CLIENT: ETHIOPIAN ELECTRICAL POWER(EEP)
CONTENT SHEET
CONTENT NO. DESCRIPTION Pages
2 PASS 8-10
10 CVT 109
11 AC POWER 110
1. Equipment Details:
Make:
Type :
Rating HV :
Rating LV :
HV Volts :
LV Volts:
Current Rating HV:
Current Rating LV:
Vector Group :
% Z HV/LV :
SI. No.
Type of transfomer:
Year of Manufacture :
2. General Checks:
SN DESCRIPTION REMARKS
1. Check all components are installed. OK
2. Check nameplates information (visible location) as per contract OK
specifications.
3. Check tightness of all bolts. OK
4. Check that all grounding is securely connected (two grounding OK
connections to main tank are required).
5. Check that the piping to Buchholz relay has proper slope. OK
6. Check that the tank pressure is positive, if applicable. OK
7. Check that the valves between the main tank and radiators are right OK
8. Check the HV, LV (if applicable) bushings for damage and OK
completeness.
9. Check for correct color and quantity of desiccant (moisture absorbing OK
media) in breathers. Check for correct breather oil levels.
SN DESCRIPTION REMARKS
10. Check heaters and humidity meters in local panel are at correct OK
settings.
11. Check that phase marking with Switchgear and cables. OK
12. Check all pipes, hoses. OK
13. Check the vertical and horizontal clearances of live parts to adjacent OK
grounded points conform to standard.
14. Check integrity of diaphragm/air bag in the conservator. OK
15. Perform all of the manufacturer's specific checks. OK
16. Check labeling of all auxiliary devices as per approved drawing. OK
17. Check proper operation of auxiliary devices as follows: OK
a) Tap changer (upper-lower-out of step and interlock).
b) Oil level gauges.
c) Top oil temperature gauges.
d) Buchholz relay by gas injection.
e) Winding temperature gauges.
f) OLTC oil/gas surge (pressure) relay.
g) Ensure correct operation of the Pressure Relief Device
microswitch.
h) Push buttons and indicators.
i) Oil sampling port (main tank and OLTC).
j) Upper and lower main tank valves.
k) Tap changer diverter switch compartment, oil filtering pumps
and filter in good condition (if available).
18. Check that the oil sampling valves for the main tank and OLTC are OK
accessible from ground level.
19. Check oil level in main tank, conservator, tap changer tank and OK
bushings, etc. Test the oil level gauges and their alarms
20. Bleed trapped air at the bushing turrets and radiators. OK
21. Check all external wiring for correctness and tightness. OK
Core-E
Clamp-E
Core-Pw
1 62.9 KV
2 60.8 KV
3 61.6 KV
4 65.8 KV
5 61.5 KV
6 48.3 KV
8. Functional Checks:
SL.
DESCRIPTION REMARKS
NO.
1. Check for current and voltage ratings of all motors for tap changer. Check that
OK
MCBs for protection are set at proper over load settings
2. MCBs in cooler control cubicle to be checked by current injection for alarm OK
and trip
3 On load Tap Changer tests: OK
a. Check current and voltage ratings of tap changer motor.
b. Raise/Lower Control (local-remote) and indication and perform
adjustment as required.
c. End of tap travel control.
d. End of winding travel control (both ends).
e. Check that the windings are not open circuited during tap
changing. This should be done during the winding
resistance test.
4. Liquid level (alarm and trip). OK
5. Top Oil Temperature Device: (stop, start alarm and trip). OK
6. Buchholz Relay {alarm and trip). OK
7. Oil / Gas Surge (pressure) relay (alarm and trip). OK
8. Pressure Relief Device (alarm and trip) OK
9.Remarks:
1. Equipment Details:
Make:
Type :
Rated Volts :
Rated Current :
Making Capacity:
Breaking Capacity:
Operating Duty:
SI. No.
Year of Manufacture :
2. General Inspection:
SN DESCRIPTION REMARKS
1. Inspect for physical damage or defects. ok
2. Check nameplate information for correctness. ok
3. Check tightness of all bolted connections (torque wrench method). ok
4. Check all wiring is correct according to approved drawings and that ok
terminal connections are secure.
5. Check that ail grounding cables are securely connected. ok
6. Check for correct breaker position indication (breaker open/closed). ok
7. For SF6 breakers: ok
a. Check for correct SF6 pressure in each pole.
b. Check for gas leakage.
c. Calibrate SF6 pressure gauge.
d. Check operation of gas density switch (alarm and lockout
functions).
e. Check air and moisture content of SF6 gas in breaker
SN DESCRIPTION REMARKS
8. For motor/spring operation mechanisms:
a. Check manual spring charge operation.
b. Verify correct spring status indication (spring ok
charged/discharged).
c. Perform all specific checks on the mechanism according to
the manufacturer’s instructions.
6. Operational checks
SN DESCRIPTION REMARKS
1. a. Manual ok
2. Close ok
3. Open ok
4. b. Electrical ok
5. Close ok
6. Open ok
7. Protection Tripping ok
8. Anti-Pumping Function ok
7.Functional Checks:
SN DESCRIPTION REMARKS
1. Emergency Trip ok
2. ON-OFF Indication ok
3. Spring charge Limit Switch ok
4. CB Aux. contacts ok
5. Auto Trip Indication ok
6. Trip circuit healthy ok
7. Sf6 gas pressure indication ok
8. Interchangeability of CB ok
9. Aux Switch operation (13No+13Nc.) ok
10. Operation Counter ok
8. Remarks:
6. Ratio Test:
R-Phase Y-Phase B-Phase
CT CORE Applied Measured Applied Measured Applied Measured
Current(A) Current(A) Current(A) Current(A) Current(A) Current(A)
CT1 1S1-1S3 10 10 10 10 10 10
30 30 30 30 30 30
60 60 60 60 60 60
90 90 90 90 90 90
CT2 2S1-2S3 10 10 10 10 10 10
30 30 30 30 30 30
60 60 60 60 60 60
90 90 90 90 90 90
CT3 3S1-3S3 10 10 10 10 10 10
30 30 30 30 30 30
60 60 60 60 60 60
90 90 90 90 90 90
CT4 4S1-4S3 10 10 10 10 10 10
30 30 30 30 30 30
60 60 60 60 60 60
90 90 90 90 90 90
7. Remarks:
1. Equipment Details:
Make:
Type :15kV GIS
SI. No
Year of Manufacture :
Operating Voltage :
Feeder Details :in comeing
Control Voltage :
2. General Inspection:
SN DESCRIPTION REMARKS
1. Inspect for physical damage or defects. ok
2. Check nameplate information for correctness. ok
3. Inspect enclosures for proper alignment, grounding . ok
4. Inspect all covers, panels section and doors for paint work and ok
proper fit.
5. Check for smooth and proper movement of racking mechanisms for ok
alignment, shutters, rollers, rails and guides.
6. Check for proper alignment of the breaker primary and secondary ok
contacts.
7. Check operation of all mechanical interlocks. ok
8. Check tightness of all bolted connections . ok
9. Check main and riser buses for correct phasing. ok
10. Verify that all front panel mounted devices (meters, push buttons, ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
11. Perform mechanical checks and visual inspection on all circuit ok
breakers.
12. Perform mechanical checks and visual inspection on all current ok
transformers.
13. Perform mechanical checks and visual inspection on all voltage ok
transformers.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, and leakage ok
where possible.
18. For SF6 breakers, check the operation of the gas density switch ok
(alarm and lockout functions).
19. Perform all specific checks on the breaker and spring operating ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. ok
23. Check that all special tools, devices, etc., as per specification have ok
been provided.
Core-1
1S1-1S2
v) CT Ratio Test:
Measured Secondary Current
Primary Current
Description Ratio ( Amps)
Injected (Amps)
R-Ph S-Ph T-Ph
Core-2
2S1-2S2
Core-2
2S1-2S3
Core-3
3S1-3S2
Core-3
3S1-3S3
PT Serial No.
R-Ph. S-Ph. T-Ph.
R S T
1a-1n
2a-2n
Da-dn
Core-2 2da-2n OK OK OK
v) PT Check List:
SI.
Check Point Remarks
No.
1. All PT quantity, rating, type & make are as per approved ok
drawings.
2. No physical damage to any of the PT. ok
3. Inter-panel wiring from PTs to disconnector terminal blocks in ok
panel as per approved drawings.
4. PT primary neutral terminals are properly earthed. ok
5. PT wiring ferrules are as per drawing. ok
6. All PT connections are properly tightened. ok
A Tripping of CB ok ok ok ok
B Closing of CB ok ok ok ok
D Heater in Switchgear ok ok ok ok
7. Remarks:
1. Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :outgoing feeder 1
Control Voltage :
2. General Inspection:
SN DESCRIPTION REMARKS
1. Inspect for physical damage or defects. ok
2. Check nameplate information for correctness. ok
3. Inspect enclosures for proper alignment, grounding and vermin ok
proofing.
4. Inspect all covers, panels section and doors for paint work and ok
proper fit.
5. Check for smooth and proper movement of racking mechanisms for ok
alignment, shutters, rollers, rails and guides.
6. Check for proper alignment of the breaker primary and secondary ok
contacts.
7. Check operation of all mechanical interlocks. ok
8. Check tightness of all bolted connections . ok
9. Check main and riser buses for correct phasing. ok
10. Verify that all front panel mounted devices (meters, push buttons, ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
11. Perform mechanical checks and visual inspection on all circuit ok
breakers.
12. Perform mechanical checks and visual inspection on all current ok
transformers.
13. Perform mechanical checks and visual inspection on all voltage ok
transformers.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. ok
23. Check that all special tools, devices, etc., as per specification have ok
been provided.
Description Remarks
CB rack in / out operation NA
CB rack in / out indications
Manual spring charging operation ok
Spring charged indication ok
Manual ON / OFF operation ok
CB ON/OFF operation ok
Emergency Trip operation ok
Power contact alignment with panel contacts ok
Core-1
1S1-1S2
v) CT Ratio Test:
Measured Secondary Current
Primary Current
Description Ratio ( Amps)
Injected (Amps)
R-Ph S-Ph T-Ph
Core-1
1S1-1S2
Core-1
1S1-1S3
6. Remarks:
1.Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :outgoing feeder 2
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
1. Inspect for physical damage or defects. ok
2. Check nameplate information for correctness. ok
3. Inspect enclosures for proper alignment, grounding and vermin ok
proofing.
4. Inspect all covers, panels section and doors for paintwork and ok
proper fit.
5. Check for smooth and proper movement of racking mechanisms for ok
alignment, shutters, rollers, rails and guides.
6. Check for proper alignment of the breaker primary and secondary ok
contacts.
7. Check operation of all mechanical interlocks. ok
8. Check tightness of all bolted connections . ok
9. Check main and riser buses for correct phasing. ok
10. Verify that all front panel mounted devices (meters, push buttons, ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
11. Perform mechanical checks and visual inspection on all circuit ok
breakers.
12. Perform mechanical checks and visual inspection on all current ok
transformers.
13. Perform mechanical checks and visual inspection on all voltage ok
transformers.
SN DESCRIPTION REMARKS
14 Perform mechanical check and visual inspection on all disconnect ok
and grounding switches.
15. Check for correct breaker position indication. ok
16. Check for correct spring status indication (spring ok
charged/discharged).
17. For SF6 breakers, check the correct gas pressure, quality and ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved N
drawing and terminal connections are secure.
21. Check all wiring is correct according to approved drawings. ok
22. Check that all phase marking have been installed per specifications. ok
23. Check that all special tools, devices, etc., as per specification have ok
been provided.
Description Remarks
CB rack in / out operation NA
CB rack in / out indications
Manual spring charging operation ok
Spring charged indication ok
Manual ON / OFF operation ok
CB ON/OFF operation ok
Emergency Trip operation ok
Power contact alignment with panel contacts ok
Description Remarks
Spring charging operation time (Sec) ok
Test / Service position switch ok
ON / OFF operation in location / remote ok
Spring charged indication ok
CB ON/OFF indication ok
Lamp indications ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
6. Remarks:
1.Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 3
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
1. Inspect for physical damage or defects. ok
2. Check nameplate information for correctness. ok
3. Inspect enclosures for proper alignment, grounding and vermin ok
proofing.
4. Inspect all covers, panels section and doors for paint work and ok
proper fit.
5. Check for smooth and proper movement of racking mechanisms for ok
alignment, shutters, rollers, rails and guides.
6. Check for proper alignment of the breaker primary and secondary ok
contacts.
7. Check operation of all mechanical interlocks. ok
8. Check tightness of all bolted connections . ok
9. Check main and riser buses for correct phasing. ok
10. Verify that all front panel mounted devices (meters, push buttons, ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
11. Perform mechanical checks and visual inspection on all circuit ok
breakers.
12. Perform mechanical checks and visual inspection on all current ok
transformers.
13. Perform mechanical checks and visual inspection on all voltage ok
transformers.
SN DESCRIPTION REMARKS
14 Perform mechanical check and visual inspection on all disconnect ok
and grounding switches.
15. Check for correct breaker position indication. ok
16. Check for correct spring status indication (spring ok
charged/discharged).
17. For SF6 breakers, check the correct gas pressure, quality and ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved ok
drawing and terminal connections are secure.
21. Check all wiring is correct according to approved drawings. ok
22. Check that all phase marking have been installed per specifications. ok
23. Check that all special tools, devices, etc., as per specification have ok
been provided.
Description Remarks
CB rack in / out operation NA
CB rack in / out indications
Manual spring charging operation ok
Spring charged indication ok
Manual ON / OFF operation ok
CB ON/OFF operation ok
Emergency Trip operation ok
Power contact alignment with panel contacts ok
Description Remarks
Spring charging operation time (Sec) ok
Test / Service position switch ok
ON / OFF operation in location / remote ok
Spring charged indication ok
CB ON/OFF indication ok
Lamp indications ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB ok ok ok ok
D Heater in Switchgear Ok Ok Ok Ok
6. Remarks:
1.Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 4
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. ok
23. Check that all special tools, devices, etc., as per specification have ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the ct is seald with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 ok ok ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB ok ok ok ok
D Heater in Switchgear ok ok ok ok
1.Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 5
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. ok
23. Check that all special tools, devices, etc., as per specification have ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
CB ON/OFF operation ok
Description Remarks
CB ON/OFF indication ok
Lamp indications ok
4. Metering / Protection CT Test Report:
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 ok ok ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
6. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1.Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 6
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
5. Check for smooth and proper movement of racking mechanisms for Ok
alignment, shutters, rollers, rails and guides.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
1.Equipment Details:
Make:
Type :15kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
1.Equipment Details:
Make:
Type :33kV GIS
SI. No
Year of Manufacture :
Operating Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
5. Check for smooth and proper movement of racking mechanisms for Ok
alignment, shutters, rollers, rails and guides.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, and leakage Ok
where possible.
18. For SF6 breakers, check the operation of the gas density switch Ok
(alarm and lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
v) CT Ratio Test:
Measured Secondary Current
Primary Current
Description Ratio ( Amps)
Injected (Amps)
R-Ph S-Ph T-Ph
Core-2
2S1-2S2
Core-2
2S1-2S3
Core-3
3S1-3S2
Core-3
3S1-3S3
SI.
Check Point Remarks
No.
PT Serial No.
R S T
1a-1n
2a-2n
Da-dn
Core-1 1a-1n Ok Ok Ok
Core-2 2da-2n Ok Ok Ok
BB VT LINE VT
v) PT Check List:
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
1.Equipment Details:
Make:
Type :33kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
iv) CT Ratio Test:
Core-1
1S1-1S2
v) CT Ratio Test:
Measured Secondary Current
Primary Current
Description Ratio ( Amps)
Injected (Amps)
R-Ph S-Ph T-Ph
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
1.Equipment Details:
Make:
Type :33kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 2
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
1.Equipment Details:
Make:
Type :33kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 3
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
CB ON/OFF operation Ok
Description Remarks
CB ON/OFF indication Ok
Lamp indications Ok
4. Metering / Protection CT Test Report:
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
6. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1.Equipment Details:
Make:
Type :33kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 4
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
CB ON/OFF operation Ok
Description Remarks
CB ON/OFF indication Ok
Lamp indications Ok
4. Metering / Protection CT Test Report:
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
Core-1
1S1-1S3
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
6. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1.Equipment Details:
Make:
Type :33kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 5
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
4. Inspect all covers, panels section and doors for paint work and Ok
proper fit.
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
Description Remarks
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
iv) CT Ratio Test:
Core-1
1S1-1S2
v) CT Ratio Test:
Measured Secondary Current
Primary Current
Description Ratio ( Amps)
Injected (Amps)
R-Ph S-Ph T-Ph
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
1.Equipment Details:
Make:
Type :33kV GIS
SI. No.
Year of Manufacture :
Operating Voltage :
Feeder Details :out going feeder 6
Control Voltage :
2.General Inspection:
SN DESCRIPTION REMARKS
10. Verify that all front panel mounted devices (meters, push buttons, Ok
switches, indicator lamps, mimic buses, etc.) are installed as per
drawings.
SN DESCRIPTION REMARKS
17. For SF6 breakers, check the correct gas pressure, quality and Ok
leakage where possible.
18. For SF6 breakers, check the operation of the switch (alarm and Ok
lockout functions).
19. Perform all specific checks on the breaker and spring operating Ok
mechanism according to the manufacture's instructions.
20, Check that all control wiring is correct according to the approved Ok
drawing and terminal connections are secure.
22. Check that all phase marking have been installed per specifications. Ok
23. Check that all special tools, devices, etc., as per specification have Ok
been provided.
R CB Close R-E
CB Close R-S
CB Open R-R'
S CB Close S-E
CB Close S-T
CB Open S-S'
T CB Close T-E
CB Close T-R
CB Open T-T'
Description Remarks
CB ON/OFF operation Ok
Description Remarks
CB ON/OFF indication Ok
Lamp indications Ok
4. Metering / Protection CT Test Report:
: Instrument
Primary to Earth
Primary to Core-1
Primary to Core-2
Primary to Core-3
Core-1 to Earth
Since the CT is sealed with the CB notable to test
Core-2 to Earth
Core-3 to Earth
Core-1 to Core-2
Core-2 to Core-3
Core-3 to Core-1
Core-1 1S1-1S2 Ok Ok Ok
1S1-2S3 Ok Ok Ok
Core-2 2S1-2S2 Ok Ok Ok
2S1-2S3 Ok Ok Ok
Core-3 3S1-3S2 Ok Ok Ok
3S1-3S3 Ok Ok Ok
Core-1
1S1-1S2
Core-1
1S1-1S3
v) CT Ratio Test:
Core-1
1S1-1S2
Core-1
1S1-1S3
SI.
Check Point Remarks
No.
A Tripping of CB Ok Ok Ok Ok
B Closing of CB Ok Ok Ok Ok
D Heater in Switchgear Ok Ok Ok Ok
6. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
Make :
Model :
SI. No. :
2. General Inspection:
CT= 800/1
CT=2000/1
CT= 2500/1
1 Wiring checks Ok
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
CT Ratio 2500/1
Earthling Transformer
ET Neutral CT Ratio 400/1
Setting current = 0.15
to= 1 sec
3Io EXT= 60A
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
CT Ratio 800/1A
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
2. Location and Feeder Name:15kVoutgoing feeder 2
3. General Inspection:
CT Ratio 800/1A
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
R ph 1A 1A 1A 1206 ms
Sph 1A 1A 0.9 1206 ms
T ph 1A 1A 1A 1206 ms
R ph 1A 1A 1A 56 ms
Sph 1A 1A 0.9 56 ms
T ph 1A 1A 1A 56 ms
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
2. Location and Feeder Name:15kVoutgoing feeder 4
3. General Inspection:
CT Ratio 800/1A
4. DMT O/C Test (I>): 1A
Time Delay: 1.2 sec
Phase Setting Current Injected Operated Current Operated time(s)
(A) Current (A) (A)
R ph 1A 1A 1A 1206 ms
Sph 1A 1A 0.9 1206 ms
T ph 1A 1A 1A 1206 ms
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
CT Ratio 400/1A
4. DMT O/C Test (I>): 1A
Time Delay: 1.2 sec
Phase Setting Current Injected Operated Current Operated time(s)
(A) Current (A) (A)
R ph 1A 1A 1A 1206 ms
Sph 1A 1A 0.9 1206 ms
T ph 1A 1A 1A 1206 ms
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
CT Ratio 2000/1
7. Remarks:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
CT Ratio 800/1
3. General Inspection:
R ph 1 1 0.98 1227ms
T ph 1 1 0.98 1227ms
R ph 1 1 0.98 54ms
T ph 1 1 0.98 54ms
Tested by: Tested by: Witnessed by: Witnessed by:
R ph 0.05 0 0 117ms
S ph 0.05 0 0 117ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
CT RATIO 800/1
3. General Inspection:
R ph 1 1 1 1216ms
T ph 1 1 1 1216ms
R ph 1 1 0.9 60ms
T ph 1 1 1 60ms
Tested by: Tested by: Witnessed by: Witnessed by:
R ph 0.05 0 0 51ms
T ph 0.05 0 0 51ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
CT RATIO 800/1
3. General Inspection:
R ph 1 1 1 1173ms
T ph 1 1 0.9 1173ms
R ph 1 1 0.99 54ms
T ph 1 1 0.99 54ms
Tested by: Tested by: Witnessed by: Witnessed by:
S ph 0.05 0 0 54ms
T ph 0.05 0 0 54ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
CT RATIO 800/1
3. General Inspection:
4. a. DMT O/C Test (I>): 1
R ph 1 1 1 1205ms
Sph 1 1 1 1205ms
T ph 1 1 1 1205ms
R ph 1 1 0.99 56ms
T ph 1 1 0.99 56ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
4. a. DMT O/C Test (I>): 1
R ph 1 1 1 1210ms
T ph 1 1 0.99 1210ms
R ph 1 1 1 58ms
T ph 1 1 0.99 58ms
R ph 0.05 0 0 57ms
T ph 0.05 0 0 57ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
3. General Inspection:
4. a. DMT O/C Test (I>): 1
R ph 1 1 1 1204ms
T ph 1 1 0.99 1204ms
R ph 1 1 1 54ms
T ph 1 1 0.99 54ms
R ph 0.05 0 0 66ms
S ph 0.05 0 0 66ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Model :
SI. No.
CT Sec.
CT RATIO 400/1
3. General Inspection:
4. a. DMT O/C Test (I>): 1A
R ph 1 1 0.09 1338ms
T ph 1 1 0.09 1338ms
R ph 1 1 0.09 55ms
T ph 1 1 0.09 55ms
S ph 0.05 0 0 0051ms
T ph 0.05 0 0 0051ms
1 Wiring checks Ok
7. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by:
1. Equipment Details:
Make :
Type :
SI. No. : R-ph : S-ph : T-ph :
Voltage Rating :
Year of Manufacture :
3. General Checks:
5. All insulators & surge counter are free from any physical defects Ok
6. Check one end of surge counter Is connected to the bottom of Ok
LA stack and one end of surge counter has been Earth
TIME:1MIN
1 Counter Reading ok ok ok
6. Remarks:
1. Equipment Details:
3. General Inspection:
6. Check that all cable trays are secure and correctly grounded. Ok
7. Check cable entry path trench as ducts are to be properly Ok
sealed.
4. Insulation Resistance Test for Before High Voltage Test: (For 1 Min)
Connection R-E S-E T-E
5. General Checks:
1. Equipment Details:
6. Check that all cable trays are secure and correctly grounded. Ok
7. Check cable entry path trench as ducts are to be properly Ok
sealed.
4. Insulation Resistance Test for Before High Voltage Test: (For 1 Min)
5. Insulation Resistance Test for After High Voltage Test: (For 1 Min)
6. General Checks:
4. Equipment Details:
6. General Inspection:
6. Check that all cable trays are secure and correctly grounded. Ok
7. Check cable entry path trench as ducts are to be properly Ok
sealed.
4. Insulation Resistance Test for Before High Voltage Test: (For 1 Min)
Connection R-E S-E T-E
5. General Checks:
4. Equipment Details:
6. Check that all cable trays are secure and correctly grounded. Ok
7. Check cable entry path trench as ducts are to be properly Ok
sealed.
4. Insulation Resistance Test for Before High Voltage Test: (For 1 Min)
5. Insulation Resistance Test for After High Voltage Test: (For 1 Min)
6. General Checks:
1. Equipment Details:
Make:
KVA:
SR. no:
Rated Voltage
Vector group:
HV-E 5KV R S T N
rs 0.4
st 0.4
tr 0.4
DATE:
Page No.117
CLIENT: ETHIOPIAN ELECTRICAL POWER (EEP)
Commented [E1]:
6.Ratio test
supply LVside
R S T r s t
rn sn tn
6.1 6.1 6.
3. Equipment Details:
Make:
KVA:
SR. no:
Rated Voltage
Vector group:
HV-E 5KV R S T N
4. Winding Resistance:
RS 44 R-N 22.3
ST 44 S-N 22.3
TR 44 T-N 22.3
rs 0.3
st 0.3
tr 0.3
DATE:
Page No.117
CLIENT: ETHIOPIAN ELECTRICAL POWER (EEP)
1 kV
2 kV
3 kV
4 kV
5 kV
TOTAL AVERAGE kV
7.Ratio test
supply LVside
RS ST RT rs st tr
rn sn tn
Make :
Type :
SI. No. : R-ph : S-ph : T-ph :
Voltage Rating :230KV
Year of Manufacture :2016
3.Winding Resistance:
11.AC POWER
TEST REPORT FOR AC POWER
DATE:
Page No.117
CLIENT: ETHIOPIAN ELECTRICAL POWER (EEP)
1.Equipment Details:
Make :
Voltage Rating :
Year of Manufacture :
2. AC POWER cheeck
16 2.24 34 2.21 52
17 2.23 35 2.2
18 2.27 36 2.23
3. Remarks:
1.Equipment Details:
Make :
Voltage Rating :
Year of Manufacture :
2. AC POWER cheeck
17 2.27 35 2.23
18 2.23 36 2.2
3. Remarks:
Tested by: Tested by: Witnessed by: Witnessed by: