Sei sulla pagina 1di 29

OPERATING &

MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

Project: RSUD Gorontalo Hospital


Order Nr: 5643

List of Contents
1.0 Description and Specification SAC

2.0 Transport and Installation Instructions SAC


2.1 Transport / Handling
2.2 Preparatory works
2.3 Base installation
2.4 Room ceiling / ceiling panelling
2.5 Fitting of OT-lamp
2.6 Final installation

3.0 Technical terms & handling Laminarizer SAC

4.0 Replacement of HEPA-Filters


4.1 General
4.2 Replacement of HEPA-Filters
4.3 Course of maintenance

5.0 Object Data/Technical data/Spare parts list


5.1 General
5.2 OT-Ceiling
5.3 HEPA-Filter
5.4 Laminarizer

6.0 Operating information lint separator louvers

7.0 Cleaning

8.0 Drawings

9.0 Order related documents

1
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

10.0 Factory Certificates

2
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

1. Description and Specification SAC

„Low Height Design“ for flat arrangement


OT-ceiling to provide a germ-free operating area, consisting of:

Ceiling housing
stainless steel casing, for easy installation of lamp base and/or ceiling stem.

Duct connections
Duct connection in galvanized steel, with universal connection flanges.

High efficiency HEPA-Filters


According to EN 1822, class „H13“ or >99.95 %; fixed at special holding frames,
adjustable clamping device and test groove for leak-proof testing of filter cells;
Frames from Aluminium profile.

Laminar air distributor


Large-area outlet as ceiling panels made of aluminium frames with tolerance
balancing, Laminarizer of not easily inflammable, disinfectant-proof white fabric with
excellent laminar air flow, without secondary air contamination. Disturbances of flow
pattern and contamination extensively avoided.
Easy reinstallation of air distributor frame without special tools for filter media
replacing and disinfection of housing and internal equipment.

OT-lamp duct
Centrically arranged for installation of the connection flanges and lead through the
lamp shaft,

3
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

2. Transport and Installation Instructions

2.1 Transport / Handling


2.1.1 The LC-S-ceiling is delivered on a wooden pallet, allowing horizontal or
vertical transport.
For the vertical handling on site by means of one or two lift trucks two square
timbers are mounted on the longitudinal side, so that the ceiling can also be
„slid“ over a smooth, solid floor.
In case of horizontal transport the fork lift truck/lifting device can be positioned
directly at the under screwed protective wooden plate.

2.1.2 For the transport into the room the min. door space should be 875/2000 mm.

2.1.3 The HEPA Filter are separately packaged in single cartons additional with
cover by foil

2.1.3 The Laminarizer segments and the required connecting screws are separately
packed in a box from galvanized steel

2.2 Preparatory works


2.2.1 Prior to the installation of the LC-S-ceiling the OT-lamp extension tube has to
be fitted; furthermore supply lines for electricity and gases, if needed, have to
be installed.

2.2.2 The carrying capacity of the raw ceiling and the selected fasteners/dowel must
be checked independently by others

2.2.3 The length of the OT-lamp extension tube must be sufficiently sized, allowing
the accommodation of all relevant flanges, connection and auxiliary
equipment in the lamp duct of the LC-S/H-ceiling.

Principally: bottom of lamp duct = 90 mm above bottom of LC-S-ceiling.

2.2.3 The OT lamp ceiling bolting must be absolutely stable and free of torsion.

4
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

2.3 Base installation


2.3.1 After the transport to the installation place (OT-room) all crate elements
(except the under screwed protective plate), including the cover plate for the
lamp duct (to be kept) can be removed.
Use suitable lifting devices (e.g. two lift trucks) to get the ceiling on mounting
level and align it to the room.

2.3.2 Special attention is to be paid to the alignment of the ceiling around the centre
of the OT-lamp. Open the inspection cover at the lamp duct and drop a
perpendicular from the centre to the bottom and carry out the exact alignment
of the ceiling.

2.3.3 For mounting are L-shaped supporting rails available, with a sufficient number
of connecting bore holes, dia. 10.5, spacing t = 300 mm, on both longitudinal
sides for the suspension of the ceiling.
Rox recommendation: Installation with thread rods, allowing exact height
alignment. Minimum number of rods is 6, size M10.

2.3.4 The connection to the raw ceiling to be carried out via a solid, traversable iron
fastening plate like drawing AH-145 (chapter 9), thus enabling the exact
alignment as described under 2.3.2 without any special demands to the
exactness of plug drill holes.
Due to the different site conditions this solution can only be regarded as a
proposal. Therefore, our supply does not include any mounting material.
Rox recommendation: Use fastening plate METU, type DB or equivalent

2.3.5 Split ceilings to be assembled and sealed at the proper installation place. The
consignment is comprising of the necessary connecting elements, sealant and
the separate assembly drawing.

2.3.6 Finally, connect the supply air ducts, lay and connect power supply of
servomotors (if any) as well as the piping of the differential pressure drop
control, see drawing AH-082 (chapter 9) For the time being, do not take off the
under screwed protective plate for the lamp duct. The revision hole in the plate
to be closed with the protective plate (2.3.1).

5
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

2.4 Fitting of OT-lamp


2.4.1 Remove the wooden protective plate under the supply air ceiling.

2.4.2 For site installation of lamp stem (arm) and for the maintenance at flanged
lamp support, the split cover of lamp duct can be taken off. Before reinserting
the cover the attached gasket must be glued carefully around the lamp stem,
see drawing AH-146 (chapter 8).

2.4.3 Not only the OP-lamp technic necessitates absolutely vibration-free and
perpendicular ceiling bolting of the lamp stem, but is of special importance for
a correct Laminarizer mounting as well and must be checked at that time.

2.4.4 Some OT-lamp manufacturers supply cover rosettes or ceiling plates for the
lamp stem (arm). These are not needed for and must not be fixed at the Rox
supply air ceiling.

2.5 Final installation


2.5.1 Prior to the final installation we recommend to carry out all site works in the
room to keep Laminarizer and filter absolutely clean.

2.5.2 The installation of the HEPA-Filters needs special care. Even the slightest
damage to the filter media during transport, unwrapping and installation
makes it unusable. When carrying or lifting the filter, only touch the outside
frame (For details see chapter 4.3 „Maintenance Instructions“.)

2.5.3 The sealed side of the HEPA-Filter to be fitted to the filter frame in the
housing. After alignment at the filter frame surface the filter is tensioned by
screwing the tension fasteners. The torque should be about 40-50 Nm.

2.5.4 The filter frame with groove and connecting nipples allows leak test according
to DIN 1946, the tubing of the test line should be made before closing of the
room ceiling on site.
Rox recommendation: Use flex. PVC tube clear, diameter inside 4,5 mm -
diameter outside 7,5 mm

2.5.5 Mounting split cover plate lamp duct as shown in drawing AH-190 (chapter 8).

2.5.6 Upper cover plate to be fixed with stand bolts on the cover plate lamp duct.
According AH-083,It 6.1-6.4 (chapter 8).

6
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

2.5.7 The laminarizers segments have to be fixed with the attached knurled screws
at the plenum of the ceiling. (Follow the marking for the position of the
laminarizers.)

Attention:

• laminarizers to be handled with care


• damaged fabric is unusable
• don’t work with open fire and/or pointed/sharp equipment
• see also chapter 3

2.5.8 Lower cover plate AH-083 It 6.5-6.9 (chapter 8) to be fixed below the
laminarizers round the lamp stem and to be bolted to the already mounted
upper cover plate Items 6.1-6.4. No gasket is needed between the lower
perforated plate inserts Item 6.8 and the lamp stem.

2.5.9 Mounting Air guidance curtain


First must be checked on site if the height between the OT lamp arms and the
lower edge of the supply air ceiling is sufficient to mount the curtain. If it is to
small the pane must be shorten.
Rox recommendation: Use therefore a hand circular saw with carbide tipped
sheet and smooth the sharp fraying with a fine venal or a knife
Mount the profiles and the pane as shown in drawing AH-814 (chapter 9) and
glue the corner careful from both sides.

7
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

3. Technical terms & handling laminarizer


3.1 The Laminarizer is a high quality special product developed by „NICKEL/ROX

3.2 The production and packing is carried out at constant climatic conditions
under clean room terms and is subject to stringent quality checks.

3.3 „Rox“’s Laminarizer serves for the generation of a stable laminar displacement
flow for clean and cleanest rooms and protects defined working areas against
particle contamination.

3.4 The application is designed for clean air only without chemical additives and is
restricted to the areas + 18 °C, 40 % r.H. to 24 °C, 60 % r.H.
Other climatic terms only in consultation with „Rox“. Prefiltering min. EU9 to
EU13 is urgently recommended.

3.5 The max. air velocity should not exceed 0.5 m/s.

3.6 The artificial or natural UV-irradiation should be avoided.

3.7 Transport and intermediate storage only in the original packing, handle
carefully and prudently to avoid damages.

3.8 In principle: damaged fabric makes the laminariser unusable.

3.9 Mounting and dismounting should be carried our by authorized employees


only.

3.10 The protective foil should be removed only immediately before mounting at the
proper place of installation.

3.11 Due to varying climatic conditions during transport and intermediate storage
laminarizers may show slight partial folds when unpacking which recede under
operating conditions.

3.12 Do not lean Laminarizer on or against the fabric.

3.13 Avoid contact with pointed, sharp or hot things.

3.14 Take care that during installation the unglued free overhanging fabric is
slightly projecting at the joints (patented density effect).

3.15 The prestressing of the fabric has been effected in such a way that under
operating conditions a light convexity of the fabric will result.

8
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

3.16.1 The fabric consists of Polyester. Do not use any aggressive substances for
cleaning and disinfection.
Rox recommendation: usable disinfectant see chapter 7.

3.17 Touch disinfected laminarizers only with sterile gloves

3.18 Defective or damaged laminarizers can be recovered in the works.

3.19 We cannot take over any warranty for damages caused by improper use and
application.

4. Replacement of HEPA-Filters

4.1 General
Based on common practice in general the replacement of HEPA-Filters in OT-
rooms does not automatically depend on the final pressure given by
manufacturer but hygienic and biological reasons need to be considered as
well.
In Germany samples were taken from the filter media and tested for bacteria.
Result of these tests was the requirement to replace HEPA-Filters after two or
up to maximum three years, independent from final pressure given by
manufacturer.
By our own experience the standard prefiltering (pre-filter EU 4 and bag-filter
EU 7) means a yearly increase of pressure drop of 30-50 Pa for the
HEPA-filter.
The nominal air flow normally causes a pressure drop of about 250 Pa for the
new filter. Based on this, replacement of the HEPA-Filter is necessary after
two (310-350 Pa) or three years (340-400 Pa).
Rox recommendation: replace the HEPA filter every two years, this saves
capital and operating costs (energy) and brings security to hygiene.

4.2 Replacement of HEPA Filters


Reinstallation and installation of Laminarizers and replacement of HEPA-
Filters should be carried out by two employees.
Please replace the HEPA-Filters at the recommended final pressure drop in
accordance with technical data sheet.
Replacement latest at air pressure drop of HEPA-Filters of 600 pa.

9
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

Ensure availability of correct replacement filters (data see spare parts list,
chapter 5).

4.3 Course of maintenance


4.3.1 For replacement take the new filter in its original, sealed packing to the OT
room.
4.3.2 Close the louver flaps in the duct system. Turn AC-system off and attach a
sign:
„MAINTENANCE WORKS - DO NOT SWITCH ON THE AC-SYSTEM“

4.3.3 Remove the Laminarizers


Laminarizer fixing device (knurling screws) can be unscrewed without any
tools.
Make sure that the polyester material (white fabric) will not get damaged.

4.3.4 Untighten the screws at the stand bolts of the filter-frame (tools: 13 mm).
4.3.5 Swing all turnbuckles to side
4.3.6 Lift HEPA-Filter with both hands and remove vertically downwards.
4.3.7 Clean the filter-frame on the SAC Housing (cleaning instruction see chapter 7)
4.3.8 Take new HEPA-Filter out of the packing (do not damage the packing, it will
be used later), and install in reverse order (see items 4.3.6 to 4.3.4).
Ensure tight fitting of filter at the fixation of housing frame.
4.3.9 Put dirty filter back into packing of spare filters and remove it.
4.3.10 Leak test with testing grooves:
Take off screw plug at measuring tube and connect leak test measuring
device airtight at measuring tube (see drawing AH-082 chapter 8).
The permissible air leak flow Vl in l/h must not be higher than the natural
leakage flow (penetration). The test pressure should at least be 2 kPa.
Take VL=permissible leak flow of each individual filter from technical data
sheet (see chapter 5.3)
Keep AC-system turned off during leak test. Each individual filter must be
leak-tested.
4.3.11 Dismount measuring device and put all screw caps back on the measuring
tubes.
4.3.12 Cleaning and disinfection of the Internal Plenum of the SAC (cleaning
instructions see chapter 7)
4.3.13 Cleaning and disinfection of Laminarizer (cleaning instructions see chapter 7)

10
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

4.3.14 Install Laminarizer fields, use sterile gloves. Note the safety instructions in
chapter 3

11
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

5. Order data/Technical data/Spare parts list

5.1 General
Order No 5643
Date of manufacturing Movember 2017
Brand: Rox, Germany
Type: LC-S 2424 4
Material casing: stainless steel
Material duct connection: galvanized steel
Material Laminarizer polyester

5.2 OT-Ceiling
Type LC-S 24244
Quantity 1
Drawing RH-933.1
Width: 2400 mm
Length: 2400 mm
Height: 400 mm
Weight: 290 kg
Diameter lamp shaft 125 mm
Number of duct connections: 2
Size of duct connections: 263*873
Number of duct connections 2
Size of duct connections 263*720

Supply air volume 5200 m³/h


Face velocity: 0,25 m/s

5.3 HEPA-Filter
Brand TROX
Type Mini Pleat F 781
Key No. MFP-H13-ALYx120/
PB/TGU/OTC
Material medium glass-fibre
Material frame aluminium
Sealing on the inlet side test groove
Grasp protection both sides
Class acc to EN 1822: H13
Degree of separation > 99,95 %
Temperature resistance up to 70°C

12
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

Quantity 2 2
Length mm 915 762
Width mm 305 305
Height mm 150 150
Weight kg 8,2 7,0
Air flow per filter nominal m³/h 1500 1265
Max. leak flow l/min 0,21 0,18
Pressure drop, clean Pa 250 250
Recommended final pressure Pa 600 600
Date of manufacturing 10/17 10/17

5.4 Laminarizer

Brand Nickel/Rox
Type LC
European Patent No 0 355 517 B1
Material frame Aluminium
Fibre Material PET, monofilament

Position 1
Quantity 4
Length 1107,5 mm
Width 1272,5 mm
Position
Quantity
Length
Width

13
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

6. not applicable

14
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

7. Cleaning/disinfection
Product to be cleaned Stainless steel housing of supply air ceiling
Aluminium- housing of HEPA filter
Proceccing Wipe disinfection using microfiber cloth
Intervals annually and after maintenance / repairs
Disinfectant PT B.Braun Medical Indonesia, Jakarta, Type Meliseptol rapid or equal
Remark Caution, avoid contact with disinfectant and acrylic curtain

Product to be cleaned Stainless steel housing and separator of fluff separator louvers

Proceccing Wipe disinfection using microfiber cloth


Intervals housing all 3 month and after maintenance / repairs
separator on top all 2 weeks
separator down daily
Disinfectant PT B.Braun Medical Indonesia, Jakarta, Type Meliseptol rapid or equal
Remark for cleaning the separator must not be removed from the mounting frame

Product to be cleaned Polyester- Laminarizer of supply air ceiling

Proceccing Spray disinfection with spray pump


disinfect Laminarizer from both sides when removed it
Use sterile gloves for remounting
Intervals annualy and after maintenance / repairs
Disinfectant PT B.Braun Medical Indonesia, Jakarta, Type Meliseptol rapid or equal
Remark Caution, avoid contact with disinfectant and acrylic curtain
Alternative Disinfectants shall be used only when they dry without
residue (risk of gluing the fine fabric pores, free of aldehyde and phenols)

Rox recommendation:
Please note the safety and handling guidelines of the manufacturer
Use only disinfectants that have been tested and approved by Rox

15
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

8. Drawings

AH-082 Arrangement of testing-nipples

AH-083 Cover Plate for lead through lamp stem

AH-144 Wooden crate

AH-145 Mounting with ceiling brackets

AH-146 Fitting of OT-lamp

AH-190 Cover plate lamp duct

16
4 3
5

pressure drop
HEPA-Filter

2
1
4
6 6 5

1 housing SAC 4 nipple for measurement pressure drop


2 duct connection 5 nipple for leaktesting sealing
3 HEPA filter 6 airtight cap

AH-082e
OT-supply air ceiling LC-S/LC-H 13.07.06
arrangement test nipple Stt

17
6.10
6.11

6.8

6.9

AH-083e
OT-supply air ceiling LC-S/LC-H
13.07.06
cover plate
for conduct lamp stem Stt

18
einteilig
one piece

H+150
L B
2400 1200
2400 1400
2400 1800
3000 1800 L+300 B+200

zweiteilig
two piece
19

H+150
L B
2400 2400
3000 2400
2800 2800
3000 3000 L+300 B/2+150

Vorschlagteile /crate elements


(bei Grundmontage entfernen /
remove by basic installation) OP-Zuluftdecke / Supply Air Ceiling LC-S AH-144
Schutzplatte /protective plate Transportverschlag 29.03.07
(bei Feinmontage entfernen /
remove by final installation) wodden crate for transport and handling Stt
cover bracket
e.g.Metu Typ DB

AH-145e
OT supply air ceiling AL-S/AL-H
Mounting with cover bracket

20
concrete ceiling

flange tube

lamp duct

laminarizer

stativ tube

lamp duct

revision plate

sealing

laminarizer

upper cover plate

lower cover plate

lamp stem

AH-146e
OT-supply air ceiling LC-H/LC-H 29.03.07
Fitting of OT-lamp
Stt

21
view from below view from top

2.4
2.2 2.2

2.4

2.1
2.3 2.2 2.4

Part list Mounting remark

2.1 lamp duct Cover plate 2.2 with opposite


2.2 cover lamp duct splitted plate 2.3 at the border from the
2.3 opposite plate 4 pcs lamp duct clamped, not srewed.
2.4 knurled srew Polyamid M In this way it is possible to make
a tolerance compensation to the
lamp stem of the operating light.

AH-190e
OT-supply air ceiling LC-S/LC-H
30.10.07
cover plate lamp duct
Stt

22
9. Order related documents

RH-933.1 OT-Supply-Air-Ceiling LC-S 24244

Data Sheet HEPA Filter

23
50
263

400
100
view from bottom
24

B = 2400 Technical data


Detail border-connection
lampcuct
supplyair volume: 5200 m³/h
outletvelocity: 0,25 m/s
2400/2400 23 filter equipment: 2 pcs 762x305x150
view from top
2 pcs 915x305x150
degree separation: H13
pressure drop ca. 250 Pa clean
wight ca. 290 kg
3
3 diameter lamp shaft 125 mm
design lamp shaft: centric
2460/2460
housing: two parts

150 873 720 150


RH-933.1
RSUD Gorontalo
L = 2400 Supply Air Ceiling 18.09.17
LC-S 24244 Stt
25
Mini pleat filter Series MFP
typ key filterpanels

MFP - H13 - ALY / 915x305x150 x120 / PB / TGU / OTC


1 2 3 4 5 6 7 8

1 Serie MFP mini pleat filter panel

2 Filterclass H13 HEPA according EN 1822

3 Housing ALY frame aluminium deep 150 mm

4 Measurement BxHxT 915x305x150 mm

5 FT 120 mm

6 Handle protection PB protection on both sides

7 Sealing TGU Testing sealing

8 Test at plant OTC oil thread testing

RH-808

26
OPERATING &
MAINTENANCE MANUAL
OT Supply Air Ceiling
Rox Type LC-S

10. Factory Certificate

Manufacturer's Declaration Rox

Manufacturer's Declaration (TROX)

Testing reports HEPA Filter (TROX)


see separate appendix

27
28
29

Potrebbero piacerti anche