Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
101
1 W.L.R.
A [QUEEN'S BENCH DIVISION]
* V O S N O C L T D . v. T R A N S G L O B A L P R O J E C T S L T D .
ORIGINATING SUMMONS
By an originating summons dated 13 March 1997 the plaintiffs, Vosnoc
Ltd., a company incorporated in Cyprus, sought a declaration, inter alia,
that all disputes between themselves and the English defendants, G
Transglobal Projects Ltd., under a contract of affreightment dated
23 August 1994 were validly referred to arbitration on or before
19 September 1995; alternatively, an extension of time for commencement
of arbitration proceedings by the plaintiffs against the defendants under
the contract of affreightment.
The facts are stated in the judgment. „
The facts
The background to the matter is as follows. Vosnoc entered a contract
of affreightment with Transglobal dated 23 August 1994 for the shipment
of pipes. They were to be shipped by four vessels from Port Kembla in
New South Wales to Kuantan in Malaysia, where they were to be coated.
They were then to be shipped to Dampier or Port Hedland in Western
Australia where they were required for a pipeline. Transglobal were to be
responsible for the stevedoring, that is, the loading and unloading, the
stowage and unstowage, of the pipes.
Clause 17.8 of the contract provides for arbitration:
D "17.8 Should any dispute between the contractor and charterers, the
matter in dispute shall be referred to three persons in London, to be
appointed by each of the parties hereto and the third by the two
chosen. Their decision or that of any two of them shall be final and
for the purpose of enforcing any award their decision may be made a
rule of court. The arbitrators shall be shipping men. The arbitration
g is to be conducted in accordance with the rules of the London
arbitrators [sic]."
Clause 17.9 was in terms which it was accepted for the purpose of the
applications before me incorporated the 1922 Hague Rules. So, by
article III, rule 6, unless suit was brought within one year of delivery
Transglobal were discharged from all liability whatever in respect of the
p pipes. Mr. Picken, who appeared for Vosnoc, reserved their right to argue
in any arbitration that this was not so.
The dates of discharge in Western Australia were: vessel 1, 19-25
September 1994; vessel 2, 4-11 October; vessel 3, 17-22 October; vessel 4,
2-8 November. The contract provided for the inspection of the pipes
during discharge. Damage was- noted, which provides the basis of the
intended claims.
G
Between 30 September 1994 and 23 March 1995 there was
correspondence between Vosnoc and Transglobal concerning the claims.
On 16 September 1995 Vosnoc sent a letter by fax to Transglobal asking
for an extension of time to commence suit. The letter said:
"Karratha to Port Hedland gas pipeline project cargo damage claim:
We refer Transglobal to our facsimile transmissions dated . . . Due to
H the complexity of the claims, final adjustment in quantifying costs for
each of the consignments will not be accomplished within the (12)
month time period. We are requesting at this juncture an extension
of suit time of (1) year effective from 30 September 1995. . . . Should
you have any further questions please feel free to contact the
undersigned. We eagerly await your response."
There was none.
The Weekly Law Reports 16 January 1998
104
V o s n o c Ltd
CkQC - v- Transglobal Projects Ltd. (Q.B.D.) [1998]
Three days later, on 19 September 1995, Vosnoc sent by fax from A
Singapore the letter to Transglobal which I mentioned at the start of the
judgment. It reads:
"Karratha . . . You are referred to the contract of affreightment
between our respective companies and made on 23 August 1994.
Pursuant to that contract of affreightment you were responsible, inter
alia, to load . . . During loading, stowage and the voyage and the g
unloading of the pipes serious damage was caused to the pipes in
consequence of which this company has suffered loss and damage
and has become liable to the owner and consignee of the pipes,
Pilbara Energy Pipeline Co. Pty. Ltd. Under the contract of
affreightment, pursuant to clause 17.8 thereof, it is provided that all
disputes to the arbitration of three persons in London. By this letter
the dispute between our respective companies is referred to the C
arbitration of three arbitrators in London pursuant to the provisions
of clause 17.8 of the contract of affreightment such arbitration to be
conducted in accordance with the rules of the London arbitrators."
The bottom of the letter had a space for a signature in acknowledgement
of receipt and it asked for that to be done by fax.
On the same date, 19 September 1995, proceedings relating to the D
damage to the pipes were commenced in the courts of South Korea
between Bredero Price (Malaysia) Sdn. Bhd. ("B.P.M.") and Yukong
Line Ltd. Transglobal had time chartered from Yukong the vessels to
perform their contract with Vosnoc. B.P.M. has the same holding company
as Vosnoc. Vosnoc had entered an agreement with B.P.M. whereby
Vosnoc were to arrange the transportation and stevedoring of the pipes £
and also their coating in Kuantan. The action in Korea is proceeding. It
is not in evidence what stage it has reached. The damages which Vosnoc
seek to claim against Transglobal are the sums of Aus.$801,055 and
U.S.S 155,216 which Vosnoc have had to pay, or are liable for, to B.P.M.
under Vosnoc's contract with B.P.M.
There was no response from Transglobal to Vosnoc's letter of
19 September 1995. Nor was anything done at this stage by either side to F
appoint arbitrators. On 25 September 1995 lawyers in Western Australia
acting for B.P.M., Cocks Macnish, wrote to Transglobal asking for
information as to the stevedores, which was given by letter of 6 October.
On 31 January 1996 they asked for further information, and wrote a
chasing letter on 15 February. On 22 February Transglobal responded
referring Cocks Macnish to their solicitors, Clifford Chance. On 1 March Q
Cocks Macnish copied to Clifford Chance their letter of 31 January and
asked for a reply as a matter of urgency. None was given. Meanwhile in
that February Clifford Chance had advised Transglobal on Vosnoc's letter
of 19 September 1995. The advice was given because Transglobal sent a
package of documentation to Clifford Chance which included the letter
and it was not specifically sought. The advice they gave is not known.
The next event is that on 6 March 1997 solicitors for Vosnoc, Richards H
Butler, asked Mr. Michael Ferryman if he would accept appointment as
arbitrator nominated by Vosnoc in respect of the relevant disputes. The
following day, 7 March, Mr. Ferryman accepted the appointment. Also
on 6 March 1997 Richards Butler wrote to Transglobal referring to the
contract of affreightment and Vosnoc's letter of 19 September 1995. They
stated that Vosnoc had appointed Mr. Ferryman as arbitrator and called
on Transglobal to appoint theirs. Clifford Chance replied on 11 March.
The Weekly Law Reports 16 January 1998
105
1 W.L.R. Vosnoc Ltd. v. Transglobal Projects Ltd. (Q.B.D.) JHCM}"™
A They said that the letter of 19 September did not satisfy the requirements
necessary to bring suit for the purpose of article III, rule 6 of the Hague
Rules. They also stated that without prejudice to that contention they had
appointed on behalf of Transglobal Mr. John Maskell as arbitrator.
Vosnoc's proceedings were issued on 13 March.
There was thus an 18-month gap between the letter of 19 September
1995 and any further step to progress an arbitration. There is no
B explanation for this in the evidence from Vosnoc. Mr. Southern has
submitted on behalf of Transglobal that the explanation has to be that
Vosnoc never intended to commence an arbitration by their letter of
19 September and did not think that they had done so. That cannot be
right. Whether or not the letter is effective for its purpose, the intention is
clear. Vosnoc had the one year time bar well in mind. That is why on
Q 16 September 1995 they wrote asking for an extension. That letter also
shows that for one reason or another they were not ready to proceed with
an arbitration once it was commenced. Having got no response to the
request for an extension Vosnoc wrote as they did on 19 September. The
intention was to protect their position by bringing suit within the year.
They intended to do so by giving notice of arbitration. Having done that,
they considered that their position was preserved. In March 1997 their
D position was such that they wished to proceed.
The law relating to commencement of arbitration and its application
It might be thought that to commence an arbitration the party claiming
should give notice to the other requesting arbitration in accordance with
the agreement. Article 21 of the United Nations Commission on
International Trade Law Model Law on International Commercial
b
Arbitration (21 June 1985) ("the UNCITRAL Model Law") takes that
approach:
"Commencement of arbitral proceedings. Unless otherwise agreed by
the parties, the arbitral proceedings in respect of a particular dispute
commence on the date on which a request for that dispute to be
referred to arbitration is received by the respondent."
Vosnoc's letter would meet this requirement. English law may take a
different approach. Whether in practice it does so is the main point which
I have to decide.
English law as to when an arbitration is commenced has based itself
on the relevant provisions of the Limitation Acts 1939 and 1980 and now
of the Arbitration Act 1996. A barring provision which does not arise
Q under statute but is contractual will not be covered by these provisions. It
is established that in those circumstances the statutory provisions should
be applied by analogy: see Nea Agrex S.A. v. Baltic Shipping Co. Ltd.
[1976] Q.B. 933.
The relevant provision here is that in force on 19 September 1995,
namely section 34(3) of the Limitation Act 1980. Its predecessor was
section 27(3) of the Limitation Act 1939, which was the provision in
H question in the Nea Agrex case. It was repealed with effect from
31 January 1997 and replaced by section 14 of the Arbitration Act 1996.
Section 27(3) of the Limitation Act 1939 provided:
"For. the purpose of this Act . . . an arbitration shall be deemed
to be commenced when one party to the arbitration serves on the
other party or parties a notice requiring him or them to appoint an
arbitrator or to agree to the appointment of an arbitrator, or, where
the arbitration agreement provides that the reference shall be to a
The Weekly Law Reports 16 January 1998
106
jSckeQRcyn,0,ld V o s n o c Ltd
- v- Transglobal Projects Ltd. (Q.B.D.) [1998)
person named or designated in the agreement, requiring him or them A
to submit the dispute to the person so named or designated."
Section 34(3) of the Limitation Act 1980 provided:
"For the purposes of this Act and of any other limitation
enactment an arbitration shall be treated as being commenced—
(a) when one party to the arbitration serves on the other . . . a notice
requiring him or them to appoint an arbitrator or to agree to the "
appointment of an arbitrator; or (b) where the arbitration agreement
provides that the reference shall be to a person named or designated
in the agreement, when one party to the arbitration serves on the
other party or parties a notice requiring him or them to submit the
dispute to the person so named or designated."
Section 14 of the Arbitration Act 1996 provides:
"(1) The parties are free to agree when arbitral proceedings are to
be regarded as commenced for the purposes of this Part and for the
purposes of the Limitation Acts. (2) If there is no such agreement the
following provisions apply. (3) Where the arbitrator is named or
designated in the arbitration agreement, arbitral proceedings are
commenced in respect of a matter when one party serves on the other ^)
party or parties notice in writing requiring him or them to submit
that matter to the person so named or designated. (4) Where the
arbitrator or arbitrators are to be appointed by the parties, arbitral
proceedings are commenced in respect of a matter when one party
serves on the other party or parties notice in writing requiring him or
them to appoint an arbitrator or to agree to the appointment of an g
arbitrator in respect of that matter. (5) Where the arbitrator or
arbitrators are to be appointed by a person other than a party to the
proceedings, arbitral proceedings are commenced in respect of a
matter when one party gives notice in writing to that person
requesting him to make the appointment in respect of that matter."