Trouble shooting Theme Flashing from die in running

Situation Flashing problem observed during running on die casting machine

P See phenomenon on actual D Do trouble shooting


after deciding priority to
C Check workmanship
of each item of A Act to start production if
necessary prevent re
site/artticle. Decide action trouble shooting by
minimize damage occurrence
items/responsible person yourself
1)Indicate a leader to prepare for
1)Check casting condition repairing 1)Make sure repairing was done. 1)Follow condition after repairing
2)Process condition as per W.I 2)Expected time to repair. 2)Check accumulator pressure 2)Incorporate check the pressure
3)Check machine condition 3)Check the next process verify 3)Check saftey (Interlocking) as per WI.
4)Check die condition blow holes during drilling 4)Check quality. 3)Share the information at worksite
5)Report the condition to boss . 4)Associate work along with maint./die maint 5)Report your boss repairing 4)Prevent ocurence and do
6)Check no. of stock . (TL) and other associate involved was done cross check.
7)Request the maint./Die maint person for 5S and other activity . 6)Check previous and next
7)Check repair condition . process
8)Make plan to recover the loss

C h e c k p o i n t
1) Check 3 G Check wt. of casting . 4) Check Hydraulic press.(H/L-150/80 KG/cm2),Accumulator pressure(140 kg/cm2
2) Check no. of Turn /Speed High Low (4T/2 T) Decleration point(as per wi) 5)Check stock condition at SFG & at machining
P Back pressure ,Die locking force(567~630T),Blue matching,
Metal temp.,
6)Inform about B.D. to before and aftere operation.

3)Inform to die maint if blue matching not ok,and to maint. If tie bar tension is a problem
Ask Person for repair time and check our estimared time.
1) Clean the place around the m/c .
2)Ask the maint. Person for repair time and check our estimated time.
D 3)Do seggregation.
4)TL should check all associate are at work as per plan during maint. Of m/c/Die
5)Inform associate for recovery the loss through O.T. on Sunday.
1)Check all part in the m/c/Die after repairing.
2)Check Blue matching of die/tie bar balancing data
C 3)Check saftey for interlocking of m/c.
4)Check Shots in Operation for Flashing and biscuit thickness
5)Inform to SL before and previous operation that m/c repaired .
1)Check feed back from associates for m/c operation.
2) Share the information in log book and change point board .
A 3)Relief tie bar/die blue matching checking point added in preventive check sheet.
4)Check point add in PM check sheet horizontal deployment.
start production if
sary prevent re
ence

after repairing
ck the pressure

mation at worksite
ce and do

essure(140 kg/cm2).