Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
MARINE OPERATIONS
CUFtRl3NT BOOKLETS
JANUARY 2000
PART 0 INTRODUCTION
Chapter 1 User Information Amendments and Indexes ........................................J a n 1996
PART 1 GErnRAL
Chapter 1 Warranty Surveys..................................................................................J a n 1996
Chapter 2 Planning of Operations ......................................................................... J a n 1996
Chapter 3 Design h a d s ........................................................................................
a n 1996
Chapter 4 Structural Design ..................................................................................
J a n 1996
DET NORSKEVERITAS
. .
Veritasveien 1. N-1322 Hgvik. Norway Tel. +47 67 57 99 00. Fax. +47 67 57 99 1 1
DNV - RULESFOR PLANNING AND EXECUTIONOF -E
OPERATIONS- 1996 REVISION
Please note the following clarifications/corrections to the DNV Rules for Planning and Execution of
Marine Operations.
m.1 C H .DESIGN
~ LOADS IlXM 2.3.3.5
d = 1.5 - (112j)
The last part of the equation may be misunderstood and is more correctly expressed as;
d = 1.5 - 1/(2j)
PT.2 C H .SUB
~ SEA OPERATIONS, 2.3.1
PARAGRAPH
i.e. the hydrodynamic force is a function of slamming, dynamic effects of buoyancy, drag and inertia
effects.
For combining load components into load cases the following combination is acceptable to DNV;
Formula 2-8 is a curve fitted to numerically calculated slamming velocities. The curve was initially
intended for cases with relatively large crane hoisting~loweringvelocities. For lowering velocities
close to zero eq. 2-8 will estimate too high slamming velocities. The asymptote value for v, with
zero lowering velocities may be taken as;
For lowering velocities close to zero, v, may be taken as the least of estimates according to eq 2-8
and the asymptote above.
This item estimate load components caused by varying buoyancy and dynamics due to waves. A
logical error (mass included twice through equations 2-4 and 2-9) resulted in unrealistic high load
estimates. It has also been found that certain combinations of crane stiffness, object geometry and
"massproperties will provide unrealistic high loads. The item is therefore revised. The revised item
is stated below;
where
The Fpneed not be taken greater than 0.5 times the total
buoyancy of the handled object.
PT.2 CH.6 SUB SEAOPERATIONS
ITEM 2.4.2.4
a, = 3.le -0.32dI H,
In order to obtain correct estimates of the DAF according to eq. 2-15, equatian 2-22 should read;
The static component would otherwise be included twice when estimating the DAF.
Please note the following corrections to the DNV Rules for Planning and Execution of Marine
Operations:
3.1.2 Main Towing Line 3.1.2.2 The main towing line should for unrestricted
towing have a len,$h not less than;
3.1.2.1 For unrestricted towing, the rninimum
breaking load W L ) ,in tonnes, of the main and spare bowline = 2000 BPIMBLwtinc
towing lines shall be taken according to Eq. 3-1.
Eq. 3-2
where
3.0 BP BP 1 40
- (3.64 - 0.8 BPl50) BP 40 < BP < 90 bowfine
: minimum tow line len,d (m) "
-
= 0.75(1 yL)
Eq. 3-4
where
yn: tug efficiency factor
YL : tug len,g.h factor, y~= (1 - ~ 1 4 5 ) ~
L: tug len,* (m), not to be taken more than 45 m
Guidance Note
For tugs performing weather routed towing or towing in
protected areaslharbours, a tug efficiency factor according to
Eq. 3-5 below may be used instead of Eq.3-4.
- -
YTE = (0.875 ~ ~ / 8 ) (YL1 * Yw)
Eq. 3 5
where
L: length of tug (m), not to be taken more than 45 m
YL : -
tug length factor, YL = (1 ~ 4 5 ) ~
Yw : wave factor, yw = Hd5
Hs : limiting significant wave height (m)for the weather
routed towing operation; or the probable significant
wave height in the protected arealharbour. Hs is not
to be taken less than 1 meter and not more than 5
meter in this equation.
- ITEM3.3.2.7
PT.2 C H . TOWING
~
Nm OPERATIONS
PART 0 : INTRODUCTION
PART 0 c m1
USER INFO NTS AND INDEXES
JANUARY 1996
SECTIONS
A
2 . AMENDMENTS AND CORRECTIONS ......8
2.1 INTRODUCTION ................................... 8
2.1.1 General ......................................... 8
8. ODUCTION TO USERS
background data to support such approach could however riot be 1.2.2.2 The user agrees that application of these Rules
found DNV will seek to include an overall probability of failure as shall be at the users sole risk, and accept by use that
soon as reliable statistical data of operational records are available DNV's liability for claims arising from omissions, faults
An probability of total loss equal to, or better than 111000 per
operation will then be aimed at or inconsistencies in these Rules shall be limited to the
amount charged for these Rules.
1.1.2.3 Recommendations and guidance are as far as
possible given based on statistical methods. Where 1.2.2.3 DNV disclaims any liability and/or
relevant statistical data have not been available, or responsibility resulting from any or all deviations from
recommendations based on a statistical approach have given requirements and/or recommendations unless such
not been developed, given requirements are based on deviations have been approved by DNV beforehand.
recognised codes, standards and "industry practice".
"Industry practice" is defined as methods and practice
commonly accepted and recognised by the branch.
Rules for Marine Operations January 1996
Pt.0 Ch.1 User Information Amendments and Indexes Paee 5 of 22
1.3.4.1 This part give specific requirements for 1.3.6.3 Cross references are made according to the
different types of marine operations. Requirements in following format;
Pt. 2 are based on the general requirements in Pt. I .
- between chapters: see Pt. 1 Ch. 1 Sec. I . 1
References back to this part are extensively used.
- within a chapter: see also 1.1.1.
1.3.7.1 Guidance notes are included where additional 1.3.13.1 A software package supporting formulas and
advice, formulas, experience, practises, explanations etc. methods specified in these Rules is planned. Users of
may be applicable. these Rules will be notified when this package is
released, and informed of subsequent updates.
1.3.8 Definitions
1.3.8.1 Definition of terms are included in this chapter. 1.4 GUIDELINES AND NOTES
Definitions of terms considered to be of particular
importance for the respective chapters are repeated in
1.4.1 General
these.
1.4.1.1 In an effort to aid the parties involved in marine
1.3.8.2 All symbols used within a chapter are listed in a engineering and classification of ships, DNV has issued
symbol list at the beginning of each chapter. Guidelines and Classification Notes giving practical
information regarding classification and other relevant
regulations as well as guidance in new fields of
1.3.9 Units
technology. These publications are available on a
1.3.9.1 These Rules generally uses SI-units. When purchase or subscription basis.
other units are used these are particularly stated.
1.4.2 Guidelines
1.3.10 Indexes
P.4.2,l Guidelines are publications which give
1.3.10.1 A systematic and an alphabetical master index information and advice on technical and formal matters
have been prepared for the complete Rules. These are related to the design, building, operation, maintenance
presented in Sec. 4 and 5. and repair of vessels and other objects, as well as the
services rendered by the Society in this connection.
1.3.10.2 The systematic index gives references to Aspects concerning classification may be included in the
sections and subsections within each partlchapter publication.
whereas the alphabetic index gives references to the page A list of Guidelines that may be relevant for marine
number within the appropriate partlchapter, e.g. Pt. 1 operations is given in Table 1.2.
Ch. 1 pl. Note that pages in each chapter are numbered
from 1.
1.4.3 Classification Notes
1.3.11 Tables of contents 1.4.3.1 Classification Notes are publications which give
practical information on engineeringldesign aspects in
1.3.11.1 'Two tables of contents levels are included at general, and on classification of ships and other objects
the beginning of each chapter. A table of sections on the in particular. Examples of design solutions, calculation
front page of the chapter, providing the starting page methods specifications of test procedures, as well as
number of each section, and a table of content including acceptable repair methods for some components are
sections, subsections and paragraphs. given as interpretations of the more general rule
requirements.
1.3.11.2 List of figures and tables in <he chapter are
included after the table of contents. A list of Classification Notes that may be relevant for
marine operations is given in T d l e 1.3.
-
Table 1.3 Classification Notes
-
Table 1.4 Certification Notes
I No. I Title I
Series No. 2 Approval Schemes
2.5 Certification of Offshore Mooring Steel Wire
Rope (May 1995).
2.6 Certification of Offshore Mooring Chain (August
January 1996 Rules for Marine Operations
Page-
- 8 of 22 R.0 Ch. l User Information Amendments and Indexes
2.1 INTRODUCTION
2.1.1 General
2.2.1 General
Heavy 1 1
3 carrier transports :Transfer at sea from one object from one support condition to another.
location to another of an object by a heavy lift carrier.
Long term :A period of time where environmental
Independent third party verij?cation :Verification conditions are non-stationary.
activities performed by a body independent from
Marine Operation Declaration : A written confirmation
company and contractor.
stating compliance with this Standard of equipment,
Inshore towing :Towing in sheltered waters. temporary and permanent structures, handled object,
procedure, preparations etc,
Insurer :The party who is providing insurance cover for
the marine operation. Mating :The activities necessary to join two floating
objects. The floating objects may be supported by
bttemal seafastening :Securing of loose items within the barges, pontoons, etc.
handled object.
Meatz wind veiocity : The average wind velocity within
Launching :An activity comprise cutting of seafastening a specified time interval.
of an object resting on a specially equipped launch
barge, the object's slide down the skid beams on the Multi barge towing :Transfer at sea from one location to
barge and diving into the water until the object is free another of an object resting on two or more barges by
floating. use of tugs.
Lift 0 8 : The activities necessary to transfer an object Natural period :?'he period of which the vessel will
positioned on land or sea bed supports into a floating move in still water.
condition.
Object: 'The object handled during the marine operation,
Liji on :A reversed lift off. 1.e. the activities necessary typically a module, deck structure, jacket, sub sea
to transfer an floating object onto landlsea bed supports. structure, pipes, other equipment.
Lift points :The attachment points for slings on the Offshore towing :Towing in waters more than 12
lifted object. Lift point are normally designed as nautical miles of the coast line.
padeyes or padearltrunnions.
Operation :A planned marine operation, with defined
Lijied object :A structure or parts thereof subjected to start- and termination point.
lifting.
Operation criteria :The acceptance criteria for start of
Lifting :The activities necessary to lift or assist an object the planned operation.
by crane or cranes.
Operation reference period : The time period to be used
Lijling equipment :Temporary installed equipment such in establishing the characteristic value of a random
as slings, shackles, sheaves, spreader beams or frames, parameter used as the basis for the design.
necessary to perform the lift.
Operator/Company :The party representing the
Limit state : A state in which a structure ceases to fulfil owner(s).
the function, or to satisfy the conditions, for which it
Padear :Lifting point on a structure consisting of a
was designed.
tubular member with a stopping piate at the end. The
Load : Any action causing stress or strain in the sling/grommet may be laid around the tubular member
structure. such that a shackle is not needed.
Load co@cient : Coefficient by which the Padeye :Lift point on a structure consisting of a steel
characteristic load is multiplied to obtain the design main plate with a matched hole for the shackle pin. The
load. hole may be reinforced by a plate (cheek plate) on each
side.
Load g e c t : Effect of load on the structure, such as
stresses and stress resultants (internal forces and Piling :The activities necessary to secure an object to
moments), strain, deflections and deformations. the sea bottom by driving piles into the sea bottom.
Load in :The activities necessary to transfer an object Plate shackle :A shackle where the bow is replaced by
from a vessel to land, i.e. a reversed load out. two steel plates and an extra pin.
Load out :The activities necessary to transfer an object Positioning :The activities necessary to position an
from land onto a vessel by a horizontal movement of the object at a certain predetermined location.
object.
Recognised code or standard : National or international,
Load tran.$er :The activities necessary to transfer an code or standard, which is recogniserl by the majority of
Rules for Marine Operations
Pt.0 Ch.1 User Information Amendments and hdexes
4. Stability Requirements
Part 1Chapter 1 4.1 General Requirements
WARRANTY SURVEYS 4.2 Barge Transports
January 1996 4.3 Self Floating Structures
4.4 Load Out Operations
Principles of Insurance Warranty Surveys 4.5 Other Vessel
1.
1.1 Introduction
1.2 Basic Definitions 5. Systems And Equipment
1.3 Marine Insurance Act 5.1 System Design
1.4 Purpose of Insurance Warranty Surveys 5.2 Vessels And Barges
1.5 Marine Operation Declarations 5.3 Mooring Systems
1.6 Breach of Warranty 5.4 Guiding And Positioning Systems
$ Part 1Chapter 3
DESIGN LOADS Load Out
January 1996 General
Loads
1. Introduction Loadcases and Analysis Of Forces
1.1 General Structures and Soil
i .2 Definitions Systems and Equipment
Load Out Vessel
2. Environmental Conditions Operational Aspects
2.1 General Special Case
2.2 Wind Conditions
2.3 Wave Conditions Float Out
2.4 Current And Tide Conditions Introduction
Loads
Loads and Load Effects Loadcases and Analysis Of Forces
Load Categories Structures
Load Analysis Systems and Equipment
Wave Loads Operational Aspects
Wind And Current Loads
Static Loads Lift Off
Hydrostatic Loads General
Restrain Loads Loads
Accidental Loads Loadcases and Analysis Of Forces
Structures
Systems and Equipment
Lift Off Vessels
Part 1 Chapter 4
Operational Aspects
STRUCTURAL DESIGN
Januar 1996
Mating
Introduction
1. Introduction
Loads
1.1 General
Loadcases and Analysis Of Forces
1.2 Definition
Structures
Systems and Equipment
2. Design Principles
Operational Aspects
2.1 Design Considerations
2.2 Load Cases
Construction Afloat
2.3 Design Analysis and Criteria
Introduction
Loads
3. Design Verification
Stability Afloat
3.1 Verification Methods
Mooring
3.2 Strength Verification
Operational Aspects
3.3 Testing
1. Introduction
Part 2 Chapter 1
1.1 General
LOAD TRANSFER OPERATIONS
1.2 Definitions
January 1996
2. Planning and Preparations
1. Introduction 2.1 Planning
1.1 General 2.2 Design
1.2 Design Phase 2.3 Structural Design Calculations
-
&
1.3 Operational Aspects
January 1996 Rules for Marine Operations
-Page 14 of 22 -
Pt.0 Ch.1 User Information Amendments and Indexes
a-
Part 2 Chapter 6
SUB SEA OPERATIONS
January 1996
1. Introduction
1.1 General
1.2 Definitions
1.3 Planning
1.4 Loads
1.5 Structures
Design Loads
General
Crane Tip Motions
Hydrodynamic Forces when Lowered through
Water Surface
Hydrodynamic Forces on Submerged Objects
Snap Forces in Hoisting Line
Other Loads
Soil Capacities
On Bottom Stability
Pull Out Forces
4. Operational Aspects
4.1 General
4.2 Systems
4.3 Installation Aids
4.4 Rov Operations
4.5 Tie-In Operations
4.6 Bundle Operations
Part 2 Chapter 7
TRANSIT Ah!Ll ANDSITIONING OF MOBILE
OFFSHORE UNITS
HOLD
January 1996 Rdes for Marine Operations
Page 16 of 22 Pt.0 Ch.1 User Information Amendments and Indexes
Documentation
Launch
Grillage and seahstening accidental flooding .....................................Pt.2 Ch.4 p9
load out ............................................Pt.2 Ch . 1 p14
Purpose Pt.2 Ch.2 p6
. anti self-launch devices ............................. Pt.2 Ch.4 p9
barge positioning ................................ Pt.2 Ch.4 pl 1
set down procedure ................................. Pt.2 Ch . 1 p 13 buoyancy tank attachments .................... Pt.2 Ch.4 p9
Grouting ........................................ Pt 2 Ch.4 p18 buoyancy tank testing ............................ Pt.2 Ch.4 p l l
equipment ...........................................Pt.2 Ch.4 p 17 buoyancy tanks ...................... . . . . . . . . . . . . . . Pt.2 Ch.4 p9
operational criteria ...............................Pt.2 Ch.4 p18 cutting facilities .................................... Pt"2 Ch.4 p10
Guiding systems
. .
fixtion .................................. :................Pt.2 Ch.4 p10
design requirements ................................ Pt . 1 Ch.2 p22 general . ..................................................
. . . Pt.2 Ch.4 p8
loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .P t 1 Ch.2 p22 launch uutiation ....................................... Pt.2 Ch.4 p8
positioning line requirements ................... Pt .1 Ch.2 p23 launch systems .......................................... Pt.2 Ch.4 p10
strength ......................................... Pt .1 Ch.2 p23 loads and loadcases ...................................Pt.2 Ch.4 p8
. .
monltomg ............................................ Pt.2 Ch.4 p l l
object Geeboard ........................................ Pt"2 Ch.4 p9
object strength ........................
........ ...... Pt.2 Ch.4 p9
January 1996 Rules for Marine Operations
Page 18 of 22 Pt.0 Ch.1 User Information Amendments and Indexes
vessels ...............................................Pt 2 Ch . 1 p2 1
Lift points
..............................................
Pt.2Ch.5 p17
Lifting
bumpers and guides ...............................Pt.2 Ch.5 p17
clearances ................................... Pt.2 Ch.5 p18
Pt.1 Ch.1 p l l
................ Pt.1 Ch.1 p5
........
breach of warranty .............. Pt 1 Ch .1 p l 1. Pt .1 Ch 1 p6
document review
duties of assured
duties of insurer
Weather forecast
acceptance criteria ...................................Pt .1 Ch.2 p l 1
assessment ..................................... Pt . 1 Ch.2 pl 1
levels... . . . ..................................P t . l C h . 2 ~ 1 1
procedure Pt.1 Ch.2 p l l
requirements .......................................... Pt-1 Ch.2 p l 1
Weather restricted operations ...................... Pt. 1 Ch.2 p10
operation vs . design criteria ....................Pt .1 Ch.2 p10
Weighmg ............................................... Pt.1 Ch.3 p16
Weight ......................, ..........................Pt.1 Ch.3 p16
Pt . 1 Ch.3 p l 5
Wind loads ...................................................
Wind velocity
unrestricted operations ..........."..-.-"..... Pt . 1 Ch.3 p7
weather restricted operations ..................... Pt .1 Ch.3 p7
NNE OPEUTIONS
PART 1 : GENERAL REQUIREMENTS
PART 1 CHAPIER 1
W NTY SU3RWYS
JANUARY 1996
SECTIONS
1.2.3 Marine operations 1.3.1.2 The above terms of reference are particularly
relevant for the London Insurance market, but are
1.2.3.1 Marine Operations are in general all activities regulated according to law in the different countries.
pertaining to the sea, but in this context limited Thus, in Norway it is necessary to be able to show a
according to the definition in Pt. 0 Ch.1 Sec. 1.1.1. This direct causal connection between the accident and the
covers the temporary phases in connection with load condition resulting in breach of warranty in order to
transfer, transportation and/or securing of units at sea. discharge the insurer from liability.
1.3 MARINE: INSURANCE ACT 1.4.1.2 The scope of work of an insurance warranty
survey is to some extent subject to agreement between
1.3.1 Terms of reference the parties involved. However, the warranty conditions
as defined in the insurance documents and disclosed to
1.3.1.1 The term Marine Insurance Warranty as used in the Warranty Surveyor shall be complied with.
marine insurance is based on the UK Marine Insurance
Act 1906 and is according to "Dictionary of Marine
Insurance Terms and Clauses" by R.H. Brown 1989 1.4.2 The role of the warranty surveyor
defined as:
1.4.2.1 The Warranty Surveyor will require;
A marine insurance warranty is a promissory
warranty by which the assured undertakes that that satisfactory plans and procedures according
some particular thing shall or shall not be done, to these Rules are prepared for the operation,
or that some condition shall be fulfilled, or that satisfactory preparations are carried out to
whereby he affirms or negatives the existence the extent and in the manner approved for the
of a particular state of facts. operation,
The assured must comply literally with the that the marine operations are performed in
terms of a warranty. Compliance in spirit is not accordance with the approved procedures, and
acceptable. If the assured fails to comply with
the terms of the warranty, the insurer is that the work is carried out in compliance with
discharged from all liability under the policy as these Rules.
from the date of breach of warranty, but
without prejudice to insured losses occurring
prior to such date. 1.5 MARINE OPERATION DECLARATIONS
A warranty may be "express" or "implied". An
express warranty is set out in the policy 1.5.1 Issuance of declarations
conditions. An implied warranty does not
appear in the policy, but is implied to be 1.5.1.1 When the required documentation has been
therein by law. approved, the prevailing conditions have been found
acceptable, and all surveys completed to the Warranty
Surveyor's satisfaction, a Marine Operation Declaration
will be issued. The general requirements to obtain a
Declaration are specified in Pt. 1 Ch.2 Sec. 2.4.1.
January 1996 Rules for Marine Operations
Page 6 of 12 Pt.1 Ch.1 Warranty Surveys
2. SCOPE OFINS CE W
2.3.1.2 The Warranty Surveyor shall evaluate the 2.4.1.2 Risk Analysis may be relevant for comparisons
warranty level selected by the Insurer during his work of alternative marine operations. The probability of
and if necessary adjust the level and inform the Assured, failure may also be calculated for structural strength in
who shall inform the Insurer. The aim shall be that all relation to e.g. the wave and wind loads in order to
operations are carried out with "tolerable risk" as document a specific safety level.
specified in 2.1.1.
2.4.2.2 In Table 2.1 some examples are given with 2.6 EXTENDED SCOPE OF WARRANTY
respect to typical Reference Cases for each warranty
level. The RC of a single barge towing is for example 2.6.1 Quality surveyor
specified under W2. However, a single barge towing
may well end up as either W 1 or W3 depending on the 2.6.1.1 The Operator/contractors may have additional
RRR checklist evaluation of the particular case. needs for marine services and/or verification over and
above what normally is covered in the scope of work for
2.4.2.3 For complex or novel operations it is Warranty Surveys. To cover such needs a role as Marine
recommended to carry out a HAZOP (HAZard and Quality Surveyor or Verification Body is introduced.
Operability) analysis as a documentation of the most
relevant risk elements and the recommended actions to 2.6.1.2 The Quality Surveyor is an independent
be taken, see Pt. I. Ch. 2 Sec 2.3.2. It is recommended facilitator in a marine operation project who is appointed
that the Warranty Surveyor participate in the HAZOP to ensure, through evaluations, verifications and
team. inspections, that the terms of quality as selected by the
Operator or Contractors and specified in the relevant
design, fabrication or operational contracts are complied
with. The combination of Warranty & Quality Surveys is
2.5 REDUCED SCOPE OF WARRANTY
expected to improve both quality and cost efficiency of
the control work and the operations.
2.5.1 Approval in principle
2.6.1.3 The typical work methods of the Quality
2.5.1.1 Marine operations are normally approved by
Surveyor are in addition to the Warranty Surveyor tools,
the Warranty Surveyor case by case. However, in
see 2.2.1;
principle these Rules opens up for approval based on
quality system and procedure certification with
- perform HAZOP studies, risk analysis etc.,
- carry out independent verifications including
documentation of skill. Due to the inherent risks in
marine operations the Warranty Surveyor will have to - separate analyses as parts of the design
base the final approval on Site Survey prior to each evaluation,
operation. Only in case of repetitive marine operations - carry out onhire/offhire surveys, and
the Site Surveys may be replaced by an Audit Scheme. - perform quality certification of
- designers and/or builders,
2.5.1.2 The basis for Approval in Principle is - operators for marine operations.
implementation of QA systems according to the IS0
9000 series. For vessels involved in the operation this 2.6.2 Marine advisory services
may be covered by the Safety Management Class
requirements introduced by DNV or the ISM 2.6.2.1 The Marine Advisor is the consultant in a
(International Safety ~ a n a ~ e d e nCode
t ) presented by marine operation project who is appointed to support the
IMO (International Maritime Organisation). Operator or Contractor in agreed aspects relevant to
design, fabrication or operation.
2.5.1.3 The additional requirements are approval of
documentation and procedures worked out for the type 2.6.2.2 In order to avoid any possible conflict of
of marine operations to be carried out under this scheme interest the Warranty Surveyor shall not be involved in
and qualification certification of the involved personnel, Marine Advisory covering e.g. direct design assistance
including documented knowledge of the relevant parts of or any other work that he may later receive for approval.
these Rules.
3.3.1 Documentation
3.3.1.1 The Warranty Surveyor shall upon his 3.4 PREPARATION FOR OPERATIONS
appointment make clear to the Assured the requirements
to fulfil the terms of warranty. 3.4.1 Site surveys
Guidance Note
For complex marine operations the Warranty Surveyor will identify 3.4.1.1 Surveys by the Warranty Surveyor will be
design and engineering document subject to review and approval carried out at the construction site(s) as required during
well in advance based on document lists submitted by the Assured. all temporary phases.
Rules for Marine Operations January 1996
Pt.1
-- Ch.1 Warranty Surveys Page 11 of 12
3.4.1.2 The Warranty Surveyor will perform surveys 3.4.4.4 In the event that the Warranty Surveyor for any
prior to the operation and may specify requirements to reason is unable to issue a Declaration, both the Assured
be met in order to comply with the terms of the and Insurer shall be informed that the requirements in
warranty. In some cases also survey of installation site the warranty clause not can be met or fulfilled.
may be necessary in order to document that it is ready to
receive the object. The Warranty Surveyor will prepare
reports on all surveys.
3.5 ATTENDANCE DURING OPERATION
M A N m OPEUTIONS
PART 1 : GENERAL REQUIREMENTS
PART 1 CHAPTER 2
NG OF OPERATIONS
JANTJARY 1996
SECTIONS
1. INTRODUCTION ................................................................................................................... 5
2. PLANNING .......................................................................................................................... 7
3. OPERATIONAL REQUIREMEN'I'S .......................................................................................... . l o
4. STABILITY REQUIREMENTS ................................................................................................ . I 4
5. SYS'EMS AND EQUIPMENT ................................................................................................. 19
Table Eist
Table 3.1 .Significant wave height .a values ....... 10
Table 3.2 .Weather Forecast Levels ................... 11
Figure Eist
Figure 2.1 .Planning and Design Sequence ............7
Figure 4.1 .Illustration of Stability Terms............ 16
Figure 4.2 .Intact Stability requirement............... 16
Figure 4.3 .Damage Stability Requirements ......... i 7
Rules for Marine Operations January 1996
Pt.1 Ch.2 Planning of Operations -
Page 5 of 23
1.2.2 Symbols
The list below define the symbols used in this chapter:
C, : Design criteria.
Co : Operation criteria.
GM : Initial metacentric height.
GZ : Righting arm, a function of heel angle.
H, : Significant wave height.
TR : Operation reference period.
Tpop: Planned operation period.
T, : Estimated contingency time.
ULS : Ultimate limit state.
PLS : Progressive limit state.
FLS : Fatigue limit state.
CL : Operatioddesign criteria ratio.
6, : Total displacement.
-
bmem . Mean displacement.
6,,, : First order motion due to waves.
Ym Material factor.
4: Positive GZ range.
: Maximum dynamic heel angle due to wind and
waves.
Rules for Marine Operations January 1996
R . 1 Ch.2 Planning of Operations Page 7 of 23
2.1.1.2 Planning of marine operations shall be 2.1.2.2 'I'he indicated sequence is illustrated in Figure
according to fail safe principles, i.e. the handled object 2.1. Planning and design should be considered as an
shall remain in a stable and controlled condition if a iterative process.
failure situation should occur.
2.1.2.3 Applicable input, and planned output
2.1.1.3 It should be possible to recover the object into a documentation should be defined as early as possible,
safe condition, or interrupt the operations in case of a see also 2.2.3 and 2.2.4.
possible failure situation.
For operations passing a point where the operation can -
Figure 2.1 Planning and Design Sequence
not be reversed, a point of no return shall be defined.
Safe conditions after passing a point of no return shall be (
defmed and considerde in the planning.
Regulations. Rules
Soecifications. Standards I
2.1.1.4 All possible contingency situations shall be
identified, and contingency plans or actions shall be
prepared for these situations. Such plans shall consider
I Overail Planning
I
redundancy, back-up equipmeat, supporting personnel,
emergency procedures and other relevant preventive
measures and actions. Contingency situations may be
defined or excluded based on conclusions from risk
evaluations, see 2 . 3 .
Identify relevant regulations, rules, company 2.1.3.1 It is recommended to develop a design basis
specifications, codes and standards. and/or a design brief in order to obtain a common basis
and understanding all parts involved during design,
Identify physical limitations.
engineering and verification.
Overall planning of operation i.e. evaluate
operational concepts, available equipment, 2.1.3.2 The design basis should describe the basic input
limitations, economical consequences, etc. parameters, characteristic environmental conditions,
characteristic loadslload effects, load combinations and
Develop a design basis describing
load cases.
environmental conditions and physical
limitations applicable for the operation.
January 1996 Rules for Marine Operations
Page 8 of 23 -- Pt.1 Ch.2 Planning of Ouerations
2.1.3.3 ' R e design brief should describe the planned 2.2.2.3 The quality and details of the documentation
verification activities, analysis methods, software toois, shall be such that it allow for independent reviews of
input specifications, acceptance criteria, etc. plans, procedures and calculations, for all parts of the
Guidance Mote
operation.
The Design Basis and the Design Brief may be combined and Guidance Mote
issued as one document. A document plan describing document hierarchy and scope for each
Guidance Note document IS recommended for major marlne operations
It is recommended to include the Design Basis and the Design
Briefs as part of the formal documentation for the operation, and
subject for review and approval according to projecUoperatiori 2.2.3 Input documentation
requirements.
2.2.3.1 Applicable input documentation, such as;
- statetory regulations,
rules,
- company specifications,
standards and codes,
2.2.1 Documentation requirement
- concept descriptions,
2.2.1.1 Acceptable characteristics shall be documented - basic engineering results (drawings, caiculations,
for the handled object and all equipment, temporary or etc.), and
permanent structures, vessels etc. involved in the
- relevant contracts or parts of contracts.
operation. should be identified before any design work is
Guidance Note performed.
Note that all elements of the marine operation shall be documerited
This also include onshore facilities such as quays, soil, pullers and
foundations 2.2.4 Output documentation
2.2.1.2 Properties for object, equipment, structures, 2.2.4.1 Necessary documentation shall be prepared to
vessels etc. may be documented with reco,pised prove acceptable quality of the intended marine
certificates. The basis for the certification shall then be operation. Typical output documentation are:
clearly stated, i.e. acceptance standard, basic Planning documents including design briefs and
assumptions, dynamics considered etc., and comply with
basis, schedules, concept evaluations, general
the philosophy and intentions of these Rules.
arrangement drawings and specifications.
2.2.1.3 Design analysis should typically consist of Design documentation including load analysis,
various levels with a "global" analysis as top level, and global strength analysis, local design strength
with strength calculations for details as a lowest level. calculations, stability and ballast calculations
Different types of analysis methods and tools may apply and structural drawings.
for the different levels. Operational procedure including testing
program and procedure, operational plans and
2.2.1.4 Operational aspects shall be documented in procedure, arrangement drawings, safety
form of procedure, operation manuals, certificates, requirement and administrative procedures.
calculations etc. Relevant qualifications of key
personnel shall be documented. Certificates, test reports, survey reports, NDE
documentation, as built reports, etc.
2.2.1.5 All relevant documentation shall be availab!e
on site during execution of the operation. 2.2.5 Operation records
2.3.2.1 In addition to, or instead of a risk evaluations, 2.4.2.2 DNV can for certain areas base an acceptance
a HAZOP (HAZard and Operability study) may be of capacities, strength, characteristic properties, etc. on
performed for assumed critical operations. The HAZOP verification work performed by other independent third
should be based on manuals and procedures covering the parties, classification societies, governmental
actual operation, and the equipment involved in the institutions, etc.
operation.
Guidance Note
2.4.2.3 DNV will in these cases limit the scope to
A HAZOP is a systematic critical team review of the planned review of loads, load cases, acceptance criteria and
operation, using a series of guide words to structure the examination verifiers conclusions.
of the effects of upsets and abnormal conditions in a planned
operation. The review team should consist of key personnel from Areas or elements proposed for this scheme is subject for
contractor familiar with the operation, in addition to company DNV acceptance.
representatives and outside members with specialist competence for
the plariried operation. It is recommended that the HAZOP leader is Applicable area may be;
independent from the contractor
- global structural integrity of object to be handled,
- global barge strength,
- overall grillage strength,
2.4 OPERATION DECLARATION - equipment strengtblcapacities and
- quayhollards.
2.4.1 General
2.4.2.4 If acceptance of elements shall be based on
2.4.1.1 DNV can, if requested, confirm compliance other third party verification work, the interface between
with these Rules of handled object, equipment, the different verifiers scope must be defined.
temporary and permanent structures, procedure etc. by
Formal communication lines between DNV and the
issuance of a Marine Operation Declaration.
verifier may be required.
January 1996 Rules for Marine Operations
Page 10 of 23 R . 1 Ch.2 Planning of Operations
3.1 OPEIRATION DESIGN CRITERIA 3.1.2.3 For weather restricted operations these Rules
consider uncertainties in weafher forecasts by applying a
3.1.1 Operation reference period operation criteria less than the design criteria. The
operation criteria should be taken as;
3.1.1.1 Planning and design of marine operations shall C, 2 a C,
be based on an operation reference period defined as;
where
C, - design criteria,
C, - operation criteria,
where
u- operationai vs. design criteria ratio,
TR- Operation reference period - for significant waves, a should be taken
TpOp- Planned operation period according to Table 3.1.
Tc - Estimated contingency time. - for wind (10 min. mean), a should be taken as
0.80.
3.1.1.2 Reference periods less than 12 hrs, should be
specially considered. For operations planned according to 3.1.2.2 the factor a
should be specially considered in each case.
The start and termination points for the intended
operation shall be clearly defined.
t
3.2 WEATHER FORECAST L e ~ eA
l
Weather forecast level A inciude major marine
3.2.1 General operations sensitive to environmental conditions.
Typical "level A" operations may be;
3.2.1.1 Arrangements for receiving weather forecasts at
regular intervals prior to, and during the marine - mating operations,
operations shall be made. Such weather forecasts shall - multi barge towing,
be obtained from recognised sources. - GBS tow out operations,
- offshore installation operations, and
3.2.1.2 Weather forecast procedures should consider - jackup rig moves.
the nature and duration of the planned operation, see
3.2.2.1. Level B
Weather forecast levei B inciude environmentai sensitive
The weather forecasts shall be in writing. operations of significant importance with regard to value
and consequences.
3.2.1.3 Ln addition to a general description of the
weather situation and the predicted development, the Typical "level B" operations may be;
weather forecast shall, as relevant, include; - float out operations,
- wind speed and direction, - offshore lifting,
- waves and swell, significant and maximum - sensitive barge towing,
height, mean or peak period and direction,
- rain, snow, lightning, ice etc., Level C
- tide variations and/or storm surge, Weather forecast level C include conventional marine
- visibility, operations less sensitive to weather conditions, and
- temperature, and carried out on a regular basis.
- barometric pressure
Typical "level C" operations may be;
for the coming 12, 24, 48 and 72 hrs. In addition an
outlook for the next days should be included. - onshore/inshore lifting,
- load out operations,
3.2.1.4 The forecast shall clearly defme forecasted tows in sheltered waterslharbour tows and
- standard barge tow without weather restrictions.
parameters, e.g. average time for wind, characteristic
wave periods (T, or T,).
3.2.2.2 Based on selected weather forecast level, a
forecast procedure complying with requirements in Table
3.2.1.5 A weather forecast is acceptable for start of 3.2 should be established.
marine operations if all relevant items listed in 3.2.1.3
are within the defined operational criteria for the
operation reference period. -
Table 3.2 Weather Forecast Levels
3.2.2 Weather forecast levels 1) Based on sensitivity w r t weather conditions smaller intervals
may be required.
3.2.2.1 Based on evaluations of the operational 2) Contact/discussionswith meteorologist shall be made
3) A written forecast from only one of the sources may be
sensitivity to weather conditions, a categorisation of the acceptable.
operation into weather forecast levels A, B or C shall be
made.
Guidance Note
Independence between weather forecast sources is satisfied if there
are organisational independence between the sources, i.e. it is
acceptable to obtain a second forecast from a national and a local
source (relevant for the actual area).
January 1996 Rules for Marine Operations
Page 12 of 23 - Pt.1 Ch.2 Planning of Operations
3.2.3 Monitoring of environmental conditions 3.3.1.6 Operations shall be carried out in accordance
with the conditions for design, the approved
3.2.3.1 For marine operations particularly sensitive for documentation, and sound practice, such that
certain environmental conditions such as waves, swell, unnecessary risks are avoided. This is the responsibility
current, tide etc., systematically monitoring of these of the operation superintendent or manager.
conditions prior to and during the operation should be
arranged. 3.3.1.7 Responsibilities in possible emergency
situations shall be described.
3.2.3.2 Monitoring should be systematic.
Responsibilities, monitoring methods and intervals 3.3.1.8 Access to the area for the operation should be
should be described in a procedure. restricted. Only authorised personnel should be allowed
into the operation area.
3.2.3.3 Essential monitoring systems should have back
up systems.
3.3.2 Communication
3.2.3.4 Predicted variations of these parameters during
3.3.2.1 Communication lines and primary and
executions of the marine operations should be based on
secondary means of communication shall be defined,
monitored variations, tabulated values and forecasted
preferably in a communication chart.
variations.
i~nportantinformation should be dedicated to un-
3.2.3.5 Any unforeseen monitoring results should be interuptable Iineslchannels.
reported without delay.
3.3.2.2 The planned flow of information during the
3.2.3.6 'Tidal variations should additionally be operation shall be described. A common language
monitored a period with the same lunar phase as for the understood by all shali be used for VHFAJHF
planned operation. communication.
Guidance Note Guidance Note
Tide variations should be plotted against established astronomical The communication chart shall reflect the ectual communication
tide curves Any discrepancies should be evaluated, duly lines that will be used during the operation
considering barometric pressure arid other weather effects Guidance Note
To avoid interference between internal andlor external users it is
recommended to allocate VHFIUHF channels as early as possible
3.3.1.5 Key personnel shall have knowledge, and 3.4.1.3 Change over from a primary to a secondary
experience within their area of responsibility. system shall be tested.
Rules for Marine Operations January 1996
Pt.1 Ch.2 Plannine of O~erations Page 13 of 23
%
-A
' 3.4.1.4 Instrumentation systems shall be calibrated and 3.5 MARINE OPERATION MANUALS
tested prior to the operation. The calibration procedure
may be subject for review. 3.5.1 General
3.4.1.5 ' R e test and inspection program shall be 3.5.1.1 Operational procedure shall be developed for
planned, and the results documented. the planned operation, and shall reflect characteristic
Guidance Note environmental conditions, physical limitations, design
The inspections and testing can be documented by survey and assumptions and tolerances. The operational procedures
inspection reports, filled in test check lists, test reports, etc shall be described in a Marine Operation Manual
covering all aspects of the operations. Such manual shall
3.4.1.6 For larger operations it is recommended to include descriptions of, as applicable;
develop a testtcommissioning program specifying the
planned inspections and tests. The test program should organisation,
indicate expected characteristics, and state acceptance communication routines and systems,
criteria based on the design assumptions. general arrangement,
operational procedures and plan of execution,
Guidance Note contingency planning and emergency procedures,
Acceptance criteria for tests may also be functional requirements.
permissible load conditions,
3.4.1.7 For operations with complex environmental operation criteria,
communicationlreporting procedures, or where proper tolerances,
information flow is vital, a "run through" of permissible draughts, trim, and heel and
communication routines is recommended. corresponding ballasting plan,
systems and equipment including layout,
'I'his training should be performed with the nominated systems and equipment operational instructions,
personnel and under conditions similar to what are vessels involved,
expected during the actual operation. tow routes and ports of refuge,
navigation,
3.4.2 Familiarisation and briefing weather and currentlwave reporting,
safety equipment,
3.4.2.1 Operation supervisors shall familiarise recording and reporting routines,
themselves with all aspects of the planned operations sample forms,
and possess a thorough knowledge with respect to check lists for preparation and performance of the
limitations and assumptions for the design. operation, and
test and commissioning planes.
3.4.2.2 Key personnel shall familiarise themselves with
3.5.1.2 Limiting criteria for marine operations or parts
the operations. A thorough briefing by the supervisors
thereof shall be clearly stated in the Operation Manual.
regarding responsibilities, conimunication, work
procedures, safety etc. shall be performed.
3 S.1.3 Documentation in the form of certificates,
Guidance Note release notes and classification documents for all
Briefings are recommended both for familiarisation with the planned
operation and as a "team building" effort. equipment and vessels involved in the marine operation
shall be enclosed andlor listed in the Operation Manual.
3.4.2.3 Other personnel participating in the operations
shall be briefed, generally about the operation and
specially about safety and assigned tasks/responsibilities.
January 1996 Rules for Marine Operations
Page 14 of 23 --- Pt.1 Ch.2 Planning of Operations
4.1.1.5 Sufficient stability should normally not include 4.1.3.1 During the calculations of stability and reserve
the up-righting contribution from occasionally buoyancy, due allowance shall be included to account for
submerged elements such as jacket legs hanging over the uncertainty in mass, centre of gravity location, density
barge sides. This contribution may, however, be of ballast arid ballasting water, and density of the sea.
included in special cases for the requirement given in
4.2.2.2 upon careful examination of the operational 4.1.3.2 Correction for free surface effects in tanks and
parameters. The contribution of the buoyancy of cargo compartments containing liquids shall be included.
elements in the stability calculations must be accounted
for in the seafastening loads. 4.1.3.3 For operations where stability andlor reserve
buoyancy at some stage is critical, special consideration
4.1.1.6 Drainage openings to avoid unacceptable shall be given to the duration of the critical condition,
accumulation of water should be considered. If drainage the risk of possible hazards and to the mobilisation time
openings are impractical, the stability of the barge for - and amount of - back-up system.
should be investigated considering this effect.
4.1.3.4 Calculations of motions and effect of wind as
input to 4.2.2.2, 4.2.2.3 and 4.3.2.1 shall be for the
decisive design condition as defined in Pt. 1 Ch.3 . If not
otherwise specified, the 1 minute average wind speed
shall be applied in the stability calculations. For
unrestricted operations in the North Sea area wind speeds
exceeding 41 m/s need normally not be considered.
Guidance Note
The load factor can for stability considerations be taken as 1 0 when
calculating wind heeling moments
Rules for Marine Operations January 1996
R . 1 Ch.2 Planning of Operations
- Page 15 of 23
4.1.4 Inclining tests 4.1.4.5 For floating objects with large metacentric
height, an inclinimg test may not give sufficient accurate
4.1.4.1 Inclining tests shall normally be performed at results. The stability calculations may then be based on
various stages during construction afloat and prior to the calculated weight and centre of gravity andlor on
major marine operations to confirm the parameters results from a thorough weight control system enforced
influencing the stability. ?'his is particularly relevanr during the construction.
when the calculated value of the metacentric height is
close to the minimum acceptable value and if such a
minimum condition is obtained by the transfer of heavy 4.1.5 Watertight integrity
loads.
4.1.5.1 ?'he number of openings in watertight
bulkheads and decks shall be kept to a minimum.
4.1.4.2 A detailed procedure for the tests should be
prepared considering the following:
4.1.5.2 Where penetrations of watertight decks, outer
Maximum allowable wind speed for execution walls, and bulkheads are necessary for access, piping,
of the tests should be established prior to the ventilation, electrical cables, etc., arrangements shall be
testing. This maximum value should normally ~nadeto maintain the watertight integrity.
not exceed 3 m/sec.
'fie inclining angle should be of the order of
41- ldeg. for large volum structures and 5 deg.
4.2 BARGE TRANSPORTS
for conventional vessels/barges.
The angles should be measured by at least two 4.2.1 Safety against entry of water
pendulums, or one pendulum and one
electronic/optical device. 4.2.1.1 ?'he requirements of The Lntemational
Conference on G a d Lines, 1966 (ILLC 66) should be
The draught should be such that the waterline
complied with as applicable with respect to air pipes,
intersects the unit in a wallside area.
overboard and inlet pipes through hull, and weather tight
The effects of external forces due to wind, securing of doors, hatches and other openings.
waves, moorings, anchors, tugs, cranes, etc.,
should be considered and preferably monitored. 4.2.1.2 All doors, hatches, windows and ventilators
shall be closed with their closing appliances, except
4.1.4.3 Before the test, a sensitivity analysis of the where use of such openings are necessary for a riding
parameters affecting the inclining test results shouid be crew. In this case, the closing appliances for the
performed. Such parameters are draught, heel angle, sea openings in use shall be stored close to their respective
water density, inclining weights and distances moved, openings. Manholes to tanks should be closed. All
variable wind speed, accuracy of the measuring water tight doors in bulkheads should be closed.
equipment, etc.
Valves on the barge sides and bottom not in use during
The sensitivity analysis should give the total expected the voyage should be closed. Pipelines leading
error on the position of the centre of gravity and also overboard without any closing appliances should be
indicate which parameters to p no nit or during the test. blanked off.
All bilges should be clean and dry on departure.
4.1.4.4 Upon completion of the inclining test, a report
containing measurements/readings and corresponding
4.2.1.3 Dry compartments and empty or slack tanks
calculations of displacement (and light weight if
which contribute significantly to the buoyancy of the
relevant), metacentric height (GM), and the position of
barge shall be fitted with sounding facilities.
the centre of gravity of the structure, should be
prepared.
After execution of inclining tests, a proper weight 4.2.2 Intact stability requirements
control system should be implemented and enforced until
4.2.2.1 For single multi barge tows the
the relevant marine operation is completed.
requirements both in 4.2.2.2 and 4.2.2.3 should
normally be met during all stages of sea transportation
operations.
January 1996 Rules for Marine Operations
Page 16 of 23 Pt.1 Ch.2 Planning of Operations
4.2.2.2 The stability should be positive to a heel angle Figure 4.2 - Intact Stability requirement
1
beyond equilibrium as given beiow:
1 I
4 2,,$( + 15 + 15/GM), max. 40 degrees NTACT S T A B I - ' ~ \
Eq. 4-1
, , 4 for the design environmental condition is
provided
i -
(h + B) 2 1 i (E + C)
c 1 P~shtingvornanl I
smaller or equal to the heel angle where the maximum
'
z I /
2 + /'
transverse righting moment occurs, otherwise : ,/ -
/*-
Wind Korrenr
r'
4 > 40 degrees F
I
- I
Eq. 4-2 - -1
I
Ll/ I ,
where I 1
_,/ d
I
%-
I
, ,$ = maximum dynamic heel angle due to wind and
waves, see also Pt. 1 Ch.3.
II I-EEL A'4G.E
4.2.4.1 Damage stability evaluations shall be based on 4.3.3 Damage stability requirements
damage scenarios according to identified contingency
situations, see 2.1. I . Collision, leakage and operational 4.3.3.1 General requirements to damage stability given
failure situations shall be evaluated. in 4.2.3 apply.
As a minimum the barges with the transported object 4.3.3.2 Damage stability evaluations shall be based on
should remain afloat in stable equilibrium with sufficient damage scenarios according to identified contingency
freeboard to preclude progressive flooding with any one situations, see 2.1.1. Collision, leakage and operational
compartments open to the sea. failure situations shall be evaluated.
?'he acceptable floating condition is determined by the As a minimum the self-floating object shall normally
following : remain afloat in a stable equilibrium with sufficient
- The requirements of 4.2.3.2 apply. freeboard to preclude progressive flooding with any one
- The steady angle of heel or pitch caused by the compartment open to the sea, as given in 4.2.3.2.
damage and wind pressure should not immerse Exemptions from this requirement are not acceptable
any non watertight closures in the hull. unless adequate, approved precautions are taken. The
- It shall be demonstrated by calculation that the precautions should ensure acceptable safety, for instance
flooding of any one compartment will not cause as given in 4.3.3.3 andor 4.3.3.4.
the damaged barge to change its heel or trim angle
relative to the overall heel or trim of the barge 4.3.3.3 If 4.3.3.1 cannot be complied with, the
unit, i.e., the damaged barge should not pivot structure shall withstand the collision loads according to
around any of the deck supports and thus loose Pt. 1 Ch.3 Sec.3, on the whole exposed circumference of
contact with the deck at other support(s). the structure from 5 metres below to 5 metres above any
operation waterline without ingress of water.
4.5.1 General
4.5.1.1 Other vessels, semi submersibles, crane vesseis,
etc., involved in marine operations shall, for both intact
and damaged conditions, compIy with national or
international (IMO) stability regulations or codes.
5, SYSTEMS
5.1.1.4 The following systems shall be considered 5.1.2.4 Automatic control systems shall be provided
where applicable; with a possibility for mand overriding.
power supply,
fuel supply,
electrical distribution systems, 5.2 VESSELS AND BARGES
machinery control systems,
valve control systems,
5.2.1 General
bilge and ballast systems,
compressed air systems, 5.2.1.1 All vessels shall be in good condition and fit
fire fighting systems, for the intended operations.
communications systems, and
instrumentation systems for monitoring of;
5.2.1.2 Vessel and barges shall satisfy the hydrostatic
- loads and/or deformations, stability requirements given in 4.
- environmental conditions,
- ballast and stability conditions,
- heel, trim, and draught, 5.2.1.3 All vessels/barges involved in the operations
shall be inspected prior to the operation to confirm
- position (navigation),
compliance with design assumptions, validity of
- underkeel clearance, and
certificates and general condition.
- penetration/settlements.
5.1.1.5 Systems shall as far as possible be designed to 5.2.1.4 Vessels classed by a Classification Society shall
be fail safe. be operated in accordance with requirements from this
Society.
5.1.1.6 Cornputerised control or data acquisition The condition for class as given in "Appendix to Class"
systems should be equipped with un-interuptable power or similar shall be presented.
supply system (UPS).
5.2.1.5 For Mobile Offshore Unites the following 5.3 MOORING SYSTEMS
annexes (or similar) to the maritime certificates shall be
presented; 5.3.1 General
Annex I operational limitations,
Annex TI: resolutions according to which the unit has 5.3.1.1 This sub section applies for design and
been surveyed, and possible deviations from verification of mooring of vessel or barges alongside
these. quays, or for mooring systems couibinhg iong and short
lines.
5.2.1.6 Valid recommendations given by the
Classification Society shall be presented. 5.3.1.2 For verification of offshore and inshore
Guidance Note catinary mooring system reference is made to Pt. 2
Modifications to vessellbarge structure or equipment may require Ch. 7.
approval from the Classification Society
5.2.1.7 Where several tugs or vessels are involved, a 5.3.1.3 For mooring of GBS structures reference is
made to Veritas Marine Operations, Guidelines No. : 1.1
stand by tug to assist or remove vessels in case of black
"Mooring and Towage of Gravity Base Structures",
out, engine failure, etc. should be considered.
November 1989.
5.2.1.8 If allowable deck load is based on "load
charts", limitations and conditions for these with respect
5.3.1.4 For certification of offshore mooring wire and
chain reference is made to DNV Certification Note 2.5,
to number of loads and simultaneousness of loads shall
"Certification of Offhore Mooring Steei Wire Rope" and
be clearly stated. Applied dynamic factors, load factors
Certification Note 2.6, "Certification of Offhore
or material factors shall be specified.
Mooring Chain".
5.2.1.9 The vessels global and local condition with
respect to corrosion shall be confirmed and considered in
5.3.1.5 Mooring lines shall be in good condition.
strength verifications, see a1,c.oP!. 1 Ch.4 Sec. 2.2.3.
5.3.2 ULS conditions
5.2.1.10 General description of vessel systems to be
used shall be presented. Ballast and towing 5.3.2.1 All relevant combinations of characteristic
equipmentlsystems shall be described in detail if used. loads and directions should be evaluated in the ULS
case.
5.2.2 Navigational lights and shapes 5.3.2.2 Characteristic mooring line loads should be
calculated with characteristic loads according to Pt. 1
5.2.2.1 The vessel or towed object should exibit
Ch.3. Sec. 2 and Sec. 3.
navigational lights and shapes in accordance with IMO
codes and local requlations.
5.3.2.3 Design loads and load cases shold be defined
according to Pt. 1 Ch. 4.
5.2.2.2 Sufficient energy supply for the navigational
lights to last for minimum 1.5 times the expected Guidance Note
duration of the voyage shoul be provided. Effect of pretension and external loads, e g from pulllpush systems,
may be categorized as live loads
5.2.3 Towing vessels 5.3.2.4 Tension in anchors and mooring lines should be
calculated based on the design loads, vessel response,
5.2.3.1 Requirements to towing vessels are given in characteristic line and fender stiffness, and the local path
Pt. 2 Ch.2 Sec. 3.3. Requirements to towing equipment of displacement.
are given in Pt. 2 Ch.2 Sec. 3.1.
5.3.2.5 A dynamic analysis of the system behaviour is
preferable. A quasistatic analyses may be acceptable
5.2.4 Barges upon consideration of natural frequencies of the system
and its individual components.
5.2.4.1 Requirements to cargo barges and barge
equipment are given in Pt. 2 Ch.2 Sec. 3.1 and 3.2.
5.3.2.6 Special considerations shall be made to the load
distribution in mooring lines for systems with several
short lines arranged in an undetermined pattern.
Rules for Marine Operations January 1996
Pt.1 Ch.2 Planning of Operations Page 21 of 23
If relevant, local dynamics of individual mooring lines should be 5.3.5.4 The material factors for certified steel wire
included The lirie may be excited by the time varying motions at the ropes and chains are normally taken as:
upper end (found from the dynamic system analysis) and by wave
and current induced vortex shedding. ym = 1.5 for ULS
ym = 1.3 for PLS
5.3.3 PLS conditions Guidance Note
Mooring arrangements with planned duration's less than 30 days
5.3.3.1 The mooring system shall be verified for a PLS and arranqed with new certified wire ropes may be verified with a
reduced material factor; =y, I35 (ULS).
case. The PLS case should be defined as a conditions
Guidance Note
with any one line broken. Dynamic effectsltransient
Wire ropes without a certified MBL may be acceptable for mooring
motion and clearances shall be considered for the PLS purposes. Design calculations for these systems shall be based on
case.. the fabricators specified MBL and a material factor: y,, 2 1 65 (ULS)
5.3.3.2 Loading conditions c and d, see Pt.1 Ch.4 5.3.5.5 If mooring lines are arranged with wire clamps
Table 3.2, should be investigated. these shall be installed, and regularly inspected,
according to fabricators instructions and procedure.
5.3.3.3 Upon failure of one mooring line the remaining Guidance Note
system should be able to resist expected loads and Special considerations shall be made to the required number of
clamps and possible tensioning andlor control procedure
displacements until1 repaired.
Guidance Note 5.3.5.6 Material factors for synthetic ropes should be
Verification of a PLS may be omitted if tugs are stand by at the taken as:
mooring site, and the system allow the tugs to provide sufficient
thrust at positions and in directions necessary to replace any one y, = 3.5 for ULS
line ym = 3.0 for PLS
5.3.6.3 Design loads for mooring details should be 5.4 GUDIf\lG AND EQSITIONEYG SYSTEMS
taken as the characteristic mooring line load multiplied
with load factors, see Pt. 1 Ch.4. 5.4.1 General
5.3.6.4 Strength verification of mooring line 5.4.1.1 This sub section applies for design and
connections shall comply with requirements in Pt. 1 verification of guiding and positioning systems to be
Ch.4. The characteristic strength shall be documented used for marine operations.
either by calculations or certificates. Strength reduction
due to corrosion and wear shall be considered. 5.4.1.2 Guides and bumpers shall have sufficient
Guidance Note strength and ductility to resist impact and guiding loads
Special consideratioris shall be given to condition of barge bollards during positioning without causing operational problems
older than 10 years (e.g, excessive positioning tolerances), and without
overioading members of the supporting structure.
5.3.6.5 Onshore bollards without a certificate from a Plastic deformation of guides due to impact Ioads may be
recognised Certifying Body should be tested before use
allowed. After contact between bumpers and guides they
to 1.25 times the characteristic line load.
should, in a deformed shape, be able to resist loads due
to the environmental conditions during operation, and
5.3.7 Anchors operational loads from tugger lines, mooring lines etc.
Guidance Note
5.3.7.1 The conditions of the seabed should be taken A factor not less than 1 3 between des~gnloads of supporting
into account in the selection of the anchor type. structure and gu~delbumperstrength IS recommended
Guidance Note
Guiding systems are often designed with a primary and secondary
5.3.7.2 Characteristic anchor forces should be system The primary system is normally designed to absorb
determined in accordance with 5.3.2 or 5.3.3. possible impact energy, and provide guiding onto the secondary
system. The secondary system is normally design to ensure
5.3.7.3 The characteristic holding capacity of anchors accurate arid controlled positioning of the object.
should be taken as the conservatively assessed mean
5.4.1.3 Guides and bumpers shall after an impact
value based on information from tests or theoretical provide a positive clearance towards neighbouring and
calculations. The values used should apply to the actual supporting structure, and maintain their functionality.
conditions of the seabed in question. The possibility and consequences of multiple impacts
shall be considered.
5.3.7.4 171e anchor material coefficient (holding
capacity coefficient) is normally taken as:
y, = 1.5 for ULS 5.4.2 Characteristic loads
ym = 1.3 for PLS
5.4.2.1 Characteristic impact loads for bumpers should
be based on impact and deformation energy
5.3.7.5 For anchors not designed to carry vertical loads considerations.
the length of anchor line should be such that no vertical
force wili occur in any loading condition. 5.4.2.2 Realistic impact velocities, impact positions and
deformation patterns shall be assumed.
5.3.7.6 Direct-embedment anchors of deep penetration
and high holding powerlweight ratio may be used
5.4.2.3 Design loads and load cases for the impact
provided the suitability of the anchors is documented in phase may, assuming realistic maximum impact
advance. Alternatively pile anchors may be used.
velocities, be established according to requirements for a
PLS case.
5.3.7.7 Anchors shall normally be tested to 1.25 times
the characteristic mooring line load. The anchors shall
5.4.2.4 Characteristic loads for the guiding and
be tested for at least 15 minutes. positioning phase shall be based on environmental
conditions during operation, in addition to operational
loads from tuggerlines, mooring lines etc. Combination
of horizontal and vertical loads during guiding shall be
considered in the design load cases. Realistic friction
coefficients shall be used.
5.4.2.5 Design loads and load cases for the guiding and
positioning phase may be established according to
requirements for an ULS case,
PART 1 C m3
DESIGN LOADS
JANUARY' 1996
1. INTRODUCTION...................................................................................................................
4
2. ENVIRONMENTAL CONDITIONS. ........................................................................................... 6
3. LOADS AND LOAD EFFECTS ................................................................................................ 12
Figure List
3. LOADS AND LOAD EFFECTS................12
Figure 2.1 .Design
. .
process .................................6
3.1 LOAD CA'ITEGOFUES .............................12 Figure 2.2 .Current stretching method ...................11
3.1.1 General ........................................12 Figure 2.3 .Definition of water levels ...................11
3.1.2 Permanent loads (P) ......................... 12
3.1.3 Live loads (L) ................................12 Table List .
3.1.4 Deformation loads (D) ......................12 Table 2.1 .Characteristic wind velocities.................7
3.1.5 Environmental loads (E) .................... 12 Table 2.2 .wind U ( ~ . ~ A / U ( ~ . ~ ..........
,A 8
3.1.6 Accidental loads (A) ........................ 12
wind,
- waves and
currents.
Conditions
Phenomena which may be of importance are;
tide,
soil conditions,
ice and snow,
- earthquake,
- temperature,
- fouling,
- visibilitylfog and
- heavy rain.
2.1.3 Environmental statistics
2.1.2 Characteristic conditions and loads
2.1.3.1 Environmental phenomena may be described by
2.1.2.1 Characteristic conditions are conditions with a statistical distributions and variables. Statistical data
defined probability of exceedance, within a defined should as far as possible be used to establish
period of time. characteristic environmental conditions. The statistical
description should reveal the extreme conditions for
2.1.2.2 Characteristic conditions and loads combined short and long term cases.
with load and material factors as specified by these Rules
complies with the overall objectives as stated in Pt.0 2.1.3.2 Statistical data used as basis for establishing
Ch.1. characteristic environmental criteria must cover a
Guidance Note sufficiently long period of time period. For
Note that these Rules adopt an approach alternative to the traditional meteorological and oceanographic data a minimum of
return period design philosophy, although with the same safety three to four years of data collection is recommended.
philosophy. A return period design will have (dependent of duration)
a variating probability of failure, while these Rules aim at a constant
probability of failure per operation. 2.1.3.3 The environmental design data should be
With a return period approach an operation would have the same representative for the geographical area or site.
characteristic condition both for a three days and a three months
planned duration. A three months period would however expose the
object for a longer period, with a corresponding higher probability of
2.1.3.4 If statistical environmental data are assumed to
failure compared to the tree days operation. follow a two parameter Weibull distribution, the
regression analysis should be performed with emphasise
2.1.2.3 Characteristic conditions and loads combined on a correct representation of the extreme values.
with load and material factors according to Pt. I Ch.4 Guidance Note
shall form the basis for design and design verification. Regression analysis of two parameter Weibull distributions are
recommended based on the 30 % highest data points, i.e
P(x=-X)=O3
Rules for Marine Operations January 1996
Pt.1 Ch.3 Design Loads Page 7 of 20
2.2.1 General
) T > 3Odays I 100 year return I
2.2.1.1 Wind velocity varies with time and height 2.2.2.4 For weather restricted operations characteristic
above the sea surface. wuid velocities less than 10mlsec are generally not
recommended. Requirements to ratio between operation
The averaged wind velocity over a d e f i e d period is and design wind is given in Pt. I Ch.2 Sec.3. I .
referred to as mean wind.
Guidance Note 2.2.2.5 ?'he wind velocity profile may be related to a
Forecasted wlnd IS normally given at z=lOm reference height and reference height (q) and mean time period (t,,,d
trneanZl0 min mean wind according to Eq. 2-3, see also Table 2.2.
2.2.1.2 'The characteristic mean wind period shall
correspond to the systems response periods.
Guidance Note. Eq. 2-3
The following periods are meant as illustrative examples,
- Local plate field 3 [set 1 where
- Mooring with "short"lines 1 [minute] z = Height above sea surface.
- Catenary mooring of vessels 10 [minutes]
- Catenary mooring of GBS 60 [minutes] Z, = Reference height 10 [m].
& a = Averaging time for design.
2.2.2 Characteristic wind velocity f ,a = Reference averaging time 10 [minutes].
U(z,&& = Average wind velocity.
2.2.2.1 The statistical behaviour of maximum mean U(&,f ,& = Reference wind speed.
wind velocities, Umx(z,t,,,d, within a "short term"
period (Td m y be described by a Weibull distribution;
Eq. 2-1
PrW) = Cumulative probability of U-(z,~-).
U = U,,(z,&-), max. mean wind speed.
U, = Weibull scale parameter.
c = Weibull slope parameter.
January 1996 Rules for Marine Operations
Page 8 of 20 R . 1 Ck.3 Design Loads
2.3.1.3 With the deterministic method the design sea 2.3.3.4 In the absence of site specific wave data the
states are represent by regular periodic waves Weibull parameters in table A1 (Appendix) may be used.
characterised by wave length (or period), wave height Guidance Note
and possible shape parameters. For operationsltransports passing through several area, the extreme
value distribution may be based on an accumulated distribution of
individual wave heights considering the exposure period in the
2.3.1.4 With the stochastic method the design sea states individual area A simplified approach would be to estimate,,,H
,
are represent by wave energy spectra characterised by based on exposure in the worst area for the whole operation period
parameters such as H, and T, or T,.
2.3.3.5 Characteristic significant wave height for the 2.3.4.2 'fie following wave periods should be
exposure period may be taken as considered for the characteristic wave height H, (P-i,,,
\l/j
in metres and T in seconds).
112
Eq, 2-5 (45~,,~,,)S T 5 20
where
i
Zmx = ~ ( f o l )
S(O) = r ~ ~exP~ o - ~ 14-r
f,., = ln(l0 . R . N) + (d - 1) ln(ln(10 .R . N)) Eq. 2-9
where
o = Angular wave frequency, w =2.rr/Tw,
Tw = Wave period.
Reference is made to 2.3.3.5 for definitions of symbols. (,IP
= Angular spectral peak frequency op=2n/'Tp
E: = Acceleration of gravity.
a = Generalised Phillips' constant,
2.3.4 Design wave method
a = (5/16)*(~~o,4/~~)*(1-0.287ln(~))
2.3.4.1 For most practical purposes the kinematics of cs = Spectral width parameter.
regular deterministic waves may be described the = 0.07 if o 6 op
following theories: = 0.09 if o > o,
Y = Peakness parameter.
W h 5 0.1 Solitary wave theory.
0.1 < W h 5 0.3 Stokes' 5th order wave theory. The Pierson Moskowitz spectrum appears for y = 1.O.
W h > 0.3 The relation between T, and Tp may be taken according
Linear wave theory.
to Eq. 2-10.
I
where
h = Water depth.
h = Wave length. Eq. 2-10
January 1996 Rules for Marine Operations
Page 10 of 20 ?to1 Ch.3 Design Loads
2.3.5.4 The Pierson Moskowitz spectrum is generally 2.3.6.2 Swell type waves may be assumed regular in
recommended for open, deep waters ( > 150m) and fully period and height, and may normally also be assumed
developed seas. 'I'he Jonswap spectrum is recommended independent from wind generated waves.
for fetch limited, growing seas and in shallow waters.
2.3.6.3 Characteristic height for swell type waves may
For a general Jonswap spectrum the y parameter may,
be taken as the 10 year return value. Criticai swell
unless specific data are available be taken as (Tzin
periods should be identified and considered in the design
seconds and H, in metres);
verification.
for
2.4.9 Current
for
2.4.1.1 Characteristic current velocity shall be based on
iocai statistical data and experiences. Unless more
2.3.5.5 A directional short crested wave spectrum, see detailed evaluations of current velocity are made the
Eq. 2-11, may be applied based on non-directional characteristic current shall be the taken as the 10 year
spectra. return value.
s(o 7cp) = S(o - f(v) 2.4.1.2 Variations in current velocity due to tide shall
Eq. 2-11 be considered for inshore operations.
where Guidance Note
Significant local variations in current velocity due to tide may occur
cp = Angle between direction of elementary wave If site specific data are not available current variations should be
trains and the main direction of the short monitored prior to and during the operation, see Pt I Ch.2 Sec 3
crested wave system.
S(o ,cp) = Directional short crested wave power density 2.4.1.3 Effects of sixnultaneous occurrence of current
spectrum. and waves shall be considered.
f(cp) = Directional function. Guidance Note
Although the tidal current velocity can be measured, and the wind
Energy conservation requires that the directional generated current velocity can be calculated, the resulting current in
function fulfils Eq. 2-12; the extreme storrn condition is a rather uncertain quantity. Note that
errors in the estimation of current velocity are offen considered to
Vmax represent one of the most critical uricertainties in the load analysis
I f(cp)dcp = 1
Vrniri
2.4.1.4 In open areas the characteristic wind-generated
Eq. 2-12 current velocities at still water level may, if statistical
In absence of more reliable data the following directional data are not available, be taken as;
function may be applied for H,between 2 and 10m; V& = 0.015*U(~,&eao)
H;") cosHs(9)
i(p)= (0"116+0.3~ -7112 r cp In/2 Eq. 2-14
where
f ( d =0 elsewhere
Eq. 2-13 U(z,f eao) is the wind velocity according to 2.2.
z = 10 [m]
Directional short crestness should not be considered for
significant wave heights exceeding 10m. tm- = 1 [hr]
2.3.6 Swell
~ ( z ) = Total current velocity at level z. 2.4.2.4 Characteristic water levels shall be taken as
z = Distance from still water level, positive expected astronomical tide variations plus/minus storm
upwards. surge effects. Both a maximum and minimum
v = Tidal current velocity at still water level. characteristic water level shall be defined for operations
v, = Wind generated current velocity at still water sensitive to tidal variations, see Figure 2.3.
ievei.
h = Water depth to still water level (taken
positive)
= Reference depth for wind generated current, h(j
=50m
-
Figure 2.2 Current stretching method
r
I I
CURRENT PROFILE CURRENT PROFILE STRETCHING
NO WAVE ( Vco = Vcl = Vc2 )
( Acl > Aco , Ac2 )
January 1996 Rules for Marine Operations
Page 12 of 20 Pt.3 Ch.3 Design Loads
3.2.5.6 Restraint effects caused by combination of 3.3.1.4 Wave slamming loads, see 3.3.7,
friction and global deflections shall be considered. hydrodynamic loads and hydrostatic loads on members
protruding over the barge side shall be considered. The
effect of such loads on motion characteristics and on
3.2.6 Tolerances seafastening /grillage shall be accounted for.
3.2.6.1 Loads caused by operational or fabrication
tolerances exceeding tolerances stated in the design 3.3.2 Second order wave loads
standardslcodes shall be considered. Typical examples
may be; 3.3.2.1 Second order wave drift forces may be
- set down tolerances (load out, positioning), important for design of certain marine operations. The
- shimming tolerances, and effect of second order drift forces shall be considered for
- uncertain deformation (in load distributing these cases.
material). Guidance Note
Drlft are particular Important for large volume structures, desrgn of
3.2.6.2 Characteristic loads shall be based on specified moorlngs and pos~t~on~rig systems, towrng resistance estimates, etc
maximum or minimum values.
3.3.2.2 Second order wave ioads may be assumed to
consist of;
3.2.7 Model testing mean wave drift forces, and
- slow varying wave drift forces.
3.2.7.1 Testing to determine motions or loads may be
required. Reference is also made to 3.3.3.1 3.3.2.3 Long period responses exitated by slow drift
forces shall be investigated.
3.2.7.2 Adequate and reliable model test data should be
used to verifylcorrelate theoretically calculated
environmental loads. This is particularly relevant for 3.3.3 Analysis of motions
geometrically complex structures and for new design or
operational concepts.
3.3.3.1 Motions of floating objects shall be determined
for the relevant environmental conditions and loads.
Testing of models or full scale structures may be carried
3.2.7.3 The law of similarity shall be carefully out where relevance of theoretical approaches are
considered in order to obtain a representative test result. uncertain, or where the design is particularly sensitive
Effects that may influence the measured quantity, and
for motions.
that can not be represented in the model test shall be
identified and consequences of these effects should be Estimation of motions from model testing or by
evaluated. theoretical calculation has associated advantages and
disadvantages. The hvo approaches are generally to be
considered as complimentary rather than as alternatives.
3.3 WAVE LOADS
3.3.3.2 It is recommended to correlate theoretical
calculations against relevant model test data (if available)
3.3.1 First order wave loads in cases where strong non-linear behaviour may be
expected. Such cases may be when;
3.3.1.1 Wave loads should be estimated according to a - overhanging cargo is being occasionally
deterministic or stochastic design method. A wave
submerged, or
period range according to 2.3.4 or 2.3.5 should be -
investigated. there are large changes in the water plane area
with draught.
Guidance Note
if any responses are found dimensioning for T, < 2 5 2 ~ ~ ,the
, 0 ~ ~ 3.3.3.3 The analytic models should be checked with
response should be checked in these areas with H,=O 17~; '* respect to sensitivity to input parameters, see 3.2.2.
3.3.1.2 Wave loads shall be determined by use of
methods applicable for the location and operation, taking 3.3.3.4 Recognised and well proven six degrees of
into account the type of structure, size, shape and freedom linear or linearized computer programs,
response characteristics. utilising the strip theory or 3D sink source techniques
are generally recommended. Special considerations shall
3.3.1.3 Effects of wave elevation shall be evaluated, be made to the non linear damping effects. 'I'he effect of
and if necessary included in the design verification. forward speed shall be evaluated.
Rules for Marine Operations January 1996
Pt.1 Ch.3 Design Loads Page 15 of 20
3.3.6.3 The gravity component shall be considered 3.4.1.3 The gravity components due to wind heeling
when determining the RAO's for inertia loads (e.g. shall be considered.
transverse accelerations). Guidance Note
DNV Classification Note 30 5 , "Environmental Conditions and
Environmental Loads" give further informatiori with respect to shape
3.3.6.4 Inertia loads due to motion should be calculated coefficients, effects of angulare wind and 3D effects
for all six degrees of freedom.
Guidance Note 3.4.2 Current loads
This include also an evaluation of inertia effects from roll and pitch
These effects should as a minirriuni be quantified, and the effect
evaluated. This is particularly relevant for barge transports with
3.4.2.1 Current loads shall be calculated based on
large roll motions characteristic current velocity, see 2.4, and recognised
methods.
3.3.7 Slamming loads
3.4.2.2 Current induced drag loads shall be calculated
3.3.7.1 Elements in the splash zone or overhanging the considering both current and wave particle velocity.
outer borders of the floating body shall be investigated
w.r.t. possibility and effect of slamming loads. 3.4.2.3 Increased current velocities/loads due to
shallow waters or narrow passages shall be considered.
3.3.7.2 Shock pressures on surfaces in the splash zone,
caused by breaking waves, shall be investigated.
January 1996 Rules for Marine Operations
Page 16 of 20 Pt. P Ch.3 Design Loads
3.5 STATIC LOADS 3.5.2.5 The weight control system should be employed
until the installation is compieted. W-eight estimates
3.5.1 Weight estimates shall be corrected for remaining work.
Guidance Note
3.5.1.1 Weight and position of centre of gravity should Note that normal weighing operations only identify the COG position
preferably be determined by weighing. If weighing is In a horizontal plan. inaccuracies in veriical COGposition should
hence be specially considered for operations sensitive to vertical
not feasible, the weight and centre of gravity should be COGposition.
calculated on basis of accurately specified weights and
volumes, and/or weighed or estimated weights of parts
of the object.
3.5.3 Centre of gravity
3.5.3.1 Inaccuracy in COG position shall be considered
3.5.1.2 Weighing equipment with inaccuracy higher in the design loads. To allow for COG inaccuracies a
than 3 % is not recommended. If weighing equipment COG envelope or box is recommended. 'fie size of the
with inaccuracy higher than 3 % is used the characteristic envelopelbox should reflect the operationai and
weight should be adjusted, e.g. by application of an structural sensitivity to COG variations. Further should
inaccuracy factor. ?'his factor should be defined object shape, size, type of operation, control possibilities
considering the weighing arrangement and procedures. (weighing, transfer operations) etc., be considered when
establishing the COGbox.
3.5.2 Characteristic weight Guidance Note
For early design phases too small envelopelbox should be avo~ded
3.5.2.1 Characteristic weight shall be taken as one of Box sizes less than I x l x l m should be avoided
the following; Guidance Note
For operations with a linear relation between COGshifts and
a) weighed weight, loadslload effects, or operations less sensitive to COGshifts,
b) weight according to a detailed weight control inaccuracy in estimated COGmay be accounted for by an
iriaccuracy factor This factor should normally not be taken less
system, or than 1 05
c) estimated weight.
For characteristic weights based on weighings after 90%
completion, an inaccuracy factor of 1.0 is acceptable, see 3.6 HYDROSTATIC LOADS
also 3.5.2.2 and 3.5.2.3. For characteristic weights
based on c), a weight inaccuracy factor of minimum 1.1
3.6.1 Characteristic hydrostatic loads
should be applied.
Guidance Note 3.6.1.1 FIydrostatic loads can generally be categorised
For designs having critical details in tension, possible minimum as permanent loads (P).
weights should also be considered in the designtengineering
phases, i e. characteristic weight divided by the inaccuracy factor. Characteristic loads should be based on maximum and/or
minimum expected values.
3.5.2.2 A weight control system that continuously
forecast final weight and COGpoition, is recommended.
3.6.1.2 The buoyancy of the object should be
The system should include all components and consider
determined on the basis of an accurate geometric model.
weight uncertainties. It is recommended to establish and
The position of the center of buoyancy should be
maintain an overall weight inaccuracy factor based on
established accordingly.
corresponding factor for each objectlcomponent The
factors should be changed (reduced) during the
designlfabrication as found appropriate.
3.7 RESTRAIN LOADS
3.5.2.3 Weight and COGposition estimates based on
weight control systems should normally be 3.7.1 General
confirmedJcalibrated towards one or more weighings.
3.7.1.1 Loads and motions due to interaction between
3.5.2.4 A detailed weighing procedure, including structures deflecting in environmental condition (e.g.
equipment specifications, should be made. The waves, temperature, redistribution of ballast etc.) shall
weighing should normally be repeated at least three be considered, see also Pt. 1 Ch.4 Sec. 2.2.4.
times.
Rules for Marine Operations January 1996
R . 1 Ch.3 Design Loads Page 17 of 20
3.7.1.2 Horizontal restraint loads may typically occur 3.8.2.2 The behaviour of the vessels or structures
with a statically undetermined seafastening arrangement. during the impact, and thus the distribution of impact
Guidance Note energy between kinetic rotation and translation and
Horizontal restraints may typically occur for "pitch" seafastening
deformation energy, should be considered by dynamic
arrangements with stoppers at both "ends" Restraint loads may equilibrium or energy considerations.
riormally be ignored for "roll" stopper arrangements if the stoppers
are arranged on both sides of the module arld each stopper supports
load in one direction only If the stoppers support load in both
3.8.2.3 Both local effects (deformation, damage, etc.)
directions the effect of restraints should be considered. and global load effects (acceleration, global stress, etc. )
It is generally recommended to, as far as possible, avoid horizorital shall be considered.
restraint loads through proven design of seafasteriing
Guidance Note
Guidance Note
DNV, Rules for Classification of Mobile Offshore Un~ts,Pt 3 Ch 1
In order to obtain a statically determined system, seafastening and
Sec 4 and DNV, Veritas Offshore Standards, RP D205 (May 1981)
grillages are often arranged with sliding surfaces If sliding surfaces
"Impact Loads from Boats" give further guidance for 2siirnating
are used, any effects caused by the sliding should be considered.
impact loads
i e possible clashes, fixation of "low friction" pads etc
3.8.1 General
-
figure A1 Area Definition.
150
0"
180
I
150
I
I?O 90
I
60
I
30
I
0
I 3?
60
9P 120
I
ieo
90 1 I I I I I I I I I I I
I
180 150 120 90 60 30 o 30 60 90 120 150 180
-
Table A2 Gamma Function Values
0.8896
0.8914
0.8935
0.8959
RULES FOR
PLANNING AND EXECUTION OF
TtE OPEIPlaTIONS
PART 1 : GENERAL REQUIREMENTS
PAR'S 1 CHAPTER 4
JANUAR 1996
SECTIONS
1. INTRODUCTION ...................................................................................................................4
2. DESIGN PRINCIPLES ............................................................................................................. 6
3. DESIGN METHODS ...............................................................................................................9
4. RESISTANCE AND MATERIALS ............................................................................................ -13
1.2.2 Symbols
The list below define the symbols used in this chapter:
A: Accidental load, see Pt. I Ch.3 Sec. 3.1.6.
D: Deformation load, see Pt. I Ch.3 Sec. 3. I. 4.
E: Environmental load, see Pt. I Ch.3 Sec. 3. i.5.
F. Load.
Fc : Characteristic load.
Fa: Characteristic load.
F, : Design load.
F,,, : Maximum loads due to deflections.
F, : Load.
F m: Characteristic static load components.
F : Amplitude of dynamic load components.
F : Maximum inertia loads due to motion.
F : 'Total design load.
F, : Wind force in x direction.
F, : Wind force in y direction.
F, : Inertia force in x direction.
Fy : Inertia force in y direction.
F, : Inertia force in z direction.
FLS : Fatigue limit state.
fc : Characteristic strength.
f, : Critical buckling stress.
fd : Design strength.
f, : Critical elastic buckling stress.
fy : Yield strength.
L: Live load, see Pt. 1 Clz.3 Sec. 3.1.3.
P: Permanent load.
PLS : Progressive collapse limit state.
4: Usage factor.
q0 : Permissible usage factor.
R: Resistance.
RJ Design resistance.
Rc : Characteristic resistance.
S: Loading effect.
S, : Design load effect.
SLS : Serviceability limit state.
ULS : Ultimate limit state.
W: Load due to self weight (vectors).
Yf : Load coefficient.
Yn : Load coefficient.
Ym : Material coefficient.
, : Material coefficient for ULS.
h: Reduced slenderness.
Januar 1996 Rules for Marine Operations
Page 6 of 15 Pt.1 Ch.4 Structural Design
2. DESIGN CWLES
2.1.1.6 Structures shall preferably not be designed to 2.1.5 Protection against accidental damage
rely on compressed air such as internal over pressure in
buoyant members or underbase air cushions to obtain 2.1.5.1 The structure shall be protected against
sufficient safety against structural failure. This may, accidental damage by the following two principles:
however, be exempted from in special cases upon - Reduction of damage probability.
thorough consideration of the systems involved, - Reduction of damage consequences.
including back-up systems, redundancy, failure
consequences, duration of the operation, etc. 2.1.5.2 Pipes, equipment, structures etc. which in a
damaged condition involves risk of accidental flooding,
explosion, fire or pollution, shall be protected to
2.1.2 Structural details lrrinimise the risk of accidental damage. The protection
may be established by providing a sheltered location, by
2.1.2.1 Transmission of tensile stresses through the
local strengthening of the structure, or by appropriate
thickness of rolled steel elements (plates, beams etc.)
fender systems.
should as far as possible be avoided.
2.1.2.2 Structural details above the waterline shall be
so arranged that water will not be trapped in the
structure if this may cause damages such as e.g. rupture
due to freezing of the water.
Rules for Marine Operations Januar I996
Pt.1 Ch.4 Structural Design Page 7 of 15
2.3 DESIGN ANALYSIS AND CRITERIA 2.3.2.3 Local modes of failure may be;
- plastic overIoading (yield),
2.3.1 General - buckling,
fracture,
2.3.1.1 The analytic models used for evaluation of - large deflections, and
responses, structural behaviour and resistance must be - excessive vibration.
relevant considering the design philosophy, type of
operation and possible failure modes. They should
satisfactory simulate the behaviour of the structures, its
supports, and the environment.
3.1 VERIFICATION METHODS 3.1.2.4 ?he method is particularly suitable for non-
linear problems since safety coefficients are included
3.1.1 Probabilistic methods both on the load side and on the material side.
3.1.1.1 The evaluation of safety may be based on 3.1.3 Permissible stress method
probabilistic methods. In these methods calculations are
made to determine the probability of failure making use 3.1.3.1 By this method the target safety is obtained by
of a probabilistic description of the joint occurrence of calibrating an inverted safety factor which is applied to
the relevant parameters involved, taking into account the the characteristic value of the structural resistance. The
true nature of the failure domain. All relevant failure inverted safety factor is normally referred to as the
modes shall be considered, see 2.3.2. permissible usage factor.
3.1.1.2 All parameters which are essential in the 3.1.3.2 Generally the factors should be defined such
analysis of an actual failure criterion shall be described that the safety level will be equal or greater than
as stochastic variables. Such parameters are loads and obtained with the partial coefficient method.
materials' strength, geometry, imperfections, Guidance Note:
uncertainties in the failure criterion model used, etc. The common used basic usage factors in ULS are 0.6 considering P
and L loads onlv and 0.8 when E loads are included as well.
The graphs in h u r e 3-1 compare the safety level (i e. characteristic
3.1.1.3 Probabilistic analyses may be directly used as a loadlcharacteristicresistance) applying the partial coefficient method
design method or it may be used in combination with and the permissible stress method Usage factors are as indicated
another method. Particular benefit of this method may above, r, = 1 15, equal characterrstrc loads and loadfactors
be achieved for the determination of partial coefficients, accordrng to Table 3 1are assumed
see 3. I. 2, to be used in dynamic problems, associated -
Figure 3-1 Comparing safety levels
with the determination of design loads for floating and
compliant structures. 17
15
3.1.1.4 In probabilistic design analyses the design 15
criteria are normally that calculated probabilities of 3: : I d
failures shall not exceed specified target probabilities, ,.
4s
1 1 3
see also Pt. 0 Ch.1 Sec.1. A
!
12
3.1.2.1 In the partial coefficient method the target The graphs in Figure 3-1 indicate that the safety level obtained by
safety is obtained by multiplying characteristic values applying an 113 allowable stress increase, i.e. from 0.6 to 0.8, due to
(reference values) of loads and structural resistance by the presence of E loads, are not generally acceptable. An acceptable
safety level may be obtained by;
calibrated coefficients such as load and material - increase the characteristic E loads, or
coefficients. - decrease the basic usage factor.
For non linear problems (e. g. buckling) an additional reduction in the
3.1.2.2 How partial coefficients are applied to obtain permissible usage factor may be applicable in order to ensure an
design values for load and structural resistance and to acceptable safety level.
ensure adequate safety is explained in 3.2.4
3.2.5 Ultimate limit state - U7LS 3.2.6.2 The evaluation of safety against progressive
collapse (PLS) shall be carried out in the following two
3.2.5.1 For the ultimate limit states (ULS) the two load steps:
conditions a and b as given in the Table 3.1 below shali Determination of effects (damages) caused by an
1)
be considered. accidental situation on the intact structure. For
this check loading condition c applies, see Table
-
Table 3.1 Load factors for ULS 3.3 (loads of type E may be ign&ed).
2) Verify that the damaged structure may resist the
design loading effect caused by P, L, D, and E
without the occurrence of a global mode of
failure, see 3.2.2.2. See also Table 3.2, loading
Load categories P, L, D, E and A are described in Pt 1 Ch 3 Sec 3
condition d.
3.2.5.2 For loads and load effects that are well
controlled a reduced load coefficient yf = 1.2 may be
used for the P and L loads instead of 1.3 in load
condition a.
Guidance Note:
A load coefficient of 1 2 is for projects within the petroleum act~vities
on the Norwegian continental shelf, subject to NPD's approval
3.2.5.3 Where a permanent load P (e.g. self weight or 3.2.7 Fatigue limit state - FLS
hydrostatic pressure) causes favourably load effects a
load coefficient yf = 1.0 shall be used for this load in 3.2.7.1 For marine operations of long durations and
load condition a. with elements exposed to high cyclic loads the
possibilities and effects of fatigue should be considered.
3.2.5.4 In cases where the load is the result of
counteracting and independent large hydrostatic 3.2.7.2 The fatigue limit state (FLS) shall be evaluated
pressures the appropriate load coefficient shall be applied according to procedures given in a recognised code or
to the pressure difference. However, the pressure standard. Such evaluation should be based on the
difference should not be taken less than 0.1 times the defined operation period and the anticipated load history
hydrostatic pressure. during the marine operation
3.2.5.5 In dynamic problems special considerations of 3.2.7.3 All load coefficients shall be
application of the load coefficients are necessary. In lieu yf = 1.0
of a refined analysis, e.g. such as indicated in 3.1, the
load effects may be found by application of load
3.2.7.4 If a deterministic approach by calculating a
coefficients after having found the responses, e.g. after
Miner sum is used, the Miner sum shall not exceed the
having solved the equations of motion for vessel motion
values indicated in Table 3.3.
response analysis.
Guidance Note
The load categories P, L, D, E and A are described in Pt I Ch 3
Sec.3.
3.3.1 General
4.1 STRUCTURAL RESISTANCE 41.2.6 The characteristic static resistance of steel, fc, is
to be taken as the smaller of;
4.1.1 General - the guaranteed minimum yield stress, fy, or
- 0.85 times minimum tensile strength of the
4.1.1.1 The structural resistance shall be determined in material.
accordance with a recognised code or standard, see
i.i.2. 4.1.2.7 The critical buckling stress f, shall be
determined from a recognised code or standard, see
i.1.2.
4.1.2 Characteristic resistance
4.1.2.1 The characteristic values of resistance 4.1.3 Material coefficients - ULS
parameters are values having agreed probabilities of
exceedance. 4.1.3.1 In ULS the material coefficient for steel
structures is normally taken as:
4.1.2.2 The characteristic resistance Rc may be y, = i.15
determined on the basis of characteristic strength of
materials, f,,; 4.4.3.2 For members in compression the material
coefficient is to be taken according to Table 4.1.
Rc = R(fc)
Eq. 4-1
where -
Table 4.1 Material coefficients for members in
R: resistance
R(fc) : R - function of fc
4.1.2.3 For structures not susceptible to structural plate feld. 1.05 1.05 1.05
instability (buckling) the characteristic resistance (if Girders, beams
written as stress) is equal to the characteristic strength of stiffeners on plates
inaterials; and shells. 1 1.15 1 1.15 1 1.15
Columns and beam
Rc = fc columns. 1 1.15 1 1.12t0.16h / 1.28
Eq. 4-2 Shells of sinale
curvature.
- I
1 1.15
1
1 1.08t0.361,
1
1 1.44
Shells of double I 1 I
4.1.2.4 For structures susceptible to buckling the curvature. 1 1.44 1 1.35+0.45A. 1 1.88
characteristic resistance may be determined on the basis
of critical buckling stress; 4.1.3.3 In ULS the material coefficient for static
strength of tubular joints should be chosen according to
Rc = R(f,)
Eq. 4 3 the applied code, but never smaller than 1.15.
where
f, : critical buckling stress
4.1.3.4 The material coefficient for plastic design
approaches should be agreed in each individual case.
R(f,) :R - function of f,
4.1.2.5 'fie characteristic strength of materials, fc, shall 4.1.3.5 If redistribution of stresses found by linear
be based on the 5th or the 95th percentile of the test elastic analysis are assumed, an increased material factor
results, whichever is the most unfavourable. for main elements, e.g. girders on a stiffened plate,
should be considered.
If statistical data are not available, the characteristic
values may be taken from a recognised code or standard,
see I. 1.2.
Januar 1996 Rules for Marine Operations
Page 14 of 15 Pt.1 Ch.4 Structural Design
4.1.3.6 In ULS the material coefficient for certified 4.2.2 Structural categories
steel wire ropes and chains shall normally be taken as:
4.2.2.1 Structural elements and connections shall be
grouped in categories determined according to;
Guidance Mote: - cype of stress,
= 1.15/0.85/0.9 = 1.5
- presence of cyclic loading,
where
1.15 is the general steel material coefficient,
- presence of stress concentrations,
0.85 is a factor to account for that the characteristic strength, - presence of restraint,
see 3.1.3) of the ropes and chains is based on the tensile - ioading rate,
strength (MBL), and - consequences of failure, and
0.9 is a factor to account for wear arid tear. (this factor may
vary considering the intended use of the ropeslchains).
- redundancy.
4.1.3.7 Material coefficients for other materials e.g. 4.2.2.2 ?'he following categories of structural elements
concrete, concrete reinforcement, wood, synthetic shall normally be used;
materials, soil, etc. shall be in accordance with a - speciui - those portions of primary structural
recognised code or standard. elements which are in a way of critical load
transfer point or stress concentrations.
4.1.3.8 If a material coefficient y, = 1.0 is found more - primary - structural elements essential to the
unfavourable than the values given above, this value overall integrity of the unit where failure could
shall be used. lead to loss of human life or considerably physical
damage, and
- secondary - structural elements of less importance
4.1.4 Material coefficient - PLS where failure is unlikely to result in loss of
human life or considerable physical damage.
4.1.4.1 The material coefficient for steel may in PLS be
taken equal to: 4.2.2.3 The categories define requirements for
materials and extent of inspection and non destructive
Ym = ~m,,/l. 15
examination.
where
y,, = the applicable material factor in ULS, see 4.1.3.
4.2.3 Material quality
4.1.4.2 The material coefficient for wire ropes may in 4.2.3.1 Selection of steel types shall be decided based
PLS be taken equal to :
structural application. All steel materials shall be
y, = 1.3 suitable for the intended service conditions and shall
have adequate properties of strength, ductility,
4.1.5 Material coefficient - SLS toughness, weldability, and corrosion resistance.
4.1.5.1 The material coefficient for steel may in SLS be 4.2.3.2 Material types and qualities shall normally
taken equal to: comply with requirements in DNV Rules for
y, = 1.0 Classification of Mobile Offshore Units, Pt.2 Ch.2 and
Pt.3 Ch. 1 Sec.2
4.1.6 Material coefficient - FLS
4.2.3.3 Non structural steels shall have adequate
4.1.6.1 The material coefficient for steel may in FLS be mechanical properties and weldability for the intended
taken equal to: application.
y, = 1.0
4.2.1 General
9
4.2.4 Fabrication
4.2.5.6 P e r s o ~ e evaluating
l results from NDE shall
posses thorough knowledge and experience with NDE.
RULES FOR
PLANNING AND EXECUTION OF
fMANm OPEWmONS
PART 2 : OPERATION SPECIFIC REQUIREMENTS
PAKT 2 CHAPTER 1
SECTIONS
1. IN'lXODUCTION ................................................................................................................... 5
2. LOAD OUT .......................................................................................................................... 7
3. FLOAT OUT....................................................................................................................... .I5
4. UFT OFF .......................................................................................................................... .18
5. MATING ...........................................................................................................................-23
6. CONSTRUCTION AFLOAT ................................................................................................... .27
DET NORSKEVERITAS
Veritasveien 1, N-1322 Hsvik, Norway Tel.: +47 67 57 99 00, Fax.: +47 67 57 99 11
' f i s is the first issue of the Rules for Planning and This chapter is valid until superseded by a revised
Execution of Marine Operations, decided by the Board chapter. Supplements to this chapter will nor be issued
of Det Norske Veritas Classification A/S as of December except for IIlinoraInendnlents and an updated list of
1995. These Rules supersedes the June 1985, Standard corrections presented in the introduction bookiet.
for Insurance Warranty Surveys in Marine Operations.
Users are advised to check the systematic index in the
These Rules come into force on 1st of January 1996. introduction booklet to ensure that that the chapter is
current.
2.4 STRUCTURES AND SOIL ........................9 3.5 SYSTEMS AND EQUIPMENT ..................16
2.4.1 General .........................................9 3.5.1 General ........................................16
2.4.2 Quays ........................................... 9 3.5.2 Installation systems..........................16
2.4.3 Soil ..............................................9 3.5.3 Air cushion systems ......................... 16
3.5.4 Mooring/Positioning/Towing System .... 16
2.5 SYSTEMS AND EQUIPMENT ................... 9
2.5.1 General ......................................... 9 3.6 OPERATIONAL ASPECTS ...................... 16
2.5.2 Push/pull systems ............................. 9 3.6.1 General ........................................16
2.5.3 Trailers ........................................ 10 3.6.2 Float out site ................................. 16
2.5.4 Skidding equipment .........................10 3.6.3 Clearances ....................................16
2.5.5 Barge ballast system.........................11 3.6.4 Monitoring ................................... 17
2.5.6 Power supply .................................12
2.5.7 Testing ........................................12
2.5.8 Mooring and fendering .....................12
January 1996 Rules for Marine Operations
Page 4 of 28 R.2 Ch.1 Load Transfer O~erations
Table List.
5.1 INTRODUCTION ................................. 23 Table 2.1 - Load out class definition ....................... 7
5.1.1 Application .................................. 23 Table 2.2 .Friction coefficients ............................ 8
5.1.2 Planning and design basis ................. 23 Table 2.3 .Push/pull requirements ....................... 10
Table 2.4 .Ballast capacity requirements ............... 11
5.2 LOADS .............................................. 23 Table 4.1 .Lift off class definition ....................... 18
5.2.1 General ....................................... 23 Table 4.2 .Ballast capacity requirements ............... 20
5.2.2 Skew loads ...................................23
1.1.1.1 Pt. 2 Ch.I , Load Transfer Operations, gives Object :Structure subjected to one or several of the
specific requirements and recommendations for load out, operations defined in this paragraph.
float out, lift off and mating operations. This chapter Site move :The activities necessary to transfer an object
also applies for the construction afloat phases. from one location at the yard to another.
1.2.2.1 General requirements to documentation are 1.3.2.1 During the operation a detailed log should be
given il Pt. 1 Ch.2. Sec. 2.2. prepared and kept, see Pt. 1 Ch. 2 Sec. 2.2.5. '-rhe
following should be recorded:.
1.2.2.2 The following design documentation are - environmental conditions,
normally required; - the sequence of events and
- documenting of adequate strength and capacity of - all monitoring results.
all involved equipment and structures,
- documentation of civil elements (soil, quay, 1.3.2.2 Monitoring of environmental conditions shall
bollards, etc.) engineering calculations, be carried out according Pt. 1 Ch.2 Sec. 3.2.3.
barge data, stability and strength verifications,
and 3.3.3 Weather forecast
- ballast caiculations covering the planned
operation as well as contingency situations. 1.3.3.11 The operation manual should clearly define
weather limitations and requirements to the weather
1.2.2.3 Evaluations and calculations of expected forecast, see Pt. I Ch. 2 Sec. 3.2.
monitoring results should be presented. Acceptable
tolerances should be stated and documented. 1.3.3.2 Weather effects such as swell and tide could be
of significant importance for load transfer operations and
1.2.2.4 An operation manual must be prepared, see should be duly considered.
Pt. 1 Ch.2 Sec. 3.5.
1.3.1 Preparations
2.2.3 Weight of load out equipment 2.2.5.4 The friction coefficient values used shouid not
be ,taken less than specified i11 Table 2.2 unless adequate
2.2.3.1 The weight of the load out equipment (Weq)is in service documentation indicates that other vaiues may
the total weight of equipment and support structures be used.
which moves with the transported object. Such
equipment may be support beams, grillages, skidding
-
Table 2.2 Friction coefficients
shoes, trailers, pushlpull jacks, hydraulic power packs,
etc.
TefloriNVood 0 25 0 08
2.2.4.1 All load effects caused by tide variations shall
be considered. Waxed woodlsteel 0 20 0 12
Sieel rollerslSteel 0 02 0 02
2.2.4.2 Load out operations should normally not be
carried out in significant waves and swell conditions.
Loads due to waves and swell should however be
Rubber wheels1Asphalt
Notes
0.03 0.03
I
considered for barge mooring after the load out - It is assumed that the sliding surfaces are properly
operation. Wave conditions and loads should be lubricated
determined in accordance with Pt. 1 Ch.3 Sec. 2 and 3. - Break out factor to account for extra loading due to long term
effects such as adheslon, settlemenrs, etc IS ~ncludedIn the
statlc coefficierlts
2.2.4.3 Wind and current loads should be determined in - The values are valid orily for contact stresses lower or equal
accordance with Pt. 1 Ch.3 Sec. 3.4. to the allowable contact stresses for the cons~deredmedium
Allowable contact stresses should be obta~nedfrom the
manufacturer or from an applicable code or standard
2.2.5 Skidding loads
2.2.5.1 The expected static and dynamic skidding loads
are respectively the loads required to start and to 2.2.6 Skew load
continue moving the object. These loads are expressed
as; 2.2.6.1 Skew load is the extra loading at object support
points due to inaccuracies in the level of the skidways,
Fs = K (W+ We,) + Ps rolling surfaces, supports, etc.
Fd, = Vd, (W +W,) + Pd,
Eq. 2-1
2.2.6.2 Skew loads could normally be disregarded for
where load out operations where the object has a 3 point
F, : Static skidding load. support system. This could be obtained by including a
F, : Dynamic skidding load. reliable load equalising system.
ps : Static friction coefficient, see 2.2.5.4.
pd, : Dynamic friction coefficient, see 2.2.5.4. 2.2.6.3 For cases not covered by 2.2.6.2, the skew
W : See2.2.2. load should be determined by considering the stiffness of
W,, : See 2.2.3. the object, the supporting structure, the tolerances of
P, : Any other ioad occurring during break out, see skidways, rolling surfaces and supports, movement of
also 2.2.5.2. barge and link beams and load on the barge.
P,, : Any other Ioad occurring during skidding, see Guidance Note
also 2.2.5.2. In lieu of a more refined analysis, the skew load may be determined
considering the object to be supported by 3 support points only
2.2.5.2 Effects of inertia, environmental loads and
slope of the skidding or rolling surface should be 2.2.7 Other loads
considered and if relevant included in the skidding loads. 2.2.7.1 Any other significant loads, not covered above
should be considered in the design of the object and in
2.2.5.3 If two or more push/pull systems are used the the planning of the operation. Such loads may include;
effect of maximum possible differential pushlpull loads - hydrostatic loads on barges,
shall be considered. - impact loads,
- local support loads on grounded barge hulls,
- mooring loads, and
- guiding loads.
Rules for Marine Operations January 1996
Pt.2 Ch.1 Load Transfer Operations Page 9 of 28
2.5.2.4 Back-up pushlpull system capacity should be 2.5.3.4 Adequate global structural strength (spine
able to compensate for the following conditions; strength) should be documented for the actual support
a) Breakdown of one arbitrary self contained conditions.
push/pull unit.
b) Unexpected increase in the skidding loads above 2.5.3.5 Trailers to be used should have adequate
the expected nominal value. handling capabilities and cargo weight capacity giving
wheel ioads within the permissible limits,
2.5.2.5 Requirements to pusW pull back up systems for
the respective load out class are given in Table 2.3. 2.5.3.6 The support lay-out on each trailer shall ensure
stability in both directions of the trailer.
Guidance Note
The back-up capacity for accidental conditions represented by Guidance Note
2 5 2 4 a) may be separate pushlpull units with nominal capacity to A trailer with a fully linked hydraulic suspension need to be regarded
complete the operation in the case of a mechanical breakdown of the more as a distributed load than a suppori structure The supports
main system The back-up capacity may also be spare parts of the on such trailers should be checked for the vertical loading from the
mairi units, if an acceptable repairlreplacement time can be prover1 trailers combined with rnaximum horizorital loads acting or1 the
The back-up capacity for conditions represented by 2 5 2.4 b) may trailers, see 2.5.3 7.
be spare capacity in the main units or back-up pushlpull units.
2.5.3.7 The trailers should be properly supported to
2.5.2.6 Any required modifications during the withstand horizontal loads. These are caused by
operation, e.g. removal of pull bars of the pushlpull "external" effects, i.e. wind, inertia and ground slope,
system lay -out should be proven feasible. Normally, in addition to "internal" effects such as differential
lay-out modifications should be avoided with the object traction and steering inaccuracies.
supported both at the quay and barge.
2.5.3.8 The traction system, either the trailers are self-
propelled or pushed/pulled by tmcks/winches, should
fulfil the requirements in 2.5.2. Ground surface
conditions should be duly considered.
I
3 1
I
120%
I
I
I
hours
No specific, but repair
possibilities shall be
I No
I
!I Guidance Note
Normally the planned operational stroke should be limited to 70% of
I ihe total theoretically available stroke
4 1 120% 1
documented
100% capacity, or repair
ssibilities within 6
I Yes I 2.5.3.10 Contingencylrepair procedures should at least
be presented for;
See 2 2 5 1 for definition of 100% pushlpull capacity - hydraulic systemlhose ruptureslleakage,
- tyre puncture,
steering problems and
2.5.3 Trailers traction failure, see 2.5.2.
2.5.3.1 Trailers (multi wheel bogies) should be used in
accordance with the manufacturer's specifications. 2.5.4 Skidding equipment
2.5.3.2 The hydraulic suspension layout (lkkhg) 2.5.4.1 Skidshoes, steel wheel bogies and steel rollers
should be thoroughly considered. Normally a layout are in this subsection defined as skidding equipment.
giving a three point support condition for the object is Any part of such equipment used for the horizontal
recommended. movement of the object is defined as part of the
pusWpul1 system, see 2.5.2.
2.5.3.3 The trailer design load calculations must
consider; 2.5.4.2 Adequate strength and stability of skidding
- equipment should be documented. All possible
weight of object and relevant equipment,
combinations of vertical load, horizontal load and
- extreme positions of COG,
support reaction distribution should be verified.
- hydraulic suspension lay-out, and
relevant horizontal loads.
Rules for Marine Operations January 1996
Pt.2 Ch.1 Load Transfer O~erations Page 11 of 28
b) Unplanned stops in object movement during the - 100% pump capacity during tide compensation is the
capacity required to compensate for the maximum expected
load out due to repair work, etc. tide variation
C) If required, retrieval of the load out object. - A pump system includes the pump(s) which will cease to
d) Breakdown of ballast pump(s). operate due to a single failure in any component, see 2.5.5.6
e) Breakdown of power supply, including cables. d through g, in the ballast system.
f) Failure of any control panel/switchboard.
g) Failure of any ballast valve or hoselpipe.
January 1996 Rules for Marine Operations
Page 12 of 28 R . 2 Ch.1 Load Transfer Operations
2.5.6.1 Adequate power supply and sources for the 2.5.8.1 General design requirements to mooring
ballast pumps and for the pushlpull units should be systems are given in Pt. 1 Ch.2 Sec.5.3. Other
ensured during the load out. additional requirements applicable for ioad outs are
given below.
2.5.6.2 The need for emergency power supply due to
the following situations should be considered; 2.5.8.2 For additional loadcases to be considered see
a) Breakdown of one arbitrary power unit. 2.3.2.4and 2.3.2.5.
b) Breakdown of the common energy supply.
c) Unexpected increase in the consumption of energy 2.5.8.3 Facilities for retensioning of mooring lines
above the expected value. should be present and in stand by during the load out.
Such facilities may be winches, jacks for tensioning, etc.
Guidance Note
The back-up capacity for accidental conditions represented by
2.5.6.2 a) and b) may be spare units in starid-by position The back- 2.5.8.4 Adequate strength, stiffness and layout of
up capacity for conditions represented by 2.5.6.2c). may be spare fenders should be documented.
capacity in the main unit or a back-up unit installed to assist the
main unit. Guidance Note
Fender desigri solut~onsshould at least consider,
2.5.6.3 Sufficient main and back-up power supply - poss~blerequirement to a stiff mooring system during load out,
- effect of extreme tide variations,
capacity should be documented by calculations. - possible impact loads, arid
- the possibility that the barge could "hang" on the fenders, see
2.5.6.4 Guidance for necessary ballast capacity for each also 2 7 2 3
load out class is given in Table 2.4. For evaluations of
back up requirements an independent power supply
source should be regarded as a "pump system". 2.6 LOAD OUT VESSEL
2.5.7.1 See general requirements in Pt. 1 Ch. 2 Sec.3.4 2.6.1.1 General requirements to vessels and barges are
with respect to testing/commissioning, test procedures given in Pt. 1 Ch. 2 Sec.5.2 and in Pt. 2 Ch. 2 Sec.3.2 and
and test reporting. 3.3.
2.6.5 Maintenance 2.7.3.3 A set down procedure for the object should be
used in order to ensure that the grillage and seafastening
2.6.5.1 A barge handling procedure should normally be
design assumptions are fulfilled.
presented. The procedure should describe berthing, any
relocation, surveys e.g. on-hire and off-hire surveys,
condition surveys etc., moorings (before and after load 2.7.3.4 Nominal set down position and set down
out), watchkeeping, need for barge engineer e.g. for tolerances should be marked on the support stools.
ballasting, etc.
2.7.3.5 Suitable shims should be present at the support
stools in case of any excessive gaps during set down.
January 1996 Rules for Marine Operations
Page 14 of 28 Pt.2 Ch.1 Load Transfer Operations
2.7.3.6 It should be ensured that skidway surface 2.8.2 Barge to barge load transfer
condition is as assumed in the friction coefficient
estimate. 2.8.2.1 A barge to barge load transfer operation is
defined as the activities necessary to transfer an object
2.7.3.7 Planned trailer tracks should provide an between vessels doing mainly a horizontal movement of
adequate surface condition and the tracks should be the object.
marked on the ground and barge.
2.8.2.2 Requirements to load our. operations are
generally applicable for barge to barge load transfer
2.7.4 Grillage and seafastening operations as well.
2.7.4.1 The main requirements for the grillage and 2.8.2.3 Barge to barge load transfer operations could be
seafastening structures of the transported object are
complex involving more than two barges, and different
presented in Pt. 2 Ch.2 Sec. 2.3.2.
support conditions on one or more of the barges. Due
attention should be paid to this fact during planning,
2.7.4.2 The seafastening should coumence immediately design and execution of the operation.
after completion of the load out operation.
Guidance Note
For operation to ae carrled out the level, trim and heel
2.7.4.3 The transported object should be secured to the measurements of the barges may not be suffic~entto control the road
barge to withstand possible impact loads andlor any heel dlstrlbutlon
and trim prior to moving the barge to another location
at the same site for further seafastening. 2.8.2.4 Tide effects can be neglected for operations
involving only floating barges if sufficient bottom
Guidance Note
As a minimum horizorital acceleration of O.lg should be considered
clearance is ensured. Hence, the operation could be
in any direction. Friction should be neglected in the calculations of defined as load out Class 4 or 5.
necessary seafastening capacity.
2.7.5 Monitoring
2.8.1 Load in
3.1 INTRODUCTION 3.2.3.2 The final buoyancy estimate should take place
when the final geometry of the object is established.
P 3.1.1 Application
3.2.4 Other loads
3.1.1.1 This section applies to objects such as gravity
base structures, jacket substructures, loading towers etc. 3.2.4.1 All loads which may occur due to effects such
fabricated in a dry dock, brought afloat and floated out as hydrostatic pressure, impacts, guiding, pulling by
from the fabrication site. tugs and winches, etc. should be considered in the
design of the object and in the planning of the operation.
3.1.2 Planning and design basis
3.2.4.2 The value of other loads should be determined
3.1.2.1 General requirements are given in 1.2.1. considering operational and equipment limitations. For
determination of accidental loads possible failure modes
3.1.2.2 Any local environmental effects should be should be sought for.
identified and considered.
3.1.2.3 Sensitivity studies, see Pt. 1 Ch.3 Sec. 3.2.2, 3.3 LOADCASES AND ANALYSIS OF FORCES
should include evaluation of;
time limitations due to the tide, 3.3.1 Basic loadcases and structural analyses
- extreme tide variations due to atmospheric and
local environmental effects, 3.3.1.1 A float out operation represents different
- limiting environmental conditions, loadcases from the condition when the self weight is
- accidental conditions, and resting on the fabrication supports to the self floating
structural limitations. condition. In principle, the entire float out sequence
should be considered step-by-step and the most critical
loadcase for each specific member should be identified.
3.2 LOADS
3.3.1.2 The global structural analysis required for
verification of the integrity of the structure for the float
3.2.1 General out operation may be omitted provided that analyses
show that other operations or conditions represent a
3.2.1.1 Loads and load effects should be established
more severe condition for the design.
according to Pt. I Ch.3.
3.3.1.3 'I'he float out operation represents a loadcase
3.2.2 Weight for the towinglpositioning winches, wires, brackets,
quick release hooks, etc. 'I'hese structures should be
3.2.2.1 The weight of the object should be calculated capable of withstanding relevant environmental loads in
on the basis of accurate specific weights and volumes addition to the positioning/towing loads.
andlor weighed or estimated weights of parts of the
object, equipment, etc. 3.3.1.4 Additional loadcases due to environmental
loads (mooring forces, etc.) should be considered for the
3.2.2.2 The requirements of 2.2.2 apply. relevant structures (mooring equipment, etc.)
3.2.3 Buoyancy
3.4 STRUCTURES
3.2.3.1 The buoyancy of the self-floating object should
be estimated on the basis of an accurate geometric 3.4.1 General
model. The buoyancy should be estimated for all
relevant draughts. The position of the centre of 3.4.1.1 Structures should be designed as indicated in
@ buoyancy should be estimated accordingly. Pt. 1 Ch.4.
January 1996 Rdes for Marine Operations
Page 16 of 28
-- - Pt.2 Ch.1 Load Transfer Operations
3.4.2.1 The stability requirements in Pt. 1 Ch.2 Sec. 4 3.5.4.1 The moorimg/positioning/towing system
apply. (wires, quick release hooks, winches, etc.) should be
capable of co~ltrollingthe object during the operations.
3.5.3.1 To achieve sufficient bottom clearance during 3.6.2.1 The dry-dock including the float out channel
the operations , air cushions may be applied under the outside the dry-dock should be surveyed prior to float
bottom slabs of the object. An adequate water seal out to verify that the required minimum underkeel
should be used. clearance will be maintained throughout the float out
operation. Obstacles that may damage the object or the
Guidance Note tugs should be removed.
The water seal should be specified considering the underbase
compartmentation, environmental conditions, motions during
operation, horizontal speed and the consequences of loss of air.
Normally, a water seal of minimum 0.5 rn should be used. 3.6.3 Clearances
3.5.3.2 The system should have adequate redundancy in 3.6.3.1 An adequate underkeel clearance inside the
all parts such that breakdown of one arbitrary delivery dock until a reasonable distance from the dock exit
line, compressor or generator does not adversely affect shouid be documented.
the operation.
3.6.3.2 Sufficient side and vertical clearances should be
3.5.3.3 The air leakage from the air cushions prior to ensured considering;
lift off shall be less than 5 % of the compressor capacity. the operational arrangement,
After lift off the leakage shall be monitored to assess the enviro~lentalconditions,
feasibility of continuing the operation. equipment and vessels to be used,
dock water inlet requirements,
3.5.3.4 A proper venting system should be designed to consequences of failure or malfunctioning of any
ensure that all trapped air under the base can be let out one of the pulling sources,
when planned. guiding and fendering arrangements,
bottom clearance, and
float out velocity.
Guidance Note
The minimum vertical bottom clearance should not be less than
0.5rn considering the maximum draught, motions and applicable trim
and heel
Rules for Marine Operations January 1996
Pt.2 Ch.1 Load Transfer Operations Page 17 of 28
Guidance Note
Normally a minlmum width of 1 2 times the object breadth is
recommended for the channel from the dock entrancelaate to open
water If the object is floated out under winch control aiong a fe'nder
at one of the channel sides, a minimum channel width of 1.05 times
the object breadth is recommended Channel width less than 1.05
times object breadth should be specially considered. If the chanr~el
width is greater than 4 times the object breadth, it may be regarded
as open water, see f f . 2 Ch.3 Sec.4.
3.6.4 Monitoring
3.6.4.1 Monitoring and recording, see 1.3.2, of;
- draught, trim, and underkeel clearance,
- position and orientation of the object,
- environmental conditions including tide,
- air pressure in air pressurised compartments,
- air leakage and
- water plug
should be carried out prior to and/or during the float out
operation.
January 1996 Rules for Marine Operations
Page 18 of 28 Pt.2 Ch.1 Load Transfer Operations
4.2.2.2 Items which may cause skew load effects are: 4.3.2.2 Local loads on the object and on the barges
- Fabrication tolerances for the object and for the during positioning and mooring at the construction site
barge supports. after lift off, tow out, etc. should be treated as separate
- Fabrication tolerances for the barge(s). loadcases.
- Vertical offset of the object for each support
condition. 4.3.2.3 Forces in anchoring, mooring and fendering
- Barge heel and trim variations. equipment/structures due to functional and
- Movement of barge centre of buoyancy, gravity environmental loads should be considered.
and flotation relative to draught and ballast
configuration. 4.3.2.4 The force distribution in the object and in the
- Inaccurate positioning of barges relative to the barges, and their global deflections, should preferably be
object supports. determined by a 3-dimensional analysis.
- Deformation of the object and the barges
including the possible introduction of horizontal
loads.
4.4 STRUCTURES
4.4.4.2 The barge supports should be shimmed in 4.5.2.7 'The ballast pumps should be arranged with one
accordance with an appropriate procedure to avoid control centre on each unit. For multi barge operations
unfavourable distortion and load distributions in the the control centre on one of the barges should also be
object or the barge supports, and to account for as built defined as the master baliast control centre. The
deviations. arrangement should be such that simultaneous
debailasting can be effected for all the relevant tanks at
4.4.4.3 A flexible support system should be used each stage.
between the top of the barge supports and the object in
order to ensure an adequate load distribution to all 4.5.2.8 The back-up ballast requirements should be
supports. The flexible support system may be obtained determined by considering the following accidental
by useing crushing tubes, lead plates, wood, a wedge conditions;
system or similar. a) Tide levels and/or tide velocities above/below the
predicted values.
b) Breakdown of ballast pumps.
4.5 SYSTEMS AMD EQUIPMENT C) Breakdown of power suppiy, including cables.
d) Failure of any control panel/switchboard.
e) Failure of any ballast valve or hoselpipe.
4.5.1 General f) One compartment damage of any barge.
g) Air leakage and adjustment of air pressure in alr
4.5.1.1 The systems used for lift off should be pressurised compartments in submerged barges.
designed, fabricated, installed, tested according to Pt. i
Ch.2 Sec. 3.4.
4 5 2 . 9 Guidance for minimum necessary total ballast
capacity, i.e. including back-up, dependent on lift off
4.5.2 Ballast system ciass is given in Tabie 4.2. See also notes below the
table.
4.5.2.1 Barge ballast systems should have sufficient Table 4.2 - Ballast capacity rc juirernents
capacity to compensate for both change of load and I Lift off I Normal Operation - Tide Compensation -
change of tide during the entire lift off operation. Class I Load transfer as planned Load transfer stopped
1 I Minimum 200% capacity Minimum 120% capacity
with intact system and with intact system and
4.5.2.2 Any strength limitations and/or hull deflection minimum 120% capacity min~mum100% capacity
restrictions should be considered in the ballast in all tanks with any one in all tanks with any one
procedure. pump system failed. pump system failed.
Minimum 130% capacity Minimum 150% capacitv
with intact system arld with intact system and
4.5.2.3 The power supply is regarded as an integrated minimum 100% capacity minimum 120% capacity
part of the ballast system in this sub-section. in all tanks with any one in all tanks with any one
pump system failed. pump system failed.
Minimum 130% capacity As Class 2
4.5.2.4 In order to maintain maximum control with the with intact system and a
ballast, it is normally recommended to apply different contingency plan
ballast tankslsystems for; covering accidental
situations, see 4.5.2.8.
tide, and 4 As Class 2 No requirements
- weight transfer. 5 As Class 3 No requirements
7
4.5.2.10 The back-up systems should be adequately 4.6.2.2 The barge deflections should be maintained
separated from the main system such that failure of any within an acceptable range during lift off by selecting
component does not adversely affect the safe conduct of adequate ballast configurations for each barge.
the operation. Tolerances for the barge deflections should be
established considering the maximum allowable skew
4.5.2.11 Any umbilicals used for air pressurisation of loads at the barge supports.
submerged barge compartments should be connected to
valves at the barge tanks. Air pressurised barge tanks
4.6.3 Stability afloat
should be fitted with safety valves.
4.6.3.1 Special attention should be paid to accurate
4.5.3 Positioning systems interpretation and application of hydrostatic data for the
barges. For complicated operations inclining tests may
4.5.3.1 General design requirements for mooring and be relevant to verify the hydrostatic stability parameters.
positioning systems are given in Pt.1 Ch.2 Sec.5.3 and
5.4. Other additional requirements applicable for lift off 4.6.3.2 Sufficient stability afloat should be ensured for
are given below. single barges during positioning. The following
requirements apply;
4.5.3.2 See 4.3.2.2 and 4.3.2.3 regarding loadcases to a) G M 2 1.0m
be considered. b) Pt. l Ch.2 Sec. 4.
c) fm=0.3m+H,,,/2,seealso2.6.4.2
4.5.3.3 The positioning and mooring system should
provide for correct alignment and securiig of the barges 4.6.3.3 The requirements to stability after lift off are
during all phases of the operation. given in Pt. 1 Ch.2 Sec. 4.2.
4.5.3.4 Facilities to re-tension mooring lines should be 4.6.3.4 For lift off operations camed out with open
present and in stand by position during the lift off. Such manholes the minimum "effective freeboard" (f&
facilities may be winches, jacks for tensioning, etc. during load transfer, including any defined "stop point"
before lift off, should be;
4.5.3.5 Fendering structures should be arranged on the
barge sides or the construction pillars to prevent
f,, = 0.5m + H,,,/2, seealso 2.6.4.2
damages to the barges during the lift off operation.
4.5.3.6 The barges should be equipped with guides to 4.7 OPERATIONAL ASPECTS
ensure accurate positioning underneath the object prior
to commencing the lift off operation. 4.7.1 General
4.6.1.1 Requirements to vessels are given in Pt.1 Ch.2 4.7.2.1 The lift off site should be surveyed prior to
Sec.5.2 and 2.6.3.1. installation of the barges. The survey should verify that
the barges vertical and lateral clearances are acceptable
4.6.1.2 For requirements to barge maintenance see for the planned operation. Obstacles that may damage
2.6.5. the barges or impede the operation should be removed.
Preparations Gu~danceNote
Normally a remote readlrlg soundlng system should be used for tank
water level control A back-up system but not necessarily remotely
.1 'The requirements of 1.3.1apply controlled (e g hand ullagelng) should be provlded If access to any
tank IS obstructed, e g by seafasten~ngsuppons, alternative access
4.7.3.2 Means for closing leakages in barge tanks snould be arranged
should be available during the operations. Such means Guidance Note
Support reactlor1measurements and comparlsorl of the results w~th
may be leak mats, steel plates, welding equipment, etc. the actual ballast water and tlde sltuatlon should be performed
conr~nuouslydurlng the Ilft off The actual devlatlon In total loaa and
moments should be noted for each measurement and Compared
4.7.4 Clearances wlth agreed tolerances
5.3.2.2 All realistic accidental load conditions should 5.5.2 Multi barge ballast systems
be identified, see Pt. 1 Ch. 3 Sec.3.8. Identified
accidental loads that cannot be neglected due to low 5.5.2.1 The requirements given in 4.5.2 apply. There
probability, see Pt. 1 Ch. 2 Sec.2.2.3, should be included is no tide influence, as the substructure is floating, hence
in the design calculations. Class 4 or 5 is applicable.
5.3.3 Deck horizontal restraint 5.5.3 Substructure ballast and sounding systems
5.3.3.1 In the period from deck weight transfer to the 5.5.3.1 The deballast systems should have sufficient
substructure until the permanent connection between capacity to complete the deck mating operation within
deck and substructure has been established, the deck the time limitations determined by the weather
shall be horizontally restrained. forecasting period.
Guidance Note
5.3.3.2 'The capacity of the horizontal restraint Normally the operation should be designed to be performed within a
per~odof 48 hours
capability shall be sufficient to hold the deck in a worst
possible damage case including wind heel and possible
5.5.3.2 Valves used for ballastingldeballasting should
effects of current and waves after deballasting to hook- be doubled when installed on self floating structures not
up draught. This heel condition may be regarded as a complying with the one compartment damage stability
PLS situation. The effects of friction may be taken into requirement.
account.
5.5.3.3 One back-up unit should be available for each
ballast pump, compressor, and generator.
5.4 STRUCTURES
5.5.3.4 The ballastldeballast systems should be capable
5.4.1 General of levelling the structure by eccentric
ballastingldeballasting to compensate for any shift in the
5.4.1.1 Structures shall be designed as indicated in centre of gravity during the mating operation.
Pt. 1 Ch. 4.
5.5.3.5 Pipe systems and valves should be designed to
prevent accidental cross flooding and uncontrolled
5.4.2 Barge supports ingress of water.
5.4.2.1 The barge supports should have sufficient
strength to withstand all vertical forces and horizontal 5.5.3.6 Ballast compartments, which are intended to
forces introduced by deflections of the deck and the remain dry, should have adequate drainage capability to
barges during deck weight transfer. eliminate free surface effect from uncontrolled ingress of
water. Water detection sensorslequipment should be
evaluated.
5.4.3 Substructure
5.5.3.7 Air venting systems from cells and ballast
5.4.3.1 The substructure should be protected against compartments should have adequate monitoring and
possible accidental loads such as mooring line failure control to prevent excess structural loading during
(not relevant if the mooring lines are slack during deck ballasting and deballasting of compartments.
mating), flooding of buoyant compartments, dropped
objects, collision loads, etc., during the mating 5.5.3.8 Umbilicals for remote power and control
operation. should be adequately protected and be backed up by
additional systems to cover breakdowns or rupture.
5.5 SYSTEMS ANZ)EQUIPMENT 5.5.3.9 Power and control systems should have
adequate redundancy to cover failures to ensure deck
transfer within the defined period.
5.5.1 General
5.5.3.10 Immersion trials should be performed at 5.6.1.3 During mating, the relative movements of the
selected draughts prior to the mating operation. These structures due to environmental loads should be carefully
trials should be used to test the performance of the considered.
pumps and powerlcontrol systems and water tightness of
the structure. 5.6.1.4 All back-up systems should be ready for
immediate activation during the critical stages of the
mating operation.
5.5.4 Primary positioning system
5.5.4.1 General requirements to guiding and 5.6.1.5 For mating operations between GBS and deck
positioning systems are given in Pt. 1 Ch.2 Sec.5.4. structures the schedules for mating should be carefully
planned in order to minimise the time at the minimum
5.5.4.2 The substructure and the deck structure should draught. In event of delays the substructure (iarge
be secured by primary positioning systems, which gravity base structure) should be returned to a stand-by
normally are; draught, such that the minimum freeboard is not less
than 20 meters. The substructure should have the
- a permanent mooring system for the substructure. capability of remaining at the stand-by draught for an
see Pr. 1 Ch.2 Sec.5.3, and indefinite period.
- the towing fleet for the deck on barge(s), see Pr.2
Ch.3 Sec.3.2.4.
I 5.6.2 Mating Site
5.5.4.3 ?'he primary positioning system should be
capable of securing the structures in the event that the 5.6.2.1 The following criteria should be considered in
deck mating operation is interrupted. the selection of the mating site:
- Environmental conditions
5.5.4.4 ?'he primary positioning system should be - Magnitude and direction of wind, waves, and
sufficiently accurate to ensure safe navigation and current, protection against swell, etc.
positioning of the multi barge unit close to the - Geographical limitations
substructure. - Feasibility of towing the deck to the mating site,
searoom for mooring, minimum water depth, etc.
5.5.5 Secondary positioning system 5.6.2.2 The seabed at the mating site should be
surveyed prior to submergence of the substructure to
5.5.5.1 'I'he secondary positioning system should
mating draught, if the seabed clearance is considered
ensure accurate and well controlled positioning of the
critical.
deck on barges above the substructure. The positioning
should take place without causing local impact loads
exceeding the energy absorption capability of the 5.6.2.3 The location where mating will take place
positioning bumpers. should be investigated for the possibility of variations in
the density of the water. If rapid changes in density is
possible, density measurements should be performed
5.5.5.2 ?'he secondary positioning system (winches,
prior to and during the mating.
wires, jacks, etc.) should have sufficient capacity to
resist inertia forces, wind forces, current forces, etc.
5.6.3 Preparations
5.6.4 Clearances
6.1.1.1 ?'his section applies for marine aspects related 6.2.1.1 The loads given in 3.2 should be considered
to the construction phase of self floating structures. during construction afloat.
NNE OPEMTIONS
PART 2 : OPERATION SPECIFIC REQUIREMENTS
PART 2 CHAPTER 2
TOWING
JANUARY 1996
SECTIONS
1. IN'IRODUCTION ...................................................................................................................
4
..
2. PLANNING AND PREPARATIONS ........................... ............................................................. 5
3. TOWING EQUIPMENT ...........................................................................................................8
4. 'TOWING OPERATIONS ........................................................................................................
-13
i
3 . TOWING EQUIPMENT .......................... 8
3.1 TOWING ARRANGEMENT...................... 8
3.1.1 General .........................................8
3.1.2 Main towing line .............................8
3.1.3 Towing bridle .................................8
3.1.4 Towline attachments .........................9
1.2.2 Symbols
1.1.1 Application The list below define symbols used in this chapter;
1.1.1.1 Pt. 2 Ch.2, Towing, give specific requirements A : Exposed cross sectional area in m2.
and recommendations for single vessel and barge towing %: Accelerations in vessel longitudinal direction.
operations. a),: Accelerations in vessel transverse direction.
a.. : Accelerations in vessel vertical direction.
Guidance Note B: Breadth.
Requirementsand recornmeridations for transportation onboard
ship, towing of multi hull vessels, self floating and self propelled BP : Static tug bollard pull in tomes.
carrier transports are given in Pt.2 Ch.3 Requirements and Fm : Wave drift forces.
recommendations for transit and positioning of Mobile Offshore g: Acceleration of gravity.
Uriites are given in Pt.2 Ch.7.
H, : Significant wave height.
L: Length.
1.1.1.2 General requirements and guidelines in Pt. 1 of
these Rules applies for towing operations. ?'his chapter
L e: Length of towline.
MBL : Certified minimum breaking load.
is complementary to Pt. 1.
M B L , : Towline MBL
SWL : Certified safe working load.
1.1.1.3 Conditions for using these Rules are stated in
T: draft.
Pt. 0 Ch. 1 Sec. 1.2. V, : Current velocity.
V, : Mean wind velocity.
v : Towing speed.
1.2 DEFINITIONS ah : Interaction efficiency factor.
rl : Shape factor.
1.2.1 Terminology
2.1.3.1 Unrestricted towing operations are designed for 2.2.3 Simplified motion criteria
unrestricted environmental conditions, see Pt. 1 Ch.2
Sec. 3.1. Note also requirements for tow out given in 2.2.3.1 The simplified criteria given below may be
4.1.1. used for preliminary design evaluations of objects,
seafastening and grillage.
The conditions for using the simplified criteria are;
- towing in open sea on a flat top barge with length
greater than 80m,
- barge natural period in roll equal to or less than 7
Sec.,
- object positioned close to midship and with no
part overhanging the barge sides, and
- object weight less than 500 tomes
January 1996 Rilles for Marine Operations
Page 6 of 14 Pt-2 Ch.2 Towine:
'I'he simplified criteria (including the component for self 2.3 STRUCTURAL DESIGN CAILCULATI[BNS
weight) may be taken as;
- ay (transverse acceleration due to roll and sway): 2.3.1 General
0.65 g at waterline, increasing 0.015 g each meter
above the bottom of the object, 2.3.1.1 Structural strength verifications shall comply
with Pt. 1 Ch.4.
- ax (longitudinal acceleration due to pitch and
surge): 0.45 g at waterline, increasing 0.01 g
2.3.1.2 All load carrying elements without a certified
each meter above the bottom of the object,
capacity shall be verified by calculations. Typical
- az (vertical acceleration due to gravity and elements requiring separate verification are;
heave), maximum 1.35 g, minimum 0.55 g (both
- local barge capacity,
conditions to be checked) and
- grillage elements,
- wind pressure: 1 0 0 0 ~ / m ~ . - seafastening elements and
- internal seafastening for items exceeding 5
2.2.4 Stability afloat tomes.
2.2.4.1 General requirements to stability are given in 2.3.1.3 Global and local conditions with respect to
Pt. 1 Ch.2 Sec.4. corrosion shall considered in the design calculations, see
also Pt. 1 Ch.4 Sec.2.1.4.
2.2.5 Loads and load effects 2.3.1.4 Element properties (e.g. strength, capacities,
dimensions, weight etc.) m y be verified by having
2.2.5.1 Characteristic loads and load effects should be
certified properties. The conditions for the certification
taken according to Pt. 1 Ch.3 Sec.3.
shall be stated, see also Pt. I Ch.2 Sec.2.2.
2.2.5.2 Additional loads due to barge deflections Elements that m y be subject for this verification
should be considered. This is pwicularly important for procedure are;
cargo supported by more than two vertical supports over - barge global strength,
the length of the barge and for cargo secured - towing brackets,
horizontally with a indetermined seafastening system, - towing equipment,
see also Pt. I Ch.3 Sec.3.7. - mooring equipment, and
winches and foundations.
2.2.6 Load eases 2.3.1.5 Modifications to, or use of certified equipment
outside specified limitations require an acceptance from
2.2.6.1 Load cases for the towing operations shall be
according to Pt. 1 Ch.4 Sec.2.6. the certifying body. Typical examples are;
- exceedance of allowable global bending moments
2.2.6.2 The towing operation should be represented by in restricted waters, and
a sequence of load cases determined by environmental - ballasting below load line.
loads, wave headings, self weight, relevant accidental
loads, and combinations of these. 2.3.2 Grillage and seafastening
2.2.6.3 The most critical load cases for the each 2.3.2.1 The transported object are normally supported
specific member of the object shall be identified. and secured to the barge by seafastening and grillage
elements.
2.2.6.4 Critical load cases m y be analysed as quasi-
static load cases, adding loads due to dynamic motions 2.3.2.2 The grillage elements shall be used to distribute
of the barge with cargo to the static loads caused by the a concentrated deck load to a sufficient number of barge
self weight of the object. load carrying elements.
2.3.2.4 Grillage and seafastening strength shall be 2.3.4.2 If allowable deck load is based on "load
verified according to Pt. 1 Ch.4 for characteristic loads charts", these shall clearly state limitations andlor
according to Pt. 1 Ch.3. conditions with respect to number of loads, spacing
Guidance Note between loads and number of simultaneous acting loads.
Further guidance for design of seafastening and grillage systems It shall also be clarified if stated capacities include or
-
are given in VMO 1.2 Guideline for Grillage and Seafastening exclude dynamic loads and if any desigdload factors are
systems included or not. Applied load and material factors shall
be specified.
2.3.2.5 Seafastening for all items exceeding 5 tonnes
shall normally be verified with calculations. Guidance Note
Approved "load chart" shall be used with care, specially for heavy
object (> 500 tonnes). For highly loaded barges separate
2.3.2.6 Seafastening design for offshore or inshore analysis/calculations are recommended for verification of local deck
installation operations should allow for easy release and strength.
provide adequate support and horizontal restraints until
the object can be lifted clear of the barge, or launched as
applicable.
3.1 TOWING ARRANGEMENT 3.1.2.3 The main towing line should for offshore
towing have a length not less than;
3.1.1 General I.+,& = 2000 BP/MBI.+,*
3.1.3.7 Fibre rope pennants should normally not be 3.2.2.2 The trailing line shall be of floating material
used where there is adequate depth and sea room to and shall have a minimum breaking load not less than 30
allow for sufficient shock absorbing in the tow line tonnes. The distance from the aft extremity of the towed
catinary. object to the buoy shall not be less than 50 metres. In
addition to the trailing line, a messenger line of length
If fibre rope pennants are used the pennants shall be in as
100 metres may be considered necessary between the
new condition. Minimum breaking load of any fibre
buoy and the trailing line.
rope pennants shall not be less than;
- 2.3 times the tow line MBL for tugs with bollard
pull less than 50 tonnes, 3.2.3 Anchoring and mooring equipment
- 1.5 times the tow line MBL for tugs with bollard 3.2.3.1 A barge should normally have at least one
pull greater than 100 tonnes, and anchor available for emergency anchoring. A windlass
- linearly interpolated between 1.5 and 2.3 times or similar arrangement should be and capable of paying
the tow l i e MBL for tugs with bollard pull out and holding the anchor. The anchor should be
between 50 and 100 tonnes secured with a easy release arrangement.
?'he anchor line length and MBL shall comply with the
3.1.4 Towline attachments Rules of the Classification Society.
I
Guidance Note
3.1.4.1 Towline attachments shall be designed to resist For barges classed by Det Norske Veritas reference is made to
towline pull from any likely direction, with the use of Rules for Classification of Ships, Pt.3 Ch.3 Sec.3
fairleads if necessary.
3.2.3.2 Mooring ropes of adequate strength and length
3.1.4.2 The ultimate capacity of any towline attachment shall be available on board.
(bracket, bollard and their foundations) shall not be less Guidance Note
than 1.3 times the minimum breaking load of the It is recommended to have at least 4 mooring ropes of 110m each
towlipe. (or 2 of 220m each) available onboard.
3.2.7 Barge documentation 3.3.2.4 Towing force for open sea towing shall be
sufficient to maintain zero speed under the following
3.2.7.1 General description of barge systems shall be conditions.
presented. Ballast and towing equipment/systems shall - sustained wind velocity V, = 20 [ads],
be described in detail.
- head current velocity V, = I [ads], and
- significant wave height H, = 5 [m].
3.2.7.2 The following main particulars should as a
minimum be described; 3.3.2.5 Towing force for coastal towing and towing in
- object particulars, narrow or shallow waters representing a danger for
- name, signal letters, owners and port of registry grounding, shall be sufficient to maintain a speed over
of barge, ground, in safe direction, of minimum 2 knots under
- draught during towing, defined environmental design conditions.
- stability properties for intact and damaged Guidance Note
conditions, Above requirements are based on the necessity to control the tow
- specification of anchoring and mooring offshore, and to ensure adequate manoeuvrability lnshore and in
narrow waters
equipment, and
- the class of the barge (if any), length, breadth, Guidance Note
Simplified wave drift force components for single "box" shaped
depth, and year of build, etc. barges may be calculated according Eq 3-3, provided,
3.3.3.1 'I'he requirements of 3.1.2 apply. Minimum 3.3.6.1 The following main particulars should normally
required tow line MBL shall consider bending of tow be described;
line over stem, or around other tow line guiding/steering - name, signal letters, owners and port of registry,
equipment. - main engine(s): manufacturer and number,
maximum continuous output and corresponding
3.3.3.2 Tugs should be equipped with suitable anti- r.p.m.,
chafmg equipment. - static continuous bollard pull,
- propeller(s): number, type, whether nozzle is
3.3.3.3 Gog rope or alternative arrangement should be fitted or not,
provided to prevent athwartship pull from the towing - side thrusters (if fitted): position and thrust,
line. - fuel capacity,
- fuel consumption, tomes .per day, and
1 3.3.3.4 For offshore towing one spare towline, - stability particulars for departure and arrival
satisfying requirements in 3.1.2, shall be available loading conditions.
onboard, preferably on a second winch drum.
3.3.6.2 Towing vessels shall have a bollard pull
Additionally the following spare equipment should be certificates not older than 10 years. The bollard pull test
"ept available on board the towing vessel and/or the procedure shall be stated.
towed object.
If the vessel has undergone significant structural or
- 1 pennant
- machinery changes a renewed bollard pull test may be
2 fibre rope springs, if used
- required.
A suitable number of shackles, rings, and other
connecting equipment for at least one complete
towing line configuration 3.3.6.3 For the towing winch and towing lines the
following should be available:
- Certificate and particulars for the towing winch
3.3.4 Towing winches
stating manufacturer, type, maximum holding and
3.3.4.1 'I'he towing winch shall be approved according stalling power.
classification requirements.
- Certificates for main and spare towing wire ropes,
stating manufacturer, diameter of rope, length,
construction, nominal tensile strength of wires,
3.3.4.2 Winches for open sea towing should be remote
operated from the wheel house and so designed and breaking strength.
instrumented that it will be possible to determine the
- A log for the towing lines, giving the following
loads in the wire rope from the drum. As examples, this information on each rope;
j - date taken in use,
may be arranged either directly by use of a load cell or
indirectly when the brake is actuated by hydraulic - records of inspection,
- date of renewal of end sockets or other end
f
pressure.
connections and
- report on damage to the rope.
3.3.5 Equipment for personnel transfer - Certificates for shackles, rings and connecting
equipment.
3.3.5.1 At least one suitable workboat with propulsion
should be carried onboard for transferring personnel and
3.3.7 Inspections and testing
equipment from the towing vessel to the towed barge.
If the workboat is of the inflatable type, a flooring of 3.3.7.1 Before departure an inspection of the towing
adequate strength should be fitted to allow the carriage vessel and towed object including all parts of the towing
of heavy objects. arrangement shall be carried out to confirm compliance
with above stated requirements.
Functional testing of towing winch systems shall as a
minimum be carried out.
NE OPERATIONS
PART 2 : OPERATION SPECIFIC REQUIREMENTS
PART 2 CHAPTER 3
SECTIONS
1. INTRODUCTION ...................................................................................................................
4
2. SmP TRANSPORTATION ....................................................................................................... 5
3. IvlULTI BARGE TOWING.. ......................................................................................................
7
4. SELF FLOATING TOWING ................................................................................................... -10
5. HEAVY LIFT CARRIERS .......................................................................................................12
2.2 OPERATION......................................... 5
2.2.1 Operational aspects ...........................5 5. HEAVY LIFT CARRIERS ......................12
2.2.2 Transport procedure .......................... 6
2.2.3 Inspection ...................................... 6 5.1 PLANNING AND PREPARATIONS ..........12
5.1.1 Application ...................................12
5.1.2 Planning....................................... 12
3. =TI BARGE TOWING.......................7 5.1.3 Stability afloat ...............................12
5.1.4 Design loads .................................. 12
3.1 PLANNING AND PREPARATIONS............ 7 5.1.5 Motions during transit ......................12
3.1.1 Application .................................... 7 5.1.6 Structural design calculation ...............12
3.1.2 Planning ........................................7 5.1.7 Cribbing and guides .........................12
3.1.3 Stability afloat.................................7 5.1.8 Self propelled carrier ........................12
3.1.4 Design loads ................................... 7 5.1.9 Documentation ...............................13
3.1.5 Skew loads ..................................... 7
3.1.6 Structural design verification ............... 7 5.2 OPERATIONAL ASPECTS ......................13
3.1.7 Barge supports ................................ 7 5.2.1 Transport procedure.........................13
3.1.8 Seafastening ................................... 8 5.2.2 On and off loading ..........................13
5.2.3 Inspections and testing ......................13
3.2 TOWNG EQUIPMENT ........................... 8
3.2.1 Barges .......................................... 8
3.2.2 Barge ballasting systems ..................... 8
3.2.3 Towing arrangement and equipment....... 8
3.2.4 Towing vessels ................................8
3.2.5 Navigational equipment ..................... 8
1.2.1 Terminology
1.2.1.1 Definitions of terms are included in the Pt.0
Ch. 1. Terms considered to be of special importance for
this chapter are repeated below.
Heavy lift carrier :A submersible barge or vessei
carrying heavy object on deck. The objects are
loadedloff-loaded the carrier by float odfloat off
operations.
Heavy ZiJi- carrier transports :Transfer at sea from one
location to another of an object by a heavy lift camer.
Object -The object handled during the marhe operation,
typically a module, deck structure, jacket, sub sea
structure, pipes, other equipment.
Multi barge towing :Transfer at sea from one location to
another of an object resting on two or more barges by
use of tugs.
Selffloating towing :Transfer at sea from one location
to another of an object supported by its own buoyancy
and pushed/ pulled by tugs.
Ship transportation :Transfer of an object at sea from
one location to another of an object onboard a
conventional vessel or supply vessel.
Rules for Marine Operations January 1996
Pt.2 Ch.3 Special Sea Transports Page 5 of 13
2.2.3 Inspection
3. M W r I B U G E TOWING
3.1.4.3 Characteristic loads shall be combined, factored 3.1.6.1 Structural design verification of multi barge
and analysed according to Pt. 1 Ch.4. towing operations shall comply with Pt. 1 Ch.4.
Guidance Note
An advanced analysis taking proper'account of the barges individual
3.1.6.2 The barge ballasting condition should be
responses is normally .
. required optimised to ensure favourable load distribution in the
barges and the transported object.
3.1.4.4 At least one of the accidental load cases shall
considered collapse of one arbitrary grillage support 3.1.6.3 Strength verification of local support points in
element. grillage and transported object shall be performed.
Guidance Note
By "grillage support element" are meant stiffener, plate field, girders
etc. that may be damaged during the operation. Elements exposed 3.1.7 Barge supports
may be identified from relevant accidental scenarios. Collapse of an
element may be considered by neglecting the element in the 3.1.7.1 Flexible support system (crushing tubes, I d
structural design analysis.
plates, wedge arrangement, etc.) shall have sufficient
3.1.4.5 Force distributions and deflections in the capacity to account for the deflections of the deck and
transported object and in the barges shall be determined the barges during transportation conditions.
and considered in the design calculations, see also Pt. 1 The flexible support system shall be designed according
Ch.3 Sec. 3.7 to a fail to safe philosophy, i.e. the supports shall resist
an overloading without total collapse.
3.1.8 Seafastening 3.2.4.2 ?'he towing fleet should have the capacity and
be arranged so that;
3.1.8.1 The transported object shall be secured by - !he unit can manoeuvre within specified
seafastening structures with sufficient strength to tolerances during all stages of the tow (this is
withstand design loads in both horizontal and vertical normally best achieved by utilising a number of
direction during the towing operation. high manoeuvrability type tugs),
- keep the barges loaded with the transported object
3.1.8.2 ?'he seafastening structures shall possess
at zero speed during the design environrnentai
sufficient flexibility to accommodate the relative
condition and
deflections and avoid overstressing the transport object
or the barges. - maintain control over the unit in all phases of the
operation with Ioss of thrust from one tug.
3.1.8.3 If seafastening is provided by means of wedges,
in fill pieces or similar, these shall be secured by tack 3.2.4.3 Sufficient tug capacity shall be present for
welding. Securing of these items shall take place as soon towinglpositioning. The towing resistance should be
as possible after completion of the load transfer determined by considering the following effects;
operation. - current velocity,
- towing speed,
- wave resistance (if applicable),
- wind velocity and
3.2 TOWING EQUIPMENT - interaction of between propeller race and the
multi barge unit, see also Pt. 2 Ch.2 Sec. 3.3.2.
3.2.1 Barges
3.2A.4 Required tug capacity shall be based on
3.2.1.1 Barges for multi barge towing shall comply characteristic environmental conditions, see Pt. 1 Ch.3
with requirements in Pt. 2 Ch.2 Sec. 3.2. See.2. Wind velocities less than 20 mlsec shall not be
used.
3.2.2 Barge ballasting systems
3.2.4.5 Required tug capacity in "hold" area or
3.2.2.1 ?+he ballasting system on each barge should be conditions shall be based on characteristic environmental
capable of redistributing loads due to flooding of any conditions for a period not less than 30 days, see Pt. 1
one compartment in the barge. Ch.3 See. 2. Required tug capacity in a hold area shall
also consider failure of one tug as a PLS case.
3.2.2.2 Spare parts (blind flanges, leak mats, welding
equipment, etc.) should be available onboard the barges 3.2.5 Navigational equipment
in case of leakage. Regular inspections of air pressure
and water level in the barge tanks should preferably be 3.2.5.1 The navigation of the towed object shall be
carried out during the transportation. monitored by means of two independent system.
3.2.3 Towing arrangement and equipment 3.2.5.2 The primary system should have all critical
functions duplicated and tested before commencement of
3.2.3.1 The towing arrangements and attachments shall the towage.
comply with requirements in Pt. 2 Ch.2 Sec.3.1
3.2.5.3 The secondary system should be separate from
3.2.3.2 Facilities such as barge deck winches, hydraulic the primary system, both in principle and location. For
jacks, thrust struts, etc., shall be considered in order to inshore towing operations, the use of theodolite
assist with accurate positioning of the barges e.g. under triangulation would be an example of a typical
construction pillars, during mating, etc. acceptable secondary system.
Guidance Note
Simultaneous operation of winches and tugs should be carefully 3.2.5.4 At critical phases of the towage, such as
evaluated. Tugs and winches should preferably be used separately . departing from a mooring location, towing in narrow
waters and arrival, both systems should be used as a
3.2.4 Towing vessels cross reference to another.
3.2.5.5 For towing in narrow channels and for accurate 3.3.4 Monitoring
positioning, the compatibility of the navigation
equipment onboard the survey ship and onboard the lead 3.3.4.1 The following should be considered to be
tug should be verified by tests carried out prior to monitored manually or by monitoring systems during the
commencing a towage. The latest edition of available towing operation;
sea charts should be used. - water level, air pressure, etc., for buoyancy tanks
- position and orientation relative to the towing
3.2.5.6 If the navigation equipment is installed on channel
board the towed object and the towing operation is - draught, heel, and trim
conducted from here, compatibility and tests as per - underkeel clearance and
3.2.5.5 apply. environmental conditions.
3.3.2 Clearances
4.1 PLANNING AND PWPARATION 4.1.6.2 The characteristic hydrostatic loads should be
based on the most severe draught or hydrostatic head for
4.1.1 Application the individual structure or compartment.
4.1.1.1 This section applies to towing of objects such 4.1.6.3 Buoyant compartments exposed to external
as gravity base structures, jacket substructures, offshore water pressure should normally be designed to withstand
towers, etc. supported by their own buoyancy and hydrostatic loads for ali relevant draughts without
pushedlpulled by tugs. pressure compensation by means of air pressurisation.
Guidance Note
Reference is also made to VMO Guideline 1"1, November 1989,
Mooring and Towage of Gravity Base Structures.
4.1.7 Other loads
4.3.1 General
5.1.2.1 Planning and preparations shall comply with 5.1.5.3 Heave induced roll motion may occur if there
Pt. 1 Ch.2 Sec. 2. are large changes in waterplane area with the draught.
For such a situation a special analysis and/or model
5.1.3 Stability afloat tests should be performed to quantify this effect.
5.1.4.1 Characteristic loads for heavy lift transports 5.1.6.2 Local strength verification of transported
shall comply with Pt.l Ch.3. object and carrier at support points shall always be
performed.
5.1.4.2 Transportation with self propelled heavy lift
carriers having a redundant propulsion system
5.1.7 Cribbing and guides
experience not more than 50 % reduced thrust in case
of any single failure, may be designed for a limited 5.1.7.1 The size of the cribbing should be adequate to
wave heading range. The range should not be taken account for possible inaccuracies in positioning of
less than 330 degrees from head seas. cargo, placement of guides, etc.
5.1.4.3 Characteristic loads shall be combined, 5.1,7.2 'Re placing of cribbing shall be such that no
factored and analysed according to Pt. 1Ch.4. overloading of cargo or vessel will occur.
5.1.4.4 Cargo hanging over the sides of the carrier 5.1.7.3 The guide posts shall be designed to absorb a
should be particularly considered for; relevant amount of energy, see Pt. I Ch. 2 Sec.5.4.
- wave slamming loads,
- uplifting, 5.1.7.4 The guide posts should normally extend 2
- drag loads, metres above the water plane at deepest draught. The
- influence on motions, and guide post shall be clearly visible during the float
- influence on stability. odfloat off operations.
5.1.9 Documentation
NE OPERATIONS
PART 2 : OPERATION SPECIFIC REQUIREMENTS
PART 2 CHA.PTER 4
OFFSHORE INSTALLATION
JANUARY 1996
SECTIONS
1. INTRODUCTION ................................................................................................................... 5
2. LOADS ................................................................................................................................
7
3. LAUNCHING ....................................................................................................................... 8
4. UPENDING .........................................................................................................................I2
5. POSITIONING AND SETTING.. .............................................................................................. -14
6. PILTNG AND GROUTING ...................................................................................................... -17
CONTENTS
INTRODUCTION ..................................5 4. WENDING ......................................... 12
GENERAL ............................................5 4.1 INTRODUCTION ..................................12
1.1.1 Application .................................... 5 4.1.1 Application ...................................12
4.1.2 General considerations ......................12
DEFINITIONS .......................................5
1.2.1 Terminology .............................5 4.2 LOADCASES AND ANALYSIS OF FORCES12
4.2.1 General ........................................
12
INSTALLATION SITE .............................5 4.2.2 Loadcases and force distribution .......... 12
1.3.1 Survey .......................................... 5
4.3 STRUC'IZTRES......................................12
4.3.1 General ........................................12
LOADS................................................ 7 4.3.2 Stability afloat................................12
4.3.3 Structural strength ...........................13
ENVIRONMENTAL LOADS .....................7
2.1.1 General .........................................7 4.4 SYSTEMS ........................................... 13
2.1.2 Hydrostatic loads ............................. 7 4.4.1 Ballasting and deballasting systems....... 13
2.1.3 Positioning loads ............................. 7
2.1.4 Loads from soil ............................... 7 4.5 OPERA'IIONAI, ASPECTS ......................13
2.1.5 Other loads .................................... 7 4.5.1 General ........................................13
4.5.2 Monitoring of upending operations ....... 13
LAUNCHING ....................................... 8
5 . POSITIONING AND SETTING ...............14
IN'I'RODUCTION ................................... 8
3.1.1 Application ....................................8 5.1 INTRODUCTION .................................. 14
3.1.2 General considerations ....................... 8 5.1.1 ~pplication................................... 14
5.1.2 General considerations...................... 14
LOADCASES AND ANALYSIS OF FORCES 8
3.2.1 General ......................................... 8 5.2 LOADCASES AND ANALYSIS OF FORCES14
3.2.2 Loadcases and force distribution ........... 8 5.2.1 General ........................................ 14
5.2.2 Load cases and force distribution ......... 14
LAUNCHED OBJECT .............................9
3.3.1 General ......................................... 9 5.3 STRUCTURES...................................... 14
3.3.2 Structural strength ............................ 9 5.3.1 General ........................................ 14
5.3.2 Stability afloat................................ 14
LAUNCH BARGE ..................................9 5.3.3 On-bottom stability .......................... 14
3.4.1 General ......................................... 9 5.3.4 Structural strength ........................... 15
3.4.2 Stability afloat ................................. 9
3.4.3 Structural strength ............................9 5.4 SYSTEMS ........................................... 15
5.4.1 Ballasting and deballasting system ........ 15
SYSTEMS AND EQUIPMENT .................. 10 5.4.2 Mooring and towing system ............... 15
3.5.1 Ballasting system ............................ 10
3.5.2 Power supply and flame cutting facilities 10 5.5 DOCKING ........................................... 15
3.5.3 Launch devices and systems ............... 10 5.5.1 General ........................................ 15
3.5.4 Equipment arrangement .................... 10 5.5.2 Vertical docking ............................. 16
3.5.5 Inspection and tests .......................... 10 5.5.3 Horizontal docking .......................... 16
1.1.1.1 Pt. 2 Ch.4, Offshore Installation, provide Launching :An activity comprise cutting of seafastening
specific requirements and recommendations for offshore of an object resting on a specially equipped launch
installation operations particularly applicable for fixed barge, the object's slide down the skid beams on the
offshore structures such as jackets, offshore towers, and barge and diving into the water until the object is free
gravity base structures. For installation of ?ZP's, floating.
loading buoys and other floating structures, parts of this Upending :'fie activities necessary to upend a floating
chapter may be used where applicable. object.
Positioning :The activities necessary to position an
1.1.1.2 General requirements and guidelines in Pt. 1of
object at a certain predetermined location.
these Rules applies to offshore installation operations.
This chapter is complementary to Pt. 1. Setting :The activities necessary to set-down an object
on the seabed after positioning, including levelling, soil
1.1.1.3 Pt. 2 Ch.4 covers the following installation penetration and suction (if applicable).
operations;
Piling :?'he activities necessary to secure an object to
- launching, the sea bottom by driving piles into the sea bottom.
- upending,
- positioning and setting down, and Grouting :The activities necessary for cementing the
- piling and grouting. void spaces between pile and pile sleeve after pile
driving or the provision of even foundation support for
Above installation operations are defined in 1.2.
an object placed on the sea bottom by injection of
cement under the base structure.
1.1.1.4 Lifting aspects of the offshore installation
operations are covered in Pt. 2 Ch.5. Lifring :The activities necessary to lift or assist an object
by crane.
1.1.1.5 Operational aspects related to execution of the
piling and grouting operations are covered in Sec. 6. For
piling and grouting operations from a structural strength
1.3 INSTALLATION SITE
point of view reference should be made to Pt. I Ch.4.
Guidance related to such aspects may also be found in a
recognised codes or standards, e.g. Veritas Rules for 1.3.1 Survey
the Design, Construction and Installation of Offshore
Structures, 1977 including Appendix F: Foundation and 1.3.1.1 A bathymetric survey of the installation site
Veritas Technical Note for Fixed Offshore Installations, should be performed with sufficient accuracy for the
Underbase Grouting of Gravity Structures, TNA 303. design of the operations listed in I. 1.1.3.
1.1.1.5 Conditions for using these Rules are stated in 1.3.1.2 The soil parameters at the target area for
Pt. 0 Ch.1 Sec. I.2. installation should be determined.
3.4.3.3 The loads on the launch barge should be 3.5.3 Launch devices and systems
verified to be within the barge's operational limitations
assessed by the barge's own Classification Society. 7'his 3.5.3.1 The object to be launched shouid be secured tc
verification normally includes evaluation of; the barge with. anti self-launch dev~cesto prevent a
- premature iaunch after cutting of the seafastening
bending and torsion of the barge hull,
members.
rocker arm reactions.
- barge submersion,
- barge hydrostatic stability, and 3.5.3.2 Launch lugs, if applicable, should be designed
- special requirements from the Classification to provide self release of pulling wires after the
Society. launching has started.
Reinforcement should be subject to acceptance by the
3.5.3.3 The launch initiating pushlpull system should
barge's own Classification Society.
have sufficient capacity to overcome the static friction
forces, and should be capable of applying this force over
3.4.3.4 Any structural components on the barge not a sufficient distance to ensure initiation of the launch
assessed by the barge's own Classification Society
should be verified to have sufficient structural strength
3.5.3.4 The sliding surfaces on the launch frames and
to withstand all loads during the launching operation.
on the launch barge skid beams should have a finish and
Such structural components may include skidbeams,
capacity that assures a relatively iow coefficient of
positioning brackets for attachment of positioning lines,
friction. For design and planning of the launch
attachments for winches, hydraulic jacks, sheaves, etc.
operation, the assumed coefficient of friction should be
as specified by the manufacturer or as experienced in
similar operations (e. g., during load out). If more
3.5 SYSTEMS AND EQUIPMENT accurate in-service values are not available, the
coefficient of friction between teflon and wood may be
taken as 0.08-0.25 (static, break out included) and 0.03-
3.5.1 Ballasting system
0.08 (dynamic). The Teflon should be mounted on the
3.5.1.1 The barge ballasting system should have barge skid beams. Similar values for lubricated steel and
sufficient capacity to achieve the predetermined barge wood may be taken as 0.1 - 0.2 (static, break out
launch parameters within a time period not to exceed inciuded) and 0.02 - 0.12 (dynamic).
25 % of the weather forecasting period.
3 5 . 4 Equipment arrangement
3.5.1.2 7'he barge tank volume should have sufficient
spare capacity such that the required trim, heel and draft 3.5.4.1 The equipment on the barge to be used prior to
can be maintained in the event of accidental flooding of and during launch should be fit for its intended purpose
any one compartment. and arranged to ensure short start-up time.
3.5.1.3 Hatch covers over barge tanks should not be 3.5.4.2 The equipment on the barge should be arranged
open prior to or during launch. to avoid damage to the object during launch.
Guidance Note
This may preclude the use of submersible pumps during the 3.5.4.3 The guiderails on the rocker arms should allow
ballasting operation. for possible object yaw during launching.
3.5.5.2 Preferably all buoyant tanks e.g. buoyant legs, All structures and equipment necessary for the
buoyancy tanks, should have a small internai operation are correctly rigged, ready to be
overpressure at departure from the shore. A monitoring used, and have been inspected and tested
system shouid be arranged such that the pressure in the Obstacles which may unduly delay the
taziks may be inspected at an easily accessible locarion. operation have been removed
Such an inspection should be performed prior to Iaunch
to verify the integrity of the tanks. 3,6.1.2 Seafastening members should be cut in
If there has been any leakage during the tow, adequate accordance with a predetermined procedure containing a
measures should be performed to identify the extent of number of steps. The cut lines should be painted.
the leakage and the consequences should be evaluated Continuous watch on the weather conditions should be
prior to launching. performed, including the weather forecast. ?'he point of
no return should be identified in the procedure.
3.5.5.3 The barge, including the permanent barge
systems and equipment, should be inspected andlor 3.6.1.3 Seafastening members that have been cut should
tested prior to departure from shore. The be removed and secured to the barge to avoid
testslinspections should verify that the state of the barge interference with the object during launch.
including the permanent systems and equipment is in
accordance with the requirements from the Classification 3.6.1.4 Rigging equipment should be connected to
Society and are fit for the intended use. attachment points (padeyes, trunnions, bollards, etc.)
specially designed for the corresponding loads. Other
3.5.5.4 Rubber diaphragms should be short term and attachment points should not be used.
long term tested.
Each individual diaphragm should be tested to 1.25 3.6.2 Positioning of barge and object
times the maximum working pressure with a minimum
duration of 10 minutes. 3.6.2.1 The launch barge should be positioned by lines
attached to the tugs. The object to be launched shouid
One diaphragm of each type should be tested at 1.1 times be connected to positioning and hold-back vessels, by
the maximum working pressure with a minimum lines with sufficient slack to allow free movement during
duration of 48 hours. the launch.
The tests should be perfomled as close to sailaway as
possible. 3.6.2.2 ?'he barge should be positioned relative to a set
of predetermined co-ordinates to ensure that the launched
3.5.5.5 A survey of the skidbeams and rocker arms object will not hit the seabed or structures positioned on
shall be performed to verify that the alignment and level the seabed.
is within the criteria considered in the structural
verification of the barge and the launched object. 3.6.2.3 ?'he barge heading for launch should, where
possible, be into the prevailing wind and wave direction.
4.2.1 General 4.3.1.4 The clearance between mudline and the lowest
protruding member should normally not be iess than 5
4.2.1.1 An upending operation represents a sequence of
meters for the critical position during the upending
different loadcases from the initial self-floating
operation considering the lowest astronomical tide and
condition to the final self-floating (installation)
any motions imposed by the environmental conditions.
condition.
For the requirement given in 4.3.2.2 a clearance of
minimum 2 meters should be available.
4.2.1.2 In principle the entire upending sequence
should be considered step-by-step and the most critical
loadcase for each specific member of the object should 4.3.2 Stability afloat
be identified.
4.3.2.1 It should be shown that the object will behave
in a stable manner during the upending operation. The
4.2.2 Loadcases and force distribution initial metacentric height (GM), corrected for free
surface effect, should hormally not be less than 1 meter
4.2.2.1 The basic loadcases described in 4.2.1 should
for any step during the operation. Model tests may be
be analysed by static analysis considering the buoyancy,
used to verify the object's behaviour during upending.
self weight
- and any - applied
-- loads. The structural
analysis verifying the global integrity of the object may
be omitted provided that a similar structural analysis will
4.3.2.2 Accidental flooding of any one buoyant
compartment should be considered during evaluation of
be carried out for the object for a more severe loading
condition during transportation, installation, or the in- hydrostatic stability and reserve buoyancy.
place phase.
Rules for Marine Operations January 1996
Pt.2 Ch.4 Offshore Installation Page 13 of 18
5.3.4.1 The object should have sufficient structural 5.4.1 Ballasting and deballasting system
strength to withstand the loads described in 5.2.
5.4.1.1 The requirements given in 4.4.1 stlouid apply
5.3.4.2 Buoyant compartments should have sufficient for the positioning and setting operation.
structural strength to withstand the loads described in
5.2.2.3. 5.4.1.2 The baliasting/deballasting systems on gravity
structures should be capable of levelling the object by
5.3.4.3 Auxiliary buoyancy tanks including their eccentric ballasting in order to counter uneven
attachments to the object should be designed to settlement. The soil parameters and the seabed
withstand vibration loads due to pile driving if the bathymetry, see 1.3.1, should be considered for the
buoyancy tanks are to remain in-place during pile evaluation of above condition.
driving.
5.3.4.4 For positioning brackets the requirements of 5.4.2 Mooring and towing system
4.3.3.4 apply.
5.4.2.1 The mooring and towing system to be used
during positioning and setting (installation) of the object
5.3.4.5 Guides and bumpers attached to the object or to should be according to Pt. 1 Ch.2 Sec.5.3 and Pt. 2 Ch.2
the seabed, should have sufficient strength and ductility Sec.3 .
to resist impact and guiding loads during positioning
without causing operational (e.g. position tolerance)
problems and without overloading members of the
object. After positioning the guides and bumpers should
be able to resist loads due to object motions caused by
the sea state. see Pt. 1 Ch.2 Sec.5.4. 5.5.1 General
5.3.4.6 Anchoring and mooring systems should have 5.5.1.1 Docking operations may be performed
sufficient strength to withstand loads due to positioning according to one of the following principles;
occurring during horizontal translation of the object and - vertical docking, and
relevant environmental loads due to wind, waves, and - horizontal docking.
current.
Docking is commonly used for accurate positioning of
platform substructures over a pre-installed template with
5.3.4.7 Clamping lines and similar devices attached to
pre-drilled wells, but may also be used in other cases
articulated structures should withstand the loads
when there is a need for accurate positioning of a
occurring during the positioning and setting operation.
platform substructure.
5.3.4.8 Footing structures such as mudmats, slabs,
5.5.1.2 The docking piles against which the structure to
skirt, etc. should have sufficient strength to withstand
be positioned is docked should be in an accurate position
installation loads occurring during setting, levelling and
relative to the target point.
soil penetration, see 5.2.
5.3.4.9 Footing structures should withstand forces due 5.5.1.3 A Positive clearances should be ensured during
the docking operation between the structure and the
to environmental loads before permanent attachment to
template and wellheads. All movements, tolerances and
the seabed is obtained. Unacceptable settlement of the
deformations shall be considered in the least favourable
object before permanent attachment to the seabed is
direction.
obtained should be avoided by sizing the footing
structures to ensure an acceptable soil pressure.
5.5.1.4 Adequate positioning and monitoring systems
should be used during the operation. Normally, suitable
hydroaccoustic systems (long-range and short,-range)
transducers and responders should be used together with
underwater video cameras.
January 1996 Rules for Marine Operatioms
Page 16 of 18 Pt.2 Ch.4 Offshore Installation
5.5.1.5 Relevant accidental conditions should be 5.6.1.2 A final survey of the seabed including a final
considered when selecting the docking system i.e.; testing of the underwater positiodorientation monitoring
system should be carried out prior to commencement of
the docking system should be able to resist a
the positioning and setting operation, see aiso 1.3.i. 6.
relevant accidental impact load considering the
design environmental condition, mass of
structure and added mass from water, and the
56.1.3 Clamping lines should be easy to release after
completion of the installation operation. Normally,
method to be used,
clamping lines should be released from a position above
a failure of one arbitrary positioning line, and the water surface.
accidental flooding of any one buoyant
compartment of the structure. 5.6.1.4 The auxiliary buoyancy tank attachments to the
object should be designed to ensure quick and easy
release with regard to the removal of the tanks. The
5.5.2 Vertical docking
tanks shouid normally be removed as soon as possible
5.5.2.1 Vertical docking is the method where it is after jacket set down to reduce wave ioading and
easiest to ensure sufficient clearances throughout the increase the on bottom stability.
operation. Two method are normally adopted, namely a
passive or an active system. 5.6.1.5 The guiding structures should be designed to
ensure accurate positioning within the given tolerances
5.5.2.2 The passive system do not require outside for the project.
intervention e.g. people on the jacket, hydraulics. The
system should be designed with a primary and a 5.6.2 Monitoring
secondary docking pile, i.e. engaging one docking pile
at the time. 5.6.2.1 The position and orientation of the object
should be monitored by surface and/or underwater
5.5.2.3 The active system normally lower the docking positioning systems.
sleeves down from the object over the docking piles in a
predetermined sequence. Some rotation and translation 5.6.2.2 Monitoring of clearances to guiding structures
of the object should be possible after having lowered positioned on the seabed to achieve strict positioning
down the docking sleeves. Lowering of the docking tolerances should be considered.
sleeves should be performed by a suitable system e.g. by
a winch system.
5.6.1 General
5.6.1.1 The requirements given in 3.6.1.1, should
apply for positioning and setting operations.
Rules for Marine Operations January 1996
Pt.2 Ch.4 Offshore Installation Page 17 of 18
6.1.2 General considerations 6.2.1.6 Special attention shall be given to pile and pile
guide design when the pile andlor hammer protrudes
6.1.2.1 The following should be considered in reiation
through or are close to the splash zone. The natural
to operational feasibility and structural limitations;
frequencies of the pile (free-standing) and pilelhammer
soil formation characteristics, system should be established. The pile and pile guide
hammer sizes, should be verified for an applicable sea state including a
- back-up equipment, range of wave periods, see also Pt. 1 Ch.3.
- pile driving procedure,
- length of pile(s) above upper pile sleeve(s), 6.2.1.7 Systems and equipment to be used during pile
- inclination of piles, installation should comply with Pt. 1 Ch.2.
- pile natural frequency. (applicable
.. for piles
or hammer which protrudes through or are close
the splash zone), 6.2.2 Clearances
- lifting equipment for hammers and piles,
- liftingtupending procedure for piles, and 6.2.2.1 Horizontal clearance between pile, hammer or
- operational and accidental impact loads from follower and structure primary elements should normally
dropped objects or vessels. not be less than l m during stabbing and retrieval.
6.1.2.2 Grout lines and packer inflation lines, if 6.2.2.2 Any positive horizontal clearance during
applicable, should be designed to resist accelerations driving through and near the splash zones are acceptable
from pile driving. if all components from fabrication tolerances, clearances,
deflections and pile sway (including possible dynamic
amplification) are summerized.
6.2 OPERATIONAL ASPECTS
6.2.2.3 Nominal horizontal clearances between hammer
and primary structure during driving should normally
6.2.1 Pile installation not be iess than lm.
6.2.1.1 The piles should be installed in a sequence
providing adequate stability to the structure in all phases 6.2.3 Followers
of the installation.
6.2.3.1 Use of followers should be considered in order
6.2.1.2 Particular attention should be paid to to increase horizontal clearances during driving.
operational procedures when Iarge self penetration
andlor "run away" during driving of piles may be 6.2.3.2 Followers shall be subject for periodical
expected. inspections by suitable NDE and a maintenance record
6.2.1.3 The pile lifting and upending sequence should shall be kept.
be carefully considered. Fkcentric loading on lifting
should be accounted for in the design, see also Pt. 2 Ch.5
for general aspects to be considered during lifting.
January 1996 Rules for Marine Operations
Page 18 of 18 Pt.2 Ch.4 Offshore Installation
6.2.4 Grouting
6.2.4.1 For GBS underbase grouting attention should
be paid to selection of systems, equipment and vessels
to ensure sound and feasible operations. Particularly the
positioning systems and manoeuvrability of the vessels
should be investigated to reduce the possibility of impact
loads to the installed object from the vessels, see also
Pt.1 Ch.3 Sec.3.8.
Appropriate fendering structures should be considered.
NE: OPERATIONS
PART 2 : OPERATION SPECIFIC REQUIREMENTS
PART 2 ClWPlER 5
LIFTING
JANUARY 1996
SECTIONS
1. GENERAL ...........................................................................................................................
5
2. LOADS.. ..............................................................................................................................
7
3. LIFTING EQUIPMENT .......................................................................................................... 12
4. S'I'RUCTURES ....................................................................................................................
.16
5. LIFT OPERATION ...............................................................................................................
-18
6. YARD LIFTS ......................................................................................................................
.20
DET NORSKEVERITAS
Veritasveien 1, N-1322 Hmik, Norway Tel.: +47 67 57 99 00, Fax.: +47 67 57 99 11
CHANGES IN THE RULES
This is the first issue of the Rules for Planning and ?'his chapter is valid until superseded by a revised
Execution of Marine Operations, decided by the Board chapter. Supplements to this chapter will not be issued
of Det Norske Veritas Classification A/S of December except for minoramendments and an updated list of
1995. 'fiese Rules supersedes the June 1985, Standard corrections presented in the introduction booklet.
for Insurance Warranty Surveys in Marine Operations.
Users are advised to check the systematic index in the
These Rules come into force on 1st of January 1996. introduction booklet to ensure that that the chapter is
current.
6.4 S T R U C T U W ................................... 21
6.4.1 Lift points .................................... 21
Figure List
Figure 2.1 .Determination of S W , .......................9
Table List
Table 2.1 .Dynamic Amplification Factors ...............8
Table 3.1 .Shackle Proof Loading .......................15
Table 4.1 .Design factors .................................16
Rules for Marine Operations January 1996
Pt.2 Ch.5 Lifting -. Page 5 of 22
1.2.1 Terminology Skew load factor :A factor accounting for the extra
loading on slings caused by the effect of inaccurate
1.2.1.1 Definitions of terms are included in Pt.0 Ch. I . sling lengths and other uncertainties with respect to
Terms considered to be of special importance for this force distribution in the rigging arrangement.
chapter are repeated below.
Sling :A strap used between liftpoint and crane hook
Bobbin :Sheaves applied to increase the bending during lifting. The term sling is also used for a steel
diameter of double slings around a pin. rope with an eye at each end.
Cable laid grommet :Steel or fibre ropes arranged into Spreader beam/Jiame :Part of the rigging which may
a stranded construction, cabled together, right or left transfer compression loads. It may be applied to;
lay, and spliced such that there is no end. - avoid horizontal loads to the lifted object,
Cable laid sling :Steel or fibre ropes arranged into a
- reduce the effect of inaccurate sling lengths or
stranded construction, cabled together, right or left lay,
- to avoid clashes between slings and the lifted
with a spliced eye in each end. object.
Trunnion :Lifting point on a structure consisting of a
Llesign factor :Factors to be applied for design of
tubular member with a stopping plate at the end. The
structural elements which includes relevant load factors,
slinglgrommet may be laid around the tubular member
consequence factors, and local dynamics.
such that a shackle is not needed.
Dynamic amplzficationfactor :A factor accounting for
the global dynamic effects normally experienced during
lifting. The dynamic amplification factor is defined as
+
(Dynamic load Static Load)/ Static Load.
Fibre sling :Slings made of high performance man
made fibres.
January 1996 Rules for Marine Operations
Page 6 of 22 Pt.2 Ch.5 Liftine;
2.1.1.1 ' f i e object weight (W) as lifted should be the 2.2.1.1 All lifts are exposed to dynamic effects due to
characteristic weight defined in Pt.1 Ch.3 Sec.3.5. variation in hoisting speeds, crane and vessel motions,
cargo barge movements, object movements etc.
2.1.1.2 Inaccuracies in COGposition should be
considered according to the principles in Pt. 1 Ch. 3 2.2.1.2 The effect of global dynamics will be
i Sec.3.5. si,&icantly influenced by parameters such as;
- the environmental conditions,
2.1.1.3 For combinations of object and rigging - rigging arrangement
geometry sensitive to COGshifts, any possible COG - type of crane vessel,
position should be considered in the design. It is not - stiffness of crane-boom and lifting appliances,
"i recommended to substitute a COGenvelope study by a - type of cargo vessel,
weight inaccuracy factor, see also Pt. 1 Ch. 3 Sec.3.5.3. - weight of lifted object
Guidance Note - lifting procedure and
Geometry changes due to COGuncertaintiesmay for unconventional whether the lift is in air or water.
rigging arrangements influence the design loads The effect of the
geometry changes shall in these cases also be considered The global dynamic loads should be accounted for taking
Guidance Note proper account of these parameters, as applicable, see
To simplify purchasing and design of lifting equipment, lifting points also 2.2.2.
etc , a sling load inaccuracy factor, based on the weight inaccuracy
and COGenvelope study, are often used. The assumptions for this
factor, e.g COGwithin envelope and weight within assumed 2.2.1.3 For lifts in water special investigations should
contingencies, must be confirmed be made in each case taking proper account of the
hydrostatic and hydrodynamic effects, see also Pt.2
2.1.2 Weight of rigging Ch. 6.
Guidance Note
2.1.2.1 The weight of rigging (W,) is the total weight For lifting in waters additional local dynamic effects may become
of the rigging arrangement, i.e. equipment such as governing for design of lifting equipment elements Such effect
could be local sling dynamics due to motion of the object inrtlated by
shackles, slings, spreader bars or frames, etc. waves
2.1.2.2 For some cranes also weight of hook, blocks 2.2.2 Dynamic amplification factor
and hoist lines should be considered part of W&.
Guidance Note 2.2.2.1 The global dynamic load effects may be
This is most relevant for cranes with several crane rigging accounted for by using a dynamic amplification factor
configurations typically for onshore crawler cranes
(DM).
2.1.2.3 W,, should be included in the applied crane
load, but does not need to be considered for elements 2.2.2.2 The D M should for major off-shore lifts be
below each part of the rigging. established based on a dynamic analysis considering the
effects in 2.2. I .
Guidance Note
2.1.3 Special loads The dynamic loads may be categorised as environmental loads (E
loads), see Pt. 1 Ch.3 ~ e c . 3 . 1 Appropriate
. load factors according to
2.1.3.1 When appropriate, allowances for special loads Pt.1 Ch 4 Table 3 1 may be considered when calculating the
(SPL) should be made. Special loads may be tugger line dynamic hook load.
loads, guide loads, wind loads, hydrodynamic and
hydrostatic loads, etc. 2.2.2.3 Environmental design conditions applied in the
dynamic analysis should be duly reflected in the
operation manual, see also Pt. 1 Ch. 2 Sec.3. I .
January 1996 Rules for Marine Operations
Page 8 of 22 Pt.2 Ch.5 Lifting
2.2.2.4 In lieu of more refined analysis the values for 2.3.2.2 The S G 1should always be calculated if the
DAF given in Table 2.1 may be considered as minimum slings or lift points have excessive fabrication tolerances,
factors for lifts in air, provided the lifting operation will the rigging has an unusually geometry, e.g. small sling
not take place under adverse conditions. opening angles and/or no symmetry and if slings with
Guidance Note
other stiffness properties than wire rope and cable laid
For offshore lifting from deck of SSCV's the DAF for inshore lifts in steel slings are used, see 2.3.2.7.
Table 2.1 may normally be used.
Guidance Note
For 0 > 60 deg., see 2.3.2.7, and utilisations less than 0.8 the skew
load effects due to sling length tolerances should be calculated in
each case.
2.3.1.2 Skew loads and load effects due to; 2.3.2.7 Direct calculation of the SKkI may be based on
- sling length inaccuracies, a sling load of 1.3 times that determined from the DHL.
- fabrication tolerances of lift points, The S Q I will decrease with increasing load since the
- multi hook lifting, relative difference between the sling loads will decrease.
- doubled slings and This effect is illustrated in Figure 2.1. The load-
- sling elongation deflection curves of the slings may be approximated as
linear for the purpose of calculating the S q I .
should be evaluated for each lift.
It is recommended not to select too strict strength
2.3.1.3 It should be carefully evaluated if the planned tolerances when skew load calculations are performed.
lifting procedure may cause other skew load effects than SKI+, below 1.1 should normally not be applied for a
mentioned in 2.3.1.2. statically indeterminate lift of a relatively rigid object.
In Eq. 2-1 the lifted object is assumed infinitely stiff,
2.3.1.4 The skew load effects should be considered as and no rotation of the crane hook is considered. As a
outlined in the sub-sections below. further refinement the object flexibility and possible
crane hook rotation may be taken into account.
2.3.2 Sling tolerance effects
2.3.2.1 The effects of sling length tolerances is
dependent on the fabrication tolerance of slings and lift
points, the rigging geometry and the utilisation of the
slings. The effects may be accounted for by a factor
SWl.
Rules for Marine Operations January 1996
Pt.2 Ch.5 Lifting Page 9 of 22
The below formula may be used for calculation of the 2.3.3.2 The effect of any COGposition within the
S&, for a 4 point statically indeterminate lift with defined envelope and the effect of tilt and yaw shall be
approximately a double symmetric single sling considered for multi hook lifts. 'fie yaw and tilt effects
arrangement, and E 2 E ~ . may result from deviations of the hooks from their ideal,
relative positions. 'Re magnitude of this deviation will
SKL,, = 1 + E,/E depend on whether the two cranes are on the same or
Eq. 2-1 separate vessels, the vessel's motion response, and the
where lifting procedure.
E : average strain in the slings at hook load 1.3 DHL
(no skew load assumed). 2.3.3.3 ?'he yaw effect factor, SKI, account for
E = 1.3 FslipgIAE sin(0). increased sling loading due to rotation of the object
F,, : dynarmc sling load in N.
about a vertical axis. Normally a yaw effect factor of
A: 3.14d214 i .05 is sufficient. For lifts with small sling opening
d: diameter of sling in mm. angles at the hooks andlor significant windltugger line
E: Young's modulus for the sling, could for cable loads a greater yaw effect factor could be appropriate.
laid slings be taken as 30,000 MPa based on A as
defined above. 2.3.3.4 A tilt effect factor, S&, should be calculated
8: average sling angle from a horizontal plane. to account for the increased sling loading caused by
total sling and padeye fabrication tolerances (or rotation of the object about a horizontal axis, and the
so :
possible length deviation) as a function of the effect of not plumb hoist lines. The tilt effect factor
sling length, i.e. E ~ =total tolerancelsling length. should be based on possible tilt caused by maximum
hook height tolerances and hoist line deviations from
Guidance Note
For lifting with grommets, the sling area A should be taken as the plumb.
total sling cross sectional area, i.e. sum of both parts. Guidance Note
For lifting with crane vessels the tilt effect factor may normally be
calculated for a tilt of 3' when the cranes are on the same vessel,
Figure 2.1 - Determination of SKI.,,, and for a tilt of 5' when the cranes are on separate vessels (hoist
I line deviation included)
2.3.4.4 If the doubled slings consists of two parallel 2.4.2.2 For two hook lifts, the dynamic hook load for
slings, the load distribution should be calculated each hook @HLJ are nonnally expressed as :
considering the maximum sling length difference and
maximum sling E modulus.
D H h = DAF ((a,, * SKL, * W) + W+,$ + F(SPL),
Eq, 2-3
where
2.3.5 Additional tilt
a,, : Maximum theoretical part of total load at hook
2.3.5.1 Different sling elongation, sling length "in with COGin extreme position.
tolerances and lift point fabrication tolerances could SKL, :Factor expressing the increase in hook load "i"
increase the object tilt. If the liftiig points are below the due to tilting of the object.
object vertical COG, the loading in the most utilised
slings will then increase. In this case a factor, SKL,, 2.4.2.3 The basic loadcase for a lift should normally be
should be estimated. calculated as a quasi static loadcase by applying DHL at
the hook position, and distributing weight and any
special loads to each element.
2.4 LOADCASES AND ANALYSIS OF FORCES 2.4.2.4 In order to find maximum dynamic forces for
each element (e.g. sling, lift points, supporting
2.4.1 General structure), the sling forces found in the basic loadcase
according to 2.4.2.3 should be adjusted considering all
2.4.1.1 A lift operation does not represent one well relevant skew load effects as described in 2.3.
defined loadcase, but a sequence of different loadcases.
Uncertainties with respect to internal force distribution, 2.4.2.5 The skew load effects will increase the force in
skew loads, dynamics, possible accidental loads, etc., some slings, and reduce the force in the others
will introduce further complications. accordingly. Hence, it may be necessary to define
various loadcases in order to cover all possible
2.4.1.2 In principle the entire lifting sequence should combinations of sling loads.
be considered step-by-step and the most critical loadcase Guidance Note
for each specific member should be identified. However, For a conventional four sling lift, the following two (skew) load cases
for most conventional lifts, the entire sequence is should normally be considered:
adequately covered by the basic loadcases described in 1. The force distribution calculated according to 2.4.2.3 modified
by multiplyingthe forces in two diagonally opposite slings with
2.4.2 and the additional loadcases described in 2.4.3. the skew load factor. The forces in the remaining two slings
should be determined by (quasi) static equilibrium.
2.4.1.3 For lifting operations including pivoting1 2 Ditto but with the skew load applied on the other pair of slings.
upending critical steps have to be identified and Guidance Note
The flexibility of the object will reduce the SKL This effect should
analysed. be considered for less torsion stiff objects such as helidecks etc
Guidance Note
Critical step shall at least include dimensioning positions for all 2.4.2.6 The maximum dynamic forces calculated
elements connected to the lift points. according to 2.4.2.4 are the design forces for
slings/grommets and shackles. For the design of
2.4.1.4 Special considerations will be necessary for
structural components, the maximum dynamic force
lifting operations in water. Guidelines for such lifting
should be multiplied by the appropriate design factor
operations are given in Pt. 2 Ch.6.
given in Table 4.1.
2.4.2 Basic loadcase and force distribution 2.4.2.7 If tugger lines are attached to the lifted object,
the attachment points should have adequate structural
2.4.2.1 For single hook lifts, the dynamic hook load is strength to withstand the maximum loads which can be
normally expressed as : imposed by the tugger lines.
DHL = D M (W W%) + + F(SPL) Guidance Note
Eq. 2-2 Preferably the tugger lines should be equipped with a system, e.g. a
DHL : Dynamic hook load. constant tension winch system, which restrict the maximum loads to
a specified value.
DAF :Dynamic amplification factor, see 0.
W : Object weight, see 2.1.1.1.
W% : Rigging weight , see 2.1.2.
SPL : Special loads, see 2.1.3.
F(SPL) : Additional hook load due to SPL.
Rules for Marine Operations January 1996
Pt.2 Ch.5 Lifting Page 11 of 22
3.1.2.2 The total nominal safety factor should be taken 3.1.4 Manufacturing and tolerances
as the greatest of:
3.1.4.1 ?'he manufacturing of slings and grommets
should be performed by a recognised manufacturer. The
rope construction should be well suited for the intended
use and comply with recognised codes or standards, e.g.
Veritas Rules for Certification of Lifting Appliances,
3.1.2.3 Calculated maximum dynamic sling load Fa%, 1994, or International Standard IS0 2408. For heavy
should fulfil Eq. 3-4; cable laid ropes Guidance Note PM 20: "Cable Laid
Slings and Grommets" from British Health and Safety
Executive, apply.
Eq. 3-4 3.1.4.2 The length of cable laid steel slings, grommets
or fibre slings should normally be within tolerances of
3.1.3 Handling i0.25% of their nominal length.
The length of ordinary wire rope slings or grommets
3.1.3.6 The eye of a single part steel sling should not should normally be within tolerances of a. 15% of their
be bent around a diameter less than the nominal diameter
nominal length.
of the cable laid rope from which it is formed.
Guidance Note
Guidance Note During measuring, the slings or grommets should be fully suppoded
In order to maintain the sling eye in good condition the sling eye and adequately tensioned The tension load should be in the range
should not be bent around a diameter less than three times the sling
diameter.
-
of 2 5 5 0 per cent of MBL Matching slings should be measured
w~ththe same tension load and under similar conditions
Testing equipment not able to comply with the above tension load
3.1.3.2 In order to maintain steel slings and grommets requirement could be test according to the procedure given below:
in good condition no other parts should be bent around a For each sling a series of at least 3 -three - separate tensioning
diameter less than 4 times the nominal diameter of the tests should be carried out, up to the available tension load
cable laid rope. A reduction of the capacity due to Measurement of elongation and force shall be taken at intervals
Based upon this, a theoretical elongation can be estimated for a load
bending should nevertheless be considered, see 3.1.2.1. corresponding to 2 5% of MBL Bending diameter during the
tensioning test should be specified. Depending of the results, a
3.1.3.3 Bending in way of splices shall be avoided. skew load factor correction may be required
3.1.6.1 All lifting equipment shall be in good condition 3.1.7.7 'fiere should be a datallog book for each sling
and thoroughly inspected before each lift or series of containing as a minimum the following information;
lifts. - all relevant certificates,
- handling and conservation procedure,
3.1.6.2 Slings and grommets shall be inspected by a - survey reports, and
competent person. Special attention should be given to - storage time and conditions.
the condition of splices and terminations.
3.1.7.8 Preservation procedure, including specification
3.1.6.3 Slings with; of protection medium, should be developed.
- damages,
- apparent deterioration 3.1.7.9 Galvanised slings shall be subjected to the same
- uncertain internal condition, preservation requirements as non-galvanised slings.
- uncertain handling or storage history,
- certificates older than 2 years, and 3.1.7.10 For revalidation of cable laid sling the
- overload indicators showing sign of previous additional requirements in 3.1.7.11 through 3.1.7.13
overloading (relevant for fibre slings). apply.
shall be subject for a revalidation according to 3.1.7
3.1.7.11 Cable laid slings and grommets subject for
revalidation shall be thoroughly inspected and evaluated
3.1.7 Revalidation of slings by a competent person from a recognised sling
manufacture.
3.1.7.1 Slings and grommets subject for revalidation
shall be thoroughly inspected and evaluated by a 3.1.7.12 In addition to requirements in 3.1.7.7 the
competent person. Destructive testing and issuance of datallog book for each cable laid sling should contain;
new certificates shall, when required, be done by a
recognised sling manufacture or body. - records of previous lifts,
- lift weights and,
- bending radius.
3.1.7.2 Slings subject for revalidation should be
properly cleaned. Random opening should be carried 3.1.7.13 When cable laid slings are being handled, the
out to check for internal condition and corrosion. The owner or an appointed representative should witness the
number of openings is subject to the length of the sling, operations. Any incidents shall be recorded in the log
but the sling should minimum be opened at least three book for the sling. Special attention should be given to
different places. incidents resultiong in compression loads in splices.
3.2.1.2 The shackle allowable load shall not be taken 3.2.4 Inspection
greater than the minimum of;
a) SWL*DAF:
3.2.4.1 Each shackle should be inspected before each
lift in order to reveal any traces of extraordinary
b) MBLl3.3.
loading, damages, cracks etc.
The acceptance criterion defined by Eq. 3-1 in Pt. 1 Ch.4
is fulfilled when the dynamic shackle load does not 3.2.4.2 For shackles in good condition that comply
exceed the allowable load as defined above. with the requirements in 3.2.5 and without traces of
extraordinary loading, damages, cracks etc. a visual
3.2.2 Design considerations inspections will normally be sufficient.
Otherwise the shackles shall be subject for thorough
3.2.2.1 Shackles are designed and load rated to support
visual inspection, magnetic particle inspection, and
centre line loading of the shackle. Other load conditions
ultrasonic testing before used.
should normally be avoided.
Guidance Note
Eccentric loading may be acceptable if the shackle capacity is 3.2.5 Certification of shackles
derated according to the manufacturer guidelines andlor
calculations. 3.2.5.1 A makers certificate and a proof loading
certificate signed by a recognised Certifying Body
3.2.2.2 Shackle dimensions should be selected with due should be provided for each shackle.
regard to bending radii of slings and grommets, see
3.1.3.1 and 3.1.3.2.
3.2.5.2 A shackle certificate should normally contain
the following minimum information;
3.2.2.3 It is not recommended to connect shackles
together. However, shackles connected bow to bow is certificate identification code,
normally acceptable. shackle identification code,
name of manufacturer,
date of manufacture,
3.2.3 Manufacturing and testing material type,
manufacturing method,
3.2.3.1 The manufacturing and testing of shackles to be reference code, standard or specification,
used for lifting should be carried out according to sound minimum breaking load,
practice and in accordance with a recognised code or proof load,
standard. For plate shackles 4.1.4 applies. safe working load and
date of certification.
3.2.3.2 Material requirements for new shackles should
be in accordance with the requirements as summarised in 3.2.5.3 For old shackles produced by a recognised
table D l in DNV - Rules for Certification of Lifting manufacturer, where the material can not be proven to
Appliances. comply with 3.2.3.2, the proof loading certificate should
Guidance Note not be older than 2 years.
Old shackles that do not comply with the requirements given in
3.2 3.2 may be acceptable if produced by a recognised shackle 3.2.5.4 Each shackle should be clearly identified with
manufacturer. Whether an old shackle is acceptable or not should
be decided on the basis of the information available, and the results reference to the corresponding certificate. The safe
of the non destructive examination, see also 3.2.4 and 3.2.5.3. working load as specified in the certificate should be
clearly marked on the shackle.
3.2.3.3 Each individual shackle should be proof loaded
after fabrication ?'he proof load should not be less than
indicated in Table 3.1.
5.1 CRANE AND CRANE VESSEL 5.1.4.2 Instructions for crane operation including
limiting parameters for crane operation (wind speed,
5.1.1 General rolllpitch angles, etc.) shall be presented.
5.1.1.2 The crane should be equipped with a reliable 5.2. P Clearances during operation
load monitoring system with an accuracy normally not
5.2.1.1 Clearances during crane vessel operations
exceeding 5 % of the maximum crane capacity or 10% of
should be decided on the basis of the expected duration
the weight of the lifted object.
of the operation, the operationdl procedure, the
environmental conditions, positioning and fenderhg
5.1.2 Positioning systems, back up system, configuration lay out etc.
5.1.2.1 The crane vessel should be moored andor 5.2.1.2 The calculated minimum clearances between the
positioned according to requirements in Pt. 2 Ch. 7. lifted object or lifting equipment and the crane boom
For moorings combining anchors and short lines to shore should normally not be less than 3m.
the requirements in Pt. 1Ch.2 Sec. 5.3 apply.
5.2.1.3 The calculated minimum clearances between the
lifting equipment or the crane boom and any other
5.1.3 Crane vessel certificates object/stmcture should normally not be less than 3m.
5.1.3.1 The crane vessel shall comply with the 5.2.1.4 The calculated minimum clearances between the
requirements in Pt. 1 Ch.2 Sec.5.2. lifted object and any other objectlstructure shall be
evaluated based on evaluations of duration of the
5.1.3.2 Hydrostatic stability data should be available operation, the operational procedure, the environmental
onboard. conditions, f e n d e ~ gsystems, etc.
Guidance Note
5.1.3.3 The following certificates should normally be For objects to be lifted over, around or between other objects a
presented: minimum clearance of 3m is recommended
- Certificate of Registry.
Certificate of Classification. 5.2.1.5 Clearances between the underside of the lifted
- Safety Construction Certificate. object and grillage or seafastening structures on the
Certificate of International Load Line. transport vesselharge should be evaluated. If these
- Safety Equipment Certificate. clearance are small, particular attention should be given
to avoid damages in case of impacts during lift off.
5.1.4 Crane documentation 5.2.1.6 Clearance between the lifted object or transport
vesselharge and the crane vessel or crane boom should
5.1.4.1 'fie following certificates for the crane should
be calculated.
normally be presented:
- Certificate of classification or makers certificate. The calculated clearance should consider motions of
- Crane test and installation report issued by a crane vessel and transport vesselharge. Clearance shall
recognised authority. be based on the environmental design conditions for the
- Latest annual survey report. operation and with a maximum values calculated
- Lift record for preceding operations. according to Pt. 1 Ch.3 Sec. 2 .
- Load-radius curves for static and dynamic lifting Clearances less than 3m should normally be avoided.
conditions.
Rules for Marine Operations January 1996
Pt.2 Ch.5 Lifting Page 19 of 22
5.2.1.7 Sufficient bottom clearance between the crane 5.2.2.8 For lifting of objects that are arranged with
vessel and the sea bed should be present for lifting shims between the support structurelgrillage and the
operations at small water depths (inshore). object, the shims should be secured to one of the
surfaces. Alternatively a check point for removal of
sfrimming plates under the lifted object should be
5.2.2 Lifting included. Removal of shims should preferably be
performed immediately after lift off.
5.2.2.1 Operational criteria such as, wind speed, wave
conditions, relative motions, etc., should be established
prior to starting the lifting operation. These criteria 5.2.3 Monitoring of lifting operations
should be included in the operation manual.
Guidance Note
5.2.3.1 Where applicable the following parameters
Lift off from another vessellbarge offshore should normally not be should be monitored manually or by monitoring systems:
performed with H, greater than 2.0 - 2.5m. Relative vertical motion - Hook load(s)
between crane hook and lift off vessel should be carefully evaluated
before commencement of the lift. Relative motions exceeding 2m is - Environmental conditions.
not recommended. - Tilt (specially for multihook lifts)
- Position and orientation.
5.2.2.2 Crane vessels with favourable motion Clearances.
characteristics may operate in relatively rough sea - Hoisting velocity.
conditions. For lifts carried out by such vessels,
considerations should be given to the effect of wind
5.2.4 Cutting of seafastening
loading, to ensure that such loads will not jeopardise the
operation. 5.2.4.1 The cutting procedure should be such that no
vertical restraint will occur during lift off.
5.2.2.3 The crane hook should be positioned accurately
Guidance Note
over the centre of gravity of the lifted object prior to Vertical cutting of seafasteningwith a flame cutter may, due to the
commencement of the lift. coarse cut. result in restraint effects. A better solution is to cut in
an angle of minimum 10 - 15 degrees with the vertical axis or remove
Guidance Note
one piece by applying two cuts
When lifting from another vessellbarge or from shore by crane
vessels, possible restraint loads between crane vessel and lifted
object should be relieved by slackening mooring lines as much as 5.2.4.2 Rotational restraint, at single support points,
possible and restricted use of thrusters. e.g. module footings, shall be avoided.
5.2.2.4 Ballasting of transportation vessellbarge prior 5.2.4.3 Cutlines should be marked on the seafastening
to or during lifting in order to obtain simultaneous lift in advance.
off at all support points should be considered.
Guidance Note
To avoid damaging the barge deck and provide for safe and easy
5.2.2.5 If counterweights are to be used to adjust the handling, considerations should be made to avoid large pieces of
centre of gravity during lifting, such weights should be loose seafastening debris. Seafastening of large loose seafastening
properly fastened to the lifted object. or grillage debris after lift off should be considered.
6.2.2 Special loads 6.2.5.2 The effect of possible swinging of the lifted
object due to crane movements (travelling) should be
6.2.2.1 For roll-up operations special loads may be of evaluated.
great importance and should be thoroughly evaluated.
6.2.6 Loadcases
6.2.2.2 As applicable, special loads for roll up
operations are; 6.2.6.1 Loadcases for yard lifts should be selected
- winchttugger l i e loads, based on the general guidelines given in 2.4 and the
- support reaction loads (vertical and horizontal) loads described in the paragraphs above.
- friction loads (at supports and slings) and
- wind loads. 6.2.6.2 For multi crane operations sensitivity analysis
with respect to possible crane load distributions, see
6.2.3 Dynamic loads 6.2.4.1, should be carried out.
6.2.3.1 Table 2.1 gives applicable factors to take into 6.2.6.3 For roll-up operations it should be justified that
account dynamic effects for onshore lifts. the selected loadcases, i.e. analysed roll-up angles,
represent the design case for, cranes, rigging and all
6.2.3.2 For crawler cranes travelling with load, structural items.
possible dynamic effects should be evaluated thoroughly.
Crane speeds and surface conditions should be
considered.
Rules for Marine Operations January 1996
Pt.2 Ch.5 Lifting Page 21 of 22
6.3.1.1 The nominal safety factor for slings and 63.2 Allowable loads
grommets for yard lifts should be calculated as described
in 3.1.2.2. 6.5.2.1 Allowable crane loads should be based on
Guidance Note Load-radii curvesltables. These should, as applicable,
Yards slings are normally multiple used slings exposed to wear and clearly state
tear, hence a wear factory, > 1 00 should be used. A y,=l 20 is
recommended.
- crane boom type and length (crawler cranes),
counter weight position(s) and weights, minimum
6.3.1.2 Slings made of soft ropes could be acceptable, quantity of hoist line legs, maximum load limited
see 3.1.1.4. by overturning or structural strength,
- crane equipment, e.g. hook, block, hoist lines,
6.3.1.3 Due attention should be paid to the effect of the jib, to be included in crane hook load and
object rotation (roll-up) on the sling connections. operational limitations.
MAMNE OPEMTIONS
PART 2 : OPERATION SPECIFIC FEQUIMMENTS
PART 2 C W I E R 6
SECTIONS
1. INTRODUCTION ................................................................................................................... 4
2. DESIGN LOADS .................................................................................................................... 8
3. SOIL CAPACITIES ................................................................................................................ 13
4. OPERATIONAL ASPECTS.. ................................................................................................... .I5
STRUCTURES....................................... 7
1.5.1 General ......................................... 7 4. OPERATIONAL ASPECTS ....................15
4.1 GENERAL ........................................... 15
DESIGN LOADS ...................................8 4.1.1 Application ................................... 15
4.1.2 Planning and preparations .................. 15
GENERAL ............................................ 8
2.1. 1 Application .................................... 8 4.2 SYSmMS ...........................................15
4.2.1 Load reducing systems...................... 15
CRANE TIP MOTIONS ............................ 8 4.2.2 Dynamic positioning systems .............. 15
2.2.1 Characteristic vessel motions ............... 8 4.2.3 Ballasting systems ........................... 15
2.2.2 Characteristic crane tip motion ............. 8 4.2.4 Manned vehicles and ADS-systems....... 16
2.2.3 Characteristic crane tip velocity ............ 8
2.2.4 Characteristic crane tip acceleration ....... 8 4.3 INSTALLATION AIDS ........................... 16
4.3.1 General ........................................16
HYDRODYNAMIC FORCES W E N 4.3.2 Guide and tugger lines ...................... 16
LOWERED ?'HROUGH WATER SURFACE . 9
2.3.1 Characteristic total force .....................9 4.4 ROV OPERATIONS ...............................16
2.3.2 Characteristic hydrodynamic force......... 9 4.4.1 Planning ................................... 16
2.3.3 Characteristic slamming impact force ..... 9 4.4.2 General recommendations.................. 16
2.3.4 Characteristic buoyancy force .............. 9 4.4.3 Launching restrictions ...................... 17
4.4.4 Monitoring ................................... 17
HYDRODYNAMIC FORCES ON
SUBMERGED OBJECTS ......................... 10 4.5 TIE-IN OPERATIONS ............................ 17
2.4.1 Characteristic total force....................10 4.5.1 ROV recommendations ..................... 17
2.4.2 Characteristic hydrodynamic force........10 4.5.2 Other recommendations ....................17
2.4.3 Effect of moon-pool ......................... 11
4.6 BUNDLE OPERATIONS ......................... 17
SNAP FORCES IN HOISTING LINE ..........11 4.6.1 Bundle transport ............................. 17
2.5.1 General ........................................
11 4.6.2 Pipeline and bundle pull-in ................ 18
2.5.2 Characteristic snap force ...................11
2.5.3 Characteristic snap velocity ................ 11
January 1996 Rules for Marine Operations
Page 4 of 18 R . 2 Ch.6 Sub Sea Operations
1.3.1 Critical design parameters 1.3.2.6 Prior to start of the operation, certificates, test
reports, release notes and classification documents if
1.3.1.1 When evaluating a sub-sea operation, the any, for equipment and vessels involved, should be
following parameters should be taken into account prior presented as applicable.
to establishing the design and operational criteria, see
Pt. 1 Ch.2 Sec.3.I ;
- water depth,
January 1996 Rules for Marine Operations
Page 6 of 18 Pt.2 Ch.6 Sub Sea Cb~erations
1.4.1.1 Characteristic loads and load combinations 1.4.5 Loads from soil
should be established according to Pt. 1 Ch. 3.
1.4.5.1 Reaction forces from the soil should be
accounted for. Loads such as foundation reactions at
1.4.1.2 Design loads and load cases shall be taken seabed impact and during the soil penetratiodretraction
according to Pt. 1 Ch.4. phase, and suction forces when repositioning of an
object is required, should be determined considering the
1.4.1.3 Static weight and weight distributions should be fo!lowing parameters;
taken according to Pt. I Ch.3 Sec. 3.5.
- soil material and parameters
- sea bed topography
1.4.2 Environmental loads - penetration depth and
- exposure time (repositioning)
1.4.2.1 Environmental loads should be determined in
accordance with Pt. 1 Ch. 3 See. 3 and 2.
1.5 STRUCTURES
1.5.1 General
2. DESIGN L O m S
2.2.2 Characteristic crane tip motion 2.2.4.1 ??he crane tip's characteristic single amplitude
vertical acceleration for a given design sea state may be
2.2.2.1 The crane tip's characteristic vertical motion taken as:
response in a given design sea state and wave heading,
may be taken as:
q, +
= JTj; (bsin(Tn))' + (l~in(~,))'
Eq. 2 3
Eq. 2-1 where
where
a, : characteristic single amplitude vertical
qa : characteristic single amplitude vertical motion of acceleration of crane tip [ds2]
crane tip [m]
q : characteristic single amplitude heave motion of
vessel [m]
(PR : characteristic single amplitude roll motion of
vessel [deg]
cpp : characteristic single amplitude pitch motion of
vessel [deg]
b: the horizontal distance from the vessel's centre
line to the crane tip, or the outboard sheave block
[ml
Rules for Marine Operations January 1996
Pt.2 Ch.6 Sub Sea Operations Page 9 of 18
Eq. 2-10
where
d: distance from water plane to centre of gravity of
submerged part of object. [ml
January 1996 Rules for Marine Operations
Page 10 of 48 R . 2 Ch.6 Sub Sea Operations
2.3.4.3 The stiffness of the hoisting system may be 2.4.4.3 Snap forces in lifting wire wili occur if
calculated by: hydrodynamic force exceeds static submerged weight of
object. Zn such case, the dynamic amplification factor
should be taken as:
Eq. 2-11
where 'static
K: stiffness of hoisting system [Nimj Eq. 2-15
ku,, : stiffness of single wire line where Fsmp
may be found according to 2.5.2..
: stiffness of soft strop if used
kblock: stiffness of multiple wirelines in a block 2.4.2 Characteristic hydrodynamic force
khm : stiffness of crane boom
k : other stiffness contributions if any 2.4.2.4 The hydrodynamic force on the object consists
of mass forces and drag forces which may be combined
2.3.4.4 The stiffness of crane boom is often neglected by:
as it is usually much larger than the line stiffness'. The F,,. = !Nl
line stiffness' may be calculated by:
Eqc 2-16
where
F, : characteristic mass force [Nl
Eq. 2-12 Fd : characteristic drag force [Nl
where
E: modulus of elasticity [~/m*j 2-4.2.2 'I'he characteristic mass force due to coinbined
effective cross section area of line, if multiple acceleration of object and water particles may be taken
A, :
as:
lines the areas are sumrnarised I~'I
L: total length of line(s) [ml F, = (m + m&)a, + p V a , + m&a, EN]
Eq. 2-17
where
2.4 RODWAMC FORCES ON
rn : mass of object in air Fg]
SUBmWGED OBJECTS
mdd: added mass of object k g1
a, : characteristic single amplitude verticai
2.4.1 Characteristic total force acceleration of crane tip, see 2.2.4 [m/s21
p : density of sea water, normally = 1025 @g/m3]
2.4.1.1 The characteristic total force on object when V : volume of displaced water [m3]
object is submerged may be taken as:
a,: characteristic vertical water particle acceleration
Ftdsl=Fmtici Fhyd [dsZl
Eq. 2-13
where 2.4.2.3 The added mass of the object may be taken as:
Fd, : static submerged weight of object, see 2.3. I.2[N] a d d = PVC,
Fhyd: characteristic hydrodynamic force [Nl Eq. 2-18
where
2.4.1.2 The capacity of the lifting equipment should be added mass coefficient as a function of depth,
C, :
checked according to PC.2 Ch.5 Sec. 2 applying: which may be determined by theoretical and/or
<,tic + Fhyd experimental methods.
DAF =
Fs,tic
2.4.2.4 The characteristic water particle acceleration
Eq. 2-14 may be taken as:
where Fhydm y be found by Eq. 2-16.
\ 1
Eq. 2-19
where
d: distance from water plane to centre of gravity of
submerged part of object [m].
H, : Significant wave height of design sea state
Rules for Marine Operations January 1996
R . 2 Ch.6 Sub Sea Operations Page 11 of 18
2.4.2.5 ?'he characteristic drag force may be taken as: 2.5.2 Characteristic snap force
F,= 0.5 p Cd Ap vr2
Eq. 2-20 2.5.2.1 Characteristic snap loads during start and stop
where may be taken as:
C, : drag coefficient as a function of depth, which may I;,, = g' ,ic +vsmpd~(*
m ma,,)
be determined by theoretical and/or expenmental
Eq. 2-22
methods.
where
Ap : area of object projected on a horizontai plane[m'].
v, : characteristic vertical relative velocity between v,, : characteristic snap velocity [ds]
1
object and water particles, see 2.3.4.2 [ d s ] . F s ~ ~ c
3.1.1.1 It should be documented that the object during 3.2.1.1 For re-positioning or retrieval of an object
all phases of the installation operation remains stable on placed on the sea bed, forces due to suction should be
the sea bed, without getting unacceptable displacements calculated. 'I'his may be done by using bearing capacity
due to soil failure. formulae as given in Classification Note 30.4, section
4.4.
3.1.1.2 A general reference is made to Classification
Note 30.4 Foundations for calculation of soil properties 3.2.1.2 The forces are dependent on soil parameters,
and capacities. foundation geometry, lifting velocity, exposure time,
contact pressure, etc.
i
3,1.2 Stability calculations
3.2.2 Time for full drainage
3.1.2.1 Whether the permanent foundation solution is
based on mat foundation or piled foundation, there will 3.2.2.1 The time for fuli drainage should be calculated
often be a temporary phase during installation where the based on specific soil data for the site in question, in
object will be supported on mats, possibly equipped with order to plan the rate of pull application, and calculate
skirts. the corresponding foundation reactions.
3.1.2.2 The stability may for reasonably homogeneous 3.2.2.2 Time for full drainage may be taken as:
soil conditions be checked by conventional bearing
capacity formulations combined with pure sliding
checks. Recommendations are given for idealised soil
conditions in Classification Note 30.4, section 4.4.
where
3.1.2.3 Stability should be checked for load h = drainage distance
combinations including gravity loads, environmentai C , = coefficient of consolidation
loads where significant, and any loads possibly applied A simple and conservative approach may be to assume
to the structure during installation, e.g. during stabbing that all pulling forces applied within the time t, is
of piles. reacted by suction, whereas all pulling forces applied
earlier, effectively reduces the net foundation contact
3.1.3 Material factors forces. More elaborate consolidation analyses may be
performed to evaluate the partial drainage for the force
,
3.1.3.1 For foundation failures which may have
unacceptable consequences, such as structural damage or
applied within the time tp.
3.2.3.2 The pulling forces caused by heave of the 3.2.6.2 ?'he soil reaction may be difficult to caiculare
installation vessel should normally be considered to be and may depend on the filter used (permeability,
reacted by a suction force in any kind of soil, unless structural flexibility. etc.). ?'he soil reaction should on
consolidation analyses are performed to demonstrate that thts case be documented by appropriate tests. or actual
drainage occurs. experience for similar condit~ons.
4. OPEWTIONAL ASPECTS
4.2 SYSTEMS
4.2.3 Ballasting systems
4.2.1 Load reducing systems 4.2.3.1 For operations requiring ballasting of the
object, a proper ballast control and monitoring system
4.2.1.1 Based upon technical specifications, onsite should be implemented. Special back-uplmonito~g
evaluations, or other documentation, operational credit devices in order to avoid uncontrolled ballasting may be
may, on a case to case basis be granted by the attending required.
VMO surveyor. Hence a more severe weather
I
v ' , condition may be acceptabie. 4.2.3.2 Ballast system utilising external umbilical
supply, are subject to the same recommendations as
4.2.2 Dynamic positioning systems outlined in 4.3.1.2.
4.2.2.1 When DP is used for station keeping, a 4.2.3.3 All panel valves to be operated by ROV, should
minimum of 3 independent DP reference system are be clearly marked opedshut (01s). Valve indicators on
required. critical valves may be considered necessary for visual
Guidance Note
verification purposes.
For operations where consequences for handled object, installation
vessel and other structures or vessels in the vicinity, of loosing the 4.2.3.4 Special back up or monitoring equipment m y
DP reference systems are small, 2 independent reference systems
may be accepted
be required in order to avoid uncontrolled ballasting
4.3.2.3 If guidetpull-down lines fixed to a pre-installed 4.4.2.4 ROV thruster capacity should normally be at
sub- sea template or similar, will require a fixed vessel
least 30% higher than the maximum expected current
heading, the weather criteria specified for the operation
force acting on the ROV and its umbilical.
should reflect this.
4.4.2.5 Means for localising and tracking of the ROV
4.3.2.4 Temporary attachments which may impose from the surface may be required.
damage to the structure, should be removed without
deiay .
4.4.2.6 For operations combining ROV and divers, any
possible restrictions that ROV and divers are not able to
work simultaneously, should be clarified in advance, and
taken into due consideration.
Rules for Marine Operations January 1996
R.2 Ch.6 Sub Sea Operations Page 17 of 18
4.4.3.1 Launching and retrieving of large ROV's, not 4.5.2.1 Procedure for abandoning habitat should be
protected by cage, over a ship's side should not take documented, as well as limiting criteria for station
place in waves exceeding H, > 2.5-~[ITI]. keeping of vessel. Abandoning of habitat in case of
deteriorating weather conditions should normally not
4.4.3.2 If exemptions from restriction in 4.4.3.1 is take longer than the tirue necessary to retrieve divers.
made, it must be documented that ROV's can be
retrieved or lauriched in a safe manner under more severe 4.5.2.2 For tie-in operations taking place in water
conditions. depths > 150[m], means should be provided for
reducing tension and drag in umbilicals, unless sufficient
4.4.3.3 Moon-pool ROV operations may however be internal strength and vessei station keeping capability is
extended to documented.
4.5.1.1 Positioning operations of habitat and Pipe 4.6.1.4 All tugs should have suitable towing
a' Handling Frame (PHF) should be subject to monitoring arrangements for 'piggy back' connection in case of
by ROV. For positioning operations sensitive to vessel engine break down/failure.
motion, limiting weather criteria should be established.
4.6.1.5 Bottom survey for towing route should be
4.5.1.2 Location of ROV onboard vessel should be carried out. Holding areas for each 100 n.mile with a
chosen with due consideration to umbilicals, wires etc. diameter of at least the bundle length +2Wm to be
attached to habitat and PHF, in order to avoid surveyed.
entangling. Back up ROV for monitoring should be
present onboard. 4.6.1.6 Maximum allowable pull-head angle with
surface should be documented.
PART 2 CHAPTER 7
SECTIONS
1. INTRODUCTION .................................................................................................................. . 4
2. PLANNING AND PREPARATIONS ..................................................................................... 6
3. TRANSIT.. .............................................................................................................................. .7
4. POSITIONING ........................................................................................................................ 9
CONTENTS
1 . INTRODUCTION .............................................. 4 4 . POSITIONING .................................................. 9
1.2.2 Symbols
The list below defines symbols used in this chapter:
H, : Significant wave height
HAT : Highest astronomical tide
LAT . Lowest astronomical tide
MBL . Minimum breaking load
MOU . Mobile offshore unit
MWL : Mean water level
NMD : Norwegian Maritime Directorate
ROV Remote operated (submersible) vehicle
SSCV : Semi-submersible crane vessel.
January 2000 Rules for Marine Operations
Page 6 of 16
- - Pt.2 Ch.7 Transit and Positioning of Mobile Offshore Units
2. PLANNING AND P m P A U T I O N S
2.1 PLANNING
2.2.2 Stability afloat
2.1.1 General
2.2.2.1 General stability requirements are given in Pt. 1
2.1.1.1 'Transit and positioning operations shall be Ch 2 Sec.4. However, compliance with the stability
planned and prepared according to the requirements and requirements of the actual Flag State and/or the
philosophies given in Pt. 1 Ch.2. classification society is sufficient, and is normally covered
in the operations manual or the stability manual of the
vessel.
2.1.2.1 Several operations may be planned to take place 2.2.3 Loads and load effects
in the sarne area at the same time, and will require co-
ordination between the various vessels and operators in 2.2.3.1 Characteristic loads and load effects shall be
order to avoid conflicts. defined according to Pt. 1 Ch. 3 Sec. 3.
This is in particular important for positioning and sub-sea
2.2.3.2 Load cases for the transit and positioning
operations in the sarne area.
operations shall generally be defined according to Pt. 1
Ch 4 Sec 2.2.
2.1.3 Documentation
2.2.3.3 Possible impact loads during setting of self-
2.1.3.1 General requirements for documentation are elevating units shall be considered.
given in Pt. 1 C17.2 Sec.2.2.
2.1.3.2 The planned transit or positioning operation shall 2.2.4 Strength evaluations
be described by procedures and drawings.
2.2.4.1 Structural strength verification shall comply with
A manual covering the relevant aspects of the operation Pt. 1 Ch 4.
shall be prepared, see also Pt. 1 Ch.2 Sec 2 2 and Pt. 1
Ch.2 Sec. 3.5. 2.2.4.2 The transit condition of the unit shall be
confirmed to be within the conditions for class, or
2.1.3.3 Certificates, test reports arid classification otherwise the unit shall be verified to have acceptable
documents for equipment, objects and vessels involved strength for the transit conditions. See also Pt.1 Ch.3 and
shall, as applicable, be presented before start of the Pt. 1 Ch.4.
operation.
2.2.4.3 Special attention shall be given to structural
integrity of legs and their supports of self-elevation units,
2.2 DESIGN EVALUATIONS both in transit and during positioning.
3.2 TOWING EQUIPMENT 3.3.1.2 Criteria for entering into a safe hold coridition,
related to actual and forecasted environmental conditions
3.2.1 General shall be clearly stated in the operations manual. The
criteria shall reflect riecessary time for reaching the safe
3.2.1.1 General requirements for towing vessels, towed condition, including required contingency timc, see also
unit and towing equipment are giver1 in Pt.2 Ch.2 Sec.3. Pt 1 Cj7.2 Sec.3.l. Reference is also rnade to 3 3.2 for
towing of jack-ups.
3.2.1.2 Requirements for the capacity of towing bridle Guidance Note
and towing brackets are given in Pt.2 Ch 2 Sec. 3.1. For "wet tow" of self-elevating units the environmental criteria for
setting are ofteri stricter than the criteria for towing, i e the
Guidance Note criteria for setting will govern the decision for entering into a safe
For some mobile offshore units these requirements rriay be in hold condition.
excess of what is required by its class. Normally, compliance with
class requirements will suffice.
Guidance Note 3.3.2 Emergency jack up locations
If the tug is oversized (i.e. has considerably more bollard pull than
specified in 3 2.2. I ) , the required strength of the towing 3.3.2.1 For a self-elevating unit with limitations in the
arrangements including the brackets on the towed unit/vessel can environmental conditioris it can sustain in floating
be reduced to comply only with the minimum bollard pull required. condition, transit operations shall be planned as weather
In such cases a restriction on maximum bollard pull to be
exercised by the tug shall be given in the towing procedure, see restricted operations with defined emergency jack up
2. I 3 2. locations. Distance between these locations will be
decided by required time for jacking down and jacking up
3.2.2 Required thrust and bollard pull the unit, time for positionirig and unit towing speed. plus
contingency time.
3.2.2.1 The combined propulsion force (total thrust Guidance Note
capacity) of the unitlvessel and the tug(s) shall be The NMD regulations concerning field rnoves for Norwegian
sufficient to maintain control of the unit under the flagged offshore units require that rnaxirrium transit time between
the emergency jack up locatioris shall not exceed 24 hours This
environmental conditioris given in Pt.2 Ch.2 Sec. 3.3.2.4 24 hours period covers jacking down to floating condition, towing
and Sec.3.3.2.5. For transit in coastal/narrow waters a and jacking up to sufficient air gap at the riew location
minimum speed over the ground of 2 knots in the
environmental design condition shall be maintained, see 3.3.2.2 For defined emergency jack up locatioris it shall
Pt.2 Ch.2 Sec. 3.3.2.5. Propulsion efficiencies for tugs be documented that the soil conditions are such that the
shall be accounted for with reduction factors as given in jack-up will not experience sudden significant penetration
Pt.2 ChZSec.3 3.2.6. of the spudcans during the jacking process or during the
stay at the locatiori in elevated position. Soil conditions
with soft, normally consolidated clays or with stiff soil
3.2.3 Emergency anchoring overlying soft soil (punch-through conditions) shall be
avoided.
3.2.3.1 The unit shall normally have at least one operable
anchor during transit. The anchor(s) is to be of sufficient
capacity and with sufficient length of mooring line 3.3.2.3 The documentation shall clearly show that the
available for emergency anchoring. locations consist of' competent soils which are either dense
sands or stiff clays to depth which excludes the possibility
Guidance Note of foundation punch-through.
The lack of an operable anchor systerri may be compensated by
additional tug capacity, after evaluation of characteristics of the
unit, towing route and season. 3.3.2.4 The docurneritation shall include bathymetric
mappirig and a shallow seismic survey for the location,
which can be tied back to nearby existing soil boring(s) to
3.3 OPERATIONAL ASPECTS assist in the assessment of the soil stratigraphy. The
seismic survey shall be of good quality using equipment
which car1 trace the shallow layering and detect possible
3.3.1 General presence of buried erosion charinels within the depth of
interest, basically down to 50 m below seabed.
3.3.1.1 General requiremerlts for towing operations are
given in Pt.2 Ch.2 Sec.4. 'The seismic surveys, the soil borings and the
iriterpretation of the corresponding soil conditioris for the
actual location shall be documented.
Rules for Marine Operations January 2000
-
Pt.2 Ch.7 Transit and Positioning of Mobile Offshore Units Page 9 of 16
4. POSITIONING
The operational criteria shall be less than the design 4.2.3.4 During installation and normal operation of the
criteria, as specified in Pi.1 C17.2 Sec. 3.1.2 3. mooring system accurate monitoring of line lengths out of
the winch and line tension is important for obtaining and
controlling the planned condition. The floating unit shall
therefore have reliable equipment with sufficient accuracy
4.2 STATION-KEEPING SYSTEMS
for continuous measurement and display of these
variables.
4.2.1 General
4.2.1.1 Two types of station-keeping systems are 4.2.4 Dynamic Positioning (DP) systems
assumed in this chapter:
- 4.2.4.1 For positioning operations close to another vessel
mooring systems with anchors, chain cable and/or
or offshore installation, the DP system of the unit shall
steel wire rope or fibre rope anchor lines, with or
comply with the requirements of DNV's "Rules for
without thruster assistance
Classification of Mobile Offshore Units", Pt.6 Ch.7 -
- dynamic positioning systems.
Dynamic Positioning Systems, class notation DYNPOS
AUTRO, or equivalent. Vessels with DP system
4.2.2 Design requirements complying with class notation DYNPOS AUTR
requirements or equivalent may be accepted after
4.2.2.1 The station-keeping system shall have acceptable consideration of procedures, equipment and consequences
capacity, see 4.2.3 and/or 4.2.4, both for intact condition of failures for the actual operation.
(ULS) and one-line or one-component failure situations
(PLS).
4.2.4.2 The capacity of the DP system shall be
documented or tested to prove compliance in the
4.2.2.2 The station-keeping system shall be designed, characteristic environmental conditions with the motion
with emphasis on flexibility and redundancy, to keep the envelopes set for the actual operation. See also 2.2.1.1.
unit in position both in the survival and the operating
condition, without overloading any component of the
4.2.4.3 The complete DP system shall be function tested
system.
with acceptable results before commencing the
positioning operation.
Rules for Marine Operations January 2000
Pt.2 Ch.7 Transit and Positioning of Mobile Offshore Units Page 11 of 16
4.3.5.2 In case of cross anchoring of two or more units - 150 meters in front of the pipeline, this distance
the documentation of the anchor pattern shall include may however be reduced to 50 meters if the
catenary plans for all anchor lines. The anchor pattern and installation of the anchor is monitored and
the tension in the anchor lines shall be such that a controlled by means of ROV
clearance exists between individual lines in all intact - 150 meters when the pipeline is parallel to the
conditions, motion of units included. In one line broken anchor line
conditions, contact with steel wire anchor lines shall not - 250 meters when the anchor line is crossing the
take place, while contact between chain cable anchor lines pipeline
is accepted. horizontal clearance between anchor and a sub-sea
structure or a fixed unit shall not be less than 300
4.3.5.3 For the intact mooring system, the following meters. This distance may however be reduced to
minimum clearance shall normally be maintained between 50 meters in the anchor drag sector away from the
the anchor lines of a unit and a fixed structure, motion of structure if the installation of the anchor is
unit included: monitored and controlled by means of ROV.
- for "hot" structures (in operation) the minimum
clearance shall be 10 meters in all directions Guidance Note
Buoys may be attached along the anchor lines during installation
- for "cold" structures (during installation, etc.) the and operation in order to ensure sufficient vertical clearance to
minimum clearance shall be 5 meters in all sub-sea structures and pipelines.
directions. Guidance Note
The minimum anchor clearances to seabed structures given are
4.3.5.4 In the one line broken condition, the following for drag-installed anchors. For other anchor types without
significant drag, less clearance may be accepted.
minimum clearance shall normally be maintained between
the anchor lines of a unit and a fixed structure:
- for "hot" structures (in operation) there shall be no
contact 4.4 INSTALLATION OF ANCHORS
- for "cold" structures (during installation, etc.)
contact may be accepted, based on a case-by-case 4.4.1 General
evaluation.
4.4.1.1 The anchor installation procedure shall in
4.3.5.5 In case of interference between sub-sea particular address how sufficient clearance between
installations such as pipelines, templates, manifolds, etc, anchor lines and sub-sea installations are achieved and
and anchor lines, the anchor(s) and the anchor line(s) shall maintained during the installation operation. Criteria for
be positioned such that an acceptable clearance exists clearance between anchors and pipelineslsub-sea
between the anchorlanchor line and the installation in all structures are given in 4.3.5.5.
conditions. Anchor lines crossing sub-sea structures are
normally not accepted. 4.4.1.2 Handling and transfer of anchors shall not take
The following clearance shall normally be maintained; place above unburied pipelines and sub-sea installations.
- vertical clearance between exposed pipeline and a Guidance Note
"Handling and transfer of anchors" in this connection means
crossing anchor line shall not be less than 10 anchors suspended over the stern or side of an anchor
meters for the intact mooring system, motion of installation vessel. "Above" means inside a sector of i 20~fronl
unit included, and positive in the one line broken the vertical through the pipelinelsub-seainstallationto the sea
case surface.
- vertical clearance between buried pipelines and a
4.4.1.3 Contact, i.e. zero clearance, between anchor lines
crossing anchor line shall be positive for the intact
and unburied pipelines during anchor handling is normally
mooring system, motion of unit included, i.e. the
not accepted.
anchor line shall not touch the seabed above the
pipeline, while contact is accepted in the one line Guidance Note
broken case Buried pipelines may have limited protection against seabed
- dragging of mooring chain. Sideways and longitudinal dragging of
horizontal clearance between exposed pipeline or mooring chain over buried pipelines should therefore not take
sub-sea structure and a anchor line not crossing place during anchor installation.
shall not be less than 150 meters
- horizontal clearance between buried pipeline and
an anchor line not crossing shall not be less than 50
meters
- tiorizontal clearance between anchor and a pipeline
shall not be less than:
Rules for Marine Operations January 2000
Page 13 of 16
- Ch.7 Transit and Positioning of Mobile Offshore Units
Pt.2
4.4.2.1 Anchors shall be installed by an anchor-handling 4.4.3.1 This section covers installation of anchors usually
tug of adequate size and bollard pull capacity. used for permanent or long-term mooring of floating
structures, such as pile anchors, plate anchors, suction
4.4.2.2 For permanent or long-term moorings, the anchor anchors and gravity anchors.
resistance after installatiori shall be verified as required by
National governmental regulations, or as given in D W ' s 4.4.3.2 The anchors are to be installed within the
"Recommended Practice RP-E301 - Design and tolerances given in the design documentation.
installation of fluke anchors in clay" or DNV's
"Recommended Practice RP-E302 - Design and 4.4.3.3 The installation manual shall as a minimum
installation of drag-in plate anchors in clay", as relevant. address:
- transport of the anchors, including seafastening
3.4.2.3 For mooring periods less than 5 years where the - installation tolerances, including position- and
consequences of anchor dragging during the maximum vertical tolerances
characteristic environmental condition is critical to - procedure for reversing the installation of any
adjacent installations, human life or the environment, the anchor not installed within acceptable tolerances
anchor resistance shall be verified by applying a mooring - procedure for tensioning and lay down of the
test load of 1.25 times the rriaximum characteristic line anchor lines after installation of the anchors
tension. intact mooring system. If this test load cannot be - procedure for inspection of anchors and anchor
obtained, the maximurn anchor line tension under normal lines after installation.
operation must not exceed 0.8 times the anchor test load
reached.
4.5 POSITIONING OF SELF-ELEVATING UNITS
4.4.2.4 For mooring periods less than 5 years where the
consequences of anchor dragging during the maximum
characteristic environmental condition is not critical, the 4.5.1 General
anchor resistance shall be verified as given in 4.4.2.3, or
4.5.1.1 The structural strength, air gap and overturning
by applying a mooring test load that previous experience
stability on the seabed of the self-elevating unit shall
at the location has proved sufficient.
comply with the requirements of DNVS "Rules for
Classification of Mobiie Offshore Units". Pt.3 Ch.2 Sec.3
1.4.2.5 The resistance of pre-set, drag-installed anchors
- Self-Elevating Units, or equivalent.
planned to be used several times should normally be
verified as given in DNV's "Recommended Practice RP- Guidance Note
Acceptable methods for design arialysis can be found in DNV's
E301 - Design and installation of fluke anchors in clay" or
"Classification Note No. 31 5 - Strength Analysis of Main
DNV's "Recommended Practice RP-E302 - Design and Structures of Self-Elevating Units".
~nstallationof drag-in plate anchors in clay". as relevant."
4.5.1.2 Limiting environmental conditions (e.g. waves,
4.1.2.6 During testing of' moorings the line tension for current, wind, motions etc.) shall be given in the
chain cable shall not exceed the proof load of the chain. Operations Manual for the following conditions:
but maximum 0.8 times the MBL of the chain. For steel - transit
wire anchor line the mooring test load shall not exceed 0.5 - installation and-retrieval
times the MBL of the wire. The tension shall be - operation.
maintained for at least 15 minutes without dragging of the
anchor to ensure that sufficient anchor resistance has bee11 4.5.1.3 Anticipated penetration shall be calculated for the
reached. actual location, based on available information 011 soil
characteristics and environmental conditions.
Table 4.2 contains a summary of the requirements for
verification of resistance of drag-installed anchors given Guidance Mote
in this section. Acceptable criteria for soil conditions and methods for analysis of
foundation behaviour can be found in DNV's "Classification Note
No 30.4 - Foundationsu.
4.4.2.7 If sufficient resistance is not obtained with a
single anchor on a mooring line due to unexpected soil
conditions on the location, "piggy back" anchor(s) may be
applied. Documentation of arrangement, strength and
operation procedure for installation and testing of "piggy
back" anchors are to be presented.
January 2000 Rules for Marine Operations
Page 14 of 16 Pt.2 Ch.7 Transit and Positioning of Mobile Offshore Units
4.5.3.2 The installation area shall be free from 4.5.6.1 As a part of the installation procedure, the unit
obstructions such as: shall be pre-loaded in such a manner that each leg is
boulders subjected to a load equivalent to the maximum load
wrecks expected at the location.
lost construction material.
4.5.6.2 The maximum loads shall be determined for the
When entering a pre-used location, care shall be taken
most unfavourable combination of environmental and
during preloading to avoid that one leg hits an abandoned
functional loads in survival and operating conditions. Full
leg-hole.
pre-load shall be maintained for minimum 1 hour after the
penetration has stopped.
4.5.4 Operational aspects
Sub-sea clearance
Anchor lines of a unit and Any a) 1 0 m a) 1 0 m
a platform in operation direction b) No contact b) No contact
("hot", in production)
Anchor lines of a unit and Any a) 5 m a) 5 m
a platform not in operation direction b) Contact b) Contact
("cold", not in production) acczpted accepted
Anchor line and an Crossing a) lOm
If ROV control during installation of anchor. " Intact system, motion of unit included, design
environmental loads
" If the anchor drag sector is away from the structure. h' One line broken, transient motion.
Rules for Marine Operations
Pt.2 Ch.7 Transit and Positioning of Mobile Offshore Units
Mooring category
Verification (testing) of As required by National If the consequences of anchor dragging during the maximum
anchor resistance as governmental regulations, characteristic environmental condition is critical, the anchor
installed on actual as given in resistance shall be verified by applying a mooring test load
location DNV R~-E301*'and of 1.25 times the maximum characteristic line tension, intact
DNV RP-E302", mooring system.
or as approved in the anchor If this test load cannot be obtained, the maximum anchor line
design. tension under normal operation must not exceed 0.8 times
the anchor test load reached.
" DNV's "Rules for Classification of Mobile Offshore Units", Pt.6 Ch.2 Sec.5.
2'
DNV's "Recornrner~dedPractice RP-E301 - Design and installation of fluke anchors in clay".
"
DNV's "Recommended Practice RP-E302 - Design and installation of drag-in plate anchors in clay".