Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Commencement
Commencement, delay and suspension:Work
Commencement, delay, suspension, work program, Rate of progress, EoT, meetings, record keeping –
program and EOT reference to PPMO clauses 26 to 31 and relevant clauses of
FIDIC.
NEC
1 2
Time Extension
Delays
Extension of intended/initial completion date of
An Excusable delay: delay beyond the fault of either the Contractor or the owner; or
contract due to delays is EOT not caused by Contractor’s negligence for which Time compensation is to be provided
.
EOT is granted when
VO is issued
Delay caused by Engineer
Compensation event occurs like Defective plans/drawings Delay caused by Owner
and specifications Failure to provide a Delay not caused by
a) Delayed possession of sites
Failure to provide drawings project site, either party
b)
c)
Employer directed changes in schedules of other Contractors
Delayed issuance of drawings, specifications, instructions on schedule Late notice to Acts of God
d) PM instructs to uncover or to carry out tests upon work which is then found to have no defect Delay in review or approval proceed, Epidemics
e) PM unreasonably delays to approve subcontract to be let of shop drawings Failure to provide Unusual weather
f) Unforeseeable ground conditions Delay in change orders proper financing, conditions (Force
g) PM instructions for dealing with an unforeseen conditions
Stop-work order, Late payment Majeure)
h) Delayed caused by other Contractors and Public authorities suspension Failure to provide Strikes
i) Delayed advance payment owner furnished
j) Effect of Employer’s risk materials/componen
k) Delayed issue of Taking Over Certificate ts,
Interfering with or
obstruction of work
EOT is to be intended within the shortest possible time of 2.Actual Progress(Delay attributable to Contractor) Liquidated Damages
Activity-A 4
event. Activity-B 3
Activity-C 5+2 D1
1
7/5/2017
Duration 1 2 3 4 5 Duration 1 2 3 4 5
Activity Activity
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 (wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1. Original Program 1. Original Program
Activity-A 4 Activity-A 4
Activity-B 3
Activity-B 3
Activity-C 5
Activity-C 5
Activity-D 4
Activity-E 7
2.Actual Progress
Activity-A 4+2 D1
2.Actual Progress
Activity-B 3 Activity-A 4
Activity-C 5+1 D2 Activity-B 3
Extention of Time Activity-C 5+2 D1
Activity-D 4
Liquidated Damages Activity-E 7+2 D2
Liquidated Damages
Critical Path and Float (1) Critical Path and Float (2)
Critical Path and Float Delay in Non-Critical Path Activities(1)
Duration 1 2 3 4 5 Duration 1 2 3 4 5
Activity Activity
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 (wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Activity-A 4 Activity-A 4
Activity-B 3 Critical Path Activity-B 3 Critical Path
Activity-C 5 Activity-C 5
Activity-D 2 Activity-D 2
Activity-E 3 Non-Critical Path Activity-E 3+1 D2 Non-Critical Path
Activity-F 4 Activity-F 4
Activity-D 2
Activity-D 2
D2
Activity-E 3+4 D1 D2 Critical Path
Activity-E 7 Critical Path
Activity-F 4
Activity-F 4
???
Extention of Time
2
7/5/2017
Critical Path and Float (5) Critical Path and Float (6)
Delay in Non-Critical Path Activities (4) Delay in Non-Critical Path Activities (5)
Duration 1 2 3 4 5 Duration 1 2 3 4 5
Activity Activity
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Activity-A 4 Activity-A 4
Activity-B 3 Non-Critical Path Activity-B 3 Non-Critical Path
Activity-C 5 Activity-C 5
Float Float
D1
Activity-D 2 Activity-D 2+4 D2
Activity-E 3+4 D2 D1 Critical Path Activity-E 3 Critical Path
Activity-F 4 Activity-F 4
??? ???
26 Program program
26.1 Within the time stated in the SCC, after the date of the 26.3 The Contractor shall submit to the Project Manager for
approval an updated Program at intervals no longer than the
Letter of Acceptance, the Contractor shall submit to the period stated in the SCC. If the Contractor does not submit an
Project Manager for approval a Program showing the general updated Program within this period, the Project Manager may
methods, arrangements, order, and timing for all the withhold the amount stated in the SCC from the next payment
certificate and continue to withhold this amount until the next
activities in the Works. In the case of a lump sum contract, payment after the date on which the overdue Program has been
the activities in the Program shall be consistent with those in submitted. In the case of a lump sum contract, the Contractor
the Activity Schedule. shall Provide an updated Activity Schedule within 15 days of being
instructed to by the Project Manager.
26.2 An update of the Program shall be a program showing 26.4 The Project Manager’s approval of the Program shall not alter
the actual progress achieved on each activity and the effect of the Contractor’s obligations. The Contractor may revise the
the progress achieved on the timing of the remaining work, Program and submit it to the Project Manager again at any time. A
revised Program shall show the effect of Variations and
including any changes to the sequence of the activities. Compensation Events.
15 16
17 18
3
7/5/2017
19 20
Quality control
Identifying defects
Tests - 33.1 If the Project Manager instructs the Contractor to
carry out a test not specified in the Specification to check whether
any work has a Defect and the test shows that it does, the
Contractor shall pay for the test and any samples. If there is no
Defect, the test shall be a Compensation Event.
Correction of defects
Uncorrected defects - 35.1 If the Contractor has not corrected a
Defect within the time specified in the Project Manager’s notice,
the Project Manager shall assess the cost of having the Defect
corrected, and the Contractor shall pay this amount.
21