Sei sulla pagina 1di 7

ID Task Name Duration Start Finish Predecessors

1 Site clearence 11 days Tue 3/06/18 Mon 3/19/18


2 Excavation for Foundation 11 days Tue 3/20/18 Tue 4/03/18 1
3 Foundation work & column 42 days Wed 4/04/18 Fri 5/25/18 2
4 Plinth work & Grade slab 24 days Mon 5/28/18 Wed 6/27/18 3
5 Column for slab-1 12 days Thu 6/28/18 Thu 7/12/18 4
6 Beam work & casting of slab-1 12 days Fri 7/13/18 Mon 7/30/18 5
7 Brickwork Ground floor 11 days Tue 7/31/18 Sat 8/11/18 6
8 Column for slab-2 11 days Mon 8/13/18 Fri 8/24/18 7
9 Beam work & casting of slab-2 16 days Sat 8/25/18 Thu 9/13/18 8
10 Brickwork first floor 14 days Fri 9/14/18 Mon 10/01/18 9
11 Column for slab-3 11 days Tue 10/02/18 Mon 10/15/18 10
12 Beam work & casting of slab-3 16 days Tue 10/16/18 Fri 11/02/18 11
13 Brickwork second floor 24 days Mon 11/05/18 Sat 12/01/18 12
14 External Plaster 12 days Mon 12/03/18 Sat 12/15/18 13
15 Internal plaster 12 days Mon 12/17/18 Mon 12/31/18 14
16 Lift Room/ OH Tank RCC Work 22 days Mon 12/03/18 Fri 12/28/18
17 Flooring for Ground floor 6 days Sat 12/29/18 Fri 1/04/19 16
18 Flooring for first floor 6 days Mon 1/07/19 Mon 1/14/19 17
19 Flooring for second floor 10 days Tue 1/15/19 Mon 1/28/19 18
20 Lift room(Brickwork/Flooring) & para13 days Tue 1/29/19 Thu 2/14/19 19
21 Electrical work 14 days Fri 2/15/19 Wed 3/06/19 20
22 Plumbing work 12 days Thu 3/07/19 Fri 3/22/19 21
23 Internal & External painting 13 days Mon 3/25/19 Wed 4/10/19 22
24 Lift work 23 days Thu 4/11/19 Mon 5/13/19 23
25 Pavement works 16 days Tue 5/14/19 Tue 6/04/19 24
26 Doors & windows 25 days Wed 6/05/19 Tue 7/09/19 25
27 Infra.works C.wall & U.G.tank 28 days Wed 7/10/19 Fri 8/16/19 26
28 Electrical fittings 4 days Mon 8/19/19 Thu 8/22/19 27
29 Water supply & sanitary fittings 8 days Tue 8/27/19 Thu 9/05/19 28
Resource Names
ID Resource name Type Material label Initials Group Max.Units
Std.Rate Ovt.Rate Cost/Use Accrue At Base Calendar Code
Uid Task name Resource name Work Duration
2019
ID Task Name Duration Start Finish November
1 Site clearence 14 days Tue 06/03/18 Mon 19/03/18
2 Excavation for Foundation 15 days Tue 20/03/18 Tue 03/0418
3 Foundation work & column 51 days Wed 04/04/18 Fri 25/05/18
4 Plinth work & Grade slab 31 days Mon 28/05/18 Wed 27/06/18
5 Column for slab-1 15 days Thu 28/06/18 Thu 12/07/18
6 Beam work & casting of slab-1 18 days Fri 13/07/18 Mon 30/07/18
7 Brickwork Ground floor 21 days Ths 07/11/19 Ths 28/11/19
10 Brickwork first floor 21 days Ths 07/11/19 Ths 28/11/19
13 Brickwork second floor 21 days Thu 21/11/2019 Sat 07/12/19
14 External Plaster 22 days Mon 09/12/19 Tue 31/12/20
15 Internal plaster 20 days Mon 16/12/19 Mon 04/12/20
16 Lift Room/ OH Tank RCC Work 27 days Mon 04/11/19 Sat 30/11/19
17 Flooring for Ground floor 20 days Wed 25/12/19 Sat 13/01/20
18 Flooring for first floor 27 days Wed 25/12/19 Sat 20/01/20
19 Flooring for second floor 27 days Wed 25/12/19 Sat 20/01/20
20 Lift room(Brickwork/Flooring) & parapet wall for terrace 21 days Mon 02/12/19 Mon 23/12/19
21 Electrical work 31 days Wed 01/01/20 Fri 31/01/20
22 Plumbing work 25 days Mon 06/01/20 Sat 08/02/20
23 Internal & External painting 33 days Mon 20/01/20 Sat 22/02/20
24 Lift work 28 days Mon 10/02/20 Sat 09/03/20
25 Pavement works 33 days Sat 01/02/20 Sat 14/03/20
26 Doors & windows 27 days Mon 10/02/20 Sat 07/03/20
27 Infra.works C.wall & U.G.tank 33 days Mon 10/02/20 Sat 14/03/20
28 Electrical fittings 20 days Mon 17/02/20 Sat 07/03/20
29 Water supply & sanitary fittings 26 days Mon 24/02/20 Sat 21/03/20
30 Miscellenious finishing works 22 days Mon 09/03/20 Tue 31/03/20

External Plaster
2019 2019 2020 2020 2020
November December January February March

Potrebbero piacerti anche