Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Contents
1 Scope ............................................................2
2 Intended Users...............................................2
3 Conflicts and Deviations..................................2
4 Applicable Documents ....................................2
5 Definitions ......................................................3
6 Projects Energy Assessment...........................4
7 FEL2 Study Phase - EOS ...............................5
8 FEL2 DBSP Phase - EOS ...............................8
9 FEL3 - EOS Recommendations Follow-up ..... 11
Revision Summary.............................................. 11
1 Scope
This procedure applies to all new facilities and expansion projects in the existing
facilities, where the overall energy consumption of the upcoming facility or new
expansion exceeds 100 MMBTu/hr of heating/cooling, or 10 MW of mechanical power.
2 Intended Users
Any conflicts between this document and other applicable Mandatory Saudi Aramco
Engineering Requirements (MSAERs) shall be addressed to the EK&RD Coordinator.
Any deviation from the requirements herein shall follow internal company procedure
SAEP-302.
4 Applicable Documents
Note: This procedure is the main reference for the project deliverable “Energy Optimization
Study”, it provides details of the requirements for conducting the energy st udy during
relevant projects.
5 Definitions
Targeting: The process of setting targets of energy, cost, utility, area, etc.,
for process/plant or even for a whole facility ahead of design, knowing its
operational requirements, capabilities and limitations. Energy Targeting
provides the target for the Minimum Energy Requirement (MER) of a given
process.
5.2 Abbreviations
P&CSD – Process and Control Systems Department
Saudi Aramco: Company General Use
Page 3 of 11
Document Responsibility: Energy Systems Optimization Standards Committee SAEP-42
Issue Date: 1 January 2018
Next Planned Update: 15 October 2019 Capital Project’s Energy Optimization Study
This procedure mandates conducting energy optimization studies in the FEL2 project
phase and to review the design in FEL3 project phase (this is okay if the review is no
later than approximately the 60% PP stage, it would seem a little bit late otherwise.
These phases as per SAEP-1350 cover the “Study” phase, “Design Basis Scoping Paper
(DBSP)” phase and the “Project Proposal” phase, as shown in Figure 1.
The main objective of conducting an EOS is to develop the proposed facility design into
an Energy-Efficient Design. Involvement of P&CSD/ESD at the early stage of project,
i.e., FEL1 business case development, is highly recommended for the success of EOS.
The EOS shall be initiated in FEL2 Study phase and completed in FEL2 DBSP phase.
EOS is carried out in two stages as initial and final assessments. Initial assessment
consists of system level integration and shall be conducted by P&CSD/ESD.
Final assessment consists of optimizing the selected systems to achieve an energy
efficient design. The scope of the final assessment will vary from project to project,
depending on its nature. The scope of final assessment shall be developed by
P&CSD/ESD during initial assessment. The scope of work for the EOS should be
developed in accordance to SABP-P-017.
During FEL3 project proposal stage, the main task is to support design development of
the identified initiatives/recommendations of EOS and to resolve any issues/concerns
that arise due to proposed design modification.
The outcome of this analysis in the form of “Energy Optimization Study Report” shall be
considered in the DBSP. All unaccepted recommendations shall be submitted to Energy
Systems Optimization Standards Committee for approval with proper justification.
7.1.1 Select a project closely resembling the current project from the available
database. Criteria for resemblance is the process configuration, plant
geographical location; and/or previous experience.
7.1.2 Gather the selected project’s related information and capitalize on the
preliminary process design and similar projects if available to obtain the
PFD and UFD simulation models, data-sheets and economic data
necessary to define current project energy requirement.
7.1.4 Develop GCC for the project with base-line energy requirement and
consequently map utilities to the base case design, otherwise establish a
new base case design for approval by project’s owner.
7.2.1 Evaluate fulfilling energy requirement with all types of utility systems
commercially available. For example, flexible designs of Tri-generation
systems, furnaces, chilled water, cooling water, air cooling, refrigeration,
etc., should be considered, as well as cogeneration scheme(s).
7.2.2 Use utility system base case configuration or develop a new one with
some alternate utility system configurations.
Note: The design configuration of the utilities system shall be developed
according to SAES-A-502.
7.4.2 Study the possibilities for integration schemes with near-by facilities
and/or residential areas to optimize energy utilization.
7.4.5 Obtain the latest energy values for primary utility (fuel, electricity,
water, cooling water, etc.)
7.4.6 Develop CHP model for the project and evaluate several utility systems
alternatives with comparisons to a base case design.
7.5.1 Define Energy Utility System configuration base case with all utility
appropriate details for future development.
7.5.2 Determine “marginal cost” for each energy utility of selected Energy
Utility System.
7.5.3 Discuss this assessment findings with the concerned project’s entities.
If a 3rd party consultant under ESD supervision is performs the energy optimization
study, then the study “Scope of Work” shall be prepared by FPD and reviewed as well
as confirmed by ESD before initiating the competitive bidding process. On other hand,
if the decision was to conduct the study in-house by ESD, then “Scope of Work”,
schedule and milestones shall be discussed and agreed between ESD and IPT leader.
Note: The recommended 3rd party consultants to conduct EOS is provided in SABP-A-058.
The following steps shall be applied to conduct the final Energy Optimization Study
during FEL2 DBSP stage;
8.1.2 Extract stream(s) data from available documents and model for each
process, this data shall be used for energy targeting.
8.1.3 Establish base-case energy usage of each plant from the current heat
Saudi Aramco: Company General Use
Page 8 of 11
Document Responsibility: Energy Systems Optimization Standards Committee SAEP-42
Issue Date: 1 January 2018
Next Planned Update: 15 October 2019 Capital Project’s Energy Optimization Study
8.1.4 Energy targets for each process/plants and all plants shall be calculated.
Utility targeting shall be conducted to identify minimum energy
demands for each plant.
8.1.5 The efficiency of the current HEN design and CHP system’s
configuration shall be assessed using an updated CHP model according
to SAES-A-502 and comparing the current utility consumption with the
energy targets identified.
8.2.4 The efficiency of the current HEN design and CHP, Cooling and
Refrigeration systems configuration shall be assessed using an updated
CHP model and comparing the current utility consumption with the
energy targets identified.
8.2.5 Identify and quantify opportunities for interplants heat recovery, and
assess them for practicality, safety and operability. Opportunities
fulfilling all considerations shall be evaluated in terms of NPV and listed
as potential improvement for the base case design.
8.3.2.1 Number and sizes of cogen units and boilers that meet energy
demand and satisfies all constraints.
8.3.3 All identified initiatives shall be evaluated one-by one in terms of NPV
with energy reduction due to its implementation.
8.4.2 Identify and evaluate all applicable technologies to capture the available
from base case design energy. Technologies fulfilling all considerations
shall be evaluated in terms of NPV and listed as potential improvement,
for the base case design now or in the future.
8.5.1 Final design and configuration of plant’s energy utilities systems and its
major components with all appropriate level of details for design
development.
Saudi Aramco: Company General Use
Page 10 of 11
Document Responsibility: Energy Systems Optimization Standards Committee SAEP-42
Issue Date: 1 January 2018
Next Planned Update: 15 October 2019 Capital Project’s Energy Optimization Study
Revision Summary
15 October 2014 New Saudi Aramco Engineering Procedure.
29 February 2016 Minor revision for name change, scope clarity, roles and responsibility clarity, including some
improvements in procedure to conduct EOS.
1 January 2018 Editorial revision to delete paragraph 3.3.