Risk Assessment/Management Form

Ref:
Section / Dept: civil,Contractor: Activity: Risk Assessment for Concreting Location:

Risk rating

Proba

Proba

ual
bility

bility
Sl Basic Job Potential Consequen Current control measure Initial Additi Ri

Resid

risk
No. Steps Hazard ce Risk onal sk
contro ra
l ti
P E A R P E A R
measu n
Proper illumination arranged at the working area in g
re
night.

Passage to be provided for the movement of the


person
Concreting Fall of man /
1 Get Injury Edge protected by railing / scaffolding pipe and 1 0 0 0 2 2
Manualy materials
use of double rope safety belt with anchoring
facilities
Before concreting work all area to be barricated at
lower level

Improper Visibility Injury/Fatality Proper illumination with WAH petrmit


Emergency Light shall be availabe at site.People
will stop the work and communicated not to be
panic in case of pwer failure. All will remain in the
Fall of person same place till the alternative arrangement of
/materials during Injury/Fatality light.Emergency Torchlight to be facilitated for
Power Failure working crew -Min-03 no.s.Definite supervisor for
Working at each area and additonal incharge overall
2 1 0 0 0 4 4
Height in night

Any work stopped due any reason in the late niight


work stopped more than 1/2 hour. Idle people should not rest in
more than half an Injury/Fatality the work area. They should come back to site
hour. office to relax and properly advise during tool box
talk every shift

Prepared By Approved By Reviewed By

1of1