Attachment 05

Project Responsibility Matrix


Scope of Work Responsibilities of the Contractor and other participants in the Wellhead Hook Up for
SCADA-2 Installation, Fabrication, Civil & Structural works are (but not necessarily limited to) the following:

Project Responsibility Items


A – Approve I – Information Contractor Company
P – Participate S - Support R - Responsibility

Project Management Related Items:


Regulatory approvals R S
Project execution management control processes R A
On-site coordination R A
Project controls, progress reports & tacking logs R A
Interface management R S
Procurement, Prefabrication, Construction,
Transportation, Installation & Commissioning
Procure all material for fabrication (other than Company supplied R A
material)
Procure all structural material R A
Procure all civil works materials R S
Procure pipe wrapping/ painting/ coating material R A
Safe storage of Company supplied valves, piping & fitting materials R A
Transportation of Free-Issued Materials to Contractor Work site R S
Transportation and mobilization of completed skid to Company R S
Work site
Supply all machinery, tools, equipment, consumables to fabricate R S
skid & mobilize skid to the well site.
Manage all aspects of subcontractor’s activities and works R I
Arrange transportation of all materials; required licenses; permits, R I
etc.
All Prefabrication works R A
All Mobilization works R A
Prepare project close out dossier R A
Provision of construction equipment fuel, maintenance and all R I
required consumables during fabrication and mobilization
Provision competent personnel to perform the Project in R A
accordance with the provisions of the Agreement
Logistics Related Items:
Mobilization of Contractor Personnel & Equipment for all phases R -
including clearances, wages & associated costs.
Establish independent self-sufficient construction support facilities - R -
accommodation, food & lodging during fabrication and mobilization
phase including provision of potable water, power and fuel.
Transportation Contractor Personnel to, from & within Kurdistan R -
Region of Iraq during mobilization, engineering, testing phase.