: QA/QC - MS -ATC-ME-003
Marassi Project,
1|Page
Document No. : QA/QC - MS -ATC-ME-003
QA/QC-MS-ATC-ME-003
INDEX
1. DESCRIPTION OF WORK.
2. SCOPE
3. References
4. Definitions
5. Responsibilities.
6. Equipment/ Tools
7. MATERIALS
8. Methodology
2|Page
Document No. : QA/QC - MS -ATC-ME-003
1. DESCRIPTION OF WORK:
This method statement is intended to inform the client how the work will be delivered in
the site associated with risks and the precautions to be taken during working
implementation. the purpose of this statement:
2. SCOPE:
The scope of this method statement covers a complete Installation of UPVC Drainage
Piping Under / Above Ground Network as per project's specifications and approved shop
drawings and approved materials.
3. References:
Bill of Quantities.
Technical Project's Specifications & Proper Approved Drawings
Approved Material Submittals.
Manufacturer's recommendations and instructions
Project’s Procedure Manuals and Quality Control Forms.
Project’s HSE Plan.
Relevant Codes & Standards (Egyptian code of practice, National plumbing code ).
4. Definitions:
ATC - Arabtec Construction
MS -Method Statement
QCP -Quality Control Plan
ITP -Inspection & Test plan
3|Page
Document No. : QA/QC - MS -ATC-ME-003
5.Responsibilities:
Project Manager
1. Ensure that all the preparation and application works are carried out according to
the contract, specification and with the approved drawings.
2. Ensure that the progressing of work is carried out according to the planned
program and as per the approved method of statement.
3. To ensure that all the equipment and materials required to execute the work are
available according to the planned construction program.
4. To Co-ordinate with the main contractor, MEP Coordinator and safety Officer, for
a safe and proper execution of the works.
QC/QA Engineer:
is responsible to ensure work has been done on the proper terms of project
specifications, approved inspection requests and under total Quality plan
recommendations in addition to offer the implemented works to the Consultant.
And ensure that the installation procedures are done as per Approved Method
Statement, shop drawing and Composite Trades Drawings.
Safety Supervisor
is responsible for ensuring that all Safety precautions are in place and all
individuals in working area are fulfilled with HSE required for work Issue.
Foreman
The foreman will carry out his duties by maintaining continuous coordination with
the site engineer on daily basis, and ensure proper distribution of the workforce in
the required and planned locations.
To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties properly.
4|Page
Document No. : QA/QC - MS -ATC-ME-003
To ensure in consultation with the site engineer that the manpower involved in the
works are moving as agreed and planned for the work.
To ensure that the daily work is progressing as planned and advice the site
engineer of any requirement for additional resources. To control disposal of waste
materials according to instructions received from the site engineer.
To ensure full coordination with the safety officer to maintain safe working and
proper housekeeping of the site, following the approved safety measures and
further ensure that all his working team are aware of the same to prevent accident
and losses.
To inform the site engineer and of the areas ready for inspection.
Store Keeper
To ensure that the material stored in ware house is safe and stored in a proper
way away of any damage
To ensure that the material shall not be handled without an official approval of
the site engineer.
To ensure that a daily material withdrawal Letter to the engineer responsible for it
6. Equipment/ Tools:
Hammers
Hand Tools
Pipe Cutter
• Water level
• Electrical drill
Step ladder.
7. MATERIALS:
The materials are predicated to be used:
5|Page
Document No. : QA/QC - MS -ATC-ME-003
All materials shall be submitted for approval prior to procurement and delivery to
site.
All related documents, such as delivery notes, country of origin, etc., shall be
available along with materials when delivered to site using MIR.
Care shall be taken to prevent the ingress of dirt or foreign objects into materials.
8. Methodology:
8.1 Preparation works
Measure length of pipe required, making due allowance for any pipe fittings
to be used. Cut the pipe to the measured length, ensuring that all burrs are
removed from the pipe.
Determine the position of the pipe supports and mark out on the concrete.
Drill the holes in the concrete using the appropriate size drill as
recommended by the anchor fixing manufacturer.
6|Page
Document No. : QA/QC - MS -ATC-ME-003
2. Use approved riser clamps, or friction clamps for this purpose. If vertical pipe is
required to stand free of any support by design specifications, or if no
structure is available for support and stability during construction,.
2.Support each length of pipe with an approved hanger located as close to the
joint as possible.
3. Always install hangers within 18 inches and more of the joint to maintain
correct system alignment and to prevent structural sagging.
5. The correct use of hangers shall provide proper piping system grade.
7. After Install vertical pipes Cover the vertical pipes with end cap cover.
Bedding layer under pipes to be formed and leveled as same slope and
checked by survey team as per approved shop drawing.
Install UPVC sewage system pipes in compliance with lines, grades,
location and slope as per approved drawings
Backfilling:
7|Page
Document No. : QA/QC - MS -ATC-ME-003
Position the pipe in the supports, check for correct level and position and,
if necessary, make adjustment on the pipe support.
Clean both the end of the pipe and inside the fitting.
Cut the pipe at right angles to the pipe axis using suitable pipe cuter.
Floor Cleanouts
Floor Drains
Each floor drain shall be of UPVC. Drain shall be the same material as the
pipe connected to it as per Specs Section (15412 ).
Roof Drains
Install roof drains at low points of roof areas, in accordance with the roof
membrane manufacturer's installation instructions so that no leakage occurs
between roof drain and adjoining roofing as per Specs Section (15412 ).
The Work shall consist of furnishing and installation of all hangers and
supports for Drainage piping Network as per Specs Section (15140 ).
Check levels of Fixture Units drain (wash basin, Water Closet, Kitchen Sink, etc.)
Test the piping of plumbing drainage and venting systems upon completion of
the rough piping installation. Tightly close all openings in the piping system, and
fill with water to the point of overflow, but not less than 3000 mm of head.
Water level shall not drop during the period from 15 minutes before the
inspection starts, through completion of the inspection. Inspect all joints for leaks
as per specs (section 15412).
Water of test may be used for cleaning branch after test finish by allowing water
to be escaped from downstream under its gravity pressure.
10.Manpower Requirement:
Copies of this method statement shall be issued to the following for Information /
Action:
( PM ) Project Manager
( CM ) Construction Manager (MEP)
SENIOR PLUMBING SITE ENGINEER
PLUMBING SITE ENGINEER
Safety Engineer
QA/QC Engineer
FOREMEN
LABOUR
STORE KEEPER
9|Page
Document No. : QA/QC - MS -ATC-ME-003
10 | P a g e