Sei sulla pagina 1di 4

7/5/2017

Commencement
 Commencement, delay and suspension:Work
Commencement, delay, suspension, work program, Rate of progress, EoT, meetings, record keeping –
program and EOT reference to PPMO clauses 26 to 31 and relevant clauses of
FIDIC.
NEC

1 2

Time Extension
Delays
 Extension of intended/initial completion date of
 An Excusable delay: delay beyond the fault of either the Contractor or the owner; or
contract due to delays is EOT not caused by Contractor’s negligence for which Time compensation is to be provided
.
 EOT is granted when
 VO is issued
Delay caused by Engineer
 Compensation event occurs like  Defective plans/drawings Delay caused by Owner
and specifications  Failure to provide a Delay not caused by
a) Delayed possession of sites
 Failure to provide drawings project site, either party
b)
c)
Employer directed changes in schedules of other Contractors
Delayed issuance of drawings, specifications, instructions on schedule  Late notice to  Acts of God
d) PM instructs to uncover or to carry out tests upon work which is then found to have no defect  Delay in review or approval proceed,  Epidemics
e) PM unreasonably delays to approve subcontract to be let of shop drawings  Failure to provide  Unusual weather
f) Unforeseeable ground conditions  Delay in change orders proper financing, conditions (Force
g) PM instructions for dealing with an unforeseen conditions
 Stop-work order, Late payment Majeure)
h) Delayed caused by other Contractors and Public authorities suspension  Failure to provide  Strikes
i) Delayed advance payment owner furnished
j) Effect of Employer’s risk materials/componen
k) Delayed issue of Taking Over Certificate ts,
 Interfering with or
obstruction of work

Delay and EOT


EOT Issues for discussion
 Timely completion and EOT issue in projects is to be given Delay in Work Progress
adequate attention. Activity
Duration
(wk)
1 2 3 4 5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

 Objective methods of evaluation of EOT has to be worked 1. Original Program


Activity-A 4

out or established. Activity-B


Activity-C
3
5

 EOT is to be intended within the shortest possible time of 2.Actual Progress(Delay attributable to Contractor) Liquidated Damages
Activity-A 4
event. Activity-B 3
Activity-C 5+2 D1

3.Actual Progress(Delay attributable to Employer) Extention of Time


Activity-A 4
Activity-B 3
Activity-C 5+2 D2

Time for Completion


Link
D1 Delay attributable to Contractor
D2 Delay attributable to Employer
6

1
7/5/2017

Delay and EOT


Delay and EOT

Delay in Work Progress Delay in Work Progress

Duration 1 2 3 4 5 Duration 1 2 3 4 5
Activity Activity
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 (wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1. Original Program 1. Original Program
Activity-A 4 Activity-A 4
Activity-B 3
Activity-B 3
Activity-C 5
Activity-C 5
Activity-D 4
Activity-E 7
2.Actual Progress
Activity-A 4+2 D1
2.Actual Progress
Activity-B 3 Activity-A 4
Activity-C 5+1 D2 Activity-B 3
Extention of Time Activity-C 5+2 D1
Activity-D 4
Liquidated Damages Activity-E 7+2 D2
Liquidated Damages

Time for Completion


Link Time for Completion
D1 Delay attributable to Contractor Link
D2 Delay attributable to Employer D1 Delay attributable to Contractor
D2 Delay attributable to Employer
7 8

Critical Path and Float (1) Critical Path and Float (2)
Critical Path and Float Delay in Non-Critical Path Activities(1)

Duration 1 2 3 4 5 Duration 1 2 3 4 5
Activity Activity
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 (wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Activity-A 4 Activity-A 4
Activity-B 3 Critical Path Activity-B 3 Critical Path
Activity-C 5 Activity-C 5

Activity-D 2 Activity-D 2
Activity-E 3 Non-Critical Path Activity-E 3+1 D2 Non-Critical Path
Activity-F 4 Activity-F 4

Float 1 Float 2 Float 1 Float 2

Time for Completion Time for Completion


Link Link
D2 Delay attributable to Employer
9 10

Critical Path and Float (3)


Critical Path and Float (4)
Delay in Non-Critical Path Activities (3)
Delay in Non-Critical Path Activities (2)
Duration 1 2 3 4 5
Duration 1 23 4 5 Activity
Activity (wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Activity-A 4
Activity-A 4
Activity-B 3 Non-Critical Path
Activity-B 3 Non-Critical Path
Activity-C 5
Activity-C 5
Float
Float

Activity-D 2
Activity-D 2
D2
Activity-E 3+4 D1 D2 Critical Path
Activity-E 7 Critical Path
Activity-F 4
Activity-F 4

???
Extention of Time

Time for Completion


Time for Completion
Link
Link
D1 Delay attributable to Contractor
D2 Delay attributable to Employer
D2 Delay attributable to Employer
11 12

2
7/5/2017

Critical Path and Float (5) Critical Path and Float (6)
Delay in Non-Critical Path Activities (4) Delay in Non-Critical Path Activities (5)

Duration 1 2 3 4 5 Duration 1 2 3 4 5
Activity Activity
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
(wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Activity-A 4 Activity-A 4
Activity-B 3 Non-Critical Path Activity-B 3 Non-Critical Path
Activity-C 5 Activity-C 5

Float Float

D1
Activity-D 2 Activity-D 2+4 D2
Activity-E 3+4 D2 D1 Critical Path Activity-E 3 Critical Path
Activity-F 4 Activity-F 4

??? ???

Time for Completion Time for Completion


Link Link
D1 Delay attributable to Contractor D1 Delay attributable to Contractor
D2 Delay attributable to Employer D2 Delay attributable to Employer
13 14

26 Program program
 26.1 Within the time stated in the SCC, after the date of the  26.3 The Contractor shall submit to the Project Manager for
approval an updated Program at intervals no longer than the
Letter of Acceptance, the Contractor shall submit to the period stated in the SCC. If the Contractor does not submit an
Project Manager for approval a Program showing the general updated Program within this period, the Project Manager may
methods, arrangements, order, and timing for all the withhold the amount stated in the SCC from the next payment
certificate and continue to withhold this amount until the next
activities in the Works. In the case of a lump sum contract, payment after the date on which the overdue Program has been
the activities in the Program shall be consistent with those in submitted. In the case of a lump sum contract, the Contractor
the Activity Schedule. shall Provide an updated Activity Schedule within 15 days of being
instructed to by the Project Manager.
 26.2 An update of the Program shall be a program showing  26.4 The Project Manager’s approval of the Program shall not alter
the actual progress achieved on each activity and the effect of the Contractor’s obligations. The Contractor may revise the
the progress achieved on the timing of the remaining work, Program and submit it to the Project Manager again at any time. A
revised Program shall show the effect of Variations and
including any changes to the sequence of the activities. Compensation Events.

15 16

Extension of intended completion date Acceleration and delay ordered by PM


 27.1 The Project Manager shall extend the Intended Completion Date if  28.1 When the Employer wants the Contractor to finish
a Compensation Event occurs or a Variation is issued which makes it before the Intended Completion Date, the Project Manager
impossible for Completion to be achieved by the Intended Completion
Date without the
shall obtain priced proposals for achieving the necessary
acceleration from the Contractor. If the Employer accepts
 Contractor taking steps to accelerate the remaining work,
these proposals, the Intended Completion Date shall be
 which would cause the Contractor to incur additional cost.
adjusted accordingly and confirmed by both the Employer
 27.2 The Project Manager shall decide whether and by how much to
extend the Intended Completion Date within 21 days of the Contractor
and the Contractor.
asking the Project Manager for a decision upon the effect of a  28.2 If the Contractor’s priced proposals for acceleration are
Compensation Event or Variation and submitting full supporting accepted by the Employer, they are incorporated in the
information at least 7 days prior to the intended completion date. If the Contract Price and treated as a Variation.
Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure shall not be  29.1 The Project Manager may instruct the Contractor to
considered in assessing the new Intended Completion Date. delay the start or progress of any activity within the Works.

17 18

3
7/5/2017

Management meeting Early Warning


 30.1 Either the Project Manager or the Contractor may  31.1 The Contractor shall warn the Project Manager at the earliest
require the other to attend a management meeting. The opportunity of specific likely future events or circumstances that
business of a management meeting shall be to review the may adversely affect the quality of the work, increase the Contract
plans for remaining work and to deal with matters raised in Price, or delay the execution of the Works. The Project Manager
accordance with the early warning procedure. may require the Contractor to provide an estimate of the expected
effect of the future event or circumstance on the Contract Price
 30.2 The Project Manager shall record the business of and Completion Date. The estimate shall be provided by the
management meetings and provide copies of the record to Contractor as soon as reasonably possible.
those attending the meeting and to the Employer. The  31.2 The Contractor shall cooperate with the Project Manager in
responsibility of the parties for actions to be taken shall be making and considering proposals for how the effect of such an
decided by the Project Manager either at the management event or circumstance can be avoided or reduced by anyone
meeting or after the management meeting and stated in involved in the work and in carrying out any resulting instruction
writing to all who attended the meeting. of the Project Manager.

19 20

Quality control
 Identifying defects
 Tests - 33.1 If the Project Manager instructs the Contractor to
carry out a test not specified in the Specification to check whether
any work has a Defect and the test shows that it does, the
Contractor shall pay for the test and any samples. If there is no
Defect, the test shall be a Compensation Event.
 Correction of defects
 Uncorrected defects - 35.1 If the Contractor has not corrected a
Defect within the time specified in the Project Manager’s notice,
the Project Manager shall assess the cost of having the Defect
corrected, and the Contractor shall pay this amount.

21

Potrebbero piacerti anche