Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken:
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures:
Section G McLaren Site Specific HSE Safety Induction:
Section H Welfare facilities:
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used.
Section L Communication/Toolbox Talks/Training Requirements:
Section M Works Permits
Section N Environmental and Waste Management:
Section O Programme for the Works:
Section P Housekeeping and Storage:
Section Q Hygiene and cleanliness
Section R Working At Height
Section S Occupational Health
Section T Sequence of Works/Activities
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Risk Assessment
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Revision Date Reason for Amendment Amended By Signature Has this amendment been briefed
No (Name) to the operatives involved and have
the operatives signed the register.
This method statement has been prepared in conjunction with the following documents;
1. OSHAD regulation and requirements
2. OHSAD- Code of Practices, HSE Regulations, Technical Guidelines, Mechanisms
3. GR HSE Guidelines and Requirements
4. Federal Environmental Authority Law No 24/1999 and its supplements.
5. Federal Labour Law No 8
6. Articles (3,4,5,7) Local Law No 21/2005 (Waste Management)
7. McLaren SHE Procedures
8. McLaren’s site specific SHEQ Plan (including TMMS, SWMP, EPP).
9. McLaren’s Integrated Management System Policy Statement (IMS) .
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Add full sketch of the project and mark up your areas of work (logistics plan to be updated)
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available either in the
Induction/First Aid Room or in the Main Office.
McLaren: (details of First Aiders ) Subcontractors(Details of First Aiders )
Joby John- 050-6372060 Prabir Kumar 0547937312
Jijo Mathew 055-2152903 Anu Baby 056-5465807
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Prior to any works taking place, all Operatives arriving at AMC project will be required to undergo a
Multiplex/Gulf Related safety induction followed by McLaren Site Safety induction, which will be held in the
induction room, by McLaren’s HSE Representative or other designated person. Once the operatives have received
the site specific safety induction, they then will be briefed on the contents of this RAMS, by their respective Site
Supervisor, from which they will then be required a sign a RAMS Briefing Register (SAF019 UAE) confirming that
they have been briefed and that they fully understand the RAMS and what is expected from them during the
execution of the site works. The Operatives will also be briefed on the Emergency and Security Procedures for the
project, which is also a part of site safety induction programme.
Any operative who will be operating any plant and equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider, to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Section H- Welfare facilities:
Drinking Water-
Clean drinking water will be provided on site (as per approved Logistics plan) and all operatives are to ensure they
take on enough fluids throughout the day.
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
*Note: All relevant competency certificates (as per OHSAD /GR requirements) to be submitted to HSE
Manager/Eng./Advisor prior to start of any activity.
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
The following Materials will be utilised during the execution of the works, the Material Data sheets being
provided, which will allow the relevant COSHH assessments to be carried out; (See Appendix C)
Item Description Of Training Has the Training been If not, when will be
completed? (Yes/No) completed(Date)
1 Scaffolding inspection and erection Yes
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren
7 Permit to Work with Ladders, steps McLaren
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
11 Supervisor to ensure that proper barricade and warning signs are provided before starting any activity.
Proper Barricading to be provided for all Ceiling cutting or dust forming activity, and this barricading will be
provided with scaffolding drops with thick plastic sheets around the area to be sealed properly.
12 Supervisor to ensure proper working platforms such as ladders and scaffoldings are been used and make
sure that all the working platforms are having permit to work.
13 Supervisor to ensure that Competent workers are involved for scaffolding erection, dismantling and
inspection.
14 Transportation to site will be as per site requirement. Timing to be agreed with Mclaren
15 Ensuring that unloading of materials is undertaken in designated area.
Make sure that the lifting equipment is adequately rated for the specified weight (shown on the rated
16
plate).
17 When offloading the materials precaution to be taken to avoid damages
18 Procedure
18.1 Off-loading & Handling of Materials
Test equipment & meters will be offloaded from the vehicle manually at site store. Store in charge /
18.1.1
Supervisor to ensure that off load material load is not exceed 20kg/ person
18.1.2 Ensure the unloading area shall be free from debris, levelled.
Ensure all instrument & meters are up to date calibrated. Test equipment will be properly stored in store
18.1.3
area
18.2 SMDB & DBs
Visual inspection for proper cable sizes & terminations, Earthing connections, Circuit Breaker rating and
18.2.1
identification labels are as per approved drawings.
18.2.2 Isolate the cables/wires and perform mechanical operation of all MCCB,ELR & MCBs.
Perform Insulation resistance test 1 minute using 500V across each phase/neutral with earth & Phase to
18.2.3
phases for all bus bars and record.
All cable terminations & Bus bars tightness shall be verified by torque wrench. All control/circuit wire
18.2.4
terminations shall be checked for the tightness.
Apply current through CTBT of the ELR and perform ELR trip check. Measure & record the trip time &
18.2.5
current.
Ensure all connections are re-terminated and properly cleaned prior to closing all panel boards and
18.2.6
updated circuit schedules shall be kept in the folder.
18.3 Cables & Wires
Visual inspection for all circuit labels, cable/wire sizes, MCCB/MCB ratings are as per the approved
18.3.1
drawings and schedules.
Disconnect all cable terminations at both ends and shall be separated. A stand by person shall be at far end
18.3.2
to protect from unauthorised entries / contact.
18.3.3 All lighting circuit, ensure all lights are disconnected.
18.3.4 Continuity check for all cables, wires & circuits shall be verified.
18.3.5 Apply 1 Minute, 1Kv insulation tester across each phase & neutral with earth and Phase to phase for all
cables and record the values. During each test, other two phases shall be earthed and on completion of
test, proper discharging shall be done.
Apply 1 Minute, 500v insulation tester across each phase & neutral with earth and Phase to neutral for all
18.3.6
circuit wires in the DB and record the values.
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Ensure all connections are re-terminated and properly cleaned prior to closing all panel boards and
18.3.7
updated circuit schedules shall be kept in the folder.
18.4 Lux Level measurement
18.4.1 Ensure all lights are cleaned prior to switch ON.
Each room light level shall be separately measured using lux meter at a plane of 0.8meter height. Every
18.4.2
room six location shall be measured and tabulated. Average reading will be recorded as room lux level.
18.5 Earthing & lightning protection.
18.5.1 Tightness for all earth terminations in SMDB & DBs is verified and it properly bonded.
18.5.2 Ensure earth bars are installed as per drawing and labelling is done.
Verify all metallic structures are bonded to earth bars and earthing for all equipment, tray/ trunkings are
18.5.3
done.
18.5.4 All lightning protection network is done as per drawing and ensure all joints shall be properly terminated.
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
APPENDIX A
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
APPENDIX B
CRISIS PLAN
CRISIS PLAN
1. Upon an incident, being discovered the first member of McLaren’s staff or the site operative
discovering the incident shall inform the Project Manager and Site HSE team through AMC Project
emergency Contact No-056-7459621.
2. Both the HSE Engineer/advisor and the First Aider are to attend the scene with their mobile. The
project Manager or authorised person waits in office ready to contact relevant emergency
services.
3. Both the HSE Engineer/advisor and the first Aider are to assess the situation and put in place the
relevant systems to end/deal with the emergency.
4. Both the HSE Engineer/advisor and the first Aider are to ensure all trades are gathered at the
assembly point and liaise with supervisor to account for all operatives - no person should leave
site.
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
5. Either the HSE Engineer/advisor or the first Aider phones the project Manager or site receptionist
and informs him/her of which emergency services are required.
7. Both the HSE Engineer/advisor and the first Aider waits for the emergency services at scene.
8. Once emergency services arrive, The Project Manager will telephone the relevant authorities, i.e.
the HSE/Client’s Safety Advisor/QHSE Manager/McLaren’s operations Director.
9. Both the HSE Engineer/advisor and the first Aider keep trades informed of the situation and
releases trades to return to work or leave site only when emergency services or The Project
Manager instruct that it is safe to do so, and all names of witnesses are recorded.
10. Project Manager or Construction Manager are to arrange for photographs of the scene to be
taken, and if necessary the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
SHEQ Director, as soon as practicably possible after the incident, including all witness statements,
11. photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.
APPENDIX C
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
(Attach if any)
APPENDIX- D
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
RISK ASSESSMENTS
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
APPENDIX-E
TECHNICAL INFORMATION
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date:
Method Statement Title Testing & Commissioning of Electrical Doc Ref No: GEMC-EL-A-MST-023
system
Project Location: AMC Connectivity Corridors & Concourse Bridge Project, AD Revision No : 00
Prepared By Syed Faisal Approved By Revision Date: