Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
COST ESTIMATION
297
CHAPTER 7
COST ESTIMATION
A. Direct cost
Cost (Php) Exhibit %
Purchased Equipment Delivered Php 39,149,628.47 A 21.46%
Installation Php 15,268,355.10 B 8.37%
Instrumentation and Control Php 10,178,903.40 C 5.58%
Piping System Php 12,136,384.83 D 6.65%
Building Php 11,353,392.26 E 6.22%
Electrical System Php 3,914,962.85 F 2.15%
Yard Improvement Php 4,697,955.42 G 2.58%
Service Facilities Php 21,532,295.66 H 11.80%
Total Direct Cost Php 118,231,877.97 64.81%
B. Indirect cost
Engineering and Supervisor Php 12,527,881.11 I 6.87%
Construct Expenses Php 13,310,873.68 J 7.30%
Legal Expenses Php 1,565,985.14 K 0.86%
Contractor's Fee Php 7,438,429.41 L 4.08%
Contingency Php 14,485,362.53 M 7.94%
Total Indirect Cost Php 49,328,531.87 27.04%
17.77
Total General Expenses
Php 68.38 %
Total Production Cost Php 384.69
299
III. SCHEDULE A-1 (PEPSIN DIGESTER)
Cost of Reactor:
From Plant Design and Economics for Chemical Engineers by Peters and
604
Present Cost of Reactor2019 = ( $ 60,000 ) ( 390.4 )
Present Cost of Reactor2019 = $ 92,827.87
Cost of Insulation:
From Plant Design and Economics for Chemical Engineers by Peters and
300
Computing for the purchased cost of insulation for a 13.0 m2 heat transfer area,
604
Present cost of insulation = ( $ 1313 ) ( 390.4 )=$ 2,031.38
Cost of Impeller:
From Plant Design and Economics for Chemical Engineers by Peter and
For stainless steel and rotational speed of 125 rpm, adjustment factor is 1.85.
604
Present Cost of One (1) Impeller = $ 29,600 ( 390.4 )=$ 45,795.08
Cost of Reactor:
302
Cost of Insulation:
303
Cost of Impeller:
For SS316 and rotational speed of 125 rpm, adjustment factor is 1.85
304
SUMMARY OF FIGURES USED IN SCHEDULE A-1
(PEPSIN DIGESTER)
305
IV. SCHEDULE A-2 (VACUUM CRYSTALLIZER)
Cost of Crystallizer:
January 1990. (PD&E for ChE, Peters, Timmerhaus, & West 4 th Ed.; Fig. 14-76,
p561).
306
0.60
4.07 ton
Present Purchased Cost of Crystallizer =($ 300,000.00) ( 90 ton ) ( 604
356 )
Cost of Pump:
307
Pressure Drop:
∆ P= ρslurry g hTDH
kg N −m
(
∆ P= 1,165
m3 )(
9.889
kg )
=11,520 Pa=1.67 psi
lb lb
Capacity Factor=gpm x 2
=( 73.31 gpm ) ( 1.67 psi ) =122.43 gpm 2
¿ ¿
lb
Present cost of centrifugal pump with capacity factor of 122.43 gpm is $
¿2
1500 as of January 1990. (PD&E for ChE, Peters, Timmerhaus, & West 4 th Ed.;
308
0.60
lb
( )
122.43 gpm
( 604
2
356 )
Present Purchased Cost of Centrifugal Pump ( 1990 ) =( $ 1,500 ) ¿ =$ 721.
lb
1000 gpm 2
¿
309
Cost of Insulation:
From PD&E for ChE, Peters, Timmerhaus, & West 5th Edition, Fig. 15-17, p797
2
Heat Transfer Area=3.06 m
0.60
$ 155 0.0063 m 604
Present Cost of Insulation= 2 (3.06 m2)
m (
0.026 m ) ( 390.4 )=$ 1,247.96
2
Heat Transfer Area=3.06 m
0.60
$ 155 0.0064 m 604
Present Cost of Insulation=
m
2
(3.06 m2)( 0.026 m ) ( 390.4 )=$ 1,259.81
311
Equipment Capacity (F-2) 4.07 m3
No. of Units 1
1 USD equivalent to Php Php 50.59
Crystallizer Cost at 1990 for 90 gal $300,000
Present cost of Crystallizer $79,418.07
Purchased Cost of Insulation per m2
$155
installed for Collection Vessel
Present Cost of Insulation for
$1,247.96
Collection Vessel
Purchased Cost of Insulation per m2
$155
installed for Cooling Condenser
Present Cost of Insulation for Cooling
$1,259.81
Condenser
Cost of Centrifugal Pump at 1990 $1500
Present Cost of Centrifugal Pump $721.79
Total Present Cost of F-2 $82,647.63
Total Present Cost of F-2 in Php Php 4,181,143.602
312
Type: Decanter, Centrifuge
Material of Construction: SS316
Solid Liquid = 1
January 2002.
(PD&E for ChE, Peters, Timmerhaus, & West 5th Ed.; Fig. 15-43, p866).
313
Present Purchased Cost of Decanter Centrifuge
0.6
$ 55,000× [ ] [
0.50
0.32
×
604
390.4]= $ 111,219.73
$ 111,219.73× [ ₱ 50.59
$1 ]
=₱ 5 , 626 , 606 .12
314
SUMMARY OF FIGURES USED IN SCHEDULE A-3
(DECANTER CENTRIFUGE)
315
VI. Schedule A-4
Equipment: Freeze-drier
Equipment code: T-2
Type: Vacuum, Freeze-drier
Material of Construction: AIS SS316L
From Equipment Design:
Capacity: 1.295 m3
No. of Units 1
Cost of Dryer:
From Plant Design and Economics for Chemical Engineers by Peter and
604
$ 100,700 ( 309.4 )=$ 196,583.06
Present cost in Philippine currency:
316
Cost of Compressor:
From Plant Design and Economics for Chemical Engineers by Peter and
Cost2002= $ 100,000
Computing for the cost of the compressor with a power requirement of 118.33kW
0.6
118.33
Cost2002= $ 100,000 (
100 ) =$ 110,625.93
604
Cost2019= $ 110,625.93 ( 390.4 )=$ 171,152.82
Present cost in Philippine currency:
From Plant Design and Economics for Chemical Engineers by Peter and
Cost2002= $ 10,000
317
Computing for the cost of the shell and tube heat exchanger with a heating area
1.97
90
Cost2002= ¿
¿
$ 10,000¿
604
Cost2019= $ 1009.56 ( 390.4 )=$ 1561.93
Present cost in Philippine currency:
50.59 Php
¿
¿
$ 1561.93 ( 1 unit ) ¿
From Plant Design and Economics for Chemical Engineers by Peter and
Cost2002= $ 10,000
Computing for the cost of the shell and tube heat exchanger with a heating area
318
0.664
90
Cost2002= ¿
¿
$ 10,000¿
604
Cost2019= $ 525.72 ( 390.4 )=$ 813.36
Present cost in Philippine currency:
50.59 Php
¿
¿
$ 813.36 ( 1unit ) ¿
Cost of Insulation:
From Plant Design and Economics for Chemical Engineers by Peter and
$ 102
Cost2002=
m2
$ 102
Cost2002= 2
( 52.71 m2 )=$ 5886.78
m
604
Cost2019= $ 5886.78 ( 390.4 )=$ 9107.62
319
Present cost in Philippine currency:
= Php 9,239,541.58
Cost of Freeze-Drier:
From Plant Design and Economics for Chemical Engineers by Peter and
320
Cost of Reciprocating Compressor:
From Plant Design and Economics for Chemical Engineers by Peter and
321
Purchased cost of Reciprocating compressor2002 with a power requirement of
100kW = $100,000
From Plant Design and Economics for Chemical Engineers by Peter and
322
Purchased Cost of Shell and Tube Heat Exchanger 2002 with a heating area of 90 m 2
= $10,000
From Plant Design and Economics for Chemical Engineers by Peter and
323
Purchased Cost of Shell and Tube Heat exchanger 2002 with a heating area of 90 m2
= $10,000
Cost of Insulation:
From Plant Design and Economics for Chemical Engineers by Peter and
325
Present cost of drier $196,583.06
Purchased Cost at 2002 of compressor with a
$110,625.93
power requirement of 118.33kW
Present Cost of compressor with a power
$171,152.82
requirement of 118.33kW
Purchased Cost at 2002 of shell and tube heat
$1009.56
exchanger (condenser)
Present Cost of shell and tube heat exchanger
$1561.93
(condenser)
Purchased cost at 2002 of shell and tube heat
$525.72
exchanger (evaporator)
Present Cost of shell and tube heat exchanger
$813.36
(evaporator)
Purchased cost at 2002 of insulation $5886.78
Present cost of insulation $9107.62
Total Present Cost of F-2 $379,218.79
Total Present Cost of F-2 in Php Php 19,184,678.59
326