Sei sulla pagina 1di 2

MANPOWR & MATERIAL CONSUMABLE UTILIZATION FOR 187-SS-03

S.NO DESCRIPTION MATERIAL CONSUMPTION EQUIPMENT/ VEHICLE MAN POWER MAN TOTAL Total Man
HOUR HOURS Hours
TIME : 6.00 Am - 02.45 Pm
Foreman 1 x 8Hr 8 hrs
Erection Engr 1 x 2Hr 2 hrs
1 Floor Mat Removing And * Mini van -2 hrs 44 Hrs
Marking location Fabrictors 1 x 8Hr 8 hrs
Driver 1 x 2Hr 2 hrs
Mat Techcian 1 x 8Hr 8 hrs
Helper 2x 8Hr 16 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Circullar Saw Wheel -2 No's Erection Engineer 1 x 2Hr 2 hrs
2 FLOOR PLATE MODIFICATION * Mini van -2 hrs 44 Hrs
WORK AG -5 Cutting wheel -5 nos Fabrictors 1 x 8Hr 8 hrs
AG-4 Grinding wheel -2 nos Helper 2 x 8Hr 16 hrs
Driver 1 x 2Hr 2 hrs
Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Disposal Coverall -3 No's Erection Engineer 1 x 2Hr 2 hrs
INSULATION REMOVING & Fabrictors 1 x 8Hr 8 hrs
3 FLOOR PLATE MODIFICATION Leather Cloves -3 No's * Mini van -2 hrs 44 Hrs
AG -5 Cutting wheel -5 nos Helper 1 x 8Hr 8 hrs
WORK
Insulator 1 x 8Hr 8 hrs
Driver 1 x 2Hr 2 hrs
Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Welding Electrode -(7018 _3.2)- 15 No's Erection Engineer 1 x 2Hr 2 hrs
C Channel -150 *75 - 5m Fabrictors 1 x 8Hr 8 hrs
4 FLOOR PLATE SUPPORT ANGLE AG -5 Cutting wheel -6 nos * Mini van -2 hrs 44 Hrs
MODIFCATION WORK AG-4 Cutting wheel -4 nos Helper 1 x 8Hr 8 hrs
AG-5 Grinding wheel -2 nos Welder 1 x 8Hr 8 hrs
Driver 1 x 2Hr 2 hrs
Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Welding Electrode -(7018 _3.2)- 15 No's Erection Engineer 1 x 2Hr 2 hrs
5 FLOOR PLATE SUPPORT ANGLE C Channel -150 *75 - 5m * Mini van -2 hrs
Fabrictors 1 x 8Hr 8 hrs
44 Hrs
MODIFCATION WORK AG -5 Cutting wheel -6 nos
AG-4 Cutting wheel -2 nos Helper 1 x 8Hr 8 hrs
AG-5 Grinding wheel -1 nos Welder 1 x 8Hr 8 hrs
Driver 1 x 2Hr 2 hrs
Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Welding Electrode -(7018 _3.2)- 15 No's Erection Engineer 1 x 2Hr 2 hrs
Angle -65*65 - 9m Fabrictors 1 x 8Hr 8 hrs
6 FLOOR PLATE SUPPORT ANGLE * Mini van -2 hrs 44 Hrs
MODIFCATION WORK AG -5 Cutting wheel -6 nos
AG-4 Cutting wheel -2 nos Helper 1 x 8Hr 8 hrs
AG-5 Grinding wheel -1 nos Welder 1 x 8Hr 8 hrs
Driver 1 x 2Hr 2 hrs
Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Red Primer - 0.5 Liter Foreman 1 x 8Hr 8 hrs
KNPC Final Paint - 0.5 Liter Erection Engineer 1 x 2 Hr 2 hrs
PAINT TOUCH UP WORK & Angle Brush _2 in -1 No's
7 Final Roller _2 In -1 No's * Mini van -2 hrs Painter 1 x 8Hr 8 hrs 44 Hrs
INSULATION INSTALLATION Driver 1 x 2Hr 2 hrs
Disposal Coverall -3 No's
Leather Cloves -3 No's Insulator 1 x 8Hr 8 hrs
Rock Wool Insulation -1 Role
Helper 2 x 8Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Welding Electrode -(7018 _3.2)- 25 No's
Angle -65*65 - 4m Erection Engineer 1 x 2Hr 2 hrs
Floor Plate -1*1.2m -1 No's
8 FLOOR PLATE MODIFICATION Floor plate -825*1.2 - 1No's * Mini van -2 hrs 44 Hrs
WORK Floor plate -885*1.2 - 1No's
AG -5 Cutting wheel -2 nos
AG-4 Cutting wheel -2 nos
AG-5 Grinding wheel -1 nos
Welding Electrode -(7018 _3.2)- 25 No's
Angle -65*65 - 4m
Floor Plate -1*1.2m -1 No's Fabrictors 1 x 8Hr 8 hrs
8 FLOOR PLATE MODIFICATION Floor plate -825*1.2 - 1No's * Mini van -2 hrs Helper 1 x 8Hr 8 hrs 44 Hrs
WORK Floor plate -885*1.2 - 1No's
AG -5 Cutting wheel -2 nos Welder 1 x 8Hr 8 hrs
AG-4 Cutting wheel -2 nos
AG-5 Grinding wheel -1 nos Driver 1 x 2Hr 2 hrs

Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Welding Electrode -(7018 _3.2)- 25 No's
Erection Engineer 1 x 2Hr 2 hrs
9 FLOOR PLATE MODIFICATION Angle -65*65 - 4m * Mini van -2 hrs 44 Hrs
WORK AG -5 Cutting wheel -2 nos Fabrictors 1 x 8Hr 8 hrs
AG-4 Cutting wheel -2 nos Helper 2 x 8Hr 16 hrs
AG-5 Grinding wheel -1 nos
Driver 1 x 2Hr 2 hrs
Fire watcher 1 x 8 Hr 8 hrs

TIME : 6.00 Am - 02.45 Pm


Foreman 1 x 8Hr 8 hrs
Red Primer - 0.5 Liter
KNPC Final Paint - 0.5 Liter Erection Engr 1 x 2Hr 2 hrs
10 Paint Touch Up & Floor Mat Final Roller _2 In -1 No's * Mini van -2 hrs Painter 1 x 8Hr 8 hrs 44 Hrs
Installation Work Floor Mat-2.5m *1.5 m-1 No's Mat Techcian 1 x 8Hr 8 hrs
Glue - 2 Lit
Driver 1 x 2Hr 2 hrs
Helper 2x 8Hr 16 hrs