Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1 Mekanika Tanah Oleh : Dr. Ir. D. Westley , Badan Penerbit Pekerjaan Umum
2 Foundation Analysis and Design, by J.E. Bowles
3 British Standard : BS 8110 : 1997 for Reinforced Concrete Code
4 Peraturan Pembebanan Indonesia 1983
5 Peraturan Beton Bertulang Indonesia 1990
6 Peraturan Beton Bertulang Indonesia 1971
7 Peraturan Perencanaan Bangunan Baja Indonesia 1983
8 Peraturan Konstruksi Kayu Indonesia 1970
9 Soil Investigation Laboratory Test - 2004 Reference of Dr. Badarul House's Pre Construction on 2004
10 Plaxis Software Reference from Consoft Technologies Sdn. Bhd.
1 Plain Reinforced Concrete Steel U-24 , mean σau = 2,400 kg/cm2--> σau* =
2 Deform Reinforced Concrete Steel U-32, mean σau= 3,200 kg/cm2--> σau* =
3 MessReinforced Concrete Steel ST-37, mean σau = 3,700 kg/cm2--> σau* =
4 Sub Structural Concrete K-225, mean σbk*= 225 kg/cm2
5 Super Structural Concrete K-175, mean σbk*= 175 kg/cm2
6 Non Structural Concrete K-125, mean σbk*= 125 kg/cm2
Structural Idealization :
1 Roof Structure is idealized simply supported on the Concrete Structural Frame. So There is only
Axial gravitation and lateral force acted on each simply support. No Torque or Moment at all.
2 The concrete structural frame is idealized as rigid concrete frame fixed supported on the founda-
tion. So there are several forces acted to the based of each collumn :
a. Axial Gravitation Load.
b. Lateral / Horisontal Load
c. Moment Load
3 The foundation is idealised as grid mat foundation. There are several assumption on this kind of
foundation :
a. The structure of the grid mat is fully rigid, all super structure load distributed spreadly to all
part of foundation.
b. Before Concreting the top concrete plate of the grid mat, vertical drain work properly to drain the
excess water on the designed consolidated soil layer , 8 meters.
c. Simultaneusly work between grid mat and consolidated designed soil layer is designed to bear
2 storeys house gravity load and lateral load such as wind load.
Engineer :Makno Basoeki, C.Eng, M.Eng www.bioconc.co.id Subject : Foundation Analysis with the Peat Drain
Project : Graha Bunda Hospital Extension _ P.70 &Peat Stabilization with Biosoil www.bioconc.co.id
Location : Pontianak Consultant: Makno Basoeki, C.Eng., M. Eng
1 Refer to the 4th floors house beside the plan area shows :
- Foundation from the deep foundation (pile foundation).
- Settlement is being process after the construction finish and house/building occupied, indicated by the decline or
settlement of the house behind those building.
- Considering the difficulties of soil investigator to take bor log or sample of shallow boring, caused by mostly soil
material is mud and mostly more water content.
- Based on this condition, main problem is water dominated content on bearing soil cause lack of bearing capacity
and settlement occurred during construction and after construction.
- To solve this problem means :
a. Increase soil bearing capacity.
b. Develop settlement during construction.
c. Eliminated settlement after construction.
2 Based on the above soil condition and based on the proven similar case and sub structure system, we design the
following "vertically drained grid-mat foundation system" :
- Develop / implant vertical drain every +/- 1,5 meter and average to 8 meters depth , to drain the excess water
to reach proper settlement due to building load.
- Develop Grid Mat Foundation to buils the solid stiff full plate foundation system to eliminate the differential settle-
ment probably occurred during the construction period (immediete settlement) due to building load and prepared
vertical drain.
Width = 14 meter
Length =
Engineer :Makno Basoeki, C.Eng, M.Eng www.bioconc.co.id Subject : Foundation Analysis with the Peat Drain
Project : Graha Bunda Hospital Extension _ P.70 &Peat Stabilization with Biosoil www.bioconc.co.id
Location : Pontianak Consultant: Makno Basoeki, C.Eng., M. Eng
Engineer :Makno Basoeki, C.Eng, M.Eng www.bioconc.co.id Subject : Foundation Analysis with the Peat Drain
Project : Graha Bunda Hospital Extension _ P.70 &Peat Stabilization with Biosoil www.bioconc.co.id
Location : Pontianak Consultant: Makno Basoeki, C.Eng., M. Eng
I. Loading Calculation :
III.1. Based on the worst soil investigation data held on 2004 from Dr Badarul's House Land ( Ø=20
on those area (wet cocopeat layer and difficult to take sample for laboratory test) - First Data :
Where :
Safety = 8.3/0,944
Safety = 22.4
Engineer :Makno Basoeki, C.Eng, M.Eng www.bioconc.co.id Subject : Foundation Analysis with the Peat Drain
Project : Graha Bunda Hospital Extension _ P.70 &Peat Stabilization with Biosoil www.bioconc.co.id
Location : Pontianak Consultant: Makno Basoeki, C.Eng., M. Eng
III.2. Based on the worst soil investigation data held on 2004 from Dr Badarul House Land ( Ø= 5
on those area (wet cocopeat layer and difficult to take sample for laboratory test) - Second Data :
Where :
Nc` = 6.70
Nq` = 1.40
N∫` = 0.20
Safety = 3.423 ====> before drained by vertical drain the foundation is "Critical Safe"
before fully construction loading. In order to increased the bearing capacity
of these peat layer, its necessary to be drained and stabilized with
' as prooven done for the house of Dr. Badarul - which is closed to this projec
IV.1. Checking The Heaviest Load Of The Column ( Calculated with tributary area method ) :
Pu_1 = 256,517 kg
Pu_2 = 234,103 kg
Hence , The Heaviest Collumn is P_max = 257 ton No Tributary Equal P_max=
Po ( 1 ) = ( 2,2 x 1,6 - 2,5 x 1 ) = 1.02 ton/m2 = 0.102 kg/cm2 Water Level on - 2.50 m
B = 16.5 meter see Length and Width of The Building (Figure No. 1)
L = 14 meter
S = H . Cc . log Po + DP If Po + DP > Pc
1 + eo Po
S = H . Cs . log Pc If Po + DP < Pc
1 + eo Po
t = 899,393,939 second
` 90
t = 29 years
` 90
Engineer :Makno Basoeki, C.Eng, M.Eng www.bioconc.co.id Subject : Foundation Analysis with the Peat Drain
Project : Graha Bunda Hospital Extension _ P.70 &Peat Stabilization with Biosoil www.bioconc.co.id
Location : Pontianak Consultant: Makno Basoeki, C.Eng.
Immediete Settlement will be occurred during the construction process with the embedment of Vertical Drain by usin
Hessian Laminated Wooden Pile, which is embedded with driven during the pilingof wooden pile. Without this syste
ment will be occurred after 29 years building construction finished and approximately settle 15 cm . In order to antic
for the construction of the building put 150 mm to be added to all elevation of the designed gound floor.
To expedite this settlement period to be used Hessian Laminated Bamboo Vertical Drain to 12 m depth
To stabilized the peat layer / cocopeat layer to be used Peat Stabilized Enzyme_MB 0,2 Ltr in 50 litres water/m
foundation coverage area which is previoustly drived by Hessian Laminated Bamboo Vertical Drain which is
prooven worked and safely construct 15 years ago (Year 2004) for the designed project on Pontianak-West K
mantan
with the Peat Drain Page..Of..
www.bioconc.co.id 1
g., M. Eng 13
onstruction on 2004
o There is only
ment at all.
on the founda-
on this kind of
readly to all
esigned to bear
ck of bearing capacity
16.5 meter
with the Peat Drain Page..Of..
www.bioconc.co.id 3
g., M. Eng 13
with the Peat Drain Page..Of..
www.bioconc.co.id 4
g., M. Eng 13
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
kg/m2
with the Peat Drain Page..Of..
www.bioconc.co.id 5
g., M. Eng 13
924 ton
924 ton
14 m
16.5 m
4. t/m2
40. kN/m2
10. t/m'
16.5 m
with the Peat Drain Page..Of..
www.bioconc.co.id 6
g., M. Eng 13
with the Peat Drain Page..Of..
www.bioconc.co.id 7
g., M. Eng 13
m
m
m
ton.m=kN.m 252
ton.m=kN.m 208
ton.m=kN.m 44
ton = kN 275
ton = kN 250
ton = kN 115
with the Peat Drain Page..Of..
www.bioconc.co.id 8
g., M. Eng 13
10 unit
1,924 ton
14 m
16.5 m
8.3. t/m2
83.3. kN/m2
20.82. t/m'
t (o.k.)
kN /m'
m
m
m
ton = kN 573
ton = kN 521
ton = kN 239
with the Peat Drain Page..Of..
www.bioconc.co.id 10
g., M. Eng 13
with the Peat Drain Page..Of..
www.bioconc.co.id 11
g., M.Eng 13
with the Peat Drain Page..Of..
www.bioconc.co.id 12
g., M.Eng 13
0.2
0.678 kg/cm2
S=Δh/h.H
Δ_h
( mm ) ( cm )
0.12985669 2.597133779
0.10532927 4.73981708
0.09640271 6.748189971
Total Settle-
ment (cm) 14.08514083
15 cm
mm
with the Peat Drain Page..Of..
www.bioconc.co.id 13
13
5 cm . In order to anticipate it
ound floor.
in to 12 m depth.
t on Pontianak-West Kali-
Lampiran II : Evaluasi Kebutuhan Material Beton sesuai dengan Standard Job Mix
Deskripsi
Total Harga Beton Grid P_70 Vol 34 m3 =Rp. 14,948,582 + 152,072 + 1,058,903 + 7,969,681 = Rp. 24,129,238
13.7 M3
PT MDP kirim (hanya ut 13,7 m3 beton) : 100 zag + 3 m3 + 5 m3 7.4 m3
Deskripsi
Total Harga Beton Grid P_70 Vol 68 m3 =Rp. 29,718,720 + 302,328 + 2,105,167 + 15,844,227 = Rp. 47,970,441
Total Harga Beton Grid P_70 Vol 68 m3 =Rp. 29,718,720 + 302,328 + 2,105,167 + 15,844,227 = Rp. 47,970,441
Harga Besi Beton ---> Ref. Belanja Besi = Rp. 98,284,000
Total Harga Beton Bertulang Pondasi dan tulangan Kolom s/d dasar Bottom Balok Lantai 2 = Rp. 146,254,441
Engineering Cost = Rp. 52,053,000
Total Cost Lantai Dasar (Diluar Finishing & M/E) = Rp. 198,307,441
Panjang Bangunan P_70 = 16 m
Lebar Bangunan P_70 = 14 m
Luas Bangunan P_70 = 226 m2
Total Harga Beton Bertulang Pondasi dan tulangan Kolom s/d dasar Bottom Balok Lantai 2 = Rp. 877,316 ,- / m2
Estimasi Biaya Finishing & Labor = Rp. 1,000,000 ,- / m2
Estimasi Biaya Mechanical & Electrical = Rp. 150,000 ,- / m2
Prakiraan Keuntungan Proyek P_70 (dan besi beton kolom lt dasar-2)Total = 226 m2 x @ Rp. 1.092.653,- / m2 = Rp. 163,354,559
(untuk Lantai dasar saja & keuntungan besi beton kolom dari Lantai dasar s/d bottom Lt_2 )
Note : Hal ini merupakan hak PT MDP, dan angka tersebut, taksiran dasar, sekedar untuk mengetahui proporsi pekerjaan Sub Struktur masih "On Budget".
Grid Elevasi Grid Bentang Grid Tinggi Grid Tebal Grid Tebal Plat Tul. Utama Sengkang
No. Centre Line +…..mm L = …mm h = ….mm tg=….mm ts=….mm A.tr = A.br As_tumpu
As A s.d. D
60 36 28 118
As A s/d D 60 36 28 118
#REF!