141 m2 2.373 65 1.543 80 1.899
black, ex Buana 604 (Type WF-3)

Sub-Total Page No. 4/15 17.744 11.533 14.195


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.2 WALL FINISHES

Plaster trowelled smooth in mortar utama, as


described

A 25mm thick, to Hebel/Celcon surfaces cinema wall 4,127 m2 9.699 95 9.214 100 9.699

B 25mm thick, to Hebel/Celcon surfaces service wall 1,240 m2 2.914 95 2.769 100 2.914

Prepare and apply acrylic emulsion paint finish as


described; ex ICI Catylac

C To walls, 1200mm high 195 m2 0.132 95 0.125 95 0.125

Prepare and apply weathershield paint finish as


described; ex Dulux

D To walls, 1500mm high 251 m2 0.356 95 0.338 95 0.338

Approved waterproofing coating system, applied


strictly in accordance with the manufacturer's
instruction; measured nett to : -

E Walls, 300mm high (Storage & Preproom) 13 m2 0.080 95 0.076 100 0.080

Sub-Total Page No. 4/16 13.181 12.522 13.157


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.2 WALL FINISHES

TOILET AND JANITOR

Approved waterproofing coating system, applied


strictly in accordance with the manufacturer's
instruction; measured nett to : -

A Walls, 300mm high (Toilet) 26 m2 0.160 100 0.160 100 0.160

B Walls, 1000mm high (Janitor) 16 m2 0.099 100 0.099 100 0.099

Backing cement and sand (1:3) mortar

C Backing, 40mm thick, to receive homogenous tiles 187 m2 0.394 100 0.394 100 0.394

D Backing, 44mm thick, to receive ceramic tiles 34 m2 0.072 100 0.072 100 0.072

Supply and Install wall tiles bedded on backing


(m.s), jointed in cement and sand (1:3) and pointed
in coloured grouting

E Homogenous tiles, size 600x600mm; 187 m2 1.894 - -

G Ditto, size 600x600mm; Black (Toilet; HT-03) 33 m2 0.334 - -

H Homogenous tiles capping, size 150x600mm; Black 10 m 0.018 - -


(Behind Wash Basin; HT-03)

I Ditto, size 200x600mm; Black (Behind WC and 25 m 0.061 - -


Urinoir; HT-03)

F Ceramic tiles, size 300x300mm (Janitor) 34 m2 0.189 - -

Sub-Total Page No. 4/17 3.221 0.724 0.724

COLLECTION

Page No. 4/15 17.744 11.533 14.195

Page No. 4/16 13.181 12.522 13.157

Page No. 4/17 3.221 0.724 0.724

2.3.2. WALL FINISHES 34.146 24.780 28.076


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

2.3. FINISHES UNDER COVER

2.3.3 CEILING FINISHES

CINEMA 1, 2, 3, 4, 5

Install Only suspended ceilings including suspension


framing, including galvanised wire hanger and
additional framing members to support diffusers, air
slots, light fitting , covered with ceiling lining , fixed with
scrimmed and flush joint, as described.

A Install Only 600x1200x9mm thick acoustic ceiling tiles e 335 m2 0.425 80 0.340 80 0.340
Amstrong; colour black with cross tee main tee
suspension system (CL-01)(Cinema)

Supply and install suspended ceilings including


suspension framing, including galvanised wire hanger
and additional framing members to support diffusers,
air slots, light fitting , covered with ceiling lining ,
fixed with scrimmed and flush joint, as described.

B 2X12mm thick, gypsumboard ceiling including 335 m2 3.050 80 2.440 100 3.050
suspension metal furing system + 50mm thick
rockwool insulation + chicken wire mesh
(1000mm above acoustic ceiling)(CL-01)

C 9mm thick, gypsumboard ceiling including suspension


metal furing system (CL-02)(Cinema Entry) 48 m2 0.178 80 0.142 100 0.178

Prepare and apply acrylic emulsion paint finish as


described; ex ICI

D To gypsumboard ceiling (CL-02)(Cinema Entry) 48 m2 0.039 80 0.031 80 0.031

GENERAL PUBLIC AREA & SERVICE

Supply and install suspended ceilings including


suspension framing, including galvanised wire hanger
and additional framing members to support diffusers,
air slots, light fitting , covered with ceiling lining ,
fixed with scrimmed and flush joint, as described.

E 9mm thick, gypsumboard ceiling including suspension 657 m2 2.431 - -


metal furing system (CL-02)

2.3.3. CEILING FINISHES 6.123 2.953 3.599


Item BILL NO. 2 2.3. FINISHES Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS UNDER COVER 18/10/2019 28/10/2019

COLLECTION

2.3.1. FLOOR FINISHES 19.348 17.372 18.236

2.3.2. WALL FINISHES 34.146 24.780 28.076

2.3.3. CEILING FINISHES 6.123 2.953 3.599

2.3. FINISHES UNDER COVER 59.616 45.105 49.911


Item BILL NO. 2 2.4. SANITARY Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS APPLIANCES 18/10/2019 28/10/2019

2.4. SANITARY APPLIANCES

Install Only the following sanitary appliances


complete including all necessary fixing accessories,
grouting all as described

A Water closet, complete set; ex TOTO 14 No. 0.170 70 0.119 70 0.119


- Bowl, CW705W/F
- Fittings, TX 901CV4N
- Flush valve, TV150NSV7J
- Vacum breaker for CW705
- Plastic seat and cover, TC 365
- Shower spray, TX4035MCRB
- Stop valve, TX277S

B Wastafel, complete set; ex TOTO 10 No. 0.041 70 0.028 70 0.028


- Under counteR lavatory, LW 651 J W/F
- Bracket, TSP0225W
- One push pop up waste w/ overflow hole, T6JV6
- P Trap for Lavatory, THX1A N

C Self closing Lavatory Faucet, complete set; 10 No. 0.047 70 0.033 70 0.033
ex TOTO, type TX126LE

D Urinal, complete set; ex TOTO 9 No. 0.061 70 0.043 70 0.043


- Urinal Body, U370M W/F
- Installation fittings,TX921UV2
- Urinal flush valve, TS60TS
- Mounting bolt, TU37D

E Soap dispenser, ex Krisbow; KW 2001473/2001474 6 No. 0.006 70 0.004 70 0.004

F Hand dryer, ex TOTO; TYC322W 4 No. 0.005 70 0.004 70 0.004

G Paper holder, ex TOTO; TX703AESV1 - Ego II 14 No. 0.019 70 0.013 70 0.013

H Double robe hook, ex TOTO; TX704AES - Ego II 14 No. 0.013 70 0.009 70 0.009

I Floor drain, ex TOTO; TX1BN 18 No. 0.034 70 0.024 70 0.024

J Faucet for Janitor 2 No. 0.003 70 0.002 70 0.002

2.4. SANITARY APPLIANCES 0.399 0.279 0.279


Item BILL NO. 2 2.5. FURNITURE Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS & FIXTURE 18/10/2019 28/10/2019

2.5. FURNITURE & FIXTURE

A Installation cinema chairs; including assesories and all 174 No. 0.296 - -
suporting as described; for cinema 1

B Ditto; for cinema 2 (26 Vip) 213 No. 0.362 - -


C Ditto; for cinema 3 (26 Vip) 213 No. 0.362 - -
D Ditto; for cinema 4 132 No. 0.225 - -
E Ditto; for cinema 5 132 No. 0.225 - -

F Supply and install speaker and sound system Support, 12 No. 0.088 - -
complete including hanger, bracket and all fixing
accessories for cinema 1; dwg 4302

G Ditto; for cinema 2 18 No. 0.131 - -


H Ditto; for cinema 3 18 No. 0.131 - -
I Ditto; for cinema 4 12 No. 0.088 - -
J Ditto; for cinema 5 12 No. 0.088 - -

K Masking cover as be back layer of screen item

2.5. FURNITURE & FIXTURE 1.996 - -


Item BILL NO. 2 SUMMARY Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS 18/10/2019 28/10/2019

2.6. Additional Volum

2.6.1 TOILET CUBICLES

TOILET & JANITOR

Toilet cubicle; constructed of 18mm thick multiplex,


covered both sides with Taco HPL Natural Ordin TH
1250 FA; install complete including doors,
ironmongery, perimeter aluminium frames,
aluminium post and all necessary fixing accessories
as described (Dwg.No.6903, Section Elevation)

FEMALE TOILET

A Toilet partitions with doors; size 900x1850mm 1 No. 0.054 - -


high, above 150mm high aluminium post

2.6. ADDITIONAL VOLUM 0.054 - -


Item BILL NO. 2 SUMMARY Qty Unit Progress, Progress,
Bobot % Nilai % Nilai %
No. ARCHITECTURAL WORKS 18/10/2019 28/10/2019

SUMMARY

2.1. INTERNAL DIVISIONS 29.734 18.344 26.368

2.2. FITTINGS AND SUNDRIES 1.234 - -

2.3. FINISHES UNDER COVER 59.616 45.105 49.911

2.4. SANITARY APPLIANCES 0.399 0.279 0.279

2.5. FURNITURE & FIXTURE 1.996 - -

2.6. ADDITIONAL VOLUM 0.054 - -

BILL NO. 2 - ARCHITECTURAL WORKS 93.032 63.728 76.558


BILL NO. 1 - PRELIMINARIES
Progress, Progress,
Ref.: BILL NO.1 - PRELIMINARIES Qty Unit Bobot % 18/10/2019 Nilai % 28/10/2019 Nilai %

Preliminaries | Constructor’s site overheads |


General Requirements

1.1 Construction management including site 1 Item 1.054 90 0.949 90 0.949


management staff and support labour
(Including allowance for restricted working hours,
overtime, weekly meetings, etc)

1.2 Temporary buildings 1 Item 0.790 90 0.711 90 0.711


(Including allowance for labour shelter, transportation,
storage, temporary toilet, protection of the works,
etc)

1.3 Securities 1 Item 0.253 90 0.227 90 0.227


(Including allowance for safeguarding the works, fire
protection, etc)

1.4 Other temporary facilities and services 1 Item


(Including allowance for providing water, lighting and
power)

1.5 Technology and communications: telephone, 1 Item 0.107 90 0.096 90 0.096


broadband, hardware, software

1.6 Constructor’s submissions, reports and as-built 1 Item 0.345 90 0.310 90 0.310
documentation
(Including allowance for providing tender
documentation fee, bid bond, programme of works,
weekly report, shop drawings, as-built drawings,
making good defects, etc)

1.7 Quality monitoring, recording and inspections 1 Item 0.239 90 0.215 90 0.215
(Including allowance for site visit, Samples and
Prototypes, Progress Photographs, etc)

1.8 Safety, health and environmental management 1 Item 0.746 90 0.671 90 0.671
(Including allowance for providing safety helmets,
protective clothing, boots for work people, removal
rubbish, cleanning up after completion, etc)

1.9 Insurances, bonds, guarantees and warranties 1 Item 0.431 90 0.388 90 0.388
(Including allowance for providing Surety Bond/
Performance Bond, Insurance of the Works (CAR)
and Public Liability Insurance (TPL), Insurance for
Workmen (BPJS), Advance Payment Bond, etc)

1.10 Mobilisation
( including cost for starting physical project, 1 Item
material delivery cost for temporary office &
storage, also equipment tool, safety equipment, etc)
1.11 Maintenance period
Maintenance cost for 6 month period, after 1st 1 Item 0.226 90 0.203 90 0.203
handover

1.12 De-Mobilisation
( All de-mobilisation cost coverage for all contractor 1 Item 0.223 90 0.201 90 0.201
equipment, asset & site staff after completion)
Progress, Progress,
Ref.: BILL NO.1 - PRELIMINARIES Qty Unit Bobot % 18/10/2019 Nilai % 28/10/2019 Nilai %

1.13 Responsibility toward Direct Suppliers


The term “Direct Supplier” shall mean a company,
firm or person supplying any goods, materials, plant or
services not forming part of the Works which has entered
into a separate contract with the Employer and is under
the coordination of the Contractor.
The Contractor’s Responsibility towards Direct Suppliers 1 Item 1.501 90 1.351 90 1.351
comprises of the following:
- Taking delivery at the “loading dock” as per instructions
of the Project Manager and subsequent unloading and
storing.
- Clearing away rubbish.
- Assembling, hoisting and putting in position as per instructions
of the Project Manager
- Protection throughout the construction period

Provision of storage facility at site for SBO (Supply


1.14
By Owner) items
The Contractor will provide storage facility at site to store
1 Item 1.054 90 0.949 90 0.949
the SBO (Supply By Owner) items

Carried to Final Summary 6.968 6.271 6.271


Part 5

FINAL SUMMARY
Item Progress, Progress,
FINAL SUMMARY Bobot ( % ) Keterangan
18/10/2019 28/10/2019
No.

PROGRESS ARCHITECTURAL WORKS

to the proposed

CINEMAXX PEJATEN VILLAGE

for

PT CINEMAXX GLOBAL PASIFIK

FINAL SUMMARY

BILL NO. 1 - PRELIMINARIES 6.968 6.27 6.27

BILL NO. 2 - ARCHITECTURAL WORKS 93.032 63.73 76.56

100 70.00 82.83

Jakarta, 30 Oktober 2019


PT. Cinemaxx Global Pasifik PT. Turner & Townsend PT.Puspa Graha Utama

IWAN SETIAWAN KUNTO AJI WIBOWO _______________ ________________


Project Manager Head of Project Manager Consultant Project Manager